Working and delivering projects in your own ‘backyard’ demands some of the highest standards of stewardship because you are entirely accountable and responsible for everything that you do and whatever happens. World class programme and project management are therefore essential tools in delivering consistent and insightful quality results.
The archipelago and nearby waters of Orkney as well as its neighbouring island groups and Scottish mainland communities have created a wealth of opportunities over the last 50 years or so for implementing programmes and project in some extremely challenging conditions and circumstances.
The combination of local expectations and working conditions have demanded the highest standards of project development and management. Even small tasks require care and consideration of issues that do not have the same potential impact elsewhere. Managing such risks and opportunities is therefore a collective skill and endeavour that the whole community needs to engage in.
In this presentation Gareth sets out some of these key driving forces in island-based developments and then gives some amazing case study examples of project activity that in underway and planned in and around the islands. These activities amount to a programme of work over the next 20-30 years which is likely to cost more than £150 billion and deliver between 20% and 50% of the UKs total clean energy requirements (electrons and molecules).
A huge prize at a local, national and even global level – which will all need to be facilitated and delivered by exemplary programme and project management – hopefully with much of it delivered locally!
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
Dr. Gareth Davies: Transformational Projects – the Orkney story so far
1. Orkney – many things to many people
Ptolemy 2nd century map
The Orkney Way: Stepping forward together, creating the future, learning from the past.
2. - Innovation and Enterprise for
the New World
Presented by Gareth Davies
Chair Aquatera Group
gareth.davies@aquatera.co.uk
3. Building from our core environmental competence in
ecological, social and physical sciences we have
assembled a comprehensive capacity across all major
areas of sustainability including:
• Strategic planning
• Option evaluation
• Project impact assessment & permitting
• Surveying & data management
• Technology development support
• Deployment and operations support
• Performance evaluation & management
• Education, training & public awareness
• Biodiversity management
• Community & societal development
• Sustainable business & supply chain development
Delivering across many core sectors on a local and
global basis
Aquatera – delivering expert sustainability services
7. Number and types of projects in the vicinity
Past examples Last 30
years
Next 30
years
Future examples
Tera projects = 10,000s people;
>£1Bs; 5-10 yrs
None - 30-50
nearby
Offshore wind farms, Scapa Flow Wind Hub,
hydrogen hubs, transmission network building
Giga projects = >1000s people,
£100Ms, >5 years
Flotta, Moray Firth wind farm, offshore oil
fields, Dounreay
1 (50
nearby)
20 -50 Onshore wind farms, tidal farms, distribution grid
upgrade, transhipment ports, oil transition
Mega projects = 100-1000 people,
£10-100M, 2-5 years
Onshore wind farms, large civil works,
ferries, hospitals, schools
10 100 Offshore fish farms, large boat replacement,
ferries, lager harbour works
Macro projects = 10-100, 1-10 m, 1-
2 yrs
Nearshore fish farms, large research
projects, housing, public buildings, civil
works, small ports
100 200 Local harbour expansion, small boat replacement,
aircraft replacement, larger research projects,
housing, public buildings, civil works,
Large projects = 5-10, 100k-1M,
0.5-1 yr
Variety of public works, business premises,
single house builds, plant replacement
1000 1500 Variety of public works, business premises, single
house builds, plant replacement
Standard = 5 ish, 10-100k, 3-6
months
Common in business, house improvements,
vehicle upgrade, day boat replacement
10000 15000 Common in business, house improvements,
vehicle upgrade, day boat replacement
Mini projects – 2-5, 1-10k, 1-3
months
Widespread in business, house
improvements
100000 150000 Widespread in business, house improvements
Micro projects = 1-2, <5k, 1 month All kinds of business, enterprise 1million 1.5million All kinds of business, enterprise
‘Project’ tasks = 1-2, free or 1-2k, 1
to few days
All kinds of activity 10million 15million All kinds of activity
8. How do we prepare for and deal with future challenges
9. Orkney Innovation a Enterprise Ecosystem
Local visionaries and thought leaders
Local adopters, committed risk takers and innovators along with their support teams and off-Orkney collaborators
Academic Pioneers Business Pioneers Community Pioneers Government Pioneers
Strategic inventors
Living laboratory
Innovation Hub Aspire ORKNEY
Enterprise sectors
Sustainable
energy
Agriculture
Fisheries Maritime
Food and
drink
Digital
enterprise
Crafts
Environmental
Archaeology
and history
Arts &
culture
Retail
3rd
sector
Health and
care
Local
government
Tourism
Sport
Events
Activities
Progressive
commerce
Innovative
services &
technologies
Applied
research
Dissemination &
conversation
Promotion &
performance
VISION
STRATEGY
ORGANISATION
INVOLVEMENT
ACTION
SUPPORT
Orkney has taken time to build the right structures, now it is ready to unleash & share its potential!
Islands Deal (ICNZ)
Orkney Community Partnership (Public Sector focus)
10. Orkney Total Energy Mix – data for 2019
Heat & light
Transport
(largely)
Done
To do
To do