SlideShare a Scribd company logo
GANG STRENGTH
CALCULATION USING
RATIONAL FORMULA
Presented By
K.A.J.BABU , ADEN/E/KGP,S.E.RLY
C.NAGARAJU, AXEN/C/KRMR,S.C.RLY
Under the Guidance of
Sri. PRAVEEN KUMAR,P/C,IRICEN/PUNE
Gang strength
 Gang strength calculation by
Maflin”s formula
Modified Maflin’s formula
Special Committee formula
Rational formulae
MAFLIN’S FORMULA
Adopted in 1931
No of gangmen required = Unit-per-
mile*2.5
Unit- per – mile depending on the traffic
carried
Man power factor is constant irrespective
of track gauge
Revised Maflin’s formula
Evolved by Lobo committee in 1959
Implemented in 1962
Gang strength was based on “Equated
Track Mile”
ETM depends on the traffic density, type
of formation, curved alignment and
annual rainfall
Special committee formula
Adopted in 1979
N = 0.95 * M * K * E
 N is the no of gang men
 M is man power factor ( 1.47 for B.G and 1.21 for
M.G and N.G)
 K is the correction factor due to modernisation of
track,methods of maintenance
 E is Equated Track Kilometre ( ETKM)
Special committee formula
 Correction factor
Type of track Mmethod of
maitenance
Convent
,DTM,M
SP
Mechanised
Fish plated 1.00 0.80
SWR 0.95 0.75
LWR on ws/ms 0.85 0.60
LWR on psc - 0.50
WHY SPECIAL COMMITTEE FORMULA
NEEDS REPLACEMENT
Gang is to carry out 12 activities and other 16 activities
are by engaging casual labourer
No uniformity of overall manpower per ETKM over the
railways
Maintance cost per ETKM is varying among Zonal
Railways
Decasualisation effect
Aspect of engagement of safaiwalas for filth removal
--Contd
Aspect of carrying out monsoon patrolling,
watching vulnerable locations and security
patrolling by out side agencies
Ageing of gang men
Absenteeism among gang men, as much as 60%
To identify the works to be executed through
contract to limit the manpower
Educational profile of the gangmen remains
deficient while mechanisation is increasingly
adopted
Modifying Special Committee formula
Railway Board in 1996 constituted a committee
Terms of reference
To study the special committee formula and suggest
modified formula
To take into account decasualisation done effect of
maintenance and track modernisation while modifying the
gang strenth formula
Categorisation of tracks
Non Sub urban sections
Machine Packed
Manually Packed
Sub urban section,Machine packed High
density
H D suburb section
 Criteria for High Density Sub urban Section
 The train frequency per hour, on any line or in a
sub section should exceed 8
 The required maintenance works can be
completed only by way of availing night blocks
• PHOD is the competent authority to classify a
suburban section as ‘HDSL’
H D suburb sections
 Special features of H D suburb section
 High frequency of trains
 Encroachments
 Corridor night blocks and integrated mega blocks
 Large number of turn outs
 Lack of drainage
 Extensive track circuits

