Evergreen Packaging
Garrett Griffith: Final Update
8/14/2014
Introduction
 Garrett Griffith
 Sophomore at Arkansas Technical University in Russellville
 Electrical Engineering Major
 From the White Hall/Pine Bluff Area
 First summer here at Evergreen
Projects
Roll Data Compilation
Flowmeters
Core Shrinkage
Roll Data Project Objectives:
 Understand how paper is made
 Compile information for all rolls on PM2 including Diameter, Cover, Shell, Roll
I.D., Crown, Cover Type, Bearings, Materials, ect.
 Obtain same information for all spare rolls
 Check for accuracy
 Place information into Excel Spreadsheet
 Learn how to use SAP and get information into program
 Configure a specific spreadsheet for use by Kevin Kidder and Bill Wilson, it
will be maintained by them after completion.
• I spent a
considerable
amount of
time looking
through
drawings for
information
on the rolls
PM2 Excel
Roll Project: Current Progress
 We definitely underestimated the amount of
information on the rolls
 Still in the information gathering phase for the
SAP aspect
 Next step will be to learn SAP and implement
information there
 Spreadsheet for Kevin and Bill complete
Flowmeter Project Objectives:
 Determine where the Mill’s water goes
 Elizabeth began by placing ultrasonic flowmeters on various pipes in the mill
to detect flow
 Out of the 16 placed, 2 did not get a reading
 The Unfiltered White Water Pipe and the Filtered White Water Pipe (UFWW &
FWW) did not deliver a reading
 Also a flowmeter will be installed in Manhole H on the Boulevard Sewer
 I took over the Mill Water Usage Monitoring System Project from Elizabeth
Lott due to pregnancy
Using Siemens Portable Flowmeter
I also learned how to utilize specific instrumentation this summer
Using the Siemens
Portable Flowmeter to
measure flow on power
house fire water pump
7/8/14
Flowmeter Project: Current Progress
 We proceeded to try different manufactures
flowmeters to determine if it was a mechanical
failure that caused no reading
 We determined that there was not enough water
in the pipe to use an ultrasonic flowmeter
 Orifice plates were then selected
 Installation was completed by Turner
 Electrical Work was completed by Evers
Flowmeter Install
Turner
installing
flowmeters
6/24/14
Completed
install of
Rosemount
flowmeter
Flowmeter Issues
The only issue
encountered upon start
up of PM2 was a small
leak. After tightening
of the bolts the
problem was resolved
Flowmeter Electrical
Evers
running
conduit for
wiring of
flowmeters
7/9/14
Flowmeter Project: Current Progress
 After setting up Process Control we discovered that the measured flow
was outside of the transmitter’s ranges
 Higher ranged transmitters were selected and received from the
storeroom
 When Rudy (Experitec) and I got ready to install the new transmitters
it was discovered that the low side valve of the orifice plate was
closed. This caused backpressure that sent a reading of much higher
flow than was actually the case. Also one of the transmitters was
ranged wrong to begin with on the instrument side
 After fixing the mistakes and watching the readings for a couple of
days, all readings are normal, accurate, and in range
Manhole H Flowmeter Progress
 Began discussion with Rudy de Anda of Experitec
for specifications of manhole and outfall
 This flowmeter will be wireless with a ten year
battery lifespan and utilize a wireless gateway
 Currently waiting on parts to arrive
 Next step: install flowmeter, mount gateway and
run cat5 and 24V power to caustic plant rack
room, then incorporate into PI
Manhole H
Core Shrinkage Study Objectives:
 Evaluate the normal shrinkage of a core for
the extruders
 Determine a way to minimize core
shrinkage or at least get some data from
which we can adjust our asking cuts on the
cores
Core Shrinkage Study Course of Action
 A meeting was conducted with Sonoco, Nero Haralalka,
