The integrity and functionality of the electricity supply cables is vital for keeping safety services operational during a building fire. Choosing a cable that is tested and classified as fire resistant is a first step when designing an electrical circuit to supply equipment that must remain functional during a fire. The next step – equally important – is to calculate the appropriate cable conductor cross section. This requires particular attention because of the fact that electrical resistance increases sharply as temperature rises.
To calculate the electrical resistance under fire conditions, the fire temperature must be known. First, it must be determined for how long the safety services must remain operational. The standard durations of fire resistance classes are 30, 60, 90, and 120 minutes. When this time span is known, the fire temperature can be derived from the standard temperature-time curve as defined in ISO 834. The electrical resistance under fire conditions can then be obtained by applying the Wiedemann-Franz law. This will establish an electrical resistance correction factor which facilitates the calculation of the voltage drop under fire conditions.
The voltage drop over the entire length of the supply cables must be restricted to ensure that fire safety equipment will maintain functionality for the required length of time. Usually, the maximum voltage drop will be specified in the equipment’s user guide. If this is not the case, one must consider a maximum voltage drop of 10%. Because buildings are often compartmentalised into fire zones, cables feeding fire protection equipment are rarely exposed to fire temperatures over their entire length. The part of the cable not affected by the fire will operate at normal temperature, while the part exposed to the fire will have increased resistance. The total resistance over the whole length of the cable is calculated by applying the electrical resistance correction factor only to that part of the cable affected. From the maximum voltage drop of the fire safety equipment, the electrical resistance correction factor and the compartmentalisation of the cable route, the maximum electrical resistance the cable is allowed to have at normal temperature (20°C) can be calculated. The minimum conductor cross section can then be derived from this using Tables 1 to 4 of the international standard EN/IEC 60228, or their equivalent in national standards.
The electrical insulation of fire-resistant cables is designed to withstand extreme temperatures, a fact which could lead to the false assumption that there is no limit to the current-carrying capacity of these cables. In reality, fire-resistant cables are not tested for the potential additional heat produced as a result of the increased electrical resistance at high temperature.
Fire safety cables - Selection and sizing of conductors supplying electrical ...Leonardo ENERGY
Cables that are exposed to fire while being expected to retain their functionality and provide power to essential equipment at another location must be appropriately selected and sized to take account of the increased electrical resistance at elevated temperature. Manufacturers offer cables and accessories that will survive a standard cellulose fire for 30, 60 or 90 minutes when correctly specified and installed.
Cables, including fire safety cables, are specified in terms that reflect their normal duty conditions; design parameters under fire conditions are rarely, if ever, specified. The objective of this paper is to provide a clear methodology for designing fire safety circuits based on the derivation and application of correction factors and standard cable parameters.
Cables that are exposed to fire while being expected to retain their functionality and provide power to essential equipment at another location must be appropriately selected and sized. This is not only a question of an appropriate insulation. Designers must take account of the increased electrical resistance at elevated temperature.
Manufacturers offer cables and accessories that will survive a standard cellulose fire for 30, 60 or 90 minutes when correctly specified and installed.
A first step to specifying a suitable fire safety cable is a good knowledge of the temperature rise characteristic in areas affected by the fire.
A second step is the correct selection and erection of the cable. This includes the correct sizing of the conductor. Cables, including fire safety cables, are specified in terms that reflect their normal duty conditions; design parameters under fire conditions are rarely, if ever, specified. The designer must take into account the consequent effects of the increased resistance on current carrying capacity, voltage drop, and short circuit capacity of the conductors. Special care should go to the current carrying capacity of the conductor if it is to supply electrically driven fire pumps drawing high starting currents. The circuit protection should also be adapted to fire conditions, as it must be designed to function with significant higher loop impedance than normal.
This paper provides a clear methodology for designing fire safety circuits based on the derivation and application of correction factors and standard cable parameters.
Having selected the appropriate cable, it must be installed properly, using suitable accessories and following the manufacturer’s restrictions.
Cables that are exposed to fire while being expected to retain their functionality and provide power to essential equipment at another location must be appropriately selected and sized to take account of the increased electrical resistance at elevated temperature. Manufacturers offer cables and accessories that will survive a standard cellulose fire for 30, 60 or 90 minutes when correctly specified and installed.
Cables, including fire safety cables, are specified in terms that reflect their normal duty conditions; design parameters under fire conditions are rarely, if ever, specified. The objective of this paper is to provide a clear methodology for designing fire safety circuits based on the derivation and application of correction factors and standard cable parameters.
Cables that are exposed to fire while being expected to retain their functionality and provide power to essential equipment at another location must be appropriately selected and sized. This is not only a question of an appropriate insulation. Designers must take account of the increased electrical resistance at elevated temperature.
Manufacturers offer cables and accessories that will survive a standard cellulose fire for 30, 60 or 90 minutes when correctly specified and installed.
A first step to specifying a suitable fire safety cable is a good knowledge of the temperature rise characteristic in areas affected by the fire.
A second step is the correct selection and erection of the cable. This includes the correct sizing of the conductor. Cables, including fire safety cables, are specified in terms that reflect their normal duty conditions; design parameters under fire conditions are rarely, if ever, specified. The designer must take into account the consequent effects of the increased resistance on current carrying capacity, voltage drop, and short circuit capacity of the conductors. Special care should go to the current carrying capacity of the conductor if it is to supply electrically driven fire pumps drawing high starting currents. The circuit protection should also be adapted to fire conditions, as it must be designed to function with significant higher loop impedance than normal.
This paper provides a clear methodology for designing fire safety circuits based on the derivation and application of correction factors and standard cable parameters.
Having selected the appropriate cable, it must be installed properly, using suitable accessories and following the manufacturer’s restrictions.
Cables that are exposed to fire while being expected to retain their functionality and provide power to essential equipment at another location must be appropriately selected and sized to take account of the increased electrical resistance at elevated temperature. Manufacturers offer cables and accessories that will survive a standard cellulose fire for 30, 60 or 90 minutes when correctly specified and installed.
Cables, including fire safety cables, are specified in terms that reflect their normal duty conditions; design parameters under fire conditions are rarely, if ever, specified. The objective of this paper is to provide a clear methodology for designing fire safety circuits based on the derivation and application of correction factors and standard cable parameters.
Cables that are exposed to fire while being expected to retain their functionality and provide power to essential equipment at another location must be appropriately selected and sized. This is not only a question of an appropriate insulation. Designers must take account of the increased electrical resistance at elevated temperature.
Manufacturers offer cables and accessories that will survive a standard cellulose fire for 30, 60 or 90 minutes when correctly specified and installed.
A first step to specifying a suitable fire safety cable is a good knowledge of the temperature rise characteristic in areas affected by the fire.
A second step is the correct selection and erection of the cable. This includes the correct sizing of the conductor. Cables, including fire safety cables, are specified in terms that reflect their normal duty conditions; design parameters under fire conditions are rarely, if ever, specified. The designer must take into account the consequent effects of the increased resistance on current carrying capacity, voltage drop, and short circuit capacity of the conductors. Special care should go to the current carrying capacity of the conductor if it is to supply electrically driven fire pumps drawing high starting currents. The circuit protection should also be adapted to fire conditions, as it must be designed to function with significant higher loop impedance than normal.
This paper provides a clear methodology for designing fire safety circuits based on the derivation and application of correction factors and standard cable parameters.
Having selected the appropriate cable, it must be installed properly, using suitable accessories and following the manufacturer’s restrictions.
Highlights:
* Electricity saving potential at 2030 horizon (non-residential buildings): 20 TWh / year, i.e. 9 million tons CO2 / year
* Average payback time of extra investment: 3 to 5 years
* Increased fire safety and improved protection against indirect contact
* Improved power quality and increased flexibility
Cable Conductor Sizing for Minimum Life Cycle CostLeonardo ENERGY
Energy prices are high and expected to rise. All CO2 emissions are being scrutinized by regulators as well as by public opinion. As a result, energy management has become a key factor in almost every business. To get the most out of each kilowatt-hour, appliances must be carefully evaluated for their energy efficiency.
It is an often overlooked fact that electrical energy gets lost in both end-use and in the supply system (cables, busbars, transformers, etc.). Every cable has resistance, so part of the electrical energy that it carries is dissipated as heat and is lost.
Such energy losses can be reduced by increasing the cross section of the copper conductor in a cable or busbar. Obviously, the conductor size cannot be increased endlessly. The objective should be the economic and/or environmental optimum. What is the optimal cross section necessary to maximize the Return on Investment (ROI) and minimize the Net Present Value (NPV) and/or the Life Cycle Cost (LCC)?
This paper will demonstrate that the maximizing of the ROI results in a cross section that is far larger than which technical standards prescribe. Those standards are based entirely on safety and certain power quality aspects. This means there is room for improvement—a great deal of improvement in fact.
Best Practice(s) in regulating Electrical Safety in the homeLeonardo ENERGY
Highlights:
* Overall goal is to safeguard the lives of citizens and avoid fires.
* Argues for a correct approach by all parties involved to achieve safe electrical installation in every home.
* Discusses the role of the contractor/installer, utilities company, network distributor, owner, user, and authorities.
* Offers some best practices to achieve safe domestic electrical installations.
* Suggests that regular inspections are also necessary.
Fire safety cables - Selection and sizing of conductors supplying electrical ...Leonardo ENERGY
Cables that are exposed to fire while being expected to retain their functionality and provide power to essential equipment at another location must be appropriately selected and sized to take account of the increased electrical resistance at elevated temperature. Manufacturers offer cables and accessories that will survive a standard cellulose fire for 30, 60 or 90 minutes when correctly specified and installed.