CLASSIFICATION OF MAINTENANCE
ACTIVITIES
PRIMARY MAINTENCE ACTIVITIES
 Directly related to P Way maintenance
 Need manpower based on the continuous length
of the track
AUXILLIARY MAINTENANCE ACTIVITIES
 For upkeep of P Way as a whole
 Need manpower based on the localised
problems,special features and geographical nature
of P way section
Classification -- contd
PRIMARY MAINTENANCE ACTIVITIES
 Activity T – Affected by traffic density
 Activity R – Routine in nature
AUXILLARY MAINTENANCE ACTIVITIES
 Activity M – Miscellaneous
 Activity S – Site specific
Activity T ( For machine packed
track)
 T1 Slack attention to
 Bad spots
 Low joints
 SEJ
 Minor curve realignment
 T2 For Tie Tamper working
 Pre-tamping operation
 Along with tamper
 Post tamping operations
 T3 Casual renewals
 Rails
 Sleepers
 Fasteners
 T4 Repair Welding
Activity T ( For manually packed
track)
 T1 Through packing
 T2 Slack attention to
 Bad spots
 Low joints
 SEJ
 Minor curve realignment
 T3 Casual renewals
 Rails
 Sleepers
 Fasteners
 T4 Creep pulling
Activity T ( For machine packed track
HD suburban)
 T1 Slack attention to
 Bad spots
 Low joints
 SEJ
 Minor curve realignment
 T2 For Tie Tamper working
 Pre-tamping operation
 Along with tamper
 Post tamping operations
 T3 Casual renewals
 Rails
 Sleepers
 Fasteners
 T4 Repair Welding
Activity R ( For machine packed track)
 R1 Lubrication of ERCs
 R2 Shallow screening (1/5 length)
 R3 Loading , leading & unloading
 R4 Overhauling of level crossing
 R5 Watching caution spot and miscellaneous
 R6 Tree cutting for visibility
 R7 Lubrication of rails in Curves
 R8 Accident relief and carcass removal
 R9 Bridge sleeper attention and renewal
 R10 Pre monsoon attention such as clearing of
 drains, waterways, deweeding etc
 R11 Creep pulling (approach of bridges and turn outs)
 R12 Rectifying damage to LC
Activity R ( For manually
packed track)
 R1 Lubrication of ERCs
 R2 Shallow screening
 R3 Loading , leading & unloading
 R4 Overhauling of level crossing
 R5 Watching caution spot and miscellaneous
 R6 Tree cutting for visibility
 R7 Lubrication of rails in Curves
 R8 Accident relief and carcass removal
 R9 Bridge sleeper attention and renewal
 R10 Pre monsoon attention
 R11 Creep pulling
 R12 Rectifying damafe to LC
Activity R ( For machine packed HD
suburban track)
 R1 Through packing
 R2 Shallow screening (1/5 length)
 R3 Loading , leading & unloading
 R4 Lubrication of ERCs
 R5 Overhauling of level crossing
 R6 Watching caution spot and look out men
 R7 Tree cutting for visibility
 R8 Lubrication of rails in Curves
 R9 Accident relief and carcass removal in run over cases
 R10 Bridge sleeper attention and renewal
 R11 Pre monsoon attention
 R12 Creep pulling
 R13 Rectifying damage to LC
 R14 Painting of weld collars
 R 15 Emergency attention
 R 16 Extra sssistance to key man & B/smith
 R17 Extra work in Night blocks
 R 18 Extra assistance for S&T Items
Activity M
 M1 Monsoon patrolling
 M2 Hot weather patrolling
 M3 Cold weather patrolling
 M4 Watching vulnerable locations
 M5 Gate keeping at level crossings
 M6 Rest giving for keyman
 M7 Waterman duty
 M8 Store watchman duty
Activity S
 S1 Tunnel maintenance
 S2 Bridge substructure maintenance
 S3 Long girder maintenance
 S4 Extra due to sharp curves, deep cutting etc
 S5 Track on extremely bad formation
 S6 Lookout man duty
 S7 Fog signal man duty
 S8 Filth removal from track
 S9 Security patrolling
 S10Watching of water level in suburban section
Work to be done through contract
1. Formation treatment
2. Ballasting
3. Deep screening
4. Sub ballast and ballast layer
5. Heavy repair to track including lifting
6. TRR,TSR,TFR
7. Complete ROC
8. Complete renewal of P&C , SEJs , traps
9. Resurfacing of crossing and switch rails
10. Loading/unloading of P way material in bulk
11. Lorrying of P way materials in bulk
12. Security of material in depot which is closed and
locked
Work to be done through contract
13. Painting of rails and weld collars
14. Painting of bridge girders
15. Heavy repair to formation, cutting,side drains &c/w
drains
16. Providing and reparing road surface at LC
17. Heavy repair to bridges, protecion works,river
training works and tunnels
18. Removal of major sand breaches
19. Restoration works following breaches, accidents
20. Clearing of vegetation in P/F and in the vicinity of
tracks in coaching and goods yards, repairs to
depots and work shops of Engg, Mech, Elec and
S&T
 Authority for certifying the correctness of factors in
activities M & S
 No of mandays for monsoon patrolling – CTE/CBE
 Need for hot/ cold patrolling – CTE
 No.of days for watching vulnerable locations-
CTE/CBE
 Need for store w/man duty – Sr DEN/C00RD
 Existance of extremely bad formation – CTE
 Track Stretches with poor visibility – Sr DEN/Coord
 Need for fog signal duty – Sr DEN/Coord
 Need for removal of filth – Sr DEN/Coord
 Need for security patrol – Sr DEN/Coord
 No of days for watching water level in suburb-
SrDEN/Co
RATIONAL FORMULAE
MANPOWER
MANPOWER NORMS FOR
NORMS FOR
VARIOUS ACTIVITIES
VARIOUS ACTIVITIES
Rational formulae
How the manpower requirement arrived at?
Activties T & R
For Main line
 Norms as per the actual manpower utilised on
various sections on various zones and analyzing
the same scientifically
 Periodicity of shallow screening has been
changed to 5 yr instead of 3 yr
 Average spacing of the LC has been taken as 1.5
km
 Quantum of work in shallow screening in PSC
sleeper track is 4 sl / head
Contd
For RYL and NRYL
1 KM of NRYL is taken as equivalent to 2/3
km of RYL
Factors A,B and C are not considered
Considered as ‘R’ activity
MACHINE PACKED “BG”
(NON SUBURBAN)
MANDAYS REQUIREMENT/YEAR/KM.
 Activity “T” : (80 +2.3GMT)*(1+A+B+C)
 Activity “R” : 159
»“R” Modified with (+) 28 as per
Board’s letter
»+28 on a/c of overhauling 4 sleeper
instead of 6 per man for concrete
sleepers
Rational formulae
MANDAYS REQD. FOR ACTIVITY- T,
MACHINE PACKED
(NON- SUBURBAN) GMT-20
65
Total T1
10
As reqd.
MINOR CURVE
REALIGNMENT
4
6x8/12
6 times/yr., 8
sl/SEJ, 12 sl/head
SEJ (1 No. PER KM)
16
12x4x4/12
12 GJ/LJ 4 TIMES,
4sl/jts 12 sl/head
LOW JOINTS (FP OR
WELDED),GJ
35
1660/(4x12)
12 SL./HEAD, ¼
LENGTH
BAD SPOTS
‘T1’ SLACK ATTENTION
MD
Requirement
Norm
Activity
Rational formulae
MANDAYS REQD. FOR ACTIVITY- T,
MACHINE PACKED (NON-
SUBURBAN) GMT-20
10
20/2
20 men/Km
PRE-TAMPING
OPERATIONS
27
Total T2
14
28/2
28 men/Km
POST TAMING
OPERATIONS
3
10x6/(10x2)
10 men for one
week for 10 Km
gang length
ALONG WITH TAMPER
2 year cycle
T2- FOR TIE TAMPER
WORKING
MD
Requirement
Norm
Activity
Rational formulae
MANDAYS REQD. FOR ACTIVITY- T,
MACHINE PACKED
(NON- SUBURBAN) GMT-20
126
Total T1 + T2 + T3 + T4
12
12 men per failure/year
T4- Repair Welding
6
60/10
60 mandays /gang
length of 10 Km.
Rails
22
Total T3
10
100/10
100 mandays /gang
length of 10 Km.
Fastening
6
60/10
60 mandays /gang
length of 10 Km.
Sleepers
T3- Casual Renewal
MD
Require
ment
Norm
Activity
T= 80 + 2.3 GMT= 80 + 2.3 * 20 = 126
Rational formulae
MANDAYS REQD. FOR ACTIVITY- R,
MACHINE PACKED
(NON- SUBURBAN) GMT-20
4
,,
R7- Lubrication of Rails
in curves
10
,,
R6- Tree cutting for
visibility
10
Field data
R5- Watching caution
spots
13
20/1.5
1 LC/ 1.5 Km, 20 men/lc
R4- Over hauling of LC
20
Field data
R3-Loading, Leading &
unloading
55
1660/(5*6)
6 sl/head, 1/5 length
R2- Shallow Screening
2
Assistance to K-man
R1- Lubrication of ERC
MD
Require
ment
Norm
Activity
Rational formulae
MANDAYS REQD. FOR ACTIVITY- R,
MACHINE PACKED
(NON- SUBURBAN) GMT-20
159
TOTAL R
2
,,
R12- Rectifying damage to LC gates and
posts
5
,,
R11- Creep Pulling
18
,,
R10- Pre monsoon attention like waterway
clearance, cess repair, deweeding etc
10
,,
R9- Bridge sleeper attention and removal
10
Field
data
R8- Accident Relief- Carcass removal
MD
Require
ment
Norm
Activity
Rational formulae
MANUALLY PACKED “BG”
(NON SUBURBAN)
MANDAYS REQUIREMENT/YEAR/KM.
 Activity “T” : (223+8.24GMT)*(1+A+B+C)
 Activity “R” : 168
»+28 on a/c of overhauling 4
sleeper instead of 6 per man for
concrete sleepers
Rational formulae
MANUALLY PACKED “MG”
MANDAYS REQUIREMENT/YEAR/KM.
 Activity “T”: (160+13.56GMT)*(1+A+B+C)
 Activity “R”: 128
Rational formulae
MANUALLY PACKED “NG”
MANDAYS REQUIREMENT/YEAR/KM.
 Activity “T”: (105+188GMT)*(1+A+B+C)
Max. value of (105+188GMT) is 180
 Activity “R”: 91
Rational formulae
HIGH DENSITY SUBURBAN
MACHINE PACKED
MANDAYS REQUIREMENT/YEAR/KM.
 Activity “T” : (115 +2.3GMT)*(1+A+B+C)
 Activity “R” : 398
Rational formulae
RUNNING YARD LINE(RYL) and
NON RUNNING YARD LINE(NRYL)
RLY mandays are 74 % to 79% of R & T activities for
mainline with “0” GMT
NRYL mandays are 2/3rd of RLY mandays
Factors A, B, C not to be applied
*This includes equivalent MMU mandays
102
152
198
-
NRYL
153
228
297
177*
RYL
NG
Manually
packed
MG
Manually
packed
Manually
packed
Machine
packed
BG
MANDAYS REQUIREMENT FOR ACTIVITY
“M”
M.1 Monsoon
Patrolling
N: Total No. of beat-lengths
D: No.of days needing patrolling
in a year in the nth beat length.
b: No.of beats in the nth beat
length.
s: No. of shifts in the nth beat
length
m: No.of men in each shift in the
nth beat-length =2 in area
infested with wild animals/
terrorists; otherwise m=1.
1 to N
 
m
s
b
D 



MANDAYS REQUIREMENT FOR ACTIVITY
“M”
M.2 Hot weather
patrolling of
LWR track
Lw X 30
M.3 Cold weather
patrolling of
LWR track
Lw X 12
Lw: Length of LWR track in
km, on single line basis
MANDAYS REQUIREMENT FOR ACTIVITY
“M”
M.4 Watching
vulnerable
locations
1 to N
M.5 Gate keeping
at level
crossings
1 to N
N: No. of vulnerable locations
s: No.of duty shifts at the nth
location
d:No.of days of watching at the
nth location in a year.
N: No. of Engg level crossings
s: No.of duty shifts at the nth
level crossing
Ng: No. of Engg Gatekeeper
posts sanctioned
(Excluding LR)
 
d
s 

Ng
s 294
*
365 

MANDAYS REQUIREMENT FOR ACTIVITY
“M”
M.6 Rest giving
for keymen
K(365-294)
M.7 Waterman
duty
N * 294
M.8 Store-
watchman
duty
N * 3 * 365
K: No. of Keyman beats
N: No. of Gangs
N: No. of stores in addition to
SSE HQ (Not more than 2)
MANDAYS REQUIREMENT FOR ACTIVITY
“S”
S.1 Tunnel
Maintenance
1.2* 0.29*
1 to N
S.2 Bridge
substructure
maintenance
1.1* 0.29*
1 to N
N: No. of tunnels
l: length of the nth
tunnel, in metre
r: No.of tracks in the
nth tunnel.
N: No.of bridges
b: Lineal waterway of the nth
bridge, in metre
r: No. of tracks on the nth bridge.
 
