Feasibility Study of Tanjung Priok Cruise Terminal
Demand Profile:
- Geographically
- Demographicall
y
Cruise Characteristics:
- Route
- Duration
- Tariff
Ability and Willingness to
Pay (ATP/WTP)
Percentage of
Potential Cruise
Passenger Demand
Cruise Passenger
Demand
Existing Land Characteristics
and Development Plan:
- Land Use
- Transportation
Cruise Terminal
Land Accessibility
Cruise Passenger
Demand Forecast
Socioeconomic
Variables
Methodology
WTP
ATP
Price (Rp)
Percentage of Respondents (%)
Percentage of Potential
Cruise Passenger
Demand
Cruise Price
Conceptual Framework
Ability-to-Pay/Willingness-to-Pay (ATP/WTP)
CruiseTrends
Source:AsiaCruiseTrends,2014Edition,CLIASoutheastAsia,2015
Cruise Trends
The table above indicates that coverage area of Tg. Priok Port as a transit port is
strictly limited to the cruise ship transit time, i.e 8-10 hours. This limitation could be
significantly relaxed by implementing the Ministerial Decree released by the Minister
of Transportation No. 121 of 2015 on the Provision of Easy Access for Foreign Tourists
Using Foreign-flagged Cruise Ships. The decree include Tg. Priok Port as
embarkation/debarkation port (also known as turnaround port) along with Benoa
Port, Tg. Perak Port, Makassar Port, and Belawan Port. Once this decree takes effect,
tourists should have higher degree of freedom in organizing their itinerary. Hence,
widening Tg. Priok Port’s coverage area.
Existing Tourist Destinations in and near Jakarta
No Tourism Destination Itinerary
1 In Jakarta • Taman Impian Jaya Ancol (Ancol Dreamland)
• Lapangan Merdeka (Merdeka Square)
• Monumen Nasional (National Monument)
• Istana Presiden (Presidential Palace)
• Museum Nasional (National Museum)
• Pelabuhan Sunda Kelapa (Sunda Kelapa Harbor)
• Taman Mini Indonesia Indah (Indonesia Miniature Park)
2 Near Jakarta • Kebun Raya Bogor (Bogor Botanical Garden)
• Puncak
• Taman Safari (Safari Garden)
54
%
46%
General Profile
86%
Employed
Retired
Unemployed
4%
10%
Diploma
Bachelor
Master
PhD
1%
18%
49%
32%
GeneralProfile
Purpose of Travel
Vacation
Business
Work
Study
Other
60%10% 20% 30% 40% 50%0% 70%
Revisit Indonesia for
vacation
80%
Not Interested
20%
Global Hinterland
Local Hinterland
0%2%4%6%8%10%12%14%16%18%
Jakarta
West Java
Bali & Lombok
Central Java
East Kalimantan
North Sumatera
West Sumatera
Surabaya
Aceh
Riau
South Kalimantan
17%
10%
7%
4%
1%
1%
0.75%
0.50%
0.25%
0.25%
0.25%
0% 30%
Frequency
5%
10%
15%
20%
25%
30%
20%10%
25%
21%
19%
1%
2%
VacationBudget
18
%
16
%
14
%
12
%
10
%
8%
6%
4%
2%
0%
Frequency(%)
<9,999
19,999
29,999
39,999
49,999
59,999
69,999
79,999
229,999
209,999
89,999
99,999
109,999
119,999
129,999
139,999
159,999
169,999
189,999
Annual Income (USD)
Income Profile
Kep. Seribu
Jakarta Old Town
TMII
Taman Safari
Bogor Botanical Garden
Gunung Padang Megalithic Site
Tangkuban Perahu
Pelabuhan Ratu
Pangandaran Beach
Tourism Destination
Bali
West Nusa Tenggara
West Papua
Yogyakarta
East Nusa Tenggara
Central Java
Sumatera
Maluku
Kalimantan
North Sulawesi
Southeast Sulawesi
South Sulawesi
Central Sulawesi
East Java
Banten
Mentawai Island
Kep. Seribu
Jakarta Old Town
TMII
Taman Safari
Bogor
Gunung Padang
Bandung
Pelabuhan Ratu
Pangandaran Beach
Other
10% 20%0% 30% 40% 50% 60% 70%
10% 20%0% 30% 40%
Vacation Behavior
Twice
37%
Once
51%
Three times