Cables, including fire safety cables, are specified in terms that reflect their normal duty conditions; design parameters under fire conditions are rarely, if ever, specified. The objective of this paper is to provide a clear methodology for designing fire safety circuits based on the derivation and application of correction factors and standard cable parameters.
Cables that are exposed to fire while being expected to retain their functionality and provide power to essential equipment at another location must be appropriately selected and sized. This is not only a question of an appropriate insulation. Designers must take account of the increased electrical resistance at elevated temperature.
Manufacturers offer cables and accessories that will survive a standard cellulose fire for 30, 60 or 90 minutes when correctly specified and installed.
A first step to specifying a suitable fire safety cable is a good knowledge of the temperature rise characteristic in areas affected by the fire.
A second step is the correct selection and erection of the cable. This includes the correct sizing of the conductor. Cables, including fire safety cables, are specified in terms that reflect their normal duty conditions; design parameters under fire conditions are rarely, if ever, specified. The designer must take into account the consequent effects of the increased resistance on current carrying capacity, voltage drop, and short circuit capacity of the conductors. Special care should go to the current carrying capacity of the conductor if it is to supply electrically driven fire pumps drawing high starting currents. The circuit protection should also be adapted to fire conditions, as it must be designed to function with significant higher loop impedance than normal.
This paper provides a clear methodology for designing fire safety circuits based on the derivation and application of correction factors and standard cable parameters.
Having selected the appropriate cable, it must be installed properly, using suitable accessories and following the manufacturer’s restrictions.
Cables that are exposed to fire while being expected to retain their functionality and provide power to essential equipment at another location must be appropriately selected and sized to take account of the increased electrical resistance at elevated temperature. Manufacturers offer cables and accessories that will survive a standard cellulose fire for 30, 60 or 90 minutes when correctly specified and installed.
Cables, including fire safety cables, are specified in terms that reflect their normal duty conditions; design parameters under fire conditions are rarely, if ever, specified. The objective of this paper is to provide a clear methodology for designing fire safety circuits based on the derivation and application of correction factors and standard cable parameters.
Cables that are exposed to fire while being expected to retain their functionality and provide power to essential equipment at another location must be appropriately selected and sized. This is not only a question of an appropriate insulation. Designers must take account of the increased electrical resistance at elevated temperature.
Manufacturers offer cables and accessories that will survive a standard cellulose fire for 30, 60 or 90 minutes when correctly specified and installed.
A first step to specifying a suitable fire safety cable is a good knowledge of the temperature rise characteristic in areas affected by the fire.
A second step is the correct selection and erection of the cable. This includes the correct sizing of the conductor. Cables, including fire safety cables, are specified in terms that reflect their normal duty conditions; design parameters under fire conditions are rarely, if ever, specified. The designer must take into account the consequent effects of the increased resistance on current carrying capacity, voltage drop, and short circuit capacity of the conductors. Special care should go to the current carrying capacity of the conductor if it is to supply electrically driven fire pumps drawing high starting currents. The circuit protection should also be adapted to fire conditions, as it must be designed to function with significant higher loop impedance than normal.
This paper provides a clear methodology for designing fire safety circuits based on the derivation and application of correction factors and standard cable parameters.
Having selected the appropriate cable, it must be installed properly, using suitable accessories and following the manufacturer’s restrictions.
Cables that are exposed to fire while being expected to retain their functionality and provide power to essential equipment at another location must be appropriately selected and sized to take account of the increased electrical resistance at elevated temperature. Manufacturers offer cables and accessories that will survive a standard cellulose fire for 30, 60 or 90 minutes when correctly specified and installed.
Cables, including fire safety cables, are specified in terms that reflect their normal duty conditions; design parameters under fire conditions are rarely, if ever, specified. The objective of this paper is to provide a clear methodology for designing fire safety circuits based on the derivation and application of correction factors and standard cable parameters.
Cables that are exposed to fire while being expected to retain their functionality and provide power to essential equipment at another location must be appropriately selected and sized. This is not only a question of an appropriate insulation. Designers must take account of the increased electrical resistance at elevated temperature.
Manufacturers offer cables and accessories that will survive a standard cellulose fire for 30, 60 or 90 minutes when correctly specified and installed.
A first step to specifying a suitable fire safety cable is a good knowledge of the temperature rise characteristic in areas affected by the fire.
A second step is the correct selection and erection of the cable. This includes the correct sizing of the conductor. Cables, including fire safety cables, are specified in terms that reflect their normal duty conditions; design parameters under fire conditions are rarely, if ever, specified. The designer must take into account the consequent effects of the increased resistance on current carrying capacity, voltage drop, and short circuit capacity of the conductors. Special care should go to the current carrying capacity of the conductor if it is to supply electrically driven fire pumps drawing high starting currents. The circuit protection should also be adapted to fire conditions, as it must be designed to function with significant higher loop impedance than normal.
This paper provides a clear methodology for designing fire safety circuits based on the derivation and application of correction factors and standard cable parameters.
Having selected the appropriate cable, it must be installed properly, using suitable accessories and following the manufacturer’s restrictions.
Highlights:
* Electricity saving potential at 2030 horizon (non-residential buildings): 20 TWh / year, i.e. 9 million tons CO2 / year
* Average payback time of extra investment: 3 to 5 years
* Increased fire safety and improved protection against indirect contact
* Improved power quality and increased flexibility
Cable Conductor Sizing for Minimum Life Cycle CostLeonardo ENERGY
Energy prices are high and expected to rise. All CO2 emissions are being scrutinized by regulators as well as by public opinion. As a result, energy management has become a key factor in almost every business. To get the most out of each kilowatt-hour, appliances must be carefully evaluated for their energy efficiency.
It is an often overlooked fact that electrical energy gets lost in both end-use and in the supply system (cables, busbars, transformers, etc.). Every cable has resistance, so part of the electrical energy that it carries is dissipated as heat and is lost.
Such energy losses can be reduced by increasing the cross section of the copper conductor in a cable or busbar. Obviously, the conductor size cannot be increased endlessly. The objective should be the economic and/or environmental optimum. What is the optimal cross section necessary to maximize the Return on Investment (ROI) and minimize the Net Present Value (NPV) and/or the Life Cycle Cost (LCC)?
This paper will demonstrate that the maximizing of the ROI results in a cross section that is far larger than which technical standards prescribe. Those standards are based entirely on safety and certain power quality aspects. This means there is room for improvement—a great deal of improvement in fact.
Best Practice(s) in regulating Electrical Safety in the homeLeonardo ENERGY
Highlights:
* Overall goal is to safeguard the lives of citizens and avoid fires.
* Argues for a correct approach by all parties involved to achieve safe electrical installation in every home.
* Discusses the role of the contractor/installer, utilities company, network distributor, owner, user, and authorities.
* Offers some best practices to achieve safe domestic electrical installations.
* Suggests that regular inspections are also necessary.
This BLH handbook is intended to educate the user regarding the proper selection ofelectronic weighing systems used in hazardous locations. This document does not cover the installation of equipment as this is typically the responsibility of the installing electrician and/ or engineering design rm. Information contained herein has been compiled from a number of published sources and condensed to cover the subject as related to electronic weighing equipment only.
EXD Hazardous Area Barrier Glands from Flexicon are manufactured from nickel plated brass with a nylon seal, to an IP rating of IP66, IP67, IP68 (5bar) and IP69K - ATEX certified barrier glands are suitable for use with Flexicon flexible conduit (liquid tight types) in Zone 1, Zone 2, Zone 21 and Zone 22.
EXD flameproof barrier glands are suitable for use in Zone 1, Zone 2, Zone 21 and Zone 22 hazardous areas, when used with the Flexicon range of liquid-tight flexible conduits.
Hazardous Area Barrier Gland (ATEX) Certified
• High mechanical strength
• Suitable for threaded entries
• Operating temperature of -60oC to +85oC
• Two-part epoxy solid-setting putty, gloves and mixing instructions
ATEX barrier glands for indoor or outdoor use in Zone 1, Zone 2, Zone 21 and Zone 22 Hazardous Areas with all types of cables housed in Liquid Tight flexible conduit systems. ATEX barrier glands are suitable for knockouts or threaded entries. Nickel plated brass compression fitting comprising of body, nut, earthing ferrule, nylon compression seal and compound barrier. The compound barrier seals around the cable conductors for hazardous area cable glanding on conduit systems. The earthing ferrule is manufactured in machined nickel plated brass to facilitate easy assembly and re-use. Also ensures high mechanical strength and electrical continuity.
Flexicon flexible conduits with ATEX flameproof barrier glands (LTP-EXD flameproof barrier glands) are suitable for use with Flexicon LTP, LTPHC, LTPUL, LTPSS and LTPPU conduits.
Fire safety in Office building Literature, net and live case studyIrene Devakirubai
Construction project management in architecture. Fire safety in Office building net and live case study. NBC norms for fire safety. Net case studies -KLK and Pam center malaysia. Live case study - Global infocity.
Make India Safer with JMV LPS Ltd Electrical Equipment & Human SafetyMahesh Chandra Manav
Human Life is not free and We all want to Live Peace full Safe Life Use of Power to Utilization of All Gadgets which for our comfort , We also Have Threat for Lightning and World wide their is Standard and Practice for our Assets and Human Safety.
in India we have very strong Documents for Electrical Installation and Fire Safety by NBC2016, NEC 2011, IS 782, RDSO , CEA (IPDS&DDUGJY) , NFC17-102.