r
l 

 
r
b 

MANDAYS REQUIREMENT FOR ACTIVITY
“S”
S.3 Long Girder
Maintenance
0.64*
1 to N
S.4 Sharp curves
> 3 D in BG
> 6 D in MG
Lc * 294
N: No. of bridges each having
more than 150m lineal
waterway
b: Lineal waterway of the nth
bridge, in metre
r: No. of tracks on the
nth bridge
Lc: Total Length of such curve
 
r
b 

MANDAYS REQUIREMENT FOR ACTIVITY
“S”
S.5 Track
maintenance
in extremely
bad formation
0.6 *
1 to N
S.6 look out man
294
1 to N
N: No.of locations where
track needs more than
4 attentions in a year
l: length of track in the nth
location, in metres
N: No. of gangs
v: length of track with poor
visibility in the nth gang length
g: length of the nth gang
 
g
v /

 
l

MANDAYS REQUIREMENT FOR ACTIVITY
“S”
S.7 Fog signalman
Mf / 3
S.8 Filth removal
from track
f * 294
S.9 Security
Patrolling
Ms / 3
Mf: Total Mandays actually utilised
in past three years
f: No. of gangs having this kind of
problem
Ms: Total Mandays actually
utilised in past three years
MANDAYS REQUIREMENT FOR ACTIVITY
“S”
S.10 Watching
water level in
suburban
sections
1 to N
N: No.of locations where flooding
of track occurs in rainy season,
due to water entering from
built-up area outside.
s:No.of shifts required at the nth
location.
d:No. of days requiring watching
at the nth location. Normally s =
2; d= 60 in Mumbai suburban
sections.
 
d
s 

MANDAYS REQUIREMENT FOR ACTIVITY
“S”
S.10 Watching
water level in
suburban
sections
1 to N
N: No.of locations where flooding
of track occurs in rainy season,
due to water entering from
built-up area outside.
s:No.of shifts required at the nth
location.
d:No. of days requiring watching
at the nth location. Normally s =
2; d= 60 in Mumbai suburban
sections.
 
d
s 

EQUIVALENT LENGTH OF
SPECIAL LAYOUTS
a) Same as per SPECIAL COMMITTEE FORMULA
Turnout 0.1 Km
Diamond 0.1 Km
Diamond crossing with single slip 0.15 Km
Diamond crossing with double slips 0.2 Km
Cross over 0.2 Km
Three-throw 0.2 Km
Scissors cross-over 0.5 Km
Trap 0.02 Km
Double trap 0.04 Km
MULTIPLYING FACTORS
Factor As per Special
Committee
As per MCNTM
A 0.1 and 0.2 for bad and
very bad formations
Same
B =0.25 for > 1.5 D for BG
> 3 D for MG
> 5 D for NG
Linear from 0 to 0.25 for
1 to 2 D for BG,
2 to 4 D for MG
3 to 7 D for NG
thereafter constant at 0.25
C =0 up to rainfall of 200 cm
=0.1 for rainfall of 200 cm
=Linear from 01 to 0.2 for
rainfall 200 to 300cm
=0.2 for rainfall > 300 cm
=0 up to rainfall of 150 cm
= Linear from 0 to 0.2 for
rainfall 150 to 300cm
=0.2 for rainfall > 300 cm
SUMMARY
TYPE MANDAYS/KM ACTIVITY
“T”
MD/KM
ATY “R”
MAC. PACKED BG
(NON- SUB URBAN)
(80+2.3*GMT)X(1+A+B+C) 159
MAN. PACKED BG
(NON SUB URBAN)
(223+8.24*GMT)X(1+A+B+C) 168
MAC. PACKED BG
(HD - SUB URBAN)
(115+2.3*GMT)X(1+A+B+C) 398
MAN. PACKED MG (160+13.56*GMT)X(1+A+B+C) 128
MAN. PACKED NG (105+188*GMT)X(1+A+B+C) 91
SUMMARY
TYPE MANDAYS/KM ACTIVITY
“T”
MD/KM
ATY “R”
MAC. PACKED BG
(NON- SUB URBAN)
(80+2.3*GMT)X(1+A+B+C) 159
MAN. PACKED BG
(NON SUB URBAN)
(223+8.24*GMT)X(1+A+B+C) 168
MAC. PACKED BG
(HD - SUB URBAN)
(115+2.3*GMT)X(1+A+B+C) 398
MAN. PACKED MG (160+13.56*GMT)X(1+A+B+C) 128
MAN. PACKED NG (105+188*GMT)X(1+A+B+C) 91
SUMMARY
TYPE MANDAYS/KM ACTIVITY
“T”
MD/KM
ATY “R”
MAC. PACKED BG
(NON- SUB URBAN)
(80+2.3*GMT)X(1+A+B+C) 159
MAN. PACKED BG
(NON SUB URBAN)
(223+8.24*GMT)X(1+A+B+C) 168
MAC. PACKED BG
(HD - SUB URBAN)
(115+2.3*GMT)X(1+A+B+C) 398
MAN. PACKED MG (160+13.56*GMT)X(1+A+B+C) 128
MAN. PACKED NG (105+188*GMT)X(1+A+B+C) 91
SUMMARY
 Staff strength arrived at by rational formulae
does not include
– LR of 12.5 %
– Posts of Gateman, Mates, Keymen, Artisans, Artisan
helpers, Trollyman, Storeman
– USFD team
– Machine Staff for maintenance or operation
 Report recommended 2% training reserve, Board yet
to take final view
MMU STAFF
 Work load catered by MMU (Machine Packed only)
Main Line Activity
T= 80 + 2.3* GMT
For GMT of 20,
T=126
Bad spots 35 out of 35
Low joints 10 out of 16
SEJ 2 out of 4
Curves 6 out of 10
Casual renewal rail 2 out of 6
Casual sleeper rail 2 out of 6
Repair welding 6 out of 12
63 I.e 50%
40+1.15
GMT
Main Line activity
R= 159
Loading Unloading 12 out of 20
OH of LC 13 out of 13
Bridge sleeper renewal 7 out of
10
Creep pulling 3 out of 5
35
MMU STAFF
 Work load catered by MMU (Machine Packed only)
Running Yard Line
R=177
Bad spots 14 out of 14
Low joints 5 out of 8
Curves 2 out of 6
Casual renewal rail 2 out of 3
Casual sleeper renewal 2 out of 3
Loading Unloading 10 out of 15
35
Gross Equivalent MMU
Mandays i.e GEMM
= Lm(40+1.15 GMT) (1+A+B+C)
+ 35 Lm + 35 Ly
Exp. on MMU 80 % of Emoluments of GEMM=
Annualized cost of SEMMU + Annual
emoluments of MMU staff



CONCEPT OF EMKM
 Committee has proposed Equated Manpower
KM (EMKM) as performance unit in place of
ETKM
 EMKM is defined as numerical equivalent to
0.6 times the number of gang man required
for activities T, R, M, S
– EMKM has been defined based on a
compensator p-way section requiring 1.66
men/KM
RATIONAL FORMULAE
How these are different ?
Zero based approach has been adopted
Formulae have been evolved on rational basis
14 non – suburban sections and 3 HD suburban sections
have been studied on 7 Zonal Railways (
NR,ER,WR,SR,CR,SER,SCR) through direct interaction
with the field Engineers
Rational formulae
What is new ?
Mandays per annum per km for each activity are computed instead
of man power factor
Man power requirement for T & R activities is same irrespective of
the type of sleepers and type of rails i.e., F.P,SWR,LWR
All the sub activities of maintenance of RYL and NRYL are
categorised under activity R (Routine maintenance )
Flexible to encourage formation of Mobile Maintenance Units (
MMUs)
Concept of Equated Manpower Kilometre (EMKM) introduced
EMKM = 0.6 ( G/men per km as per Rational formulae )
Rational formula
 Conclusions
1. As the formulae are arrived at more rationally, there will be saving in the
manpower and at the same time ensures equitable distribution of
manpower in accordance with the work load.
2. The adoption of rational formulae ensures uniformity of manpower
provision commensurate with work load.
3. Optimisation of manpower can be achieved
4. uniform degree of track maintenance and equitable allotment of funds.
5. The concept of EMKM enables to evaluate the manpower requirement
for optimal utilization
6. The formulae are more flexible to allow for redistribution of strength of
the various gangs as per the age profile of track.
7. The formulae allows for introduction of Mobile Maintenance Units
Gang Strenght Formula.ppt

