SlideShare a Scribd company logo
IAEA International Conference on Topical Issues
in Nuclear Installation Safety
Guidance on the Implementation of
Modifications to Mitigate Beyond Design
Basis Accidents
Fred Dermarkar
Vice President Engineering Strategy
Ontario Power Generation
October 2013
Presentation Overview
• Canadian Utility Principles for Beyond Design
Basis Events
– Approach to achieve “practical elimination….”
• Guidance on Modifications for Beyond Design
Basis Events and Accidents
2
Canadian Nuclear Utility Principles for
Beyond Design Basis Events
• Developed and agreed to by the 3 Utilities
• Provide guidance for utility decision making to
maintain consistency
• Clearly defines the end point
• Provides a vehicle for communication within
the Nuclear industry, with the Public and
Regulators
3
4
Objective of the Principles
Practically eliminate the potential
for societal disruption due to a
nuclear incident by maintaining
multiple and flexible barriers to
severe event progression
5
Principle 1 – Event Progression Defences
Actions and defences will focus on stopping
accident progression prior to a severe
accident.
• Maintaining adequate fuel cooling prevents fuel failures.
• Severity of consequences escalates with event progression.
• Mitigation should receive the majority of the actions and
focus from the utilities.
6
Principle 1 - Event Progression Defenses
7
Quick connections for Steam
Generator EME Supply
Flood barriers installed
Principle 2 – Multiple Barriers
Multiple barriers to event progression and multiple means to supply water
or electricity will be used to ensure adequate defence
8
Principle 2 – Multiple Barrier Actions
9
Heat Transport Steam Generators Moderator Shield Tank
Supply water to
CANDU heat
sinks with
portable pumps
Principle 3 – Early Fuel Cooling
Methods and actions to initiate heat transport
system (HTS) cool-down and maintain fuel
cooling will be a primary and early priority
• Cooldown is achieved by opening Steam Reject Valves (SRVs)
– Increases margin to fuel failures (lower temperature).
– Allows for EME to inject additional water into a depressurized steam
generators.
• Actions to open SRVs need to be simple and reliable.
10
Principle 3 – Early Fuel Cooling Actions
• Cooldown of the Heat Transport can be achieved by opening
boiler steam Reject Valves manually
11
• Air Supply connections installed
to open and hold open valves
• Class II battery banks confirmed
to be seismically robust
Principle 4 – Containment Integrity
Actions to maintain Containment integrity will
be utilized to minimize radioactive releases
• Control pressure
– Containment Cooling
– Containment Venting (Principle 5)
• Control hydrogen
– Minimize generation
– Effective removal
• Control water inventory to minimize flooding
– Water injection and control
12
Principle 4 - Containment Integrity Actions
13
Containment ACUs supplied with
water and electricity
Passive Autocatalytic
Recombiners
1 MW
Generators
Principle 5 – Filtered Venting
Containment venting will be controlled
through a filtered system
• With a functional containment, decisions can be made when
to vent and for how long.
• Controlled filtered venting will minimize radioactive releases
and their potential impact on the environment.
• The ability to delay when containment will be vented allows
for short lived material to be reduced through decay.
14
Principle 5 – Filtered Venting
15
Principle 6 – Equipment Integrity
Necessary systems, structures and components will
be confirmed to survive rare yet credible conditions
for external hazards
• Existing Plant equipment will only be relied upon if
shown available after Beyond Design Basis Event
• Review Level Conditions (RLCs) established for rare
yet credible conditions.
e.g., seismic Design Basis ~1,000 yr; RLC ~10,000 yr
• Provides assurance that the plants will meet the
objective for BDBE
16
Principle 6 –Equipment Integrity Actions
• Seismic Margin Assessments or Fragility analyses
being completed:
o Passive water supply to Steam Generators (Dearator)
o Class II batteries and rack
• EME Quick connects designed to meet BDBE
requirement.
• Seismic safety margin and vulnerabilities assessed as
part of station PSAs.
• Seismically-induced internal fires and internal flooding
assessments in progress.
• Credible external hazard magnitudes being updated
(seismic, tsunami, wind)
17
Principle 7 – Spent Fuel Cooling
Irradiated Fuel Bay (IFB) water levels will be
maintained sufficiently above the top of the
fuel to mitigate high radiation fields,
hydrogen production, and fuel damage
• The time required to respond to a loss of IFB cooling is
typically quite long.
• The volume of water in the IFB should be maximized within
normal water levels to the extent practicable.
• EME to supply water to account for leakage and steaming.
18
Principle 7 – Spent Fuel Cooling Actions
19
EME Water Supply piping
to IFB
Principle 8 – Readily Deployed
Emergency Mitigating Equipment will be robust,
readily available, easily deployable within required
timeframes, and have adequate redundancy
• Stored at higher elevation, away from station, close enough for timely
deployment and accessible following BDBE
– Pre-staging is an option for predictable events (e.g., severe weather)
• Deployable by diverse work groups, supported by procedures, training and
practice and validated by drills
• More than one method for deployment (trucks, tractors, security vehicles)
• Reliability of EME supported by using proven technology, preventative
maintenance and routine testing
• On-site fuel supplies adequate for > 72 hour run time, with provisions for
refueling in place.
20
Principle 8 – “Readily Deployed” Actions
21
Principle 9 - Common Philosophy
Canadian utilities will utilize a common philosophy
