SlideShare a Scribd company logo
1 of 26
1
Plan A Plan B Plan C……how far ?
A new methodology for preparing Alternate Plans
Paramita Mukerji
28 September 2013
2Plan A Plan B Plan C……how far ?
Agenda
Current Scenario in IT projects
Why plans change?
Constraints in Alt Planning
Alt-PM : The Alternate Planning Methodology
Prepare Guidelines
Define Benchmarks
Calculate Total weight
Derive the number of alternate plans
Critical factors for success
Benefits
3
Current Scenario in IT Projects
• Plans are prepared by PMs during project planning
• All relevant information is taken in consideration
• Senior management approval, followed by customer assent
BUT THESE PLANS FREQUENTLY CHANGE
WHY?
Plan A Plan B Plan C……how far ?
4
Why plans change?
Plan A Plan B Plan C……how far ?
5
Factors leading to change in plans
• Factors Internal to the team
– lack of skilled resources
– lack of experience
– lack of technical competence
– processes which are either not defined or not followed
• Factors external to the team (in decreasing order of impact)
– change in scope
– change in timelines
– change in final product quality/specifications
– change in budget
Plan A Plan B Plan C……how far ?
6
Root causes which lead to the failure of the
plans
Above data based on inputs from people working in various types of IT projects majorly in
the role of Project Managers and some in various types of other roles like Project
Lead, Analyst, Architect, Tester, Quality Assurance, Developer, vendor side SPOC across
organizations.
43%
22%
11%
9%
4%
4%
7%
Customer driven
Technology related
Unavailability of resources
In capability of the delivery
team
Competition driven
Statutory regulations
Others
Plan A Plan B Plan C……how far ?
7
Is there a need for Alternate Plan ?
Existing Scenario in IT projects reflect that:
• 90% Project Managers feel the need for Alternate Plans
• 60% of the Projects do not prepare Alternate Plans
• 40% projects have Alternate Plans
– BUT they are created post failure of earlier plan
• 70% PMs believe Alternate Plans should be made proactively
Plan A Plan B Plan C……how far ?
8
Constraints in Alt Planning
Plan A Plan B Plan C……how far ?
9
Constraints in proactive planning
• Inability to forecast
• Unavailability of time (budget)
• Unavailability of data
• Not part of defined process
• Reactive versus Proactive
– Hindsight is 20:20
Plan A Plan B Plan C……how far ?
10
Constraints in implementation
• Tendency to revert to earlier plan
• Revised plan not detailed enough
• Unavailability of resources (Human, Hard or Software).
• Lack of faith
• Frequent changes in the revised plan
• Delay in mid-project approval
– Customer approval
– Senior management approvals
Plan A Plan B Plan C……how far ?
11
Recap
• Projects will undergo changes
• These changes have to be handled
• In order to handle changes we should:
– Identify the need for Alternate Plans
– Prepare Alternate Plans proactively
– Implement Alternate Plans appropriately
Plan A Plan B Plan C……how far ?
12
Alt-PM
Alternate Planning Methodology
A reference tool to help projects identify the optimum number of alternate
plans required under varying project conditions
Plan A Plan B Plan C……how far ?
13
About Alt-PM Methodology
Alt-PM is a methodology aimed towards helping the managers
identify the alternate plans proactively based on information
available. It factors in the challenges with respect to
implementation of these plans.
It is a simple methodology in which :
– Guidelines are prepared by experienced project managers
– Projects use these guidelines to prepare Alternate Plans
– Guidelines evolve dynamically with usage
Plan A Plan B Plan C……how far ?
14
Using Alt-PM
The usage of this methodology is a two step process:
Step 1: Preparation of the Guidelines & Benchmarks
Step 2: Calculating the number of Alternate Plans for a new project
Plan A Plan B Plan C……how far ?
15
Step 1a. Prepare guidelines
1. Choose the group of project with similar characteristics
2. Creating the Factor table
– List the constraints which are generally faced by such projects.
We call them Factors
• Assign weight to each factor in a scale of 0-5 (5 means
highest impact on plans) – Factor Table
3. Creating the Phase table
– Sequence in which these projects get executed. We call them
Phases
• Arrange phases in chronological order
• Assign weight to each phase ( higher weight means
change in this phase has higher impact on plans) – Phase
Table
Plan A Plan B Plan C……how far ?
16
Factor & Phase Tables for a typical IT
Development Project ( An Example )
Factors Weight (A)
Team not experienced in the