12%
Four times and more
2.5%
* in a year
45% 2% 2% 2% 1%
Holiday (family, school, pre-semester), break (spring, winter)
Off days, avoid holiday
season, other
Weather, low price,
work season, new year,
long holiday
GENERAL CRUISE
CHARACTERISTIC
24%
15%
19%10%
10%
5%
10%
10%Intra-continental
cruise trip
Inter-continental
cruise trip
adj PATP/WTP = ϕATP/WTP . r . PATP/WTP
ATP/WTP
No Cruise Packages Price ϕATP ϕWTP r adj PATP adj PWTP
1 3-5 days $500 0.13 0.28 0.10 9% 10%
2 6-8 days $1500 0.20 0.47 0.10 12% 11%
3 9-15 days $4500 0.06 0.17 0.10 3% 0.20%
y = 254.61x-4.513
R² = 0.8757
y = 252.94x-1.306
R² = 0.907
$-
$500
$1,000
$1,500
$2,000
$2,500
$3,000
$3,500
$4,000
$4,500
$5,000
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
CruisePrice(USD)
Percentage of Respondent (%)
High Price
Medium Price
Low Price
ATP Med
WTP 6-8 days
Power (ATP Med)
Power (WTP 6-8 days)
DemandForecast
Direct Demand Linear Growth
Cruise Passenger
Demand
Direct Demand1
Induced Demand2
Estimated from historical
demand of Tg. Priok Port
Estimated form historical
demand of Soetta3 & Halim4
Airports
1Demand due to existing
capacity, i.e normal demand
2Demand due to increased
capacity, i.e additional
demand
Year Soetta+Halim Tg. Priok Total Tourists
2005 1,149,800 66,332 1,216,132
2006 1,168,843 66,671 1,235,514
2007 1,150,322 65,735 1,216,057
2008 1,466,903 67,886 1,534,789
2009 1,392,702 59,212 1,451,914
2010 1,829,007 63,859 1,892,866
2011 1,938,773 65,171 2,003,944
2012 2,059,345 66,168 2,125,513
2013 2,070,255 65,227 2,135,482
2014 2,254,354 64,941 2,319,295
Source: Compiled from BPS 2006 - 2015
ExistingandForecastedTg.PriokTourist 1
2
1
ExistingTg.PriokPassengers
3Soekarno-Hatta Airport
4Halim Perdanakusuma Airport
Scenario 1 Polynomial Growth Scenario 2 Linear Growth
Scenario 3 Power Growth Year Soetta+Halim Tg. Priok Total Tourists
2005 1,149,800 66,332 1,216,132
2006 1,168,843 66,671 1,235,514
2007 1,150,322 65,735 1,216,057
2008 1,466,903 67,886 1,534,789
2009 1,392,702 59,212 1,451,914
2010 1,829,007 63,859 1,892,866
2011 1,938,773 65,171 2,003,944
2012 2,059,345 66,168 2,125,513
2013 2,070,255 65,227 2,135,482
2014 2,254,354 64,941 2,319,295
Source: Compiled from BPS 2006 - 2015
DemandForecast
ForecastedSoettaandHalimTourist
2
Soekarno-HattaPassengersSoekarno-HattaPassengers
Soekarno-HattaPassengers
Demand Forecast
Japan
S. Korea
Malaysia
China
Singapore
Thailand
Vietnam
Hong Kong
Taiwan
India
Philippines
Myanmar
Cambodia
Sri Lanka
Maldives
Cruise Passengers in
Asia in 2015
* In thousands
Source: Asia Cruise Trends,
2014 Edition, CLIA Southeast
Asia, 2015
Total demand = direct demand + adj PWTP . Induced demand
Construction
Phase
The proposed “M” Island
Source: http://jakartalrt.com/info-dan-rute-mrt-
jakarta/, accessed on June, 19th 2016 04:31
Jakarta MRT
Jakarta MRT
Source: http://jakartalrt.com/info-dan-rute-mrt-jakarta/,
accessed on June, 19th 2016 04:31
Jakarta LRT
Source: http://jakartalrt.com/info-dan-rute-lrt-jabodetabek/ ,
accessed June, 19th 2016 04:31
The Proposed
“M” Island
KETERANGAN
1
2
3
4
5
6
7
Corridor 2: Pulo Mas-Tanah Abang
Corridor 3: Joglo-Tanah Abang
Corridor 4: Puri Indah-Tanah Abang
Corridor 5: Pesing-Kelapa Gading
Corridor 6: Ancol-Kemayoran
Corridor 7: Bandara Soetta-Kemayoran
Corridor 1: Kebayoran-Kelapa Gading
LRT Lines
LRT SERVICE SYSTEM