for the prevention of a Beyond Design Basis
Accident (BDBA)
• Interaction between utilities gives a larger
perspective and experience base
– Encourages challenging and learning
– Improves capability to respond and to provide
mutual assistance
– Provides credibility
– Facilitates regulatory concurrence.
22
Principle 9 -Common Philosophy Actions
• COG Severe Accident Joint Project Technical Reports
o Shutdown and Low Power, Multi-unit Station, Technical Basis Document and
SAMG Update, Containment Integrity, In-Vessel Retention, Instrument
Survivability, Habitability
• COG Emergency Preparedness Work Shop III June
3&4,
o Diverse participation including CNSC, Health Canada and
provincial agencies.
• WANO SOER 13-2 corrective action plans
o Developed cooperatively
• Mutual Aid Agreement in effect
• Regional Emergency Response Support Centre
o Site selection complete
23
Designing for Beyond Design Basis
• Objective
– Deliver functionality to prevent or mitigate significant adverse
consequences with reasonable assurance
• Maintain fuel cooling
• Arrest core damage
• Protect containment integrity
– Ensure functionality for design basis conditions is not
compromised
• Graded approach
• Recognized as providing interim direction
24
Graded Approach
2. Equipment upgrades installed
on existing engineered SSCs to
manage BDBAs.
25
• Four categories of Systems, Structures & Components
(SSCs):
1. Existing engineered SSCs
called upon to manage
BDBAs
Steam Reject Valves to depressurize
Steam Generators
Additional Air supply to hold Steam
Reject Valves open
Graded Approach
26
4. Portable SSCs to be
attached to existing SSC
to manage BDBAs
3. New engineered SSCs for
the sole purpose of
managing BDBAs
Application to Design
27
• For all Categories:
– Analysis based on more realistic initiating conditions
– Interfacing components designed to requirements of the
parent system
– Robustness demonstrated
for Review Level Conditions
(RLCs)
• RLC: appropriate estimate of
the intensity of a rare, yet
credible external hazard to
confirm adequate safety
margin for beyond design
basis events
Application to Design
28
• For Category 4:
– Design process documented, approved by the Design
Authority.
– Codes / standards appropriate for portable equipment to be
used
– Equipment to be designed
for two tie-in points, at least
one of which is an
engineered tie-in point
Application to Procurement
• For Categories 1,2:
– Full procurement rigour as applied to nuclear components
• For Category 3:
– As above, but typical commercial / industrial process may
apply beyond system isolation tie-in points. Deviations
approved by Design Authority.
29
Quick connect:
commercial
Piping to isolation
point: nuclear
Application to Procurement
• Spare parts:
– Appropriately considered in the procurement process.
– For Category 4, provide for N+1 running spares, per FLEX.
30
• For Category 4:
– Commercial/industrial
processes apply and
manufacturer’s standards
apply.
– Equipment to be stored in
a manner to make it
resilient to BDBEs
Application to Installation,
Commissioning and Testing
• For Category 1, 2:
– Process for installation, testing, commissioning same as for
normal engineering change control process
• For Category 3, 4:
– Commercial/industrial processes apply for installation, testing
and commissioning
– Demonstration that functional performance requirements
have been met
31
Application to Operations and
Maintenance
• For all categories:
– Operator Routines and Testing are performed regularly to
ensure reliability and availability of SSCs.
– Allowable outage times as defined in Operational Safety
Requirements, which are part of the design and licensing
basis
• For Category 4:
– Where equipment redundancy exists, equipment can be taken
out of service for maintenance for up to 90 days.
– Where no equipment redundancy exists, equipment can be
taken out of service for up to 14 days for maintenance.
– A longer restoration period requires approval of the
Operations and Maintenance Director.
32
Principles for Sustainability
• The technical basis for BDBA Response Capability (BDBA
RC) shall be formally documented and periodically
reviewed to ensure that it remains current.
• Regular maintenance and testing of BDBA RC shall be
controlled through a predefined process consistent with
regular station equipment; it shall be documented and
periodically audited.
• The maintenance of BDBA RC shall be routinely self-
assessed and independently audited
• BDBA RC shall be revisited when new safety analysis is
performed
33
Principles for Sustainability
• Station modification control processes shall ensure that
BDBA RC is not inadvertently altered.
• BDBA RC functional requirements shall be documented in
a manner similar to the Operational Safety Requirements
for design basis credits.
• Station transient material processes shall include controls
to ensure that access to tie-in points and staging locations
for BDBA RC are accessible.
• Maintenance and Outage Management processes shall
account for capability to implement BDBA RC.
34
Conclusion
• Recent applications at OPG:
– Flood barrier protection at Pickering
– Emergency Mitigating Equipment at Pickering and
Darlington
– Containment Filtered Venting System at Darlington
• The application of the process has confirmed that
it is sound and provides required flexibility.
• Communication between project staff, nuclear
safety staff and design organizations is key to
ensure the correct balance and rigour is applied.
35
SUMMARY
• Canada is committed to the objective to
“Practically Eliminate the Potential for Societal
Disruption”
• We have defined the steps and processes to
meet and sustain this objective
• We are well advanced
• We are willing to learn and improve
36