More Related Content

What's hot

CULVERTS.pdf
CULVERTS.pdfCULVERTS.pdf
CULVERTS.pdf
ShadrackOsoro1
 
Highway engineering
Highway engineeringHighway engineering
Highway engineering
Er. Akash Gupta
 
Spillways and Diversion Headwork's
Spillways and Diversion Headwork'sSpillways and Diversion Headwork's
Spillways and Diversion Headwork's
kartikchourasia
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
KHUSHBU SHAH
 
Hill_Roads
Hill_RoadsHill_Roads
Hill_Roads
ArAayushGoel
 
Nepal bridge standards 2067
Nepal bridge standards 2067Nepal bridge standards 2067
Nepal bridge standards 2067
Naresh Prasad Keshari
 
railway and bridge engineering ppt.pptx
railway and bridge engineering ppt.pptxrailway and bridge engineering ppt.pptx
railway and bridge engineering ppt.pptx
RESHMAFEGADE
 
Highway drainage system and how it works
Highway drainage system and how it worksHighway drainage system and how it works
Highway drainage system and how it works
Rana Ibrahim
 
2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...
2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...
2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...
Malyar Talash
 
Highway Vertical Alignment
Highway Vertical AlignmentHighway Vertical Alignment
Highway Vertical Alignment
AkshathaBhandary
 
3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash
Malyar Talash
 
4. Introduction to DSS LSM.pdf
4. Introduction to DSS LSM.pdf4. Introduction to DSS LSM.pdf
4. Introduction to DSS LSM.pdf
DEVNAIK7
 
Alighnment & horizontal alignment of highway (transportation engineering)
Alighnment & horizontal alignment of highway (transportation engineering)Alighnment & horizontal alignment of highway (transportation engineering)
Alighnment & horizontal alignment of highway (transportation engineering)
Civil Zone
 
Chapter 6 design of irrigation channel1
Chapter 6 design of irrigation channel1Chapter 6 design of irrigation channel1
Chapter 6 design of irrigation channel1Mulugeta Abera
 
Chapter 1 introduction to transport system and planning
Chapter 1 introduction to transport system and planningChapter 1 introduction to transport system and planning
Chapter 1 introduction to transport system and planning
ephaceurla
 
Design of vertical alignment
Design of vertical alignmentDesign of vertical alignment
Design of vertical alignment
Wyman Words
 
Planning for system of transportation
Planning for system of transportationPlanning for system of transportation
Planning for system of transportation
KU Leuven
 
Highway Geometric Design control and criteria-2
Highway Geometric Design control and criteria-2Highway Geometric Design control and criteria-2
Highway Geometric Design control and criteria-2
Muhammad Faisal
 
History of road in Nepal
History of road in NepalHistory of road in Nepal
History of road in Nepal
pnbastola
 
Simple circular curve
Simple circular curveSimple circular curve
Simple circular curve
Kathan Sindhvad
 

What's hot (20)

CULVERTS.pdf
CULVERTS.pdfCULVERTS.pdf
CULVERTS.pdf
 
Highway engineering
Highway engineeringHighway engineering
Highway engineering
 
Spillways and Diversion Headwork's
Spillways and Diversion Headwork'sSpillways and Diversion Headwork's
Spillways and Diversion Headwork's
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
 
Hill_Roads
Hill_RoadsHill_Roads
Hill_Roads
 
Nepal bridge standards 2067
Nepal bridge standards 2067Nepal bridge standards 2067
Nepal bridge standards 2067
 
railway and bridge engineering ppt.pptx
railway and bridge engineering ppt.pptxrailway and bridge engineering ppt.pptx
railway and bridge engineering ppt.pptx
 
Highway drainage system and how it works
Highway drainage system and how it worksHighway drainage system and how it works
Highway drainage system and how it works
 
2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...
2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...
2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...
 
Highway Vertical Alignment
Highway Vertical AlignmentHighway Vertical Alignment
Highway Vertical Alignment
 
3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash
 
4. Introduction to DSS LSM.pdf
4. Introduction to DSS LSM.pdf4. Introduction to DSS LSM.pdf
4. Introduction to DSS LSM.pdf
 
Alighnment & horizontal alignment of highway (transportation engineering)
Alighnment & horizontal alignment of highway (transportation engineering)Alighnment & horizontal alignment of highway (transportation engineering)
Alighnment & horizontal alignment of highway (transportation engineering)
 
Chapter 6 design of irrigation channel1
Chapter 6 design of irrigation channel1Chapter 6 design of irrigation channel1
Chapter 6 design of irrigation channel1
 
Chapter 1 introduction to transport system and planning
Chapter 1 introduction to transport system and planningChapter 1 introduction to transport system and planning
Chapter 1 introduction to transport system and planning
 
Design of vertical alignment
Design of vertical alignmentDesign of vertical alignment
Design of vertical alignment
 
Planning for system of transportation
Planning for system of transportationPlanning for system of transportation
Planning for system of transportation
 
Highway Geometric Design control and criteria-2
Highway Geometric Design control and criteria-2Highway Geometric Design control and criteria-2
Highway Geometric Design control and criteria-2
 
History of road in Nepal
History of road in NepalHistory of road in Nepal
History of road in Nepal
 
Simple circular curve
Simple circular curveSimple circular curve
Simple circular curve
 

Similar to Gang Strenght Formula.ppt

Rail Grinding Machine:A Basic approach
Rail Grinding Machine:A Basic approachRail Grinding Machine:A Basic approach
Rail Grinding Machine:A Basic approach
Prem Prakash Kumar
 
Prashant patel
Prashant patelPrashant patel
Prashant patel
PRASHANT KUMAR PATEL
 
Download-manuals-surface water-manual-surfacewatero&m-norms
 Download-manuals-surface water-manual-surfacewatero&m-norms Download-manuals-surface water-manual-surfacewatero&m-norms
Download-manuals-surface water-manual-surfacewatero&m-normshydrologyproject0
 
Download-manuals-surface water-manual-surfacewatero&m-norms
 Download-manuals-surface water-manual-surfacewatero&m-norms Download-manuals-surface water-manual-surfacewatero&m-norms
Download-manuals-surface water-manual-surfacewatero&m-normshydrologywebsite1
 
Planning track maintenance.ppt
Planning track maintenance.pptPlanning track maintenance.ppt
Planning track maintenance.ppt
AfendiAriff
 
ENGINEERING PPT BOX PUSHING ON PUNE DIVISION
ENGINEERING PPT BOX PUSHING ON PUNE DIVISIONENGINEERING PPT BOX PUSHING ON PUNE DIVISION
ENGINEERING PPT BOX PUSHING ON PUNE DIVISION
bridgelc
 
Goverment Of India Trainee at Kanchrapara Workshop, Eastern Railway electr...
Goverment Of India Trainee at Kanchrapara Workshop, Eastern Railway    electr...Goverment Of India Trainee at Kanchrapara Workshop, Eastern Railway    electr...
Goverment Of India Trainee at Kanchrapara Workshop, Eastern Railway electr...SUBHAMOY SINGHA ROY
 
ROAD SAFETY AUDIT
ROAD SAFETY AUDITROAD SAFETY AUDIT
ROAD SAFETY AUDIT
lokeshthondamanati
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)
Malyar Talash
 
Featutes of New Guideline for the Design of Flexible Pavement.pptx
Featutes of New Guideline for the Design of Flexible Pavement.pptxFeatutes of New Guideline for the Design of Flexible Pavement.pptx
Featutes of New Guideline for the Design of Flexible Pavement.pptx
bnraj2
 