Now Fire and Safety is released Document for Awareness to Common Public SACHET installation of Electrical Equipment (Earthing and lightning Protection).
Make in India Govt Advisory to give Preference Manufacturer of India and Complies Strongly India Standard by BIS, CEA,SECI, RDSO and MBBL2019.
We request all the Authorities to use Latest Specification in their Present Project on Floor and upcoming Project .
our Electrical Inspection and Fire Safety Officer to follow National building Code Strictly.
SMART CITY, CCTV and Security Surveillance, Project AMRUT (WTP), Solar PV, Electrical Vehicle Charging Infra, Metro Rail , Indian Railway, Sea Ports and Air Ports, Power , Transmission & Distribution, Building Infra Housing, Commercial , Hospital,University, Defense ,Telecom and all other Industries.
We all has to work India Safer , Green and Clean
Pay Money for Electrical Safety
FIRE ALARM PHYSICS PROJECT CBSE CLASS 12NIKHIL DUGGAL
FIRE ALARM PROJECT FOR CBSE CLASS 12 STUDENTS
Completely made by me as it is not available on any of the websites. I hope this will definatety help you to rescue.
Transformer replacement before failure can be motivated by several legitimate reasons. These include changes in the load or the voltage level, an increased risk of failure due to transformer ageing, environmental and fire safety regulations or just the aim to improve the energy performance. This last motivation is less common. This is unfortunate, because replacing a transformer with a new one with higher energy performance will in many cases lead to a lower Life Cycle Cost of the unit. This Application Note will demonstrate how to assess whether it is worthwhile to leave a transformer in place for another year, or whether it is sound practice to replace it with a more performant and reliable one immediately. The primary factor is that of life-cycle costing. The methodology proposed is to calculate the Equivalent Annual Cost (EAC) for the upcoming year of both the existing and the new transformer. The cost of the load losses, which depend upon the load profile of the transformer, and the risk of failure, which depends on the ageing state of the transformer, are the most difficult terms of the EAC to estimate accurately. In the majority of cases, the EAC is dominated by the energy losses, as we will demonstrate in a calculation example.
The most well known reasons for building fires were from warming, electrical appropriation, and lighting frameworks. Chimneys utilized during the special seasons and colder months can make risks also. An alarm framework incorporates numerous segments and highlights to help keep you secured. It spares lives by notice building inhabitants of crises so they can escape risk. In case of a fire, they give discovery and warning without you busy. They can likewise consequently dispatch the local group of fire fighters to your area. At the point when an alarm is actuated, it supports your security and wellbeing during a hazardous occasion. A fire location framework utilizes a smoke alarm to distinguish a fire before it really begins. The point of the framework planned is to caution the removed land owner with proficiency and rapidly by causing short message SMS by means of GSM network. Sreejith S P | Kuldeep Baban Vayadande "Advanced Fire Monitoring System" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-5 | Issue-1 , December 2020, URL: https://www.ijtsrd.com/papers/ijtsrd37978.pdf Paper URL : https://www.ijtsrd.com/computer-science/artificial-intelligence/37978/advanced-fire-monitoring-system/sreejith-s-p
ECI position on the revision of the Energy Efficiency Directivefernando nuño
The European Copper Institute (ECI) supports the EU’s climate ambitions for 2030 and
2050 and welcomes the proposed recast of the Energy Efficiency Directive (EED). Copper is
a key material for energy efficiency in all sectors and contributes significantly to the clean energy
transition as a sustainable raw material that is essential to decarbonise the economy.
The EED recast proposal goes in the right direction in many areas. We welcome the
mainstreaming of the Energy Efficiency First principle and the strengthening of the
exemplary role of public buildings in driving renovation. The revised provisions on energy
audits and energy management systems are also useful to help small and medium-sized
enterprises (SMEs) catch up on energy efficiency measures, although we believe that mandatory
certification can be a barrier to the adoption of energy management systems by SMEs.
However, more needs to be done to facilitate the exploitation of the significant potential for
utilising waste heat from industrial processes under the EED. It is welcome that under the
revised article 23, Member States are mandated to take measures for district heating and cooling
infrastructure to be developed where benefits exceed costs.
However, in many cases it will not be possible to direct industrial excess heat to district heating
networks, and in such cases, the conversion of waste heat into electricity for own
consumption should be explicitly included under EED Article 23 as an energy savings
measure to be considered by Member States in the cost-benefit analyses underlying their
comprehensive heating and cooling assessments, and under Article 24 when assessing the
utilisation of waste heat on-site and off-site when large industrial installations are newly planned
or refurbished.
Finally, it is important to acknowledge that increasing energy efficiency will sometimes have an
impact on the realisation of other environmental objectives, such as environmental protection,
resource efficiency or decarbonisation. In some cases, decarbonisation measures such as
switching to low carbon energy sources or increasing energy system flexibility may reduce energy
efficiency, while the implementation of higher environmental protection standards can increase
energy demand. Policymakers should be mindful of such trade-offs and take care to avoid setting
conflicting targets.
Infographic Energy Efficiency Directive - Waste heat-to-power - European Cop...fernando nuño
The primary route for copper manufacturing releases important amounts of heat. Consequently, ECI had asked to have an explicit recognition of projects recovering and valorising waste heat flows. Such demand has been reflected in the article 23.4 of the directive as follows: “ [...] Member States shall take adequate measures for efficient district heating and cooling infrastructure to be developed and/or to encourage the development of installations for the utilisation of waste heat, including in the industrial sector
More Related Content
Similar to Fire-Resistant Cable Sizing of conductors supplying electrical equipment that must remain functional during a fire
This BLH handbook is intended to educate the user regarding the proper selection ofelectronic weighing systems used in hazardous locations. This document does not cover the installation of equipment as this is typically the responsibility of the installing electrician and/ or engineering design rm. Information contained herein has been compiled from a number of published sources and condensed to cover the subject as related to electronic weighing equipment only.
EXD Hazardous Area Barrier Glands from Flexicon are manufactured from nickel plated brass with a nylon seal, to an IP rating of IP66, IP67, IP68 (5bar) and IP69K - ATEX certified barrier glands are suitable for use with Flexicon flexible conduit (liquid tight types) in Zone 1, Zone 2, Zone 21 and Zone 22.
EXD flameproof barrier glands are suitable for use in Zone 1, Zone 2, Zone 21 and Zone 22 hazardous areas, when used with the Flexicon range of liquid-tight flexible conduits.
Hazardous Area Barrier Gland (ATEX) Certified
• High mechanical strength
• Suitable for threaded entries
• Operating temperature of -60oC to +85oC
• Two-part epoxy solid-setting putty, gloves and mixing instructions
ATEX barrier glands for indoor or outdoor use in Zone 1, Zone 2, Zone 21 and Zone 22 Hazardous Areas with all types of cables housed in Liquid Tight flexible conduit systems. ATEX barrier glands are suitable for knockouts or threaded entries. Nickel plated brass compression fitting comprising of body, nut, earthing ferrule, nylon compression seal and compound barrier. The compound barrier seals around the cable conductors for hazardous area cable glanding on conduit systems. The earthing ferrule is manufactured in machined nickel plated brass to facilitate easy assembly and re-use. Also ensures high mechanical strength and electrical continuity.
Flexicon flexible conduits with ATEX flameproof barrier glands (LTP-EXD flameproof barrier glands) are suitable for use with Flexicon LTP, LTPHC, LTPUL, LTPSS and LTPPU conduits.
Fire safety in Office building Literature, net and live case studyIrene Devakirubai
Construction project management in architecture. Fire safety in Office building net and live case study. NBC norms for fire safety. Net case studies -KLK and Pam center malaysia. Live case study - Global infocity.
Make India Safer with JMV LPS Ltd Electrical Equipment & Human SafetyMahesh Chandra Manav
Human Life is not free and We all want to Live Peace full Safe Life Use of Power to Utilization of All Gadgets which for our comfort , We also Have Threat for Lightning and World wide their is Standard and Practice for our Assets and Human Safety.
in India we have very strong Documents for Electrical Installation and Fire Safety by NBC2016, NEC 2011, IS 782, RDSO , CEA (IPDS&DDUGJY) , NFC17-102.
Now Fire and Safety is released Document for Awareness to Common Public SACHET installation of Electrical Equipment (Earthing and lightning Protection).
Make in India Govt Advisory to give Preference Manufacturer of India and Complies Strongly India Standard by BIS, CEA,SECI, RDSO and MBBL2019.
We request all the Authorities to use Latest Specification in their Present Project on Floor and upcoming Project .
our Electrical Inspection and Fire Safety Officer to follow National building Code Strictly.
SMART CITY, CCTV and Security Surveillance, Project AMRUT (WTP), Solar PV, Electrical Vehicle Charging Infra, Metro Rail , Indian Railway, Sea Ports and Air Ports, Power , Transmission & Distribution, Building Infra Housing, Commercial , Hospital,University, Defense ,Telecom and all other Industries.
We all has to work India Safer , Green and Clean
Pay Money for Electrical Safety
FIRE ALARM PHYSICS PROJECT CBSE CLASS 12NIKHIL DUGGAL
FIRE ALARM PROJECT FOR CBSE CLASS 12 STUDENTS
Completely made by me as it is not available on any of the websites. I hope this will definatety help you to rescue.
