SlideShare a Scribd company logo
1 of 2
Download to read offline
FM CASE STUDY multi-tenanted building  glenn massey




                                maintain
                                your cool
                                Carrying out refurbishments in occupied
                                buildings may seem challenging but one
                                flagship property in Regent Street managed to
                                successfully cut costs and increase efficiency




                                I
                                    n 2007, a major refurbishment      within the office and retail store
                                    strategy commenced at a            environments. This in turn created
                                    flagship building in Regent        concern from tenants regarding
                                    Street, London.                    service charge levels.
                                       The typical Edwardian West         The original appraisal of the site,
                                End property has a floor area in       which took place on a summer’s
                                the region of 38,000 sq ft and         day, immediately revealed that
                                different commercial classifications   the heating was operating at the
                                of use, with retail premises on the    same time as the cooling. Further
                                ground floor and basement and six      investigation showed that the
                                floors of commercial office space      major plant items, such as chillers,
                                above. The retail part is home to      boilers, lifts and air treatment plant
                                a high-end luxury womenswear           were in a dilapidated state. The
                                and menswear retail brand. The         standard of maintenance was also
                                office floors are multi-tenanted and   poor and this contributed to the
                                are home to some internationally       high number of contractor call outs.
                                known businesses, and therefore        From the frequency of call outs it
                                have a mixture of different            was clear that a rationalisation of
                                business needs.                        the maintenance and maintenance
                                                                       contract was needed.
                                The challenge
                                The site’s fixed building services
                                were in a dilapidated state
                                and were operating extremely
                                inefficiently. The performance of
                                the heating and cooling systems
                                serving the building was such
                                that heating and cooling often
                                operated simultaneously. Both
  ILLUSTRATION: ROBERT HANSON




                                would often break down when
                                needed most because the systems
                                were being operated for long
                                hours and in seasons when they
                                were not needed. The result of
                                this inefficiency was an increase
                                in utility costs and discomfort

24 | 9 deCembeR 2010 | FM WORLD                                                                                 www.fm-world.co.uk
multi-tenanted buildings