Asset Velocity
Asset VelocityAsset Velocity
Asset Velocity
findram
 
Summer Internship Report.pptx
Summer Internship Report.pptxSummer Internship Report.pptx
Summer Internship Report.pptx
Deepak37004
 
Subsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the futureSubsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the futureStatoil
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverter
RidhoIrawan12
 
Doubling presentation
Doubling  presentationDoubling  presentation
Doubling presentation
Neha Singh
 
Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading Mechanism
IRJET Journal
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)coderweb
 
RAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERINGRAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERING
bhavin_pindoriya
 
Assessment the Need of Al Kut City for Solid Waste Transfer Station
Assessment the Need of Al Kut City for Solid Waste Transfer StationAssessment the Need of Al Kut City for Solid Waste Transfer Station
Assessment the Need of Al Kut City for Solid Waste Transfer Station
IRJET Journal
 
Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution . Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution .
gunjatetm
 

Similar to Gang Strenght Formula.ppt (20)

Rail Grinding Machine:A Basic approach
Rail Grinding Machine:A Basic approachRail Grinding Machine:A Basic approach
Rail Grinding Machine:A Basic approach
 
Prashant patel
Prashant patelPrashant patel
Prashant patel
 
Download-manuals-surface water-manual-surfacewatero&m-norms
 Download-manuals-surface water-manual-surfacewatero&m-norms Download-manuals-surface water-manual-surfacewatero&m-norms
Download-manuals-surface water-manual-surfacewatero&m-norms
 
Download-manuals-surface water-manual-surfacewatero&m-norms
 Download-manuals-surface water-manual-surfacewatero&m-norms Download-manuals-surface water-manual-surfacewatero&m-norms
Download-manuals-surface water-manual-surfacewatero&m-norms
 
Planning track maintenance.ppt
Planning track maintenance.pptPlanning track maintenance.ppt
Planning track maintenance.ppt
 
ENGINEERING PPT BOX PUSHING ON PUNE DIVISION
ENGINEERING PPT BOX PUSHING ON PUNE DIVISIONENGINEERING PPT BOX PUSHING ON PUNE DIVISION
ENGINEERING PPT BOX PUSHING ON PUNE DIVISION
 
Goverment Of India Trainee at Kanchrapara Workshop, Eastern Railway electr...
Goverment Of India Trainee at Kanchrapara Workshop, Eastern Railway    electr...Goverment Of India Trainee at Kanchrapara Workshop, Eastern Railway    electr...
Goverment Of India Trainee at Kanchrapara Workshop, Eastern Railway electr...
 
ROAD SAFETY AUDIT
ROAD SAFETY AUDITROAD SAFETY AUDIT
ROAD SAFETY AUDIT
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)
 
Featutes of New Guideline for the Design of Flexible Pavement.pptx
Featutes of New Guideline for the Design of Flexible Pavement.pptxFeatutes of New Guideline for the Design of Flexible Pavement.pptx
Featutes of New Guideline for the Design of Flexible Pavement.pptx
 
Asset Velocity
Asset VelocityAsset Velocity
Asset Velocity
 
Summer Internship Report.pptx
Summer Internship Report.pptxSummer Internship Report.pptx
Summer Internship Report.pptx
 
Subsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the futureSubsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the future
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverter
 
Doubling presentation
Doubling  presentationDoubling  presentation
Doubling presentation
 
Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading Mechanism
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
 
RAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERINGRAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERING
 
Assessment the Need of Al Kut City for Solid Waste Transfer Station
Assessment the Need of Al Kut City for Solid Waste Transfer StationAssessment the Need of Al Kut City for Solid Waste Transfer Station
Assessment the Need of Al Kut City for Solid Waste Transfer Station
 
Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution . Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution .
 

Recently uploaded

Zeeshan Hayat - A Guide to Efficient Business Management.pdf
Zeeshan Hayat - A Guide to Efficient Business Management.pdfZeeshan Hayat - A Guide to Efficient Business Management.pdf
Zeeshan Hayat - A Guide to Efficient Business Management.pdf
Zeeshan Hayat
 
在线办理(uofc毕业证书)芝加哥大学毕业证学历学位证书原版一模一样
在线办理(uofc毕业证书)芝加哥大学毕业证学历学位证书原版一模一样在线办理(uofc毕业证书)芝加哥大学毕业证学历学位证书原版一模一样
在线办理(uofc毕业证书)芝加哥大学毕业证学历学位证书原版一模一样
pv4uhplv
 
Get To Know About Salma Karina Hayat.pdf
Get To Know About Salma Karina Hayat.pdfGet To Know About Salma Karina Hayat.pdf
Get To Know About Salma Karina Hayat.pdf
Salma Karina Hayat
 
在线办理(加拿大Concordia毕业证书)康考迪亚大学毕业证学历证书一模一样
在线办理(加拿大Concordia毕业证书)康考迪亚大学毕业证学历证书一模一样在线办理(加拿大Concordia毕业证书)康考迪亚大学毕业证学历证书一模一样
在线办理(加拿大Concordia毕业证书)康考迪亚大学毕业证学历证书一模一样
ch775c0l
 
Showcase Portfolio- Marian Andrea Tana.pdf
Showcase Portfolio- Marian Andrea Tana.pdfShowcase Portfolio- Marian Andrea Tana.pdf
Showcase Portfolio- Marian Andrea Tana.pdf
MarianAndreaSTana
 
Legal Mandates of technopreneurship.pptx
Legal Mandates of technopreneurship.pptxLegal Mandates of technopreneurship.pptx
Legal Mandates of technopreneurship.pptx
JadielByronAntonio
 
Michael Economou - Don't build a marketplace.pdf
Michael Economou - Don't build a marketplace.pdfMichael Economou - Don't build a marketplace.pdf
Michael Economou - Don't build a marketplace.pdf
Michael Oikonomou
 
Create a spend money transaction during bank reconciliation.pdf
Create a spend money transaction during bank reconciliation.pdfCreate a spend money transaction during bank reconciliation.pdf
Create a spend money transaction during bank reconciliation.pdf
andreakaterasco
 

Recently uploaded (8)

Zeeshan Hayat - A Guide to Efficient Business Management.pdf
Zeeshan Hayat - A Guide to Efficient Business Management.pdfZeeshan Hayat - A Guide to Efficient Business Management.pdf
Zeeshan Hayat - A Guide to Efficient Business Management.pdf
 
在线办理(uofc毕业证书)芝加哥大学毕业证学历学位证书原版一模一样
在线办理(uofc毕业证书)芝加哥大学毕业证学历学位证书原版一模一样在线办理(uofc毕业证书)芝加哥大学毕业证学历学位证书原版一模一样
在线办理(uofc毕业证书)芝加哥大学毕业证学历学位证书原版一模一样
 
Get To Know About Salma Karina Hayat.pdf
Get To Know About Salma Karina Hayat.pdfGet To Know About Salma Karina Hayat.pdf
Get To Know About Salma Karina Hayat.pdf
 
在线办理(加拿大Concordia毕业证书)康考迪亚大学毕业证学历证书一模一样
在线办理(加拿大Concordia毕业证书)康考迪亚大学毕业证学历证书一模一样在线办理(加拿大Concordia毕业证书)康考迪亚大学毕业证学历证书一模一样
在线办理(加拿大Concordia毕业证书)康考迪亚大学毕业证学历证书一模一样
 
Showcase Portfolio- Marian Andrea Tana.pdf
Showcase Portfolio- Marian Andrea Tana.pdfShowcase Portfolio- Marian Andrea Tana.pdf
Showcase Portfolio- Marian Andrea Tana.pdf
 
Legal Mandates of technopreneurship.pptx
Legal Mandates of technopreneurship.pptxLegal Mandates of technopreneurship.pptx
Legal Mandates of technopreneurship.pptx
 
Michael Economou - Don't build a marketplace.pdf
Michael Economou - Don't build a marketplace.pdfMichael Economou - Don't build a marketplace.pdf
Michael Economou - Don't build a marketplace.pdf
 