Transformer replacement before failure can be motivated by several legitimate reasons. These include changes in the load or the voltage level, an increased risk of failure due to transformer ageing, environmental and fire safety regulations or just the aim to improve the energy performance. This last motivation is less common. This is unfortunate, because replacing a transformer with a new one with higher energy performance will in many cases lead to a lower Life Cycle Cost of the unit. This Application Note will demonstrate how to assess whether it is worthwhile to leave a transformer in place for another year, or whether it is sound practice to replace it with a more performant and reliable one immediately. The primary factor is that of life-cycle costing. The methodology proposed is to calculate the Equivalent Annual Cost (EAC) for the upcoming year of both the existing and the new transformer. The cost of the load losses, which depend upon the load profile of the transformer, and the risk of failure, which depends on the ageing state of the transformer, are the most difficult terms of the EAC to estimate accurately. In the majority of cases, the EAC is dominated by the energy losses, as we will demonstrate in a calculation example.
The most well known reasons for building fires were from warming, electrical appropriation, and lighting frameworks. Chimneys utilized during the special seasons and colder months can make risks also. An alarm framework incorporates numerous segments and highlights to help keep you secured. It spares lives by notice building inhabitants of crises so they can escape risk. In case of a fire, they give discovery and warning without you busy. They can likewise consequently dispatch the local group of fire fighters to your area. At the point when an alarm is actuated, it supports your security and wellbeing during a hazardous occasion. A fire location framework utilizes a smoke alarm to distinguish a fire before it really begins. The point of the framework planned is to caution the removed land owner with proficiency and rapidly by causing short message SMS by means of GSM network. Sreejith S P | Kuldeep Baban Vayadande "Advanced Fire Monitoring System" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-5 | Issue-1 , December 2020, URL: https://www.ijtsrd.com/papers/ijtsrd37978.pdf Paper URL : https://www.ijtsrd.com/computer-science/artificial-intelligence/37978/advanced-fire-monitoring-system/sreejith-s-p
ECI position on the revision of the Energy Efficiency Directivefernando nuño
The European Copper Institute (ECI) supports the EU’s climate ambitions for 2030 and
2050 and welcomes the proposed recast of the Energy Efficiency Directive (EED). Copper is
a key material for energy efficiency in all sectors and contributes significantly to the clean energy
transition as a sustainable raw material that is essential to decarbonise the economy.
The EED recast proposal goes in the right direction in many areas. We welcome the
mainstreaming of the Energy Efficiency First principle and the strengthening of the
exemplary role of public buildings in driving renovation. The revised provisions on energy
audits and energy management systems are also useful to help small and medium-sized
enterprises (SMEs) catch up on energy efficiency measures, although we believe that mandatory
certification can be a barrier to the adoption of energy management systems by SMEs.
However, more needs to be done to facilitate the exploitation of the significant potential for
utilising waste heat from industrial processes under the EED. It is welcome that under the
revised article 23, Member States are mandated to take measures for district heating and cooling
infrastructure to be developed where benefits exceed costs.
However, in many cases it will not be possible to direct industrial excess heat to district heating
networks, and in such cases, the conversion of waste heat into electricity for own
consumption should be explicitly included under EED Article 23 as an energy savings
measure to be considered by Member States in the cost-benefit analyses underlying their
comprehensive heating and cooling assessments, and under Article 24 when assessing the
utilisation of waste heat on-site and off-site when large industrial installations are newly planned
or refurbished.
Finally, it is important to acknowledge that increasing energy efficiency will sometimes have an
impact on the realisation of other environmental objectives, such as environmental protection,
resource efficiency or decarbonisation. In some cases, decarbonisation measures such as
switching to low carbon energy sources or increasing energy system flexibility may reduce energy
efficiency, while the implementation of higher environmental protection standards can increase
energy demand. Policymakers should be mindful of such trade-offs and take care to avoid setting
conflicting targets.
Infographic Energy Efficiency Directive - Waste heat-to-power - European Cop...fernando nuño
The primary route for copper manufacturing releases important amounts of heat. Consequently, ECI had asked to have an explicit recognition of projects recovering and valorising waste heat flows. Such demand has been reflected in the article 23.4 of the directive as follows: “ [...] Member States shall take adequate measures for efficient district heating and cooling infrastructure to be developed and/or to encourage the development of installations for the utilisation of waste heat, including in the industrial sector
European Copper Institute position on Transformers Regulation revision - Sept...fernando nuño
The EU Green Deal aims to establish a general reduction of final energy demand in the decades to come, combined with a shift towards electricity as the main energy carrier. Materialising this ambition will require further efforts to increase energy efficiency, notably in the electricity grid and its applications. In an electricity generation mix dominated by renewables, increasing the energy efficiency translates into savings of material and land use for generation infrastructure as well as for transmission and distribution networks.
Given the increasing share of electricity in final energy demand and its importance in heating and transport, transformers with an increased capacity at limited cost and with minimal size and weight are needed.
The circular economy is a key pillar of the EU Green Deal. The use of materials must be optimised, both by limiting their quantity and by improving their circularity (design-for-recycling).
Taking the above considerations into account, ECI recommends the following measures:
1) Strengthen Minimum Energy Performance Standards (MEPS) of transformers while introducing material efficiency requirements (MMPS). Given the need to further electrify the economy, while at the same time boosting energy efficiency; given the circular economy objectives and the fact that saved energy translates into a reduced need for electrical infrastructure; given the electricity price evolution in the past years and the recent reform of the electricity market design; we believe the minimum level of energy performance for transformers should be re-assessed, while at the same time making sure that the potential new Tier 3 requirements following from this assessment do not lead to an excessive use of materials. A preliminary modelling exercise points to 1.8 TWh/year of electricity savings and a reduction of 0.8 to 1.6 million tons of materials used if Tier 3 requirements were introduced for distribution transformers.
2) Allow flexibility in design. Together with the free choice of active materials, flexible design strategies should be permitted. These strategies create an additional degree of freedom in design, making it easier to respond to MEPS and MMPS requirements, They include approaches such as the Peak Efficiency Index (PEI) in distribution transformers and concepts such as the Sustainable Peak Load (SPL) transformer in less loaded networks.
3) Promote the lowest life cycle cost at system level. Allow transformer owners to make the best decision on the optimal transformer design considering both their expected load profiles and their additional investment costs in substation and cables. Operational costs should be fully considered in the decision-making process. In the case of regulated utilities, a harmonised approach should be implemented by National Regulatory Authorities to minimise net societal costs (lifetime capex + opex).
Induction Motors Matching Permanent Magnet Performances at Lower Costsfernando nuño
Due to a continued concern on the external dependence of permanent magnets in Europe, induction technology is being pushed beyond its limits to maximise performance.
With novel materials, material characterisation and multi-domain design, power-speed capability of laminated rotor induction motors can match that typically associated with surface permanent magnet machines, at a fraction of the cost.
This session reviews the findings relating to lower cost induction motors, highlighting how they can successfully be used as an alternative to permanent magnets.
Doing More With Less: How to Reach Material Efficiency Goals in Transformersfernando nuño
Ecodesign regulation addresses both energy and material efficiency requirements.
This poses a number of challenges to electricity distribution operators.
This panel discussion analyses possible solutions at hand to meet these new requirements taking into consideration managing the end of life and varying degrees of recyclability.
DISTRIBUTION GRIDS:
How can existing substations accommodate more load?
How do you figure out future loads: same transformers with higher average load or more transformers as loaded as today?
TECHNOLOGY OPTIONS:
How could the capacity of existing substations be boosted?
CHALLENGES OF THE ELECTRICITY GRID:
Increase of e-consumption by 55% by 2050 mainly due to electrification in mobility
More extreme consumption profiles
Increased consumption peak in the evening
More (decentralized) renewables during the day
The evolution of ‘the Duck Curve’ requires investments on a local and on a system level
Copper, a Strategic Raw Material - Circularity, GHG Emissions Pathway and Ava...fernando nuño
With its superior electrical conductivity, copper is a key material for the clean energy transition. The fact that the metal is endlessly recyclable without loss of properties is a major trump card in this context. Recycling alone, however, will never suffice to meet the predicted demand growth. There are enough resources on earth to produce the additional copper that is required, but the lead times from exploration to production will have to speed up and to the carbon emissions of copper production will have to be brought down to zero. The copper industry is well on track to deal with these challenges, but the involvement and commitment of multiple stakeholders is needed to make it happen.
Used in a wide variety of electrical applications
Copper has the highest electrical conductivity of all non-precious metals, which is the reason why it can be found in a wide variety of electrical applications. At the side of electricity generation, both photovoltaic and wind power plants contain high quantities of copper. Transformers, batteries and interconnectors are built with copper and play a key role in the electricity grid. Many electrical end-use applications also have copper as key material, including electric vehicles and their charging infrastructure, electric motors, electro-processing systems, heat pumps and heat recovery systems. This makes copper into an essential material to electrify and decarbonise the European economy, with EU copper demand expected to increase by 35% between 2020 and 2050.
Today, 30% of the copper demand in the EU is met through local extraction and processing, 20% through the recycling of local end-of-life products, 30% through the import of copper concentrates, and 20% through the import of refined copper.
Recycling as a major trump card
Copper’s infinite recyclability is a major advantage. About 80 percent of copper is used in an unalloyed form, facilitating the recycling process. Even for copper that is alloyed or contains other materials, recycling without downgrading is still possible and efficient. This means that the unwanted elements can be removed to recover the copper in its pure state, ready to be re-used in any kind of application. In fact, recycled copper and newly mined copper go through the same refining process. Depending on the purity of the scrap, the required processing steps vary, but the end product is always the same and provides the required purity for electrical applications. Because of its high degree of recyclability, the copper in use in its various applications is not lost, but can be considered a legitimate part of the world copper reserve, often referred to as society’s “urban mine”.