More Related Content

What's hot

Norwegian subsea
Norwegian subseaNorwegian subsea
Norwegian subsea
Business Finland
 
Case studies: Predictive maintenance in the petrochemical industry
Case studies: Predictive maintenance in the petrochemical industryCase studies: Predictive maintenance in the petrochemical industry
Case studies: Predictive maintenance in the petrochemical industry
Advisian
 
Global Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyGlobal Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea Technology
Conference_Presentations
 
Life extension of aging petroleum production facilities offshore
Life extension of aging petroleum production facilities offshoreLife extension of aging petroleum production facilities offshore
Life extension of aging petroleum production facilities offshore
E.ON Exploration & Production
 
2012 ig cc-overview
2012 ig cc-overview2012 ig cc-overview
2012 ig cc-overviewCal Gov
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineerankur sood
 
Farook Presentation for Chief Engineer
Farook Presentation for Chief EngineerFarook Presentation for Chief Engineer
Farook Presentation for Chief EngineerFarook Pallikkalakath
 
Barriers and opportunities for use of low gwp alternatives
Barriers and opportunities for use of low gwp alternatives Barriers and opportunities for use of low gwp alternatives
Barriers and opportunities for use of low gwp alternatives UNEP OzonAction
 
Insulation Technologies and Materials: Technologies, Systems and Tools in the...
Insulation Technologies and Materials: Technologies, Systems and Tools in the...Insulation Technologies and Materials: Technologies, Systems and Tools in the...
Insulation Technologies and Materials: Technologies, Systems and Tools in the...
International Energy Agency
 