More Related Content

Viewers also liked

CRUISE TERMINAL - Thesis research writing
CRUISE TERMINAL - Thesis  research writingCRUISE TERMINAL - Thesis  research writing
CRUISE TERMINAL - Thesis research writing
Jasmine Sidhu
 
Thesis -International Cruise Terminal in Goa
Thesis -International Cruise Terminal in GoaThesis -International Cruise Terminal in Goa
Thesis -International Cruise Terminal in GoaSanah Patel
 
Terminal Design
Terminal DesignTerminal Design
Terminal Design
Mal Mai
 
Terminal de Cruzeiros de Hong Kong
Terminal de Cruzeiros de Hong KongTerminal de Cruzeiros de Hong Kong
Terminal de Cruzeiros de Hong Kong
Ernesto São Thiago
 
Cruise Terminal in Callao, Peru - Terminal marítimo para cruceros en el Callao.
Cruise Terminal in Callao, Peru - Terminal marítimo para cruceros en el Callao.Cruise Terminal in Callao, Peru - Terminal marítimo para cruceros en el Callao.
Cruise Terminal in Callao, Peru - Terminal marítimo para cruceros en el Callao.
Joe Malpica Pimentel
 
Architectural thesis national maritime complex
Architectural thesis   national maritime complexArchitectural thesis   national maritime complex
Architectural thesis national maritime complexAishwarya Baskaran
 
2010 Thesis Project
2010 Thesis Project2010 Thesis Project
2010 Thesis Project
Charissa.Williams
 
Cruise Tourism
Cruise TourismCruise Tourism
Cruise Tourism
wilson tom
 
Presentasi pilotage port of newtanjung priok
Presentasi pilotage port of  newtanjung priokPresentasi pilotage port of  newtanjung priok
Presentasi pilotage port of newtanjung priok
kundil
 
Sistem Informasi Angkutan Barang - Basic Concept
Sistem Informasi Angkutan Barang - Basic ConceptSistem Informasi Angkutan Barang - Basic Concept
Sistem Informasi Angkutan Barang - Basic Concept
Daniel Bastian Tandjung, PMP
 
Analisis dampak lalu lintas
Analisis dampak lalu lintasAnalisis dampak lalu lintas
Analisis dampak lalu lintas
Ilhamhidayatullah Ilhamhidayatullah
 
El hombre y la ciudad
El hombre y la ciudadEl hombre y la ciudad
El hombre y la ciudadmotor159head
 
Ciudad Del Transporte
Ciudad Del TransporteCiudad Del Transporte
Ciudad Del Transporteguesta276a8a
 
Urban Destinies_Latin America
Urban Destinies_Latin AmericaUrban Destinies_Latin America
Urban Destinies_Latin AmericaManisha Balani
 
Tacna turística
Tacna turísticaTacna turística
Tacna turística
Reynaldo de la Cruz
 
Terminal Depósito para el Transporte Urbano
Terminal Depósito para el Transporte UrbanoTerminal Depósito para el Transporte Urbano
Terminal Depósito para el Transporte Urbanopato
 

Viewers also liked (20)

CRUISE TERMINAL - Thesis research writing
CRUISE TERMINAL - Thesis  research writingCRUISE TERMINAL - Thesis  research writing
CRUISE TERMINAL - Thesis research writing
 
Thesis -International Cruise Terminal in Goa
Thesis -International Cruise Terminal in GoaThesis -International Cruise Terminal in Goa
Thesis -International Cruise Terminal in Goa
 
Terminal Design
Terminal DesignTerminal Design
Terminal Design
 
Terminal de Cruzeiros de Hong Kong
Terminal de Cruzeiros de Hong KongTerminal de Cruzeiros de Hong Kong
Terminal de Cruzeiros de Hong Kong
 
Cruise Terminal in Callao, Peru - Terminal marítimo para cruceros en el Callao.
Cruise Terminal in Callao, Peru - Terminal marítimo para cruceros en el Callao.Cruise Terminal in Callao, Peru - Terminal marítimo para cruceros en el Callao.
Cruise Terminal in Callao, Peru - Terminal marítimo para cruceros en el Callao.
 