Create a spend money transaction during bank reconciliation.pdf
Create a spend money transaction during bank reconciliation.pdfCreate a spend money transaction during bank reconciliation.pdf
Create a spend money transaction during bank reconciliation.pdf
 

Gang Strenght Formula.ppt

  • 1. GANG STRENGTH CALCULATION USING RATIONAL FORMULA Presented By K.A.J.BABU , ADEN/E/KGP,S.E.RLY C.NAGARAJU, AXEN/C/KRMR,S.C.RLY Under the Guidance of Sri. PRAVEEN KUMAR,P/C,IRICEN/PUNE
  • 2. Gang strength  Gang strength calculation by Maflin”s formula Modified Maflin’s formula Special Committee formula Rational formulae
  • 3. MAFLIN’S FORMULA Adopted in 1931 No of gangmen required = Unit-per- mile*2.5 Unit- per – mile depending on the traffic carried Man power factor is constant irrespective of track gauge
  • 4. Revised Maflin’s formula Evolved by Lobo committee in 1959 Implemented in 1962 Gang strength was based on “Equated Track Mile” ETM depends on the traffic density, type of formation, curved alignment and annual rainfall
  • 5. Special committee formula Adopted in 1979 N = 0.95 * M * K * E  N is the no of gang men  M is man power factor ( 1.47 for B.G and 1.21 for M.G and N.G)  K is the correction factor due to modernisation of track,methods of maintenance  E is Equated Track Kilometre ( ETKM)
  • 6. Special committee formula  Correction factor Type of track Mmethod of maitenance Convent ,DTM,M SP Mechanised Fish plated 1.00 0.80 SWR 0.95 0.75 LWR on ws/ms 0.85 0.60 LWR on psc - 0.50
  • 7. WHY SPECIAL COMMITTEE FORMULA NEEDS REPLACEMENT Gang is to carry out 12 activities and other 16 activities are by engaging casual labourer No uniformity of overall manpower per ETKM over the railways Maintance cost per ETKM is varying among Zonal Railways Decasualisation effect Aspect of engagement of safaiwalas for filth removal
  • 8. --Contd Aspect of carrying out monsoon patrolling, watching vulnerable locations and security patrolling by out side agencies Ageing of gang men Absenteeism among gang men, as much as 60% To identify the works to be executed through contract to limit the manpower Educational profile of the gangmen remains deficient while mechanisation is increasingly adopted
  • 9. Modifying Special Committee formula Railway Board in 1996 constituted a committee Terms of reference To study the special committee formula and suggest modified formula To take into account decasualisation done effect of maintenance and track modernisation while modifying the gang strenth formula
  • 10. Categorisation of tracks Non Sub urban sections Machine Packed Manually Packed Sub urban section,Machine packed High density
  • 11. H D suburb section  Criteria for High Density Sub urban Section  The train frequency per hour, on any line or in a sub section should exceed 8  The required maintenance works can be completed only by way of availing night blocks • PHOD is the competent authority to classify a suburban section as ‘HDSL’
  • 12. H D suburb sections  Special features of H D suburb section  High frequency of trains  Encroachments  Corridor night blocks and integrated mega blocks  Large number of turn outs  Lack of drainage  Extensive track circuits 
  • 13. CLASSIFICATION OF MAINTENANCE ACTIVITIES PRIMARY MAINTENCE ACTIVITIES  Directly related to P Way maintenance  Need manpower based on the continuous length of the track AUXILLIARY MAINTENANCE ACTIVITIES  For upkeep of P Way as a whole  Need manpower based on the localised problems,special features and geographical nature of P way section
  • 14. Classification -- contd PRIMARY MAINTENANCE ACTIVITIES  Activity T – Affected by traffic density  Activity R – Routine in nature AUXILLARY MAINTENANCE ACTIVITIES  Activity M – Miscellaneous  Activity S – Site specific
  • 15. Activity T ( For machine packed track)  T1 Slack attention to  Bad spots  Low joints  SEJ  Minor curve realignment  T2 For Tie Tamper working  Pre-tamping operation  Along with tamper  Post tamping operations  T3 Casual renewals  Rails  Sleepers  Fasteners  T4 Repair Welding
  • 16. Activity T ( For manually packed track)  T1 Through packing  T2 Slack attention to  Bad spots  Low joints  SEJ  Minor curve realignment  T3 Casual renewals  Rails  Sleepers  Fasteners  T4 Creep pulling
  • 17. Activity T ( For machine packed track HD suburban)  T1 Slack attention to  Bad spots  Low joints  SEJ  Minor curve realignment  T2 For Tie Tamper working  Pre-tamping operation  Along with tamper  Post tamping operations  T3 Casual renewals  Rails  Sleepers  Fasteners  T4 Repair Welding
  • 18. Activity R ( For machine packed track)  R1 Lubrication of ERCs  R2 Shallow screening (1/5 length)  R3 Loading , leading & unloading  R4 Overhauling of level crossing  R5 Watching caution spot and miscellaneous  R6 Tree cutting for visibility  R7 Lubrication of rails in Curves  R8 Accident relief and carcass removal  R9 Bridge sleeper attention and renewal  R10 Pre monsoon attention such as clearing of  drains, waterways, deweeding etc  R11 Creep pulling (approach of bridges and turn outs)  R12 Rectifying damage to LC
  • 19. Activity R ( For manually packed track)  R1 Lubrication of ERCs  R2 Shallow screening  R3 Loading , leading & unloading  R4 Overhauling of level crossing  R5 Watching caution spot and miscellaneous  R6 Tree cutting for visibility  R7 Lubrication of rails in Curves  R8 Accident relief and carcass removal  R9 Bridge sleeper attention and renewal  R10 Pre monsoon attention  R11 Creep pulling  R12 Rectifying damafe to LC
  • 20. Activity R ( For machine packed HD suburban track)  R1 Through packing  R2 Shallow screening (1/5 length)  R3 Loading , leading & unloading  R4 Lubrication of ERCs  R5 Overhauling of level crossing  R6 Watching caution spot and look out men  R7 Tree cutting for visibility  R8 Lubrication of rails in Curves  R9 Accident relief and carcass removal in run over cases  R10 Bridge sleeper attention and renewal  R11 Pre monsoon attention  R12 Creep pulling  R13 Rectifying damage to LC  R14 Painting of weld collars  R 15 Emergency attention  R 16 Extra sssistance to key man & B/smith  R17 Extra work in Night blocks  R 18 Extra assistance for S&T Items
  • 21. Activity M  M1 Monsoon patrolling  M2 Hot weather patrolling  M3 Cold weather patrolling  M4 Watching vulnerable locations  M5 Gate keeping at level crossings  M6 Rest giving for keyman  M7 Waterman duty  M8 Store watchman duty
  • 22. Activity S  S1 Tunnel maintenance  S2 Bridge substructure maintenance  S3 Long girder maintenance  S4 Extra due to sharp curves, deep cutting etc  S5 Track on extremely bad formation  S6 Lookout man duty  S7 Fog signal man duty  S8 Filth removal from track  S9 Security patrolling  S10Watching of water level in suburban section