Rob Luter, Andrew Blue, myself, and others to determine
a way to accurately measure shrinkage
 Our plan was to go to Sonoco and measure 27 cores of
different lengths and ages and bring the back to the mill
to be measured periodically in different areas of varying
moisture and temperature
 The cores were placed in the core room, humidity lab,
and also on the wet end. They were measured in the
same 4 positions twice daily for a week while recording
temperature, humidity, and time
Core measurements
3530252015
0.18
0.16
0.14
0.12
0.10
0.08
0.06
S 0.01 07999
R-Sq 93.9%
R-Sq(adj) 93.0%
Cut Length
avgshrink
Fitted Line Plot - Core room
avg shrink = - 0.01 020 + 0.005059 Cut Length
3530252015
0.175
0.150
0.125
0.100
0.075
0.050
S 0.01 80290
R-Sq 82.4%
R-Sq(adj) 79.9%
Cut Length
avgshrink
Fitted Line Plot - Humidity Lab
avg shrink = - 0.01 635 + 0.004675 Cut Length
3530252015
0.26
0.24
0.22
0.20
0.18
0.16
0.14
0.12
0.10
S 0.01 1 8928
R-Sq 95.4%
R-Sq(adj) 94.8%
Cut Length
avgshrink
Fitted Line Plot - Wet End
avg shrink = 0.00668 + 0.006521 Cut Length
Results of Shrinkage Study
All measurements had strong
correlation to one another.
Based off of this information we
were able to adjust our asking
cut accordingly.
Teamwork makes the
dream work!
 Hanging signs
with Tyler
 Measuring
Flow with
Adam
 Observing the
base of a
pump
 Looking up
drawings for
all of our
projects
What I have learned
 Incorporating what I have learned at school into the real world is the most
important thing I have taken from this summer at the Mill
 From talks with people like Mike Cottrell I have gained a better understanding of
all things electrical
 There is a lot that goes into making paper
 This mill spends a ton of money
 How to do real research
 Project Management
 Not all flow meters are created equal
 How to ask for help
 How to look up a loop sheet
 It is always better to go in the field and look with your own eyes
 How to write a Requisition and Purchase Order
 Double check EVERYTHING
Questions?

Evergreen Packaging FINAL update 2014

  • 1.
  • 2.
    Introduction  Garrett Griffith Sophomore at Arkansas Technical University in Russellville  Electrical Engineering Major  From the White Hall/Pine Bluff Area  First summer here at Evergreen
  • 3.
  • 4.
    Roll Data ProjectObjectives:  Understand how paper is made  Compile information for all rolls on PM2 including Diameter, Cover, Shell, Roll I.D., Crown, Cover Type, Bearings, Materials, ect.  Obtain same information for all spare rolls  Check for accuracy  Place information into Excel Spreadsheet  Learn how to use SAP and get information into program  Configure a specific spreadsheet for use by Kevin Kidder and Bill Wilson, it will be maintained by them after completion.
  • 5.
    • I spenta considerable amount of time looking through drawings for information on the rolls
  • 6.
  • 7.
    Roll Project: CurrentProgress  We definitely underestimated the amount of information on the rolls  Still in the information gathering phase for the SAP aspect  Next step will be to learn SAP and implement information there  Spreadsheet for Kevin and Bill complete
  • 8.
    Flowmeter Project Objectives: Determine where the Mill’s water goes  Elizabeth began by placing ultrasonic flowmeters on various pipes in the mill to detect flow  Out of the 16 placed, 2 did not get a reading  The Unfiltered White Water Pipe and the Filtered White Water Pipe (UFWW & FWW) did not deliver a reading  Also a flowmeter will be installed in Manhole H on the Boulevard Sewer  I took over the Mill Water Usage Monitoring System Project from Elizabeth Lott due to pregnancy
  • 9.
    Using Siemens PortableFlowmeter I also learned how to utilize specific instrumentation this summer Using the Siemens Portable Flowmeter to measure flow on power house fire water pump 7/8/14
  • 10.