Architectural thesis national maritime complex
Architectural thesis   national maritime complexArchitectural thesis   national maritime complex
Architectural thesis national maritime complex
 
2010 Thesis Project
2010 Thesis Project2010 Thesis Project
2010 Thesis Project
 
Concept sheet - Thesis
Concept sheet - ThesisConcept sheet - Thesis
Concept sheet - Thesis
 
Kai Tak Submission Documents
Kai Tak Submission DocumentsKai Tak Submission Documents
Kai Tak Submission Documents
 
Cruise Tourism
Cruise TourismCruise Tourism
Cruise Tourism
 
Presentasi pilotage port of newtanjung priok
Presentasi pilotage port of  newtanjung priokPresentasi pilotage port of  newtanjung priok
Presentasi pilotage port of newtanjung priok
 
Sistem Informasi Angkutan Barang - Basic Concept
Sistem Informasi Angkutan Barang - Basic ConceptSistem Informasi Angkutan Barang - Basic Concept
Sistem Informasi Angkutan Barang - Basic Concept
 
Analisis dampak lalu lintas
Analisis dampak lalu lintasAnalisis dampak lalu lintas
Analisis dampak lalu lintas
 
El hombre y la ciudad
El hombre y la ciudadEl hombre y la ciudad
El hombre y la ciudad
 
Ciudad Del Transporte
Ciudad Del TransporteCiudad Del Transporte
Ciudad Del Transporte
 
Urban Destinies_Latin America
Urban Destinies_Latin AmericaUrban Destinies_Latin America
Urban Destinies_Latin America
 
Tacna turística
Tacna turísticaTacna turística
Tacna turística
 
Pelindo i
Pelindo iPelindo i
Pelindo i
 
Exposicion
ExposicionExposicion
Exposicion
 
Terminal Depósito para el Transporte Urbano
Terminal Depósito para el Transporte UrbanoTerminal Depósito para el Transporte Urbano
Terminal Depósito para el Transporte Urbano
 

Similar to Feasibility Study of Tanjung Priok Cruise Terminal

20140528 nok
20140528 nok20140528 nok
20140528 nokShaen PD
 
Suape Institucional
Suape InstitucionalSuape Institucional
Suape Institucionalriverbank-au
 
İsthubs v1.8-video with-voice
İsthubs v1.8-video with-voiceİsthubs v1.8-video with-voice
İsthubs v1.8-video with-voice
Istanbul Hub
 
Sukanto Roy_Latest CV
Sukanto Roy_Latest CVSukanto Roy_Latest CV
Sukanto Roy_Latest CVSukanto Roy
 
Regional ports interregional trade flows of grain production of Indonesia
Regional ports interregional trade flows of grain production of IndonesiaRegional ports interregional trade flows of grain production of Indonesia
Regional ports interregional trade flows of grain production of Indonesia
Eugene Tkachenko
 
Corrosion Management System and Implementation of IMO PSPC on FPSO
Corrosion Management System and Implementation of IMO PSPC on FPSOCorrosion Management System and Implementation of IMO PSPC on FPSO
Corrosion Management System and Implementation of IMO PSPC on FPSO
Putu Indra Mahatrisna
 
Improvement of urban transport system
Improvement of urban transport systemImprovement of urban transport system
Improvement of urban transport system
Dr. Zar Rdj
 
Port cost as a component of total supply chain cost
Port cost as a component of total supply chain cost   Port cost as a component of total supply chain cost
Port cost as a component of total supply chain cost
Tristan Wiggill
 
Johor port bcg
Johor port bcgJohor port bcg
Johor port bcg
Fikri Zaidi
 
Expanding Tourism in the Cooperative Sector
Expanding Tourism in the Cooperative SectorExpanding Tourism in the Cooperative Sector
Expanding Tourism in the Cooperative Sector
jo bitonio
 
VCDNP_ Sri Lanka Indunil.pdf
VCDNP_ Sri Lanka Indunil.pdfVCDNP_ Sri Lanka Indunil.pdf
VCDNP_ Sri Lanka Indunil.pdf
ssuserddf2ae
 