   A strategic plan of works was        posing the most risk of failure to      anticipated for a building of this        the Disability Discrimination Act.
implemented while maintaining           the operation of the building. This     type – in fact, costs had doubled         The majority of recent legislation
full occupation and rental              allowed a forward replacement           since the services were installed.        and regulations affecting fixed
income in order to rectify the          budget to be developed and                 A detailed analysis of the way the     building services facilitate
problems that were causing erratic      enabled capital spend to be             building was operating in relation        improvements in energy efficiency.
internal temperatures and tenant        understood and planned carefully.       to the business needs of the tenants        In addition to legislative
dissatisfaction.                        Failure to undertake such a robust      was undertaken. The outcome was           and regulatory compliance,
   Undertaking refurbishments in        assessment of plant life and an         the implementation of a strategy          manufacturers’ research and
existing buildings is challenging but   accurate forward replacement            that allowed the plant to operate         development over the past 15
not impossible. Inevitably there will   capital works plan can lead to          and meet the tenant’s business            years has seen energy efficiency
be some disruption to tenants while     plant being replaced in the wrong       needs and which, together with the        improvements in plant such as
key items of plant, such as cooling     sequence and unexpected and             rectification of HVAC faults, made        chillers and boilers, thus the
or heating equipment, are replaced.     unplanned costs for the landlord.       running cost savings.                     replacement plant items selected
The trick is to plan to replace                                                                                           had much better efficiencies.
heating and cooling when it isn’t       Phase 2                                 Phase 4
needed – so replace the boilers in      InterIm perIod management of            ImplementatIon of capItal works           The results
summer and the chillers in winter.      fInancIal rIsk to the servIce charge    programme                                 The building as a whole is now set
Disruption will then be minimised                                                                                         for operation for the next 25 years.
and, as long as tenants are kept        With the capital works programme        All tenant business operations            And all the projects described were
informed and the replacement            plan in place, the costs incurred       were maintained while the                 undertaken without loss of rental
programme is planned and                and the service charges made            refurbishment and replacement of          revenue. Running costs (gas and
managed effectively, the desired        by the maintenance contractor           the boilers, pumps, chillers, lifts and   electricity) have been halved and
end result can be achieved.             were analysed. Examples of              HVAC controls took place.                 maintenance contractor call-outs
                                        dozens of contractor call-outs                                                    dropped by 95 per cent.
Action taken                            each week were found, dealing           Phase 5                                      At the time of going to print the
                                        with a variety of faults, such          ongoIng performance                       building was put under offer thus
Phase 1                                 as the heating and cooling not                                                    the name of the building has been
plant appraIsal and scheduled capItal   working – normally at a time when       In a multi-tenanted building,             removed to protect the interests
works programme                         the tenants needed it most. The         the goalposts frequently move.            of the vendor. This situation quite
                                        maintenance contract was clearly        Management of churn and change            accurately represents the typical
 An assessment of the life              not benefiting either the tenants       and the verification of tenants’          unknowns that often unexpectedly
expectancy of items of fixed            or the building owner. A new M&E        licence to alter submissions are          come into play when working
building services was undertaken        maintenance contract was prepared       key to ensuring that the building’s       with existing buildings. After all,
and a scheduled capital works           with a view to limiting costs           functionality is not diminished.          existing commercial buildings are
programme prepared. The creation        incurred by the service charge.            The refurbishment work allowed         primarily someone’s high value
of this programme in turn led to        This contract was underpinned           the building to be bought in to           investment. FM
the development of a plan of action     by a process of continual               line with relevant legislative and
covering a period of five to seven      review of the maintenance               regulatory compliance, for example        Glenn Massey is an associate at
                                                                                                                          Hoare Lea
years, with a focus on the items        contractor’s performance against        F Gas regulations for chillers and
                                        key performance indicators.
                                        Within the first 12 months after        poinTs To remember
                                        implementation of the new
                                        maintenance contract, contractor        l Do  undertake a robust building services condition survey and report
                                        call-outs dropped by 95 per cent.       l Do  prepare a costed forward replacement matrix
                                                                                l Do maximise the life of existing plant
                                        Phase 3                                 l Do ensure maintenance contractor’s contracts are appropriate
                                        BuIldIng operatIng cost analysIs          for the building
                                                                                l Do keep tenants informed of the plan
                                        The dilapidated state of the building   l Do establish a starting point (baseline) to enable the magnitude of
                                        created a 24/7 operation mentality,       improvement to be assessed when the project is complete
                                        simultaneous heating and cooling,       l Do install sub metering as part of refurbishments
                                        causing inefficiencies, such as         l Don’t rush ahead with short term fixes that don’t complement an
                                        unnecessary use of electricity and        over-arching replacement plan
                                        gas. The lack of a control strategy     l Don’t replace plant that is not life expired
                                        was causing operating costs to be       l Don’t believe salesmen selling the next best thing since ‘sliced bread’.
                                        higher than would normally be             Suggest a test and verification first.

www.fm-world.co.uk                                                                                                                  FM WORLD | 9 deCembeR 2010 | 25

More Related Content

Viewers also liked

Virtual dj 5 user guide
Virtual dj 5   user guideVirtual dj 5   user guide
Virtual dj 5 user guideluis177p
 
Respuesta Inmunitaria: Innata, Inflamatoria, de Fase Aguda y Adaptativa
Respuesta Inmunitaria: Innata, Inflamatoria, de Fase Aguda y AdaptativaRespuesta Inmunitaria: Innata, Inflamatoria, de Fase Aguda y Adaptativa
Respuesta Inmunitaria: Innata, Inflamatoria, de Fase Aguda y AdaptativaPolam A. Olivares E.
 