"We've got to do what now?" Webinar
"We've got to do what now?" Webinar"We've got to do what now?" Webinar
"We've got to do what now?" Webinar
New Jersey Future
 
Integrity Management Plan for Pipeline-G03178 Idzuari Azli
Integrity Management Plan for Pipeline-G03178 Idzuari AzliIntegrity Management Plan for Pipeline-G03178 Idzuari Azli
Integrity Management Plan for Pipeline-G03178 Idzuari AzliIdzuari Azli Bin Kamilan
 
Ca industrial storm water program brainslam
Ca industrial storm water program brainslamCa industrial storm water program brainslam
Ca industrial storm water program brainslamGreg Gearheart
 
Presentation at wr conference may 13 draft 1 ivs
Presentation at wr conference may 13  draft 1 ivsPresentation at wr conference may 13  draft 1 ivs
Presentation at wr conference may 13 draft 1 ivsIouri Vaisman
 
Webinar: CO2 pipeline infrastructure: Lessons learned
Webinar: CO2 pipeline infrastructure: Lessons learnedWebinar: CO2 pipeline infrastructure: Lessons learned
Webinar: CO2 pipeline infrastructure: Lessons learned
Global CCS Institute
 
Operation & maintenance of stormwater quality treatment assets
Operation & maintenance of stormwater quality treatment  assetsOperation & maintenance of stormwater quality treatment  assets
Operation & maintenance of stormwater quality treatment assets
Iouri Vaisman
 
Primary Continuous Processing Retrofit
Primary Continuous Processing RetrofitPrimary Continuous Processing Retrofit
Primary Continuous Processing Retrofit
Hargrove Life Sciences
 

What's hot (20)

Norwegian subsea
Norwegian subseaNorwegian subsea
Norwegian subsea
 
Resume2016
Resume2016Resume2016
Resume2016
 
Case studies: Predictive maintenance in the petrochemical industry
Case studies: Predictive maintenance in the petrochemical industryCase studies: Predictive maintenance in the petrochemical industry
Case studies: Predictive maintenance in the petrochemical industry
 
Global Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyGlobal Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea Technology
 
Life extension of aging petroleum production facilities offshore
Life extension of aging petroleum production facilities offshoreLife extension of aging petroleum production facilities offshore
Life extension of aging petroleum production facilities offshore
 
2012 ig cc-overview
2012 ig cc-overview2012 ig cc-overview
2012 ig cc-overview
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
 
Farook Presentation for Chief Engineer
Farook Presentation for Chief EngineerFarook Presentation for Chief Engineer
Farook Presentation for Chief Engineer
 
Zaheer-CV- 2015
Zaheer-CV- 2015Zaheer-CV- 2015
Zaheer-CV- 2015
 
Barriers and opportunities for use of low gwp alternatives
Barriers and opportunities for use of low gwp alternatives Barriers and opportunities for use of low gwp alternatives
Barriers and opportunities for use of low gwp alternatives
 
Insulation Technologies and Materials: Technologies, Systems and Tools in the...
Insulation Technologies and Materials: Technologies, Systems and Tools in the...Insulation Technologies and Materials: Technologies, Systems and Tools in the...
Insulation Technologies and Materials: Technologies, Systems and Tools in the...
 
"We've got to do what now?" Webinar
"We've got to do what now?" Webinar"We've got to do what now?" Webinar
"We've got to do what now?" Webinar
 
Integrity Management Plan for Pipeline-G03178 Idzuari Azli
Integrity Management Plan for Pipeline-G03178 Idzuari AzliIntegrity Management Plan for Pipeline-G03178 Idzuari Azli
Integrity Management Plan for Pipeline-G03178 Idzuari Azli
 
Ca industrial storm water program brainslam
Ca industrial storm water program brainslamCa industrial storm water program brainslam
Ca industrial storm water program brainslam
 
Presentation at wr conference may 13 draft 1 ivs
Presentation at wr conference may 13  draft 1 ivsPresentation at wr conference may 13  draft 1 ivs
Presentation at wr conference may 13 draft 1 ivs
 
