Production	equipment	maintenance	planning	is	a	weekly	practice	
within	all	production	departments	at	Commercial	Metals	
Ø Production	equipment	maintenance	planning	is	a	weekly	practice	within	
all	production	departments	at	Commercial	Metals	Company	Steel	Texas.	
Prioritizing	equipment	repairs	and	preventive	maintenance	work	is	a	
challenge	because	there	is	no	equipment	performance	data	to	support	a	
plan	of	action.	
Ø Deliverables:
1. A	simulation	model	with	equipment	failure	modes	costs’	on	production	
and	maintenance
2. Recommendations	regarding	preventive	maintenance	plan
Problem The Shredding Process
Shredder Equipment Failure Modes and
Maintenance Planning
Logan Hanson, Matt Mitcham, Jeremy DiGiovanni, Doga Hacisalihoglu
Isidro Rosas, Richard Welfel, Adrain Ramos, Dillon Sterling
Project Process Map
Gantt Chart
Time Studies
Data Analysis
Simulation Findings and Future WorkCost Analysis
Consultants
• Based	on	the	data	given,	15	different	types	
were	identified	for	scheduled	downtime	and	
41	for	unscheduled	downtime
• Pareto	Chart	shows	the	frequencies	for	all	of	
these	types	of	downtime
• Using	the	80/20	rule,	top	3	most	problematic	
downtimes	were	selected	for	both	scheduled	
and	unscheduled
• Coefficients	of	Variances	
with	values	over	1	were	
used	to	determine	
which	down	times	were	
out	of	control.	
• Based	on	this	finding,	a	
list	of	prioritization	was	
constructed	with	the	
intention	of	helping	
preventive	maintenance	
planning.
• The	pie	chart	shows	the	contribution	of	each	of	
41	unscheduled	downtimes	to	total	downtime
• Using	Arena’s	Input	Analyzer,	probability	
distributions	for	each	6	selected	downtimes	
were	calculated
Dr.	Jesus	Jimenez	– Department	of	Engineering
Dr.	Francis	Mendez	- Department	of	Computer	Information	Systems
Dr.	Ricki	G.	Ingalls	– Department	of	Computer	Information	Systems
• 29%	of	all	processed	
scrap	metal	is	sent	
through	the	Non-Ferrous	
side	passing	through	the	
Eddy	Current	System.
• Using	this	project’s	
methodology	of	Data	
Analysis	and	through	the	
use	of	simulation,	more	
conclusions	regarding	the	
Non-Ferrous	side	could	
be	found.
• This	project’s	methodology	could	also	be	implemented	to	find	
differences	between	times	where	changes	are		applied	upon	the	
system	such	as	machine	replacements.
• Since	the	design	of	data	analysis	is	already	constructed,	the	user	
would	only	need	to	change	data	points	at	any	given	time	to	
dictate	the	findings	of	the	simulation
Daily	Down	Time	Costs
Weekly	Down	Time	Costs
Monthly	Down	Time	Costs
*
**Barko Crane	9	was	
down	during	data	
collection
*Time	Studies	on	Barko Cranes	and	Meatball	
Sorters	were	conducted	at	three	different	times	
to	calculate	the	infeed	and	exiting	rates
• Time	Studies	
data	
collected	for	
Barko Cranes	
and	
Meatball	
Sorters
**

FinalPresentationPoster2.5

  • 1.
    Production equipment maintenance planning is a weekly practice within all production departments at Commercial Metals Ø Production equipment maintenance planning is a weekly practice within all production departments at Commercial Metals Company Steel Texas. Prioritizing equipment repairs and preventive maintenance work is a challenge because there is no equipment performance data to support a plan of action. Ø Deliverables: 1.A simulation model with equipment failure modes costs’ on production and maintenance 2. Recommendations regarding preventive maintenance plan Problem The Shredding Process Shredder Equipment Failure Modes and Maintenance Planning Logan Hanson, Matt Mitcham, Jeremy DiGiovanni, Doga Hacisalihoglu Isidro Rosas, Richard Welfel, Adrain Ramos, Dillon Sterling Project Process Map Gantt Chart Time Studies Data Analysis Simulation Findings and Future WorkCost Analysis Consultants • Based on the data given, 15 different types were identified for scheduled downtime and 41 for unscheduled downtime • Pareto Chart shows the frequencies for all of these types of downtime • Using the 80/20 rule, top 3 most problematic downtimes were selected for both scheduled and unscheduled • Coefficients of Variances with values over 1 were used to determine which down times were out of control. • Based on this finding, a list of prioritization was constructed with the intention of helping preventive maintenance planning. • The pie chart shows the contribution of each of 41 unscheduled downtimes to total downtime • Using Arena’s Input Analyzer, probability distributions for each 6 selected downtimes were calculated Dr. Jesus Jimenez – Department of Engineering Dr. Francis Mendez - Department of Computer Information Systems Dr. Ricki G. Ingalls – Department of Computer Information Systems • 29% of all processed scrap metal is sent through the Non-Ferrous side passing through the Eddy Current System. • Using this project’s methodology of Data Analysis and through the use of simulation, more conclusions regarding the Non-Ferrous side could be found. • This project’s methodology could also be implemented to find differences between times where changes are applied upon the system such as machine replacements. • Since the design of data analysis is already constructed, the user would only need to change data points at any given time to dictate the findings of the simulation Daily Down Time Costs Weekly Down Time Costs Monthly Down Time Costs * **Barko Crane 9 was down during data collection *Time Studies on Barko Cranes and Meatball Sorters were conducted at three different times to calculate the infeed and exiting rates • Time Studies data collected for Barko Cranes and Meatball Sorters **