Csr of bangkok airways
Csr of bangkok airwaysCsr of bangkok airways
Csr of bangkok airways
Chormvirak Moulsem
 
Greater Jakarta Transport - on the way to transformation
Greater Jakarta Transport - on the way to transformationGreater Jakarta Transport - on the way to transformation
Greater Jakarta Transport - on the way to transformation
Institute for Transport Studies (ITS)
 
Management Presentation 2016_Update 1Q-16_v20
Management Presentation 2016_Update 1Q-16_v20Management Presentation 2016_Update 1Q-16_v20
Management Presentation 2016_Update 1Q-16_v20Adrianto Januri
 
Maputo corridor: Where to now?
Maputo corridor: Where to now?Maputo corridor: Where to now?
Maputo corridor: Where to now?
Tristan Wiggill
 
Moya Group Profile Company (Moya Indonesia Holdings)
Moya Group Profile Company (Moya Indonesia Holdings)Moya Group Profile Company (Moya Indonesia Holdings)
Moya Group Profile Company (Moya Indonesia Holdings)
ibadil haqqi
 
моделирование спроса на услуги контейнерного терминала
моделирование спроса на услуги контейнерного терминаламоделирование спроса на услуги контейнерного терминала
моделирование спроса на услуги контейнерного терминала
Александр Головизнин
 
Topic 3 Papua New Guinea Experience in Global Sourcing.pptx
Topic 3 Papua New Guinea Experience in Global Sourcing.pptxTopic 3 Papua New Guinea Experience in Global Sourcing.pptx
Topic 3 Papua New Guinea Experience in Global Sourcing.pptx
ShaAbdurahman
 

Similar to Feasibility Study of Tanjung Priok Cruise Terminal (20)

20140528 nok
20140528 nok20140528 nok
20140528 nok
 
Suape Institucional
Suape InstitucionalSuape Institucional
Suape Institucional
 
İsthubs v1.8-video with-voice
İsthubs v1.8-video with-voiceİsthubs v1.8-video with-voice
İsthubs v1.8-video with-voice
 
Sukanto Roy_Latest CV
Sukanto Roy_Latest CVSukanto Roy_Latest CV
Sukanto Roy_Latest CV
 
Regional ports interregional trade flows of grain production of Indonesia
Regional ports interregional trade flows of grain production of IndonesiaRegional ports interregional trade flows of grain production of Indonesia
Regional ports interregional trade flows of grain production of Indonesia
 
Corrosion Management System and Implementation of IMO PSPC on FPSO
Corrosion Management System and Implementation of IMO PSPC on FPSOCorrosion Management System and Implementation of IMO PSPC on FPSO
Corrosion Management System and Implementation of IMO PSPC on FPSO
 
Improvement of urban transport system
Improvement of urban transport systemImprovement of urban transport system
Improvement of urban transport system
 
Port cost as a component of total supply chain cost
Port cost as a component of total supply chain cost   Port cost as a component of total supply chain cost
Port cost as a component of total supply chain cost
 
Johor port bcg
Johor port bcgJohor port bcg
Johor port bcg
 
Welcome Irkutsk
Welcome IrkutskWelcome Irkutsk
Welcome Irkutsk
 
Expanding Tourism in the Cooperative Sector
Expanding Tourism in the Cooperative SectorExpanding Tourism in the Cooperative Sector
Expanding Tourism in the Cooperative Sector
 
VCDNP_ Sri Lanka Indunil.pdf
VCDNP_ Sri Lanka Indunil.pdfVCDNP_ Sri Lanka Indunil.pdf
VCDNP_ Sri Lanka Indunil.pdf
 
CV CE.Yana
CV CE.YanaCV CE.Yana
CV CE.Yana
 
Csr of bangkok airways
Csr of bangkok airwaysCsr of bangkok airways
Csr of bangkok airways
 
Greater Jakarta Transport - on the way to transformation
Greater Jakarta Transport - on the way to transformationGreater Jakarta Transport - on the way to transformation
Greater Jakarta Transport - on the way to transformation
 
Management Presentation 2016_Update 1Q-16_v20
Management Presentation 2016_Update 1Q-16_v20Management Presentation 2016_Update 1Q-16_v20
Management Presentation 2016_Update 1Q-16_v20
 
Maputo corridor: Where to now?
Maputo corridor: Where to now?Maputo corridor: Where to now?
Maputo corridor: Where to now?
 