Globally, copper demand is expected to double by 2050, driven by the clean energy transition, population growth and economic development. This leads to the question whether copper production will be able to follow this steadily increasing demand.
Pros and cons of copper conductors in power cables - March 2018fernando nuño
Pros and cons of copper conductors in power cables.
Life cycle cost, failure resistance, repairability, application suitability, compactness, environmental performance, recyclability, life cycle assessment
Webinar - Simulación de Sistemas de Iluminaciónfernando nuño
Se presentan los conceptos generales de la luminotecnia como base para definir los elementos necesarios para el diseño de sistemas de iluminación y para explicar los métodos más usados para su simulación. Lo anterior con el objetivo de comprender el funcionamiento de los programas de computadora usados con este fin y obtener mejor provecho de ellos.
Introducción a la luminotecnia
Conceptos generales
a. Iluminación
b. Unidades de medida
c. Distribución luminosa
d. Elementos de diseño
Métodos de simulación
a. Métodos simples
b. Método de cavidades zonales
c. Método punto por punto
Software para simulación de sistemas de iluminación
Ponente: El Ing. Humberto García Flores es consultor independiente en diseño, simulación y evaluación de sistemas de iluminación. Docente en la Academia de Ingeniería Eléctrica del Instituto Tecnológico de Puebla y Planeador de Proyectos en el Laboratorio de Visión por Computadora del Instituto Nacional de Astrofísica, Óptica y Electrónica. Es el desarrollador del software SIMCLI. Iluminación Interior, usado para simulación y evaluación de sistemas de iluminación en interiores.
Generacion de electricidad_renovable_latinoamericafernando nuño
América Latina tiene una historia importante del uso de los recursos de energía renovable. El uso de estos recursos en la región se ha hecho a través de grandes centrales hidroeléctricas. Sin embargo, existe un enorme potencial para una mayor utilización de nuevas fuentes de energía renovables: pequeñas plantas hidroeléctricas, energía eólica, solar, geotérmica. En la actualidad, estas tecnologías de producción de energía renovable (sin considerar las grandes centrales hidroeléctricas) contribuyen con sólo 2.5 a 5% de la capacidad instalada existente en los países estudiados.
En este webinar se presentan los resultados de un estudio sobre la situación y tendencias actuales de la expansión del uso de pequeñas plantas hidroeléctricas, energía eólica, solar, geotérmica en seis países latinoamericanos: Argentina, Brasil, Chile, Colombia, Perú, México, Venezuela y América Central de una manera global. El estudio analiza los planes de expansión del sector energético de cada país hasta el periodo 2020-30, la regulación actual y la presencia de los organismos interesados y comprometidos con la generación de electricidad renovable.
Webinar energia renovable latinoaméricafernando nuño
América Latina tiene una historia importante del uso de los recursos de energía renovable. El uso de estos recursos en la región se ha hecho a través de grandes centrales hidroeléctricas. Sin embargo, existe un enorme potencial para una mayor utilización de nuevas fuentes de energía renovables: pequeñas plantas hidroeléctricas, energía eólica, solar, geotérmica. En la actualidad, estas tecnologías de producción de energía renovable (sin considerar las grandes centrales hidroeléctricas) contribuyen con sólo 2.5 a 5% de la capacidad instalada existente en los países estudiados.
En este webinar se presentan los resultados de un estudio sobre la situación y tendencias actuales de la expansión del uso de pequeñas plantas hidroeléctricas, energía eólica, solar, geotérmica en seis países latinoamericanos: Argentina, Brasil, Chile, Colombia, Perú, México, Venezuela y América Central de una manera global. El estudio analiza los planes de expansión del sector energético de cada país hasta el periodo 2020-30, la regulación actual y la presencia de los organismos interesados y comprometidos con la generación de electricidad renovable.
En el webinar se presentarán los principales resultados relativos a los mercados de la electricidad, las tendencias en las políticas energéticas regionales y los reglamentos y la presencia de los organismos interesados en los países analizados. ¿Qué tecnologías están siendo preferidas? ¿Cuáles son los tipos de regulaciones que se practican?
Webinar1Webinar - Transformadores Eficientes y Cambio de Tarifafernando nuño
Resumen:El transformador es un dispositivo primordial para la transmisión y utilización de la energía eléctrica, ya que al elevar el voltaje permite la transmisión de energía a grandes distancias y al disminuir el voltaje permite la utilización de la energía eléctrica por grandes, medianos y pequeños usuarios, dependiendo del voltaje requerido. Conocer su funcionamiento, componentes y características constructivas; permite a los diferentes usuarios una mejor elección, privilegiando siempre los equipos más eficientes que provoquen las menores pérdidas, ya que en la mayoría de los casos, estos equipos permanecen conectados las 24 horas los 365 días del año, por lo que instalando equipos de alta eficiencia, se reducen drásticamente la emisión de gases de efecto invernadero y se mejora considerablemente la eficiencia del sistema de toda la red eléctrica involucrada.
Acerca del Autor: El Ing. Roger García es egresado de la Escuela Superior de Ingeniería Mecánica y Eléctrica del Instituto Politécnico Nacional de México; se ha desempañado siempre en las áreas de proyectos y eficiencia energética, es especialista en motores, transformadores y calidad de la energía. Ha coordinado y realizado varios diagnósticos energéticos, como resultado de ellos, ha realizado también la instalación de gran cantidad de motores, variadores de frecuencia, transformadores, bancos de capacitores y otros equipos eléctricos. Es consultor de FIDE y Comisión Federal de Electricidad. Ha impartido diferentes cursos de motores y variadores de frecuencia, transformadores, factor de potencia, calidad de la energía; en Universidades, Industrias, Colegios de Ingenieros, en México y Centroamérica. Actualmente se desempaña como Gerente de Proyectos en Ingeniería Energética Integral.
• Criterios de dimensionamiento : producción invernal máxima vs maximización de la producción
• Sistemas híbridos
• Almacenamiento
• Tipos de baterías
• Importancia de la eficiencia energética en sistemas aislados
• Mantenimiento
• Importancia de un buen procedimiento de mantenimiento
• Componentes a mantener
• Tipos de mantenimiento
• Suministros
• Gestión de recambios y stock
• Tipos de inspecciones y alcance
OPERACIÓN
• Sistemas de control y telecomunicaciones
• Sistemas de control: components e infraestructura requerida
• Monitoreo y detección de averías
• Gestión de la información proporcionada por el sistema de control
• Seguridad de la instalación
• Protección contra robos
• Obra civil y preparación de la infraestructura
• Lote mecánico
• Instalación eléctrica
• Aspectos ambientales y gestión de residuos
• Calidad. Aspectos críticos del desarrollo de la instalación
• Ensayos. Puntos clave
Epistemic Interaction - tuning interfaces to provide information for AI supportAlan Dix
Paper presented at SYNERGY workshop at AVI 2024, Genoa, Italy. 3rd June 2024
https://alandix.com/academic/papers/synergy2024-epistemic/
As machine learning integrates deeper into human-computer interactions, the concept of epistemic interaction emerges, aiming to refine these interactions to enhance system adaptability. This approach encourages minor, intentional adjustments in user behaviour to enrich the data available for system learning. This paper introduces epistemic interaction within the context of human-system communication, illustrating how deliberate interaction design can improve system understanding and adaptation. Through concrete examples, we demonstrate the potential of epistemic interaction to significantly advance human-computer interaction by leveraging intuitive human communication strategies to inform system design and functionality, offering a novel pathway for enriching user-system engagements.
JMeter webinar - integration with InfluxDB and GrafanaRTTS
Watch this recorded webinar about real-time monitoring of application performance. See how to integrate Apache JMeter, the open-source leader in performance testing, with InfluxDB, the open-source time-series database, and Grafana, the open-source analytics and visualization application.
In this webinar, we will review the benefits of leveraging InfluxDB and Grafana when executing load tests and demonstrate how these tools are used to visualize performance metrics.
Length: 30 minutes
Session Overview
-------------------------------------------
During this webinar, we will cover the following topics while demonstrating the integrations of JMeter, InfluxDB and Grafana:
- What out-of-the-box solutions are available for real-time monitoring JMeter tests?
- What are the benefits of integrating InfluxDB and Grafana into the load testing stack?
- Which features are provided by Grafana?
- Demonstration of InfluxDB and Grafana using a practice web application
To view the webinar recording, go to:
https://www.rttsweb.com/jmeter-integration-webinar
Accelerate your Kubernetes clusters with Varnish CachingThijs Feryn
A presentation about the usage and availability of Varnish on Kubernetes. This talk explores the capabilities of Varnish caching and shows how to use the Varnish Helm chart to deploy it to Kubernetes.
This presentation was delivered at K8SUG Singapore. See https://feryn.eu/presentations/accelerate-your-kubernetes-clusters-with-varnish-caching-k8sug-singapore-28-2024 for more details.
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Jeffrey Haguewood
Sidekick Solutions uses Bonterra Impact Management (fka Social Solutions Apricot) and automation solutions to integrate data for business workflows.
We believe integration and automation are essential to user experience and the promise of efficient work through technology. Automation is the critical ingredient to realizing that full vision. We develop integration products and services for Bonterra Case Management software to support the deployment of automations for a variety of use cases.