NS Resume S
NS  Resume SNS  Resume S
NS Resume S
 
Webinar: CO2 pipeline infrastructure: Lessons learned
Webinar: CO2 pipeline infrastructure: Lessons learnedWebinar: CO2 pipeline infrastructure: Lessons learned
Webinar: CO2 pipeline infrastructure: Lessons learned
 
Operation & maintenance of stormwater quality treatment assets
Operation & maintenance of stormwater quality treatment  assetsOperation & maintenance of stormwater quality treatment  assets
Operation & maintenance of stormwater quality treatment assets
 
Belimo_Facility
Belimo_FacilityBelimo_Facility
Belimo_Facility
 
Primary Continuous Processing Retrofit
Primary Continuous Processing RetrofitPrimary Continuous Processing Retrofit
Primary Continuous Processing Retrofit
 

Similar to Dermarkar

1 3 amec
1 3 amec1 3 amec
1 3 amec
Ahmed Awaise
 
Barangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact Sheet
DeanDallwitz
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydNitin Sethi
 
Electronics recycling webinar final presentation
Electronics recycling webinar final presentationElectronics recycling webinar final presentation
Electronics recycling webinar final presentation
Nimonik
 
Aged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptxAged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptx
Schneider Electric
 
John Charles Snyder Lead Engineer resume
John Charles Snyder Lead Engineer resumeJohn Charles Snyder Lead Engineer resume
John Charles Snyder Lead Engineer resumeJohn Snyder
 
Clearwater Controls - DERAGGER
Clearwater Controls - DERAGGERClearwater Controls - DERAGGER
Clearwater Controls - DERAGGER
Invest Northern Ireland
 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/Projects
ScottMadden, Inc.
 
Design basis - PROCESS DESIGN FUNDAMENTALS
Design basis  - PROCESS DESIGN FUNDAMENTALSDesign basis  - PROCESS DESIGN FUNDAMENTALS
Design basis - PROCESS DESIGN FUNDAMENTALS
iFluids Engineering
 
Design basis - PROCESS DESIGN FUNDAMENTALS
Design basis  - PROCESS DESIGN FUNDAMENTALSDesign basis  - PROCESS DESIGN FUNDAMENTALS
Design basis - PROCESS DESIGN FUNDAMENTALS
iFluids Engineering
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
Comit Projects Ltd
 
Nidec asi service capabilities overview
Nidec asi service capabilities overviewNidec asi service capabilities overview
Nidec asi service capabilities overview
Nidec Corporation
 
Duke Energy - Case Study
Duke Energy - Case StudyDuke Energy - Case Study
Duke Energy - Case Study
Sentient Science
 
George Booras, EPRI - Power plant capture case studies - Introduction
George Booras, EPRI - Power plant capture case studies - IntroductionGeorge Booras, EPRI - Power plant capture case studies - Introduction
George Booras, EPRI - Power plant capture case studies - IntroductionGlobal CCS Institute
 
Following the-EXEED-methodology: data centre design
Following the-EXEED-methodology: data centre designFollowing the-EXEED-methodology: data centre design
Following the-EXEED-methodology: data centre design
SustainableEnergyAut
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
SAJJAD KHUDHUR ABBAS
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
SAJJAD KHUDHUR ABBAS
 

Similar to Dermarkar (20)

Safety Concepts of Plant Design
Safety Concepts of Plant DesignSafety Concepts of Plant Design
Safety Concepts of Plant Design
 
1 3 amec
1 3 amec1 3 amec
1 3 amec
 
Barangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact Sheet
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj Lloyd
 
Electronics recycling webinar final presentation
Electronics recycling webinar final presentationElectronics recycling webinar final presentation
Electronics recycling webinar final presentation
 
Aged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptxAged Data Center Infrastructure.pptx
Aged Data Center Infrastructure.pptx
 
John Charles Snyder Lead Engineer resume
John Charles Snyder Lead Engineer resumeJohn Charles Snyder Lead Engineer resume
John Charles Snyder Lead Engineer resume
 