Tunne asiakkaasi paremmin postin tietoisku mvv2015
Tunne asiakkaasi paremmin postin tietoisku mvv2015Tunne asiakkaasi paremmin postin tietoisku mvv2015
Tunne asiakkaasi paremmin postin tietoisku mvv2015Posti Group
 
Despacho proyecto de ley modificacion codigo de faltas
Despacho proyecto de ley modificacion codigo de faltas Despacho proyecto de ley modificacion codigo de faltas
Despacho proyecto de ley modificacion codigo de faltas Jime Catalá
 
History report final [pdf] [updated]
History report final [pdf] [updated]History report final [pdf] [updated]
History report final [pdf] [updated]Soh Shing
 
International courts and forums
International courts and forums International courts and forums
International courts and forums Sergey Ulitenok
 
ISB Case Competition | Final round
ISB Case Competition | Final roundISB Case Competition | Final round
ISB Case Competition | Final roundTarun Gupta
 

Viewers also liked (12)

Virtual dj 5 user guide
Virtual dj 5   user guideVirtual dj 5   user guide
Virtual dj 5 user guide
 
Respuesta Inmunitaria: Innata, Inflamatoria, de Fase Aguda y Adaptativa
Respuesta Inmunitaria: Innata, Inflamatoria, de Fase Aguda y AdaptativaRespuesta Inmunitaria: Innata, Inflamatoria, de Fase Aguda y Adaptativa
Respuesta Inmunitaria: Innata, Inflamatoria, de Fase Aguda y Adaptativa
 
BA
BABA
BA
 
report (Autosaved)
report (Autosaved)report (Autosaved)
report (Autosaved)
 
Tunne asiakkaasi paremmin postin tietoisku mvv2015
Tunne asiakkaasi paremmin postin tietoisku mvv2015Tunne asiakkaasi paremmin postin tietoisku mvv2015
Tunne asiakkaasi paremmin postin tietoisku mvv2015
 
Despacho proyecto de ley modificacion codigo de faltas
Despacho proyecto de ley modificacion codigo de faltas Despacho proyecto de ley modificacion codigo de faltas
Despacho proyecto de ley modificacion codigo de faltas
 
History report final [pdf] [updated]
History report final [pdf] [updated]History report final [pdf] [updated]
History report final [pdf] [updated]
 
Refurbishment
RefurbishmentRefurbishment
Refurbishment
 
International courts and forums
International courts and forums International courts and forums
International courts and forums
 
ISB Case Competition | Final round
ISB Case Competition | Final roundISB Case Competition | Final round
ISB Case Competition | Final round
 
Design case study
Design case studyDesign case study
Design case study
 
Health and spirituality
Health and spiritualityHealth and spirituality
Health and spirituality
 

Similar to Energy Efficiency Refurbishment Case Study

1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report1-2 Broadgate Final Project Report
1-2 Broadgate Final Project ReportPaul Warrington
 
Development Magazine Tustin Commons A Tired Asset Comes of Age
Development Magazine Tustin Commons A Tired Asset Comes of AgeDevelopment Magazine Tustin Commons A Tired Asset Comes of Age
Development Magazine Tustin Commons A Tired Asset Comes of Agelarryarmstrong
 
Warner Robins Air Logistics Center Strives for Energy Efficiency : Energy Ser...
Warner Robins Air Logistics Center Strives for Energy Efficiency : Energy Ser...Warner Robins Air Logistics Center Strives for Energy Efficiency : Energy Ser...
Warner Robins Air Logistics Center Strives for Energy Efficiency : Energy Ser...McKenney's Inc
 
Ron wilkinson cx for new and exist bldgs
Ron wilkinson cx for new and exist bldgsRon wilkinson cx for new and exist bldgs
Ron wilkinson cx for new and exist bldgsEllieNowels
 
Implementing the Poughkeepsie Green Data Center
Implementing the Poughkeepsie Green Data CenterImplementing the Poughkeepsie Green Data Center
Implementing the Poughkeepsie Green Data CenterElisabeth Stahl
 
STI Real Estate Article
STI Real Estate ArticleSTI Real Estate Article
STI Real Estate ArticleTony Miller
 
Energy Efficiency, Myths and Misperceptions
Energy Efficiency, Myths and MisperceptionsEnergy Efficiency, Myths and Misperceptions
Energy Efficiency, Myths and MisperceptionsBetterBricks
 