This video focuses on the notifications, alerts, and approval requests using Slack for Bonterra Impact Management. The solutions covered in this webinar can also be deployed for Microsoft Teams.
Interested in deploying notification automations for Bonterra Impact Management? Contact us at sales@sidekicksolutionsllc.com to discuss next steps.
PHP Frameworks: I want to break free (IPC Berlin 2024)Ralf Eggert
In this presentation, we examine the challenges and limitations of relying too heavily on PHP frameworks in web development. We discuss the history of PHP and its frameworks to understand how this dependence has evolved. The focus will be on providing concrete tips and strategies to reduce reliance on these frameworks, based on real-world examples and practical considerations. The goal is to equip developers with the skills and knowledge to create more flexible and future-proof web applications. We'll explore the importance of maintaining autonomy in a rapidly changing tech landscape and how to make informed decisions in PHP development.
This talk is aimed at encouraging a more independent approach to using PHP frameworks, moving towards a more flexible and future-proof approach to PHP development.
Let's dive deeper into the world of ODC! Ricardo Alves (OutSystems) will join us to tell all about the new Data Fabric. After that, Sezen de Bruijn (OutSystems) will get into the details on how to best design a sturdy architecture within ODC.
State of ICS and IoT Cyber Threat Landscape Report 2024 previewPrayukth K V
The IoT and OT threat landscape report has been prepared by the Threat Research Team at Sectrio using data from Sectrio, cyber threat intelligence farming facilities spread across over 85 cities around the world. In addition, Sectrio also runs AI-based advanced threat and payload engagement facilities that serve as sinks to attract and engage sophisticated threat actors, and newer malware including new variants and latent threats that are at an earlier stage of development.
The latest edition of the OT/ICS and IoT security Threat Landscape Report 2024 also covers:
State of global ICS asset and network exposure
Sectoral targets and attacks as well as the cost of ransom
Global APT activity, AI usage, actor and tactic profiles, and implications
Rise in volumes of AI-powered cyberattacks
Major cyber events in 2024
Malware and malicious payload trends
Cyberattack types and targets
Vulnerability exploit attempts on CVEs
Attacks on counties – USA
Expansion of bot farms – how, where, and why
In-depth analysis of the cyber threat landscape across North America, South America, Europe, APAC, and the Middle East
Why are attacks on smart factories rising?
Cyber risk predictions
Axis of attacks – Europe
Systemic attacks in the Middle East
Download the full report from here:
https://sectrio.com/resources/ot-threat-landscape-reports/sectrio-releases-ot-ics-and-iot-security-threat-landscape-report-2024/
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Ramesh Iyer
In today's fast-changing business world, Companies that adapt and embrace new ideas often need help to keep up with the competition. However, fostering a culture of innovation takes much work. It takes vision, leadership and willingness to take risks in the right proportion. Sachin Dev Duggal, co-founder of Builder.ai, has perfected the art of this balance, creating a company culture where creativity and growth are nurtured at each stage.
"Impact of front-end architecture on development cost", Viktor TurskyiFwdays
I have heard many times that architecture is not important for the front-end. Also, many times I have seen how developers implement features on the front-end just following the standard rules for a framework and think that this is enough to successfully launch the project, and then the project fails. How to prevent this and what approach to choose? I have launched dozens of complex projects and during the talk we will analyze which approaches have worked for me and which have not.
Transcript: Selling digital books in 2024: Insights from industry leaders - T...BookNet Canada
The publishing industry has been selling digital audiobooks and ebooks for over a decade and has found its groove. What’s changed? What has stayed the same? Where do we go from here? Join a group of leading sales peers from across the industry for a conversation about the lessons learned since the popularization of digital books, best practices, digital book supply chain management, and more.
Link to video recording: https://bnctechforum.ca/sessions/selling-digital-books-in-2024-insights-from-industry-leaders/
Presented by BookNet Canada on May 28, 2024, with support from the Department of Canadian Heritage.
Leading Change strategies and insights for effective change management pdf 1.pdf
Fire-Resistant Cable Sizing of conductors supplying electrical equipment that must remain functional during a fire
1. APPLICATION NOTE
FIRE-RESISTANT CABLE SIZING
Sizing of conductors supplying electrical equipment that must remain
functional during a fire
Marko Ahn, Bruno De Wachter, Franck Gyppaz, Angelo Baggini
December 2022
ECI Publication No Cu0109
Available from https://help.leonardo-energy.org
3. Publication No Cu0109
Issue Date: December 2022
Page ii
CONTENTS
Summary ........................................................................................................................................................ 1
Introduction.................................................................................................................................................... 2
The development of a fire............................................................................................................................... 3
Fire-resistant cables........................................................................................................................................ 4
Conductor sizing of fire-resistant cables ......................................................................................................... 5
The conductor resistance under fire conditions.....................................................................................................5
Calculating the voltage drop...................................................................................................................................6
Application in buildings............................................................................................................................7
Motor starting currents............................................................................................................................9
Assessing current-carrying capacity .......................................................................................................................9
Conclusion .................................................................................................................................................... 11
4. Publication No Cu0109
Issue Date: December 2022
Page 1
SUMMARY
The integrity and functionality of the electricity supply cables is vital for keeping safety services operational
during a building fire. Choosing a cable that is tested and classified as fire resistant is a first step when designing
an electrical circuit to supply equipment that must remain functional during a fire. The next step – equally
important – is to calculate the appropriate cable conductor cross section. This requires particular attention
because of the fact that electrical resistance increases sharply as temperature rises.
To calculate the electrical resistance under fire conditions, the fire temperature must be known. First, it must
be determined for how long the safety services must remain operational. The standard durations of fire
resistance classes are 30, 60, 90, and 120 minutes. When this time span is known, the fire temperature can be
derived from the standard temperature-time curve as defined in ISO 834. The electrical resistance under fire
conditions can then be obtained by applying the Wiedemann-Franz law. This will establish an electrical
resistance correction factor which facilitates the calculation of the voltage drop under fire conditions.
The voltage drop over the entire length of the supply cables must be restricted to ensure that fire safety
equipment will maintain functionality for the required length of time. Usually, the maximum voltage drop will
be specified in the equipment’s user guide. If this is not the case, one must consider a maximum voltage drop of
10%. Because buildings are often compartmentalised into fire zones, cables feeding fire protection equipment
are rarely exposed to fire temperatures over their entire length. The part of the cable not affected by the fire
will operate at normal temperature, while the part exposed to the fire will have increased resistance. The total
resistance over the whole length of the cable is calculated by applying the electrical resistance correction factor
only to that part of the cable affected. From the maximum voltage drop of the fire safety equipment, the
electrical resistance correction factor and the compartmentalisation of the cable route, the maximum electrical
resistance the cable is allowed to have at normal temperature (20°C) can be calculated. The minimum conductor
cross section can then be derived from this using Tables 1 to 4 of the international standard EN/IEC 60228, or
their equivalent in national standards.
The electrical insulation of fire-resistant cables is designed to withstand extreme temperatures, a fact which
could lead to the false assumption that there is no limit to the current-carrying capacity of these cables. In
reality, fire-resistant cables are not tested for the potential additional heat produced as a result of the increased
electrical resistance at high temperature. Moreover, any additional temperature rise above that represented by
the standard temperature-time curve (ISO 834, post-flashover fire) could bring the cable close to the melting
temperature of copper. Laboratory tests have demonstrated that this additional heat production does not affect
the cable performance up to the 90 minute mark of the ISO 834 temperature-time curve. For these cases, the
conductor cross sections and associated current-carrying capacities can be chosen based on the IEC 60364-5-52
standard for cables working under normal service conditions. If the installation must remain functional beyond
90 minutes (safety class 120), measures should be taken to avoid a loss of integrity in the cable.
The cross-section to be chosen is the highest value obtained from the voltage drop and current-carrying capacity
assessments.
5. Publication No Cu0109
Issue Date: December 2022
Page 2
INTRODUCTION
When there is a fire in a building, safety services should not fail. They can save the lives of occupants and
emergency workers. The first objective is to provide safe evacuation routes from the affected areas and to
ensure that all services required for firefighting are maintained for as long as necessary. Another objective may
be to ensure that services in areas not directly affected by fire are secured to provide a safe environment for
occupants who are evacuated, pending complete evacuation or the end of the incident. Preserving property is
also at stake.
The length of time for which safety services are required to operate depends on the building’s use, the number
and type of occupants, and the specifications given by national regulation and insurance companies. While it
may be feasible to evacuate a dwelling or a small office building quickly, larger or taller structures and many
public buildings will take much longer. The longer safety services can remain operational, the better the chance
of bringing a fire under control, avoiding injuries, and reducing property damage.
A prerequisite for keeping safety services operational during a fire is to maintain a reliable power supply.
Choosing a power cable tested and classified as fire resistant is a first step when designing an electrical circuit
supplying equipment that must remain functional during a fire. The second step – just as crucial – is to calculate
the minimum cable conductor cross section, which is the main subject of this application note.
6. Publication No Cu0109
Issue Date: December 2022
Page 3
THE DEVELOPMENT OF A FIRE
How a building fire develops depends on many factors, of which the fire load is the most important. The fire load
is the average calorific value of combustible material per square metre of fire zone and is expressed in mega-
joules per square metre (MJ/m2
).
The key to being able to specify a suitable fire-resistant cable is having a sound knowledge of the temperature
rise characteristics in areas affected by the fire. Although the exact process depends on the location and fire
load, standard temperature-time curves that model typical fires have been developed. In this application note
we will use the standard temperature-time curve of post-flashover fire as defined in ISO 834. This standard curve
is the most common in the fire-testing of buildings and is used in construction products regulation (CPR) tests.