  • 23. Work to be done through contract 1. Formation treatment 2. Ballasting 3. Deep screening 4. Sub ballast and ballast layer 5. Heavy repair to track including lifting 6. TRR,TSR,TFR 7. Complete ROC 8. Complete renewal of P&C , SEJs , traps 9. Resurfacing of crossing and switch rails 10. Loading/unloading of P way material in bulk 11. Lorrying of P way materials in bulk 12. Security of material in depot which is closed and locked
  • 24. Work to be done through contract 13. Painting of rails and weld collars 14. Painting of bridge girders 15. Heavy repair to formation, cutting,side drains &c/w drains 16. Providing and reparing road surface at LC 17. Heavy repair to bridges, protecion works,river training works and tunnels 18. Removal of major sand breaches 19. Restoration works following breaches, accidents 20. Clearing of vegetation in P/F and in the vicinity of tracks in coaching and goods yards, repairs to depots and work shops of Engg, Mech, Elec and S&T
  • 25.  Authority for certifying the correctness of factors in activities M & S  No of mandays for monsoon patrolling – CTE/CBE  Need for hot/ cold patrolling – CTE  No.of days for watching vulnerable locations- CTE/CBE  Need for store w/man duty – Sr DEN/C00RD  Existance of extremely bad formation – CTE  Track Stretches with poor visibility – Sr DEN/Coord  Need for fog signal duty – Sr DEN/Coord  Need for removal of filth – Sr DEN/Coord  Need for security patrol – Sr DEN/Coord  No of days for watching water level in suburb- SrDEN/Co
  • 26. RATIONAL FORMULAE MANPOWER MANPOWER NORMS FOR NORMS FOR VARIOUS ACTIVITIES VARIOUS ACTIVITIES
  • 27. Rational formulae How the manpower requirement arrived at? Activties T & R For Main line  Norms as per the actual manpower utilised on various sections on various zones and analyzing the same scientifically  Periodicity of shallow screening has been changed to 5 yr instead of 3 yr  Average spacing of the LC has been taken as 1.5 km  Quantum of work in shallow screening in PSC sleeper track is 4 sl / head
  • 28. Contd For RYL and NRYL 1 KM of NRYL is taken as equivalent to 2/3 km of RYL Factors A,B and C are not considered Considered as ‘R’ activity
  • 29. MACHINE PACKED “BG” (NON SUBURBAN) MANDAYS REQUIREMENT/YEAR/KM.  Activity “T” : (80 +2.3GMT)*(1+A+B+C)  Activity “R” : 159 »“R” Modified with (+) 28 as per Board’s letter »+28 on a/c of overhauling 4 sleeper instead of 6 per man for concrete sleepers
  • 30. Rational formulae MANDAYS REQD. FOR ACTIVITY- T, MACHINE PACKED (NON- SUBURBAN) GMT-20 65 Total T1 10 As reqd. MINOR CURVE REALIGNMENT 4 6x8/12 6 times/yr., 8 sl/SEJ, 12 sl/head SEJ (1 No. PER KM) 16 12x4x4/12 12 GJ/LJ 4 TIMES, 4sl/jts 12 sl/head LOW JOINTS (FP OR WELDED),GJ 35 1660/(4x12) 12 SL./HEAD, ¼ LENGTH BAD SPOTS ‘T1’ SLACK ATTENTION MD Requirement Norm Activity
  • 31. Rational formulae MANDAYS REQD. FOR ACTIVITY- T, MACHINE PACKED (NON- SUBURBAN) GMT-20 10 20/2 20 men/Km PRE-TAMPING OPERATIONS 27 Total T2 14 28/2 28 men/Km POST TAMING OPERATIONS 3 10x6/(10x2) 10 men for one week for 10 Km gang length ALONG WITH TAMPER 2 year cycle T2- FOR TIE TAMPER WORKING MD Requirement Norm Activity
  • 32. Rational formulae MANDAYS REQD. FOR ACTIVITY- T, MACHINE PACKED (NON- SUBURBAN) GMT-20 126 Total T1 + T2 + T3 + T4 12 12 men per failure/year T4- Repair Welding 6 60/10 60 mandays /gang length of 10 Km. Rails 22 Total T3 10 100/10 100 mandays /gang length of 10 Km. Fastening 6 60/10 60 mandays /gang length of 10 Km. Sleepers T3- Casual Renewal MD Require ment Norm Activity T= 80 + 2.3 GMT= 80 + 2.3 * 20 = 126
  • 33. Rational formulae MANDAYS REQD. FOR ACTIVITY- R, MACHINE PACKED (NON- SUBURBAN) GMT-20 4 ,, R7- Lubrication of Rails in curves 10 ,, R6- Tree cutting for visibility 10 Field data R5- Watching caution spots 13 20/1.5 1 LC/ 1.5 Km, 20 men/lc R4- Over hauling of LC 20 Field data R3-Loading, Leading & unloading 55 1660/(5*6) 6 sl/head, 1/5 length R2- Shallow Screening 2 Assistance to K-man R1- Lubrication of ERC MD Require ment Norm Activity
  • 34. Rational formulae MANDAYS REQD. FOR ACTIVITY- R, MACHINE PACKED (NON- SUBURBAN) GMT-20 159 TOTAL R 2 ,, R12- Rectifying damage to LC gates and posts 5 ,, R11- Creep Pulling 18 ,, R10- Pre monsoon attention like waterway clearance, cess repair, deweeding etc 10 ,, R9- Bridge sleeper attention and removal 10 Field data R8- Accident Relief- Carcass removal MD Require ment Norm Activity
  • 35. Rational formulae MANUALLY PACKED “BG” (NON SUBURBAN) MANDAYS REQUIREMENT/YEAR/KM.  Activity “T” : (223+8.24GMT)*(1+A+B+C)  Activity “R” : 168 »+28 on a/c of overhauling 4 sleeper instead of 6 per man for concrete sleepers
  • 36. Rational formulae MANUALLY PACKED “MG” MANDAYS REQUIREMENT/YEAR/KM.  Activity “T”: (160+13.56GMT)*(1+A+B+C)  Activity “R”: 128
  • 37. Rational formulae MANUALLY PACKED “NG” MANDAYS REQUIREMENT/YEAR/KM.  Activity “T”: (105+188GMT)*(1+A+B+C) Max. value of (105+188GMT) is 180  Activity “R”: 91
  • 38. Rational formulae HIGH DENSITY SUBURBAN MACHINE PACKED MANDAYS REQUIREMENT/YEAR/KM.  Activity “T” : (115 +2.3GMT)*(1+A+B+C)  Activity “R” : 398
  • 39. Rational formulae RUNNING YARD LINE(RYL) and NON RUNNING YARD LINE(NRYL) RLY mandays are 74 % to 79% of R & T activities for mainline with “0” GMT NRYL mandays are 2/3rd of RLY mandays Factors A, B, C not to be applied *This includes equivalent MMU mandays 102 152 198 - NRYL 153 228 297 177* RYL NG Manually packed MG Manually packed Manually packed Machine packed BG
  • 40. MANDAYS REQUIREMENT FOR ACTIVITY “M” M.1 Monsoon Patrolling N: Total No. of beat-lengths D: No.of days needing patrolling in a year in the nth beat length. b: No.of beats in the nth beat length. s: No. of shifts in the nth beat length m: No.of men in each shift in the nth beat-length =2 in area infested with wild animals/ terrorists; otherwise m=1. 1 to N   m s b D    
  • 41. MANDAYS REQUIREMENT FOR ACTIVITY “M” M.2 Hot weather patrolling of LWR track Lw X 30 M.3 Cold weather patrolling of LWR track Lw X 12 Lw: Length of LWR track in km, on single line basis
  • 42. MANDAYS REQUIREMENT FOR ACTIVITY “M” M.4 Watching vulnerable locations 1 to N M.5 Gate keeping at level crossings 1 to N N: No. of vulnerable locations s: No.of duty shifts at the nth location d:No.of days of watching at the nth location in a year. N: No. of Engg level crossings s: No.of duty shifts at the nth level crossing Ng: No. of Engg Gatekeeper posts sanctioned (Excluding LR)   d s   Ng s 294 * 365  
  • 43. MANDAYS REQUIREMENT FOR ACTIVITY “M” M.6 Rest giving for keymen K(365-294) M.7 Waterman duty N * 294 M.8 Store- watchman duty N * 3 * 365 K: No. of Keyman beats N: No. of Gangs N: No. of stores in addition to SSE HQ (Not more than 2)