Roofing System Selection
Roofing System SelectionRoofing System Selection
Roofing System SelectionTony Loup
 
The role of delivered performance june2009
The role of delivered performance june2009The role of delivered performance june2009
The role of delivered performance june2009Toronto 2030 District
 
Case study -4 Mort Street
Case study -4 Mort StreetCase study -4 Mort Street
Case study -4 Mort StreetShamitha Reddy
 
BBP BL Case Study
BBP BL Case StudyBBP BL Case Study
BBP BL Case StudyEPTUK
 
commissioning-federal-facilities.pdf
commissioning-federal-facilities.pdfcommissioning-federal-facilities.pdf
commissioning-federal-facilities.pdfVincent Bui
 
Colliers Spark - b class building in a class market email
Colliers Spark - b class building in a class market emailColliers Spark - b class building in a class market email
Colliers Spark - b class building in a class market emailChris Fyvie
 
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...Blake Morgan
 
Fault Tolerant MEP Infrastructure 2N or not 2N? 3
 Fault Tolerant MEP Infrastructure 2N or not 2N? 3 Fault Tolerant MEP Infrastructure 2N or not 2N? 3
Fault Tolerant MEP Infrastructure 2N or not 2N? 3Hurley Palmer Flatt
 
HVAC Cent vs decent ac systems
HVAC Cent vs decent ac systemsHVAC Cent vs decent ac systems
HVAC Cent vs decent ac systemsvarunsingh383
 
Anthony_F_Vitola_Engineer_Resume
Anthony_F_Vitola_Engineer_ResumeAnthony_F_Vitola_Engineer_Resume
Anthony_F_Vitola_Engineer_ResumeAnthony Vitola
 
م.60-مبادرة#تواصل_تطوير-أ.د.سيد شبل محمد-"مدينة العلمين الجديدة - نظام التكي...
م.60-مبادرة#تواصل_تطوير-أ.د.سيد شبل محمد-"مدينة العلمين الجديدة -  نظام التكي...م.60-مبادرة#تواصل_تطوير-أ.د.سيد شبل محمد-"مدينة العلمين الجديدة -  نظام التكي...
م.60-مبادرة#تواصل_تطوير-أ.د.سيد شبل محمد-"مدينة العلمين الجديدة - نظام التكي...Egyptian Engineers Association
 

Similar to Energy Efficiency Refurbishment Case Study (20)

1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report
 
Development Magazine Tustin Commons A Tired Asset Comes of Age
Development Magazine Tustin Commons A Tired Asset Comes of AgeDevelopment Magazine Tustin Commons A Tired Asset Comes of Age
Development Magazine Tustin Commons A Tired Asset Comes of Age
 
Warner Robins Air Logistics Center Strives for Energy Efficiency : Energy Ser...
Warner Robins Air Logistics Center Strives for Energy Efficiency : Energy Ser...Warner Robins Air Logistics Center Strives for Energy Efficiency : Energy Ser...
Warner Robins Air Logistics Center Strives for Energy Efficiency : Energy Ser...
 
Ron wilkinson cx for new and exist bldgs
Ron wilkinson cx for new and exist bldgsRon wilkinson cx for new and exist bldgs
Ron wilkinson cx for new and exist bldgs
 
Implementing the Poughkeepsie Green Data Center
Implementing the Poughkeepsie Green Data CenterImplementing the Poughkeepsie Green Data Center
Implementing the Poughkeepsie Green Data Center
 
STI Real Estate Article
STI Real Estate ArticleSTI Real Estate Article
STI Real Estate Article
 
Energy Efficiency, Myths and Misperceptions
Energy Efficiency, Myths and MisperceptionsEnergy Efficiency, Myths and Misperceptions
Energy Efficiency, Myths and Misperceptions
 
Roofing System Selection
Roofing System SelectionRoofing System Selection
Roofing System Selection
 
The role of delivered performance june2009
The role of delivered performance june2009The role of delivered performance june2009
The role of delivered performance june2009
 