For some application areas, alternative temperature-time curves, such as hydrocarbon or tunnel curves, must
be used.
The ISO 834 standard temperature-time curve of a post-flashover fire is expressed by the formula:
𝑇𝑇 = 345 log(8𝑡𝑡 + 1) + 20
where:
T is the temperature, in °C
t is time, in minutes
FIGURE 1 – TEMPERATURE-TIME CURVE FOR A STANDARD TEMPERATURE-TIME CURVE (ISO 834, POST-FLASHOVER FIRE)
After 30 minutes of fire, the temperature is already in excess of 800°C. It will continue to rise and reach more
than 1000°C after 90 minutes.
7. Publication No Cu0109
Issue Date: December 2022
Page 4
FIRE-RESISTANT CABLES
There are a number of circumstances where high risk demands enhanced fire protection. These include buildings
with high numbers of occupants, especially where they are unfamiliar with their environment. The need for
enhanced protection can also depend on the nature of the activities, or risk in terms of loss of life, historic
artefacts, or economic value.
Typical locations include:
• Public buildings and spaces – cinemas, theatres, hotels, museums, transport hubs, and shopping centres
• Buildings with vulnerable occupants – schools, hospitals, and day-care centres
• Where evacuation and rescue access may be difficult – mines, tunnels
• Hazardous locations – chemical manufacturing and storage, bulk powder storage
• Sensitive infrastructure – data centres, communications facilities, banks
• High-rise buildings, where fire could spread very quickly, hampering firefighting and evacuation
The types of equipment that must be available during a fire include:
• Smoke venting systems, including pressurisation and depressurisation fans
• Electrically operated fire shutters and smoke curtains
• Firefighting lifts
• Sprinkler and wet-riser pumps
• Equipment for explosion prevention and suppression
• Command and communications systems, including audible warning devices addressing the public
• Emergency lighting
Cables commonly used for electrical installations would already suffer damage at temperatures much lower than
those experienced in a fire. For this reason, one of the following measures must be put in place:
• Protect the cables by installing them in a fire-resistant sleeve, conduit, or trunk, or
• Use cables with intrinsic fire-resistance, specifically designed for the purpose.
Cables with intrinsic fire-resistance can be used unprotected and are classified based on the minimum time they
are able “to maintain a reliable form of power supply when exposed to the conditions of the standard
temperature-time curve” (EN 13501-3 §5.1.6), expressed in minutes. The standard durations of fire resistance
are 30, 60, 90, and 120 minutes – hereunder simply called “fire safety classes”.
Calculating the minimum cable cross section for cables that must remain functional during a fire is different from
the calculations for cables operating under normal conditions. Because of the high temperatures, the electrical
resistance will be much higher. This must be taken into account when assessing the voltage drop and current-
carrying capacity. This is discussed in detail in the following chapters.
8. Publication No Cu0109
Issue Date: December 2022
Page 5
CONDUCTOR SIZING OF FIRE-RESISTANT CABLES
We will first calculate the electrical resistance under fire conditions, before relating it to the voltage drop and
the current carrying capacity of the cable. The appropriate conductor cross section will follow from a
combination of both assessments.
THE CONDUCTOR RESISTANCE UNDER FIRE CONDITIONS
In normal electrical applications, the resistance of a copper conductor can be calculated using the following
formula, which is valid up to about 200 °C:
𝑅𝑅 = 𝑅𝑅20(1 + 𝛼𝛼20∆𝑇𝑇)
where:
20
R is the conductor resistance at 20°C, in Ω
α20 is the temperature coefficient of resistance at 20°C, per °C. α = 0.0039 for copper
∆T = Tk – 20 is the temperature difference, in °C
Tk is the final temperature, in °C.
At temperatures higher than 200°C, the relationship between the temperature and the conductor's resistance
becomes non-linear and is given by the formula:
𝑅𝑅 = 𝑅𝑅20(1 + 𝛼𝛼20∆𝑇𝑇 + 𝛽𝛽20∆𝑇𝑇2
)
where:
β20 = 6.0 x 10-7
°C-2
Alternatively, application of the Wiedemann-Franz law yields:
𝑅𝑅 = 𝑅𝑅20 �
𝑇𝑇
𝑇𝑇20
�
1.16
= 𝑅𝑅20 �
𝑇𝑇
293
�
1.16
where:
R is the resistance at temperature T
R20 is the resistance at 20°C (293 K)
T is the temperature in K (i.e., temperature in °C + 273)
Neither formula are exact laws of physics, but they are both useful approximations. The minor differences in
outcomes of the two formulae, and their slight variance with physical reality, are negligible compared to the
range of uncertainties involved in modelling a fire situation.
Using the Wiedemann-Franz law, the correction factor m to be applied when calculating the electrical resistance
at fire temperature Ty (in K) compared to the resistance at base temperature Tx (in K) can be obtained from:
𝑚𝑚𝑥𝑥 = �
𝑇𝑇𝑦𝑦
𝑇𝑇𝑥𝑥
�
1.16
9. Publication No Cu0109
Issue Date: December 2022
Page 6
FIGURE 2 – EVOLUTION OF THE ELECTRICAL RESISTANCE, RELATIVE TO THE ELECTRICAL RESISTANCE AT 20°C, OF A CABLE SUBJECTED TO
A STANDARD TEMPERATURE-TIME CURVE. AFTER 120 MINUTES, THE ELECTRICAL RESISTANCE IS ALMOST 6 TIMES HIGHER.
CALCULATING THE VOLTAGE DROP
To ensure that all fire safety equipment will maintain its functionality for the required length of time, the voltage
drop in the cable supplying it must be restricted. Usually, the maximum voltage drop will be specified in the
equipment’s user guide. If this is not the case, one must consider a maximum voltage drop of 10%.
Since the voltage drop is caused by the energy losses over the entire length of the cable, those losses must be
restricted. This can be done by choosing an adequate cable cross section.
The voltage drop can be calculated from the following formulae for single-phase and three-phase circuits:
1/ for a single-phase circuit:
∆𝑈𝑈 = 2 . 𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡 . (𝑅𝑅𝑓𝑓 . cos 𝜑𝜑 + 𝜔𝜔 . 𝐿𝐿 . sin 𝜑𝜑 ) . 𝐼𝐼 = 2 . 𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡 . (𝑅𝑅20 .
𝑅𝑅𝑓𝑓
𝑅𝑅20
. cos 𝜑𝜑 + 𝜔𝜔 . 𝐿𝐿 . sin 𝜑𝜑 ) . 𝐼𝐼
2/ for a three-phase circuit:
∆𝑈𝑈 = √3 . 𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡. (𝑅𝑅𝑓𝑓 . cos 𝜑𝜑 + 𝜔𝜔 . 𝐿𝐿 . sin 𝜑𝜑 ) . 𝐼𝐼 = √3 . 𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡. (𝑅𝑅20.
𝑅𝑅𝑓𝑓
𝑅𝑅20
. cos 𝜑𝜑 + 𝜔𝜔 . 𝐿𝐿 . sin 𝜑𝜑 ) . 𝐼𝐼
where:
𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡 is the total cable length
Rf is the electrical resistance per cable length in case of a fire
Cos ϕ is the power factor
10. Publication No Cu0109
Issue Date: December 2022
Page 7
𝜔𝜔 is the radial frequency
L is the inductance per cable length
R20 is the electrical resistance per cable length at 20°C
I is the rated current
The relation between the resistance at 20°C (R20) and the cable cross section is given in national standards and
in Tables 1 to 4 of IEC/EN 60228.
The quotient
𝑅𝑅𝑓𝑓
𝑅𝑅20
is given by the correction factor m20.
APPLICATION IN BUILDINGS
Because buildings are often compartmentalised into fire zones, cables feeding fire protection equipment are
rarely exposed to fire temperatures over their entire length. The part of the cable not affected by the fire will
operate at normal temperature, while that exposed to fire will have increased electrical resistance. The task of
the designer is to assess which areas may be simultaneously affected by fire in the worst-case scenario, and
what proportion of the cable runs through those affected areas. The total conductor resistance is then calculated
by assuming normal resistance for the length unaffected by fire and applying the correction factor m to the
length that is affected by fire. This means the total correction factor q20 can be calculated from:
𝒒𝒒𝟐𝟐𝟐𝟐 =
𝑹𝑹𝑻𝑻
𝑹𝑹𝟐𝟐𝟐𝟐
=
�(𝟏𝟏𝟏𝟏𝟏𝟏−𝒚𝒚)+(𝒚𝒚 . 𝒎𝒎𝟐𝟐𝟐𝟐)�
𝟏𝟏𝟏𝟏𝟏𝟏
(EQUATION 1)
where:
y is the percentage of the cable length estimated to be affected by fire
m20 is the electrical resistance correction factor, relative to the value at 20°C
The value of m20 at 30, 60, 90 and 120 minutes of the standard cellulosic curve are shown in Table 1.
TABLE 1
The resulting values of q20 are given in Table 2.