Moya Group Profile Company (Moya Indonesia Holdings)
Moya Group Profile Company (Moya Indonesia Holdings)Moya Group Profile Company (Moya Indonesia Holdings)
Moya Group Profile Company (Moya Indonesia Holdings)
 
моделирование спроса на услуги контейнерного терминала
моделирование спроса на услуги контейнерного терминаламоделирование спроса на услуги контейнерного терминала
моделирование спроса на услуги контейнерного терминала
 
Topic 3 Papua New Guinea Experience in Global Sourcing.pptx
Topic 3 Papua New Guinea Experience in Global Sourcing.pptxTopic 3 Papua New Guinea Experience in Global Sourcing.pptx
Topic 3 Papua New Guinea Experience in Global Sourcing.pptx
 

Feasibility Study of Tanjung Priok Cruise Terminal

  • 1. PT Rayasurverindo Tirtasarana PORT AUTHORITY TANJUNG PRIOK HUB PORT JL. Palmas No.1 Pelabuhan Tanjung Priok Jakarta 14310 2016 Financial Year Final Presentation Feasibility Study of Tanjung Priok Cruise Terminal
  • 2. Demand Profile: - Geographically - Demographicall y Cruise Characteristics: - Route - Duration - Tariff Ability and Willingness to Pay (ATP/WTP) Percentage of Potential Cruise Passenger Demand Cruise Passenger Demand Existing Land Characteristics and Development Plan: - Land Use - Transportation Cruise Terminal Land Accessibility Cruise Passenger Demand Forecast Socioeconomic Variables Methodology
  • 3. WTP ATP Price (Rp) Percentage of Respondents (%) Percentage of Potential Cruise Passenger Demand Cruise Price Conceptual Framework Ability-to-Pay/Willingness-to-Pay (ATP/WTP)
  • 5. Cruise Trends The table above indicates that coverage area of Tg. Priok Port as a transit port is strictly limited to the cruise ship transit time, i.e 8-10 hours. This limitation could be significantly relaxed by implementing the Ministerial Decree released by the Minister of Transportation No. 121 of 2015 on the Provision of Easy Access for Foreign Tourists Using Foreign-flagged Cruise Ships. The decree include Tg. Priok Port as embarkation/debarkation port (also known as turnaround port) along with Benoa Port, Tg. Perak Port, Makassar Port, and Belawan Port. Once this decree takes effect, tourists should have higher degree of freedom in organizing their itinerary. Hence, widening Tg. Priok Port’s coverage area. Existing Tourist Destinations in and near Jakarta No Tourism Destination Itinerary 1 In Jakarta • Taman Impian Jaya Ancol (Ancol Dreamland) • Lapangan Merdeka (Merdeka Square) • Monumen Nasional (National Monument) • Istana Presiden (Presidential Palace) • Museum Nasional (National Museum) • Pelabuhan Sunda Kelapa (Sunda Kelapa Harbor) • Taman Mini Indonesia Indah (Indonesia Miniature Park) 2 Near Jakarta • Kebun Raya Bogor (Bogor Botanical Garden) • Puncak • Taman Safari (Safari Garden)
  • 8. Purpose of Travel Vacation Business Work Study Other 60%10% 20% 30% 40% 50%0% 70% Revisit Indonesia for vacation 80% Not Interested 20%
  • 10. Local Hinterland 0%2%4%6%8%10%12%14%16%18% Jakarta West Java Bali & Lombok Central Java East Kalimantan North Sumatera West Sumatera Surabaya Aceh Riau South Kalimantan 17% 10% 7% 4% 1% 1% 0.75% 0.50% 0.25% 0.25% 0.25%
  • 12.
  • 14. Taman Safari Bogor Botanical Garden Gunung Padang Megalithic Site Tangkuban Perahu
  • 16. Tourism Destination Bali West Nusa Tenggara West Papua Yogyakarta East Nusa Tenggara Central Java Sumatera Maluku Kalimantan North Sulawesi Southeast Sulawesi South Sulawesi Central Sulawesi East Java Banten Mentawai Island Kep. Seribu Jakarta Old Town TMII Taman Safari Bogor Gunung Padang Bandung Pelabuhan Ratu Pangandaran Beach Other 10% 20%0% 30% 40% 50% 60% 70% 10% 20%0% 30% 40%
  • 17. Vacation Behavior Twice 37% Once 51% Three times 12% Four times and more 2.5% * in a year 45% 2% 2% 2% 1% Holiday (family, school, pre-semester), break (spring, winter) Off days, avoid holiday season, other Weather, low price, work season, new year, long holiday
  • 19. adj PATP/WTP = ϕATP/WTP . r . PATP/WTP ATP/WTP No Cruise Packages Price ϕATP ϕWTP r adj PATP adj PWTP 1 3-5 days $500 0.13 0.28 0.10 9% 10% 2 6-8 days $1500 0.20 0.47 0.10 12% 11% 3 9-15 days $4500 0.06 0.17 0.10 3% 0.20% y = 254.61x-4.513 R² = 0.8757 y = 252.94x-1.306 R² = 0.907 $- $500 $1,000 $1,500 $2,000 $2,500 $3,000 $3,500 $4,000 $4,500 $5,000 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% CruisePrice(USD) Percentage of Respondent (%) High Price Medium Price Low Price ATP Med WTP 6-8 days Power (ATP Med) Power (WTP 6-8 days)
  • 20. DemandForecast Direct Demand Linear Growth Cruise Passenger Demand Direct Demand1 Induced Demand2 Estimated from historical demand of Tg. Priok Port Estimated form historical demand of Soetta3 & Halim4 Airports 1Demand due to existing capacity, i.e normal demand 2Demand due to increased capacity, i.e additional demand Year Soetta+Halim Tg. Priok Total Tourists 2005 1,149,800 66,332 1,216,132 2006 1,168,843 66,671 1,235,514 2007 1,150,322 65,735 1,216,057 2008 1,466,903 67,886 1,534,789 2009 1,392,702 59,212 1,451,914 2010 1,829,007 63,859 1,892,866 2011 1,938,773 65,171 2,003,944 2012 2,059,345 66,168 2,125,513 2013 2,070,255 65,227 2,135,482 2014 2,254,354 64,941 2,319,295 Source: Compiled from BPS 2006 - 2015 ExistingandForecastedTg.PriokTourist 1 2 1 ExistingTg.PriokPassengers 3Soekarno-Hatta Airport 4Halim Perdanakusuma Airport
  • 21. Scenario 1 Polynomial Growth Scenario 2 Linear Growth Scenario 3 Power Growth Year Soetta+Halim Tg. Priok Total Tourists 2005 1,149,800 66,332 1,216,132 2006 1,168,843 66,671 1,235,514 2007 1,150,322 65,735 1,216,057 2008 1,466,903 67,886 1,534,789 2009 1,392,702 59,212 1,451,914 2010 1,829,007 63,859 1,892,866 2011 1,938,773 65,171 2,003,944 2012 2,059,345 66,168 2,125,513 2013 2,070,255 65,227 2,135,482 2014 2,254,354 64,941 2,319,295 Source: Compiled from BPS 2006 - 2015 DemandForecast ForecastedSoettaandHalimTourist 2 Soekarno-HattaPassengersSoekarno-HattaPassengers Soekarno-HattaPassengers
  • 22. Demand Forecast Japan S. Korea Malaysia China Singapore Thailand Vietnam Hong Kong Taiwan India Philippines Myanmar Cambodia Sri Lanka Maldives Cruise Passengers in Asia in 2015 * In thousands Source: Asia Cruise Trends, 2014 Edition, CLIA Southeast Asia, 2015 Total demand = direct demand + adj PWTP . Induced demand Construction Phase
  • 23. The proposed “M” Island Source: http://jakartalrt.com/info-dan-rute-mrt- jakarta/, accessed on June, 19th 2016 04:31 Jakarta MRT
  • 25. Jakarta LRT Source: http://jakartalrt.com/info-dan-rute-lrt-jabodetabek/ , accessed June, 19th 2016 04:31 The Proposed “M” Island KETERANGAN 1 2 3 4 5 6 7 Corridor 2: Pulo Mas-Tanah Abang Corridor 3: Joglo-Tanah Abang Corridor 4: Puri Indah-Tanah Abang Corridor 5: Pesing-Kelapa Gading Corridor 6: Ancol-Kemayoran Corridor 7: Bandara Soetta-Kemayoran Corridor 1: Kebayoran-Kelapa Gading LRT Lines LRT SERVICE SYSTEM