Clearwater Controls - DERAGGER
Clearwater Controls - DERAGGERClearwater Controls - DERAGGER
Clearwater Controls - DERAGGER
 
Technical evaluation in cpv systems
Technical evaluation in cpv systemsTechnical evaluation in cpv systems
Technical evaluation in cpv systems
 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/Projects
 
Design basis - PROCESS DESIGN FUNDAMENTALS
Design basis  - PROCESS DESIGN FUNDAMENTALSDesign basis  - PROCESS DESIGN FUNDAMENTALS
Design basis - PROCESS DESIGN FUNDAMENTALS
 
Design basis - PROCESS DESIGN FUNDAMENTALS
Design basis  - PROCESS DESIGN FUNDAMENTALSDesign basis  - PROCESS DESIGN FUNDAMENTALS
Design basis - PROCESS DESIGN FUNDAMENTALS
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
 
Nidec asi service capabilities overview
Nidec asi service capabilities overviewNidec asi service capabilities overview
Nidec asi service capabilities overview
 
AESP_Spring
AESP_SpringAESP_Spring
AESP_Spring
 
Duke Energy - Case Study
Duke Energy - Case StudyDuke Energy - Case Study
Duke Energy - Case Study
 
George Booras, EPRI - Power plant capture case studies - Introduction
George Booras, EPRI - Power plant capture case studies - IntroductionGeorge Booras, EPRI - Power plant capture case studies - Introduction
George Booras, EPRI - Power plant capture case studies - Introduction
 
Following the-EXEED-methodology: data centre design
Following the-EXEED-methodology: data centre designFollowing the-EXEED-methodology: data centre design
Following the-EXEED-methodology: data centre design
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 