  • 44. MANDAYS REQUIREMENT FOR ACTIVITY “S” S.1 Tunnel Maintenance 1.2* 0.29* 1 to N S.2 Bridge substructure maintenance 1.1* 0.29* 1 to N N: No. of tunnels l: length of the nth tunnel, in metre r: No.of tracks in the nth tunnel. N: No.of bridges b: Lineal waterway of the nth bridge, in metre r: No. of tracks on the nth bridge.   r l     r b  
  • 45. MANDAYS REQUIREMENT FOR ACTIVITY “S” S.3 Long Girder Maintenance 0.64* 1 to N S.4 Sharp curves > 3 D in BG > 6 D in MG Lc * 294 N: No. of bridges each having more than 150m lineal waterway b: Lineal waterway of the nth bridge, in metre r: No. of tracks on the nth bridge Lc: Total Length of such curve   r b  
  • 46. MANDAYS REQUIREMENT FOR ACTIVITY “S” S.5 Track maintenance in extremely bad formation 0.6 * 1 to N S.6 look out man 294 1 to N N: No.of locations where track needs more than 4 attentions in a year l: length of track in the nth location, in metres N: No. of gangs v: length of track with poor visibility in the nth gang length g: length of the nth gang   g v /    l 
  • 47. MANDAYS REQUIREMENT FOR ACTIVITY “S” S.7 Fog signalman Mf / 3 S.8 Filth removal from track f * 294 S.9 Security Patrolling Ms / 3 Mf: Total Mandays actually utilised in past three years f: No. of gangs having this kind of problem Ms: Total Mandays actually utilised in past three years
  • 48. MANDAYS REQUIREMENT FOR ACTIVITY “S” S.10 Watching water level in suburban sections 1 to N N: No.of locations where flooding of track occurs in rainy season, due to water entering from built-up area outside. s:No.of shifts required at the nth location. d:No. of days requiring watching at the nth location. Normally s = 2; d= 60 in Mumbai suburban sections.   d s  
  • 49. MANDAYS REQUIREMENT FOR ACTIVITY “S” S.10 Watching water level in suburban sections 1 to N N: No.of locations where flooding of track occurs in rainy season, due to water entering from built-up area outside. s:No.of shifts required at the nth location. d:No. of days requiring watching at the nth location. Normally s = 2; d= 60 in Mumbai suburban sections.   d s  
  • 50. EQUIVALENT LENGTH OF SPECIAL LAYOUTS a) Same as per SPECIAL COMMITTEE FORMULA Turnout 0.1 Km Diamond 0.1 Km Diamond crossing with single slip 0.15 Km Diamond crossing with double slips 0.2 Km Cross over 0.2 Km Three-throw 0.2 Km Scissors cross-over 0.5 Km Trap 0.02 Km Double trap 0.04 Km
  • 51. MULTIPLYING FACTORS Factor As per Special Committee As per MCNTM A 0.1 and 0.2 for bad and very bad formations Same B =0.25 for > 1.5 D for BG > 3 D for MG > 5 D for NG Linear from 0 to 0.25 for 1 to 2 D for BG, 2 to 4 D for MG 3 to 7 D for NG thereafter constant at 0.25 C =0 up to rainfall of 200 cm =0.1 for rainfall of 200 cm =Linear from 01 to 0.2 for rainfall 200 to 300cm =0.2 for rainfall > 300 cm =0 up to rainfall of 150 cm = Linear from 0 to 0.2 for rainfall 150 to 300cm =0.2 for rainfall > 300 cm
  • 52. SUMMARY TYPE MANDAYS/KM ACTIVITY “T” MD/KM ATY “R” MAC. PACKED BG (NON- SUB URBAN) (80+2.3*GMT)X(1+A+B+C) 159 MAN. PACKED BG (NON SUB URBAN) (223+8.24*GMT)X(1+A+B+C) 168 MAC. PACKED BG (HD - SUB URBAN) (115+2.3*GMT)X(1+A+B+C) 398 MAN. PACKED MG (160+13.56*GMT)X(1+A+B+C) 128 MAN. PACKED NG (105+188*GMT)X(1+A+B+C) 91
  • 53. SUMMARY TYPE MANDAYS/KM ACTIVITY “T” MD/KM ATY “R” MAC. PACKED BG (NON- SUB URBAN) (80+2.3*GMT)X(1+A+B+C) 159 MAN. PACKED BG (NON SUB URBAN) (223+8.24*GMT)X(1+A+B+C) 168 MAC. PACKED BG (HD - SUB URBAN) (115+2.3*GMT)X(1+A+B+C) 398 MAN. PACKED MG (160+13.56*GMT)X(1+A+B+C) 128 MAN. PACKED NG (105+188*GMT)X(1+A+B+C) 91
  • 54. SUMMARY TYPE MANDAYS/KM ACTIVITY “T” MD/KM ATY “R” MAC. PACKED BG (NON- SUB URBAN) (80+2.3*GMT)X(1+A+B+C) 159 MAN. PACKED BG (NON SUB URBAN) (223+8.24*GMT)X(1+A+B+C) 168 MAC. PACKED BG (HD - SUB URBAN) (115+2.3*GMT)X(1+A+B+C) 398 MAN. PACKED MG (160+13.56*GMT)X(1+A+B+C) 128 MAN. PACKED NG (105+188*GMT)X(1+A+B+C) 91
  • 55. SUMMARY  Staff strength arrived at by rational formulae does not include – LR of 12.5 % – Posts of Gateman, Mates, Keymen, Artisans, Artisan helpers, Trollyman, Storeman – USFD team – Machine Staff for maintenance or operation  Report recommended 2% training reserve, Board yet to take final view
  • 56. MMU STAFF  Work load catered by MMU (Machine Packed only) Main Line Activity T= 80 + 2.3* GMT For GMT of 20, T=126 Bad spots 35 out of 35 Low joints 10 out of 16 SEJ 2 out of 4 Curves 6 out of 10 Casual renewal rail 2 out of 6 Casual sleeper rail 2 out of 6 Repair welding 6 out of 12 63 I.e 50% 40+1.15 GMT Main Line activity R= 159 Loading Unloading 12 out of 20 OH of LC 13 out of 13 Bridge sleeper renewal 7 out of 10 Creep pulling 3 out of 5 35
  • 57. MMU STAFF  Work load catered by MMU (Machine Packed only) Running Yard Line R=177 Bad spots 14 out of 14 Low joints 5 out of 8 Curves 2 out of 6 Casual renewal rail 2 out of 3 Casual sleeper renewal 2 out of 3 Loading Unloading 10 out of 15 35 Gross Equivalent MMU Mandays i.e GEMM = Lm(40+1.15 GMT) (1+A+B+C) + 35 Lm + 35 Ly Exp. on MMU 80 % of Emoluments of GEMM= Annualized cost of SEMMU + Annual emoluments of MMU staff   
  • 58. CONCEPT OF EMKM  Committee has proposed Equated Manpower KM (EMKM) as performance unit in place of ETKM  EMKM is defined as numerical equivalent to 0.6 times the number of gang man required for activities T, R, M, S – EMKM has been defined based on a compensator p-way section requiring 1.66 men/KM
  • 59. RATIONAL FORMULAE How these are different ? Zero based approach has been adopted Formulae have been evolved on rational basis 14 non – suburban sections and 3 HD suburban sections have been studied on 7 Zonal Railways ( NR,ER,WR,SR,CR,SER,SCR) through direct interaction with the field Engineers
  • 60. Rational formulae What is new ? Mandays per annum per km for each activity are computed instead of man power factor Man power requirement for T & R activities is same irrespective of the type of sleepers and type of rails i.e., F.P,SWR,LWR All the sub activities of maintenance of RYL and NRYL are categorised under activity R (Routine maintenance ) Flexible to encourage formation of Mobile Maintenance Units ( MMUs) Concept of Equated Manpower Kilometre (EMKM) introduced EMKM = 0.6 ( G/men per km as per Rational formulae )
  • 61. Rational formula  Conclusions 1. As the formulae are arrived at more rationally, there will be saving in the manpower and at the same time ensures equitable distribution of manpower in accordance with the work load. 2. The adoption of rational formulae ensures uniformity of manpower provision commensurate with work load. 3. Optimisation of manpower can be achieved 4. uniform degree of track maintenance and equitable allotment of funds. 5. The concept of EMKM enables to evaluate the manpower requirement for optimal utilization 6. The formulae are more flexible to allow for redistribution of strength of the various gangs as per the age profile of track. 7. The formulae allows for introduction of Mobile Maintenance Units