Case study -4 Mort Street
Case study -4 Mort StreetCase study -4 Mort Street
Case study -4 Mort Street
 
BBP BL Case Study
BBP BL Case StudyBBP BL Case Study
BBP BL Case Study
 
commissioning-federal-facilities.pdf
commissioning-federal-facilities.pdfcommissioning-federal-facilities.pdf
commissioning-federal-facilities.pdf
 
Colliers Spark - b class building in a class market email
Colliers Spark - b class building in a class market emailColliers Spark - b class building in a class market email
Colliers Spark - b class building in a class market email
 
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
Blake Lapthorn's green breakfast with guest speaker Keeran Jugdoyal, Faithful...
 
Fault Tolerant MEP Infrastructure 2N or not 2N? 3
 Fault Tolerant MEP Infrastructure 2N or not 2N? 3 Fault Tolerant MEP Infrastructure 2N or not 2N? 3
Fault Tolerant MEP Infrastructure 2N or not 2N? 3
 
HVAC Cent vs decent ac systems
HVAC Cent vs decent ac systemsHVAC Cent vs decent ac systems
HVAC Cent vs decent ac systems
 
O & C Refurb
O & C RefurbO & C Refurb
O & C Refurb
 
report.docx
report.docxreport.docx
report.docx
 
Anthony_F_Vitola_Engineer_Resume
Anthony_F_Vitola_Engineer_ResumeAnthony_F_Vitola_Engineer_Resume
Anthony_F_Vitola_Engineer_Resume
 
م.60-مبادرة#تواصل_تطوير-أ.د.سيد شبل محمد-"مدينة العلمين الجديدة - نظام التكي...
م.60-مبادرة#تواصل_تطوير-أ.د.سيد شبل محمد-"مدينة العلمين الجديدة -  نظام التكي...م.60-مبادرة#تواصل_تطوير-أ.د.سيد شبل محمد-"مدينة العلمين الجديدة -  نظام التكي...
م.60-مبادرة#تواصل_تطوير-أ.د.سيد شبل محمد-"مدينة العلمين الجديدة - نظام التكي...
 