    Flowmeter Project: CurrentProgress  We proceeded to try different manufactures flowmeters to determine if it was a mechanical failure that caused no reading  We determined that there was not enough water in the pipe to use an ultrasonic flowmeter  Orifice plates were then selected  Installation was completed by Turner  Electrical Work was completed by Evers
  • 11.
  • 12.
    Flowmeter Issues The onlyissue encountered upon start up of PM2 was a small leak. After tightening of the bolts the problem was resolved
  • 13.
  • 14.
    Flowmeter Project: CurrentProgress  After setting up Process Control we discovered that the measured flow was outside of the transmitter’s ranges  Higher ranged transmitters were selected and received from the storeroom  When Rudy (Experitec) and I got ready to install the new transmitters it was discovered that the low side valve of the orifice plate was closed. This caused backpressure that sent a reading of much higher flow than was actually the case. Also one of the transmitters was ranged wrong to begin with on the instrument side  After fixing the mistakes and watching the readings for a couple of days, all readings are normal, accurate, and in range
  • 15.
    Manhole H FlowmeterProgress  Began discussion with Rudy de Anda of Experitec for specifications of manhole and outfall  This flowmeter will be wireless with a ten year battery lifespan and utilize a wireless gateway  Currently waiting on parts to arrive  Next step: install flowmeter, mount gateway and run cat5 and 24V power to caustic plant rack room, then incorporate into PI
  • 16.
  • 17.
    Core Shrinkage StudyObjectives:  Evaluate the normal shrinkage of a core for the extruders  Determine a way to minimize core shrinkage or at least get some data from which we can adjust our asking cuts on the cores
  • 18.
    Core Shrinkage StudyCourse of Action  A meeting was conducted with Sonoco, Nero Haralalka, Rob Luter, Andrew Blue, myself, and others to determine a way to accurately measure shrinkage  Our plan was to go to Sonoco and measure 27 cores of different lengths and ages and bring the back to the mill to be measured periodically in different areas of varying moisture and temperature  The cores were placed in the core room, humidity lab, and also on the wet end. They were measured in the same 4 positions twice daily for a week while recording temperature, humidity, and time
  • 19.
  • 20.
    3530252015 0.18 0.16 0.14 0.12 0.10 0.08 0.06 S 0.01 07999 R-Sq93.9% R-Sq(adj) 93.0% Cut Length avgshrink Fitted Line Plot - Core room avg shrink = - 0.01 020 + 0.005059 Cut Length 3530252015 0.175 0.150 0.125 0.100 0.075 0.050 S 0.01 80290 R-Sq 82.4% R-Sq(adj) 79.9% Cut Length avgshrink Fitted Line Plot - Humidity Lab avg shrink = - 0.01 635 + 0.004675 Cut Length 3530252015 0.26 0.24 0.22 0.20 0.18 0.16 0.14 0.12 0.10 S 0.01 1 8928 R-Sq 95.4% R-Sq(adj) 94.8% Cut Length avgshrink Fitted Line Plot - Wet End avg shrink = 0.00668 + 0.006521 Cut Length Results of Shrinkage Study All measurements had strong correlation to one another. Based off of this information we were able to adjust our asking cut accordingly.
  • 21.
    Teamwork makes the dreamwork!  Hanging signs with Tyler  Measuring Flow with Adam  Observing the base of a pump  Looking up drawings for all of our projects
  • 22.
    What I havelearned  Incorporating what I have learned at school into the real world is the most important thing I have taken from this summer at the Mill  From talks with people like Mike Cottrell I have gained a better understanding of all things electrical  There is a lot that goes into making paper  This mill spends a ton of money  How to do real research  Project Management  Not all flow meters are created equal  How to ask for help  How to look up a loop sheet  It is always better to go in the field and look with your own eyes  How to write a Requisition and Purchase Order  Double check EVERYTHING
  • 23.