1) Repair work on the damaged liner in Cell E6 was ongoing and expected to continue through Thursday.
2) Final concrete pouring for the western stormwater diversion structure was delayed until Wednesday due to access issues. Work on the box culvert and pipe continued.
3) Preparations were made to access and restore the Cell E6 leachate risers starting on Wednesday.