Energy Efficiency Refurbishment Case Study

  • 1. FM CASE STUDY multi-tenanted building  glenn massey maintain your cool Carrying out refurbishments in occupied buildings may seem challenging but one flagship property in Regent Street managed to successfully cut costs and increase efficiency I n 2007, a major refurbishment within the office and retail store strategy commenced at a environments. This in turn created flagship building in Regent concern from tenants regarding Street, London. service charge levels. The typical Edwardian West The original appraisal of the site, End property has a floor area in which took place on a summer’s the region of 38,000 sq ft and day, immediately revealed that different commercial classifications the heating was operating at the of use, with retail premises on the same time as the cooling. Further ground floor and basement and six investigation showed that the floors of commercial office space major plant items, such as chillers, above. The retail part is home to boilers, lifts and air treatment plant a high-end luxury womenswear were in a dilapidated state. The and menswear retail brand. The standard of maintenance was also office floors are multi-tenanted and poor and this contributed to the are home to some internationally high number of contractor call outs. known businesses, and therefore From the frequency of call outs it have a mixture of different was clear that a rationalisation of business needs. the maintenance and maintenance contract was needed. The challenge The site’s fixed building services were in a dilapidated state and were operating extremely inefficiently. The performance of the heating and cooling systems serving the building was such that heating and cooling often operated simultaneously. Both ILLUSTRATION: ROBERT HANSON would often break down when needed most because the systems were being operated for long hours and in seasons when they were not needed. The result of this inefficiency was an increase in utility costs and discomfort 24 | 9 deCembeR 2010 | FM WORLD www.fm-world.co.uk
  • 2. multi-tenanted buildings A strategic plan of works was posing the most risk of failure to anticipated for a building of this the Disability Discrimination Act. implemented while maintaining the operation of the building. This type – in fact, costs had doubled The majority of recent legislation full occupation and rental allowed a forward replacement since the services were installed. and regulations affecting fixed income in order to rectify the budget to be developed and A detailed analysis of the way the building services facilitate problems that were causing erratic enabled capital spend to be building was operating in relation improvements in energy efficiency. internal temperatures and tenant understood and planned carefully. to the business needs of the tenants In addition to legislative dissatisfaction. Failure to undertake such a robust was undertaken. The outcome was and regulatory compliance, Undertaking refurbishments in assessment of plant life and an the implementation of a strategy manufacturers’ research and existing buildings is challenging but accurate forward replacement that allowed the plant to operate development over the past 15 not impossible. Inevitably there will capital works plan can lead to and meet the tenant’s business years has seen energy efficiency be some disruption to tenants while plant being replaced in the wrong needs and which, together with the improvements in plant such as key items of plant, such as cooling sequence and unexpected and rectification of HVAC faults, made chillers and boilers, thus the or heating equipment, are replaced. unplanned costs for the landlord. running cost savings. replacement plant items selected The trick is to plan to replace had much better efficiencies. heating and cooling when it isn’t Phase 2 Phase 4 needed – so replace the boilers in InterIm perIod management of ImplementatIon of capItal works The results summer and the chillers in winter. fInancIal rIsk to the servIce charge programme The building as a whole is now set Disruption will then be minimised for operation for the next 25 years. and, as long as tenants are kept With the capital works programme All tenant business operations And all the projects described were informed and the replacement plan in place, the costs incurred were maintained while the undertaken without loss of rental programme is planned and and the service charges made refurbishment and replacement of revenue. Running costs (gas and managed effectively, the desired by the maintenance contractor the boilers, pumps, chillers, lifts and electricity) have been halved and end result can be achieved. were analysed. Examples of HVAC controls took place. maintenance contractor call-outs dozens of contractor call-outs dropped by 95 per cent. Action taken each week were found, dealing Phase 5 At the time of going to print the with a variety of faults, such ongoIng performance building was put under offer thus Phase 1 as the heating and cooling not the name of the building has been plant appraIsal and scheduled capItal working – normally at a time when In a multi-tenanted building, removed to protect the interests works programme the tenants needed it most. The the goalposts frequently move. of the vendor. This situation quite maintenance contract was clearly Management of churn and change accurately represents the typical An assessment of the life not benefiting either the tenants and the verification of tenants’ unknowns that often unexpectedly expectancy of items of fixed or the building owner. A new M&E licence to alter submissions are come into play when working building services was undertaken maintenance contract was prepared key to ensuring that the building’s with existing buildings. After all, and a scheduled capital works with a view to limiting costs functionality is not diminished. existing commercial buildings are programme prepared. The creation incurred by the service charge. The refurbishment work allowed primarily someone’s high value of this programme in turn led to This contract was underpinned the building to be bought in to investment. FM the development of a plan of action by a process of continual line with relevant legislative and covering a period of five to seven review of the maintenance regulatory compliance, for example Glenn Massey is an associate at Hoare Lea years, with a focus on the items contractor’s performance against F Gas regulations for chillers and key performance indicators. Within the first 12 months after poinTs To remember implementation of the new maintenance contract, contractor l Do undertake a robust building services condition survey and report call-outs dropped by 95 per cent. l Do prepare a costed forward replacement matrix l Do maximise the life of existing plant Phase 3 l Do ensure maintenance contractor’s contracts are appropriate BuIldIng operatIng cost analysIs for the building l Do keep tenants informed of the plan The dilapidated state of the building l Do establish a starting point (baseline) to enable the magnitude of created a 24/7 operation mentality, improvement to be assessed when the project is complete simultaneous heating and cooling, l Do install sub metering as part of refurbishments causing inefficiencies, such as l Don’t rush ahead with short term fixes that don’t complement an unnecessary use of electricity and over-arching replacement plan gas. The lack of a control strategy l Don’t replace plant that is not life expired was causing operating costs to be l Don’t believe salesmen selling the next best thing since ‘sliced bread’. higher than would normally be Suggest a test and verification first. www.fm-world.co.uk FM WORLD | 9 deCembeR 2010 | 25