Dermarkar

  • 1. IAEA International Conference on Topical Issues in Nuclear Installation Safety Guidance on the Implementation of Modifications to Mitigate Beyond Design Basis Accidents Fred Dermarkar Vice President Engineering Strategy Ontario Power Generation October 2013
  • 2. Presentation Overview • Canadian Utility Principles for Beyond Design Basis Events – Approach to achieve “practical elimination….” • Guidance on Modifications for Beyond Design Basis Events and Accidents 2
  • 3. Canadian Nuclear Utility Principles for Beyond Design Basis Events • Developed and agreed to by the 3 Utilities • Provide guidance for utility decision making to maintain consistency • Clearly defines the end point • Provides a vehicle for communication within the Nuclear industry, with the Public and Regulators 3
  • 4. 4
  • 5. Objective of the Principles Practically eliminate the potential for societal disruption due to a nuclear incident by maintaining multiple and flexible barriers to severe event progression 5
  • 6. Principle 1 – Event Progression Defences Actions and defences will focus on stopping accident progression prior to a severe accident. • Maintaining adequate fuel cooling prevents fuel failures. • Severity of consequences escalates with event progression. • Mitigation should receive the majority of the actions and focus from the utilities. 6
  • 7. Principle 1 - Event Progression Defenses 7 Quick connections for Steam Generator EME Supply Flood barriers installed
  • 8. Principle 2 – Multiple Barriers Multiple barriers to event progression and multiple means to supply water or electricity will be used to ensure adequate defence 8
  • 9. Principle 2 – Multiple Barrier Actions 9 Heat Transport Steam Generators Moderator Shield Tank Supply water to CANDU heat sinks with portable pumps
  • 10. Principle 3 – Early Fuel Cooling Methods and actions to initiate heat transport system (HTS) cool-down and maintain fuel cooling will be a primary and early priority • Cooldown is achieved by opening Steam Reject Valves (SRVs) – Increases margin to fuel failures (lower temperature). – Allows for EME to inject additional water into a depressurized steam generators. • Actions to open SRVs need to be simple and reliable. 10
  • 11. Principle 3 – Early Fuel Cooling Actions • Cooldown of the Heat Transport can be achieved by opening boiler steam Reject Valves manually 11 • Air Supply connections installed to open and hold open valves • Class II battery banks confirmed to be seismically robust
  • 12. Principle 4 – Containment Integrity Actions to maintain Containment integrity will be utilized to minimize radioactive releases • Control pressure – Containment Cooling – Containment Venting (Principle 5) • Control hydrogen – Minimize generation – Effective removal • Control water inventory to minimize flooding – Water injection and control 12
  • 13. Principle 4 - Containment Integrity Actions 13 Containment ACUs supplied with water and electricity Passive Autocatalytic Recombiners 1 MW Generators
  • 14. Principle 5 – Filtered Venting Containment venting will be controlled through a filtered system • With a functional containment, decisions can be made when to vent and for how long. • Controlled filtered venting will minimize radioactive releases and their potential impact on the environment. • The ability to delay when containment will be vented allows for short lived material to be reduced through decay. 14
  • 15. Principle 5 – Filtered Venting 15
  • 16. Principle 6 – Equipment Integrity Necessary systems, structures and components will be confirmed to survive rare yet credible conditions for external hazards • Existing Plant equipment will only be relied upon if shown available after Beyond Design Basis Event • Review Level Conditions (RLCs) established for rare yet credible conditions. e.g., seismic Design Basis ~1,000 yr; RLC ~10,000 yr • Provides assurance that the plants will meet the objective for BDBE 16
  • 17. Principle 6 –Equipment Integrity Actions • Seismic Margin Assessments or Fragility analyses being completed: o Passive water supply to Steam Generators (Dearator) o Class II batteries and rack • EME Quick connects designed to meet BDBE requirement. • Seismic safety margin and vulnerabilities assessed as part of station PSAs. • Seismically-induced internal fires and internal flooding assessments in progress. • Credible external hazard magnitudes being updated (seismic, tsunami, wind) 17
  • 18. Principle 7 – Spent Fuel Cooling Irradiated Fuel Bay (IFB) water levels will be maintained sufficiently above the top of the fuel to mitigate high radiation fields, hydrogen production, and fuel damage • The time required to respond to a loss of IFB cooling is typically quite long. • The volume of water in the IFB should be maximized within normal water levels to the extent practicable. • EME to supply water to account for leakage and steaming. 18
  • 19. Principle 7 – Spent Fuel Cooling Actions 19 EME Water Supply piping to IFB
  • 20. Principle 8 – Readily Deployed Emergency Mitigating Equipment will be robust, readily available, easily deployable within required timeframes, and have adequate redundancy • Stored at higher elevation, away from station, close enough for timely deployment and accessible following BDBE – Pre-staging is an option for predictable events (e.g., severe weather) • Deployable by diverse work groups, supported by procedures, training and practice and validated by drills • More than one method for deployment (trucks, tractors, security vehicles) • Reliability of EME supported by using proven technology, preventative maintenance and routine testing • On-site fuel supplies adequate for > 72 hour run time, with provisions for refueling in place. 20
  • 21. Principle 8 – “Readily Deployed” Actions 21