30' (842°C) 60' (945°C) 90' (1006°C) 120' (1049°C)
Electrical resistance correction factor m20,
relative to the resistance of a cable specified at 20°C
4.71 5.22 5.53 5.74
Fire resistance class, standard temperature-time curve
(ISO 834)
11. Publication No Cu0109
Issue Date: December 2022
Page 8
TABLE 2
With this, we can write the voltage drop formulae as follows:
1/ for a single-phase circuit:
∆𝑈𝑈 = 2 . 𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡 . (𝑅𝑅20 . 𝑞𝑞20 . cos 𝜑𝜑 + 𝜔𝜔 . 𝐿𝐿 . sin 𝜑𝜑 ) . 𝐼𝐼
2/ for a three-phase circuit:
∆𝑈𝑈 = √3 . 𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡. (𝑅𝑅20 . 𝑞𝑞20 . cos 𝜑𝜑 + 𝜔𝜔 . 𝐿𝐿 . sin 𝜑𝜑 ) . 𝐼𝐼
The maximum electrical resistance at 20°C (R20) that will limit the voltage drop to ∆𝑈𝑈 under fire conditions can
be calculated from:
1/ for a single-phase circuit:
𝑅𝑅20 =
∆𝑈𝑈
2 . 𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡. 𝐼𝐼 . 𝑞𝑞20 . cos 𝜑𝜑
−
𝜔𝜔 . 𝐿𝐿 . sin 𝜑𝜑
𝑞𝑞20 . cos 𝜑𝜑
2/ for a three-phase circuit:
𝑅𝑅20 =
∆𝑈𝑈
√3 . 𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡. 𝐼𝐼 . 𝑞𝑞20 . cos 𝜑𝜑
−
𝜔𝜔 . 𝐿𝐿 . sin 𝜑𝜑
𝑞𝑞20 . cos 𝜑𝜑
For conductor cross sections less than 16 mm², the inductive part may be ignored.
For cross sections greater than 16 mm², 𝜔𝜔 . 𝐿𝐿 . sin 𝜑𝜑 can be approximated by the value 0.048 in all cases.
Following on from this:
1/ for a single-phase circuit:
𝑅𝑅20 =
∆𝑈𝑈
2 . 𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡. 𝐼𝐼 . 𝑞𝑞20 . cos 𝜑𝜑
−
0.048
𝑞𝑞20 . cos 𝜑𝜑
2/ for a three-phase circuit:
Proportion in hot zone
10% 1.37 1.42 1.45 1.47
20% 1.74 1.84 1.91 1.95
30% 2.11 2.27 2.36 2,42
40% 2.48 2.69 2.81 2.90
50% 2.85 3.11 3.26 3.37
60% 3.23 3.53 3.72 3.84
70% 3.60 3.95 4.17 4.32
80% 3.97 4.38 4.62 4.79
90% 4,34 4.80 5.08 5.27
100% 4.71 5.22 5.53 5.74
Correction factor q20
Fire safety class (minutes)
30' 60' 90' 120'
12. Publication No Cu0109
Issue Date: December 2022
Page 9
𝑅𝑅20 =
∆𝑈𝑈
√3 . 𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡. 𝐼𝐼 . 𝑞𝑞20 . cos 𝜑𝜑
−
0.048
𝑞𝑞20 . cos 𝜑𝜑
With q20 given by Table 2, or calculated by Equation 1 (and m20, given by Table 1).
When the maximum voltage drop ∆𝑈𝑈 is known, the formulae above give the maximum electrical resistance R20.
The appropriate cable cross section associated with R20 can be obtained from national standards, or from Tables
1 to 4 of IEC/EN 60228.
Consulting the cable manufacturer is advised to validate these calculations. Depending on national regulations,
some modification may be necessary.
MOTOR STARTING CURRENTS
Electric motors draw starting currents many times greater than the running current. Fire pump motors are not
usually equipped with soft starters or variable speed drives to mitigate this phenomenon. Add to this the
increased electrical resistance under fire conditions, and these currents could lead to a voltage drop that is too
great for the motors to continue their start-up. Fire safety circuits must be designed to avoid such failures.
Squirrel-cage induction motors are often used to drive fire pumps because of their simple construction and good
reliability. For this type of motor, and in the working conditions of a fire pump, the voltage drop must in no
scenario exceed 10%. This figure is to be taken as an initial indication; the exact maximum permissible voltage
drop value will be indicated in the motor’s user guide and/or in the national regulation.
ASSESSING CURRENT-CARRYING CAPACITY
The IEC 60364-5-52 standard stipulates the maximum current-carrying capacity for cables working under normal
service conditions, depending on the nominal cross-section of the conductor(s), the type of electrical insulation,
and the installation method. The limiting factor is the maximum temperature the cable insulation can withstand
– typically 70°C or 90°C. In the case of fire-resistant cables, the electrical insulation is designed to withstand
extreme temperatures for a defined duration (30, 60, 90 or 120 minutes), which could lead to the false
assumption that there is no limit in the current-carrying capacity of those cables.
In reality, Joule losses might cause fire resistant cables to reach higher temperatures than those they were
designed for, since the prevailing testing protocols described in the standards do not fully take into account the
potential additional heat production caused by the increased electrical resistance at high temperature combined
with the reduced heat dissipation under fire conditions.
Indeed, the cable’s thermal balance depends on:
• Internal heat production due to electrical losses (Joule losses), and
• Heating or heat dissipation through radiation, convection, and conduction.
The Joule losses are proportional to the square of the current. In fire conditions, their contribution to the cable’s
thermal balance will be more significant due to:
• The increased electrical resistance at high temperature, and
• The reduced heat exchange with the cable surroundings due to the high temperature of flames.
The Joule losses could consequently result in a cable temperature surpassing the maximum value it was designed
for, in particular towards the end of the duration corresponding to the safety class under consideration. To
investigate whether this could affect cable performance, laboratory tests were carried out at Nexans in Lyon,
France in November 2022, while a second series of tests is due to be carried out in a different laboratory in the
first half of 2023 to validate the results.
13. Publication No Cu0109
Issue Date: December 2022
Page 10
The tests were carried out on:
• 1.5 mm2
fire-resistant cables carrying 25 A
• 4 mm2
fire-resistant cables carrying 45 A
They followed the standard temperature-time curve of a post-flashover fire as defined in ISO 834.
The tests revealed that, up to 90 minutes, the Joule losses do not affect the performance of the copper
conductors. After that time, they lead to a conductor temperature approaching the copper melting point,
causing the conductor to break. If the installation must remain functional beyond 90 minutes (safety class 120),
measures should be taken to avoid such a loss of integrity in the cable. It is highly recommended to consult cable
manufacturers or fire engineers who can assist in modelling the thermal balance of the cable under fire
conditions according to the IEC 60287-1 analytical method. Subsequently, the conductor cross-section can be
increased until the impact of the Joule losses on the thermal balance is sufficiently minimized. This measure can
be combined with the installation of additional support structures to reduce the mechanical stress on the cable.
Up to safety class 90, following the IEC 60364-5-52 standard for cables under normal working conditions is
sufficient to guarantee the current-carrying capacity, with no further calculations required.
14. Publication No Cu0109
Issue Date: December 2022
Page 11
CONCLUSION
Just as cables used in normal operating conditions, fire resistant cables must have a minimum conductor cross
section to ensure that the voltage drop is restricted and the current-carrying capacity guaranteed. When making
calculations, however, the increased electrical resistance at high temperature must be taken into account.
1. Limiting the voltage drop
The maximum voltage drop ∆𝑈𝑈 will normally be specified in the user guides of the fire safety
equipment. If this is not the case, one must consider a maximum voltage drop of 10%. The associated
maximum electrical resistance at 20°C (R20) can be calculated from:
For a single-phase circuit:
𝑅𝑅20 =
∆𝑈𝑈
2 . 𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡. 𝐼𝐼 . 𝑞𝑞20 . cos 𝜑𝜑
−
0.048
𝑞𝑞20 . cos 𝜑𝜑
For a three-phase circuit:
𝑅𝑅20 =
∆𝑈𝑈
√3 . 𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡. 𝐼𝐼 . 𝑞𝑞20 . cos 𝜑𝜑
−
0.048
𝑞𝑞20 . cos 𝜑𝜑
where:
𝑙𝑙𝑡𝑡𝑡𝑡𝑡𝑡 is the total cable length
Cos ϕ is the power factor
I is the rated current of the circuit
q20 is the electrical resistance correction factor under fire conditions, compared to 20°C
For cables smaller than 16 mm2
, the last term of the equation (0.048/q20 . cos 𝜑𝜑) can be ignored.
The value of q20 can be obtained from Table 2 or from:
𝑞𝑞20 =
�(100 − 𝑦𝑦) + (𝑦𝑦 . 𝑚𝑚20)�
100
where:
y is the percentage of the cable length estimated to be affected by fire, taking
compartmentalisation into account
m20 is the electrical resistance correction factor, relative to the value at 20°C; see Table 1 for a
standard cellulosic curve
The maximum cross section associated with R20 can be obtained from national standards for cables
operating under normal service conditions, or from Tables 1 to 4 of IEC/EN 60228.
2. Ensuring the current-carrying capacity
Up to 90-minute mark of the standard temperature-time curve as defined in ISO 834, the Joule losses do
not affect the performance of the copper conductors. The IEC 60364-5-52 standard for cables under normal
working conditions is sufficient to guarantee the current-carrying capacity.
15. Publication No Cu0109
Issue Date: December 2022
Page 12
After that time (safety class 120), the Joule effect, combined with the fire conditions, lead to a conductor
temperature approaching the copper melting point, with the risk of cable breakage. If safety class 120
applies, it is highly recommended to consult cable manufacturers or fire engineers who can assist in
modelling the thermal balance of the cable and formulating the required measures.
3. Determining the minimum cable cross section
The cross-section to be chosen is the higher of the two values from assessments 1 and 2.