Executive DCIMCopyright © 2011 Viridity Software, Inc. All Rights Reserved
AgendaCurrent Data Center Management ApproachData Center Management TrendsEmergence of Data Center Infrastructure Management (DCIM) ToolsCase Study & ROI MethodologyCopyright © 2011 Viridity Software, Inc. All Rights Reserved 2
Copyright © 2010 Viridity Software, Inc. All Rights Reserved 3Energy (Power & Cooling) is the FastestGrowing Expense in the Data Center Source: IDC, Worldwide Server Energy Expense 2009–2013 Forecast (12/09)
PUEPUE (and variations) A good startBecoming the de facto standard(s) for measuring data center efficiencyCopyright © 2011 Viridity Software, Inc. All Rights Reserved 4Total Facility Power     IT Equipment PowerNot the end-all-be-all
Fluctuations can be a good thing, reducing total energy consumption may cause your PUE to increase or decrease Lowering PUE – Incomplete PictureMust understand the affect of  Infrastructure Load and its Efficiency            IT Load and its EfficiencyCopyright © 2011 Viridity Software, Inc. All Rights Reserved 5
Without insight into utilization and IT power consumption,energy use and capacity are impossible to manage efficiently6Copyright © 2011 Viridity Software, Inc. All Rights Reserved
Trends: DCIM SolutionsCopyright © 2011 Viridity Software, Inc. All Rights Reserved 7DCIM… the new ‘buzzword’The premise… Don't just understand infrastructure or IT, understand how they intersectSolutions are new but are becoming more matureBridge the gap between IT, Facilities, and the needs of the business
Copyright © 2011 Viridity Software, Inc. All Rights Reserved Data center infrastructure management (DCIM) is the integration of (IT) and facilities management disciplines to centralize monitoring, management and intelligent capacity planning of a data center’s critical systems and increase availability.FeaturesBaseline, plan and intelligently manage capacity-- space, power, coolingDrive energy efficiency initiativesUse virtualization effectivelyOptimize critical infrastructure, improve uptimeReduce costs through effective utilization of infrastructureStreamline data center operations, implement best practices8What is DCIM?
How Does this Happen?FacilitiesCIOIT
Legacy Data Center ManagementCopyright © 2011 Viridity Software, Inc. All Rights Reserved 10
Current DCIMCopyright © 2011 Viridity Software, Inc. All Rights Reserved 11
Future ConvergenceCopyright © 2011 Viridity Software, Inc. All Rights Reserved 12
Case StudyOptimized Data CenterCopyright © 2011 Viridity Software, Inc. All Rights Reserved
Data Center: BeforeCopyright © 2011 Viridity Software, Inc. All Rights Reserved 14Data center before consolidation, tech refresh, and elimination of stranded assets.
Retire, Refresh, ConsolidateDetermine if an asset is nonproductive, under-productive, or only productive on demandVirtualize what makes senseTurning Off = Immediate bottom-line savingsCopyright © 2011 Viridity Software, Inc. All Rights Reserved 15
Data Center: AfterCopyright © 2011 Viridity Software, Inc. All Rights Reserved 16Data center after consolidation, tech refresh, and elimination of stranded assets.
Consolidation Results$148,309/yr. in Power & Cooling SavedCopyright © 2011 Viridity Software, Inc. All Rights Reserved 17
ROI savings calculationsRetiring a server = 300 watts at $.11/kWhUse PUE to estimate cooling savings Network cost savings = $50/portIf every server uses 1 man hour per month in support, then removing 100 servers is worth 10,000 man hours (5 man years)OS and application costs between $3-5K/yr
Estimated Annual ROI
EnergyCenterAsset Placement AssistanceSavings AssessmentTop Power ConsumersUtilization vs. Power20Copyright © 2011 Viridity Software, Inc. All Rights Reserved
EnergyCenterUnderutilized ServersBranch Circuit MonitorsRack Power Drill DownRack Power21Copyright © 2011 Viridity Software, Inc. All Rights Reserved
2011 Uptime Institute Award – “Outstanding IT Product in a User Deployment”“The only Data Center Energy Management solution thatprovides detailed understanding of power consumption withinhours of beginning deployment.”-- Andy Lawrence – The 451 Group22Copyright © 2011 Viridity Software, Inc. All Rights Reserved
Q & ACopyright © 2011 Viridity Software, Inc. All Rights Reserved
Register for a Live DemoDiscover the full power of the EnergyCenter Download EnergyCheck Free energy health-check in your data center!Copyright © 2011 Viridity Software, Inc. All Rights Reserved VIRIDITY.COM24