  • 22. Principle 9 - Common Philosophy Canadian utilities will utilize a common philosophy for the prevention of a Beyond Design Basis Accident (BDBA) • Interaction between utilities gives a larger perspective and experience base – Encourages challenging and learning – Improves capability to respond and to provide mutual assistance – Provides credibility – Facilitates regulatory concurrence. 22
  • 23. Principle 9 -Common Philosophy Actions • COG Severe Accident Joint Project Technical Reports o Shutdown and Low Power, Multi-unit Station, Technical Basis Document and SAMG Update, Containment Integrity, In-Vessel Retention, Instrument Survivability, Habitability • COG Emergency Preparedness Work Shop III June 3&4, o Diverse participation including CNSC, Health Canada and provincial agencies. • WANO SOER 13-2 corrective action plans o Developed cooperatively • Mutual Aid Agreement in effect • Regional Emergency Response Support Centre o Site selection complete 23
  • 24. Designing for Beyond Design Basis • Objective – Deliver functionality to prevent or mitigate significant adverse consequences with reasonable assurance • Maintain fuel cooling • Arrest core damage • Protect containment integrity – Ensure functionality for design basis conditions is not compromised • Graded approach • Recognized as providing interim direction 24
  • 25. Graded Approach 2. Equipment upgrades installed on existing engineered SSCs to manage BDBAs. 25 • Four categories of Systems, Structures & Components (SSCs): 1. Existing engineered SSCs called upon to manage BDBAs Steam Reject Valves to depressurize Steam Generators Additional Air supply to hold Steam Reject Valves open
  • 26. Graded Approach 26 4. Portable SSCs to be attached to existing SSC to manage BDBAs 3. New engineered SSCs for the sole purpose of managing BDBAs
  • 27. Application to Design 27 • For all Categories: – Analysis based on more realistic initiating conditions – Interfacing components designed to requirements of the parent system – Robustness demonstrated for Review Level Conditions (RLCs) • RLC: appropriate estimate of the intensity of a rare, yet credible external hazard to confirm adequate safety margin for beyond design basis events
  • 28. Application to Design 28 • For Category 4: – Design process documented, approved by the Design Authority. – Codes / standards appropriate for portable equipment to be used – Equipment to be designed for two tie-in points, at least one of which is an engineered tie-in point
  • 29. Application to Procurement • For Categories 1,2: – Full procurement rigour as applied to nuclear components • For Category 3: – As above, but typical commercial / industrial process may apply beyond system isolation tie-in points. Deviations approved by Design Authority. 29 Quick connect: commercial Piping to isolation point: nuclear
  • 30. Application to Procurement • Spare parts: – Appropriately considered in the procurement process. – For Category 4, provide for N+1 running spares, per FLEX. 30 • For Category 4: – Commercial/industrial processes apply and manufacturer’s standards apply. – Equipment to be stored in a manner to make it resilient to BDBEs
  • 31. Application to Installation, Commissioning and Testing • For Category 1, 2: – Process for installation, testing, commissioning same as for normal engineering change control process • For Category 3, 4: – Commercial/industrial processes apply for installation, testing and commissioning – Demonstration that functional performance requirements have been met 31
  • 32. Application to Operations and Maintenance • For all categories: – Operator Routines and Testing are performed regularly to ensure reliability and availability of SSCs. – Allowable outage times as defined in Operational Safety Requirements, which are part of the design and licensing basis • For Category 4: – Where equipment redundancy exists, equipment can be taken out of service for maintenance for up to 90 days. – Where no equipment redundancy exists, equipment can be taken out of service for up to 14 days for maintenance. – A longer restoration period requires approval of the Operations and Maintenance Director. 32
  • 33. Principles for Sustainability • The technical basis for BDBA Response Capability (BDBA RC) shall be formally documented and periodically reviewed to ensure that it remains current. • Regular maintenance and testing of BDBA RC shall be controlled through a predefined process consistent with regular station equipment; it shall be documented and periodically audited. • The maintenance of BDBA RC shall be routinely self- assessed and independently audited • BDBA RC shall be revisited when new safety analysis is performed 33
  • 34. Principles for Sustainability • Station modification control processes shall ensure that BDBA RC is not inadvertently altered. • BDBA RC functional requirements shall be documented in a manner similar to the Operational Safety Requirements for design basis credits. • Station transient material processes shall include controls to ensure that access to tie-in points and staging locations for BDBA RC are accessible. • Maintenance and Outage Management processes shall account for capability to implement BDBA RC. 34
  • 35. Conclusion • Recent applications at OPG: – Flood barrier protection at Pickering – Emergency Mitigating Equipment at Pickering and Darlington – Containment Filtered Venting System at Darlington • The application of the process has confirmed that it is sound and provides required flexibility. • Communication between project staff, nuclear safety staff and design organizations is key to ensure the correct balance and rigour is applied. 35
  • 36. SUMMARY • Canada is committed to the objective to “Practically Eliminate the Potential for Societal Disruption” • We have defined the steps and processes to meet and sustain this objective • We are well advanced • We are willing to learn and improve 36