Executive DCIM

  • 1.
    Executive DCIMCopyright ©2011 Viridity Software, Inc. All Rights Reserved
  • 2.
    AgendaCurrent Data CenterManagement ApproachData Center Management TrendsEmergence of Data Center Infrastructure Management (DCIM) ToolsCase Study & ROI MethodologyCopyright © 2011 Viridity Software, Inc. All Rights Reserved 2
  • 3.
    Copyright © 2010Viridity Software, Inc. All Rights Reserved 3Energy (Power & Cooling) is the FastestGrowing Expense in the Data Center Source: IDC, Worldwide Server Energy Expense 2009–2013 Forecast (12/09)
  • 4.
    PUEPUE (and variations)A good startBecoming the de facto standard(s) for measuring data center efficiencyCopyright © 2011 Viridity Software, Inc. All Rights Reserved 4Total Facility Power IT Equipment PowerNot the end-all-be-all
  • 5.
    Fluctuations can bea good thing, reducing total energy consumption may cause your PUE to increase or decrease Lowering PUE – Incomplete PictureMust understand the affect of Infrastructure Load and its Efficiency IT Load and its EfficiencyCopyright © 2011 Viridity Software, Inc. All Rights Reserved 5
  • 6.
    Without insight intoutilization and IT power consumption,energy use and capacity are impossible to manage efficiently6Copyright © 2011 Viridity Software, Inc. All Rights Reserved
  • 7.
    Trends: DCIM SolutionsCopyright© 2011 Viridity Software, Inc. All Rights Reserved 7DCIM… the new ‘buzzword’The premise… Don't just understand infrastructure or IT, understand how they intersectSolutions are new but are becoming more matureBridge the gap between IT, Facilities, and the needs of the business
  • 8.
    Copyright © 2011Viridity Software, Inc. All Rights Reserved Data center infrastructure management (DCIM) is the integration of (IT) and facilities management disciplines to centralize monitoring, management and intelligent capacity planning of a data center’s critical systems and increase availability.FeaturesBaseline, plan and intelligently manage capacity-- space, power, coolingDrive energy efficiency initiativesUse virtualization effectivelyOptimize critical infrastructure, improve uptimeReduce costs through effective utilization of infrastructureStreamline data center operations, implement best practices8What is DCIM?
  • 9.
    How Does thisHappen?FacilitiesCIOIT
  • 10.
    Legacy Data CenterManagementCopyright © 2011 Viridity Software, Inc. All Rights Reserved 10
  • 11.
    Current DCIMCopyright ©2011 Viridity Software, Inc. All Rights Reserved 11
  • 12.
    Future ConvergenceCopyright ©2011 Viridity Software, Inc. All Rights Reserved 12
  • 13.
    Case StudyOptimized DataCenterCopyright © 2011 Viridity Software, Inc. All Rights Reserved
  • 14.
    Data Center: BeforeCopyright© 2011 Viridity Software, Inc. All Rights Reserved 14Data center before consolidation, tech refresh, and elimination of stranded assets.
  • 15.
    Retire, Refresh, ConsolidateDetermineif an asset is nonproductive, under-productive, or only productive on demandVirtualize what makes senseTurning Off = Immediate bottom-line savingsCopyright © 2011 Viridity Software, Inc. All Rights Reserved 15
  • 16.
    Data Center: AfterCopyright© 2011 Viridity Software, Inc. All Rights Reserved 16Data center after consolidation, tech refresh, and elimination of stranded assets.
  • 17.
    Consolidation Results$148,309/yr. inPower & Cooling SavedCopyright © 2011 Viridity Software, Inc. All Rights Reserved 17
  • 18.
    ROI savings calculationsRetiringa server = 300 watts at $.11/kWhUse PUE to estimate cooling savings Network cost savings = $50/portIf every server uses 1 man hour per month in support, then removing 100 servers is worth 10,000 man hours (5 man years)OS and application costs between $3-5K/yr
  • 19.
  • 20.
    EnergyCenterAsset Placement AssistanceSavingsAssessmentTop Power ConsumersUtilization vs. Power20Copyright © 2011 Viridity Software, Inc. All Rights Reserved
  • 21.
    EnergyCenterUnderutilized ServersBranch CircuitMonitorsRack Power Drill DownRack Power21Copyright © 2011 Viridity Software, Inc. All Rights Reserved
  • 22.
    2011 Uptime InstituteAward – “Outstanding IT Product in a User Deployment”“The only Data Center Energy Management solution thatprovides detailed understanding of power consumption withinhours of beginning deployment.”-- Andy Lawrence – The 451 Group22Copyright © 2011 Viridity Software, Inc. All Rights Reserved
  • 23.
    Q & ACopyright© 2011 Viridity Software, Inc. All Rights Reserved
  • 24.
    Register for aLive DemoDiscover the full power of the EnergyCenter Download EnergyCheck Free energy health-check in your data center!Copyright © 2011 Viridity Software, Inc. All Rights Reserved VIRIDITY.COM24

Editor's Notes

  • #5 In the end, the importance is ensuring business availability at the best cost.
  • #6 Here’s why…When reducing IT load, PUE calculation changes and looks worse. Adjustments to infrastructure must be made.How many of you receive bonuses based on PUE?
  • #8 Understand how IT and Infrastructure intersect because it is the only way to tie the costs to the business. >1% of organizations using DCIM today, 60% within 5 years according to Gartner
  • #9 Achieved through the implementation of specialized software, or hardware and sensors, DCIM will enable a common, real-time monitoring and management platform for all interdependent systems across IT and facility infrastructures.
  • #10 Each department is focused on their responsibility, without congruence.Facilities-- Energy Delivery, CIO-- Business Intelligence, IT-- Power ConsumptionAll three speak different languages.
  • #12 Darker shade initial Focus,Building out over time (lighter shade), focus on high value firstBuilding out elements in the lighter shadePurpose Built DCIMConnect to Business Value from Day 1Our approach to Asset Management - Automated Deep Discovery - Monitoring IT as well as Infrastructure Systems - Power - Utilization
  • #14 This case study reflects an Emerson site evaluation. That same data was run through Viridity’s simulation capabilities to demonstrate increasing IT efficiency and reducing costs.
  • #15 (This screen shot will be altered to accurately reflect this case study).
  • #17 Brief example. A real world scenario--- we have worked with a fortune 500 company, a 10x ROI was incurred of our software. $1,000,000/yr. was saved.
  • #19 Power---PUE= 2Network--- Port= $50/per port for lifetime (212 ports)Storage--- $10k/ server lifetimeCooling--- PUE=2Salary= $77k/yr.Licenses--- Application=$3K/ yr
  • #20 Power---PUE= 2 … $429K over 3 yearsNetwork--- Port= $50/per port for lifetime (212 ports)Storage--- $10k/ server lifetimeCooling--- PUE=2Salary= $77k/yr.Licenses--- Application=$3K/ yrGartner estimates $50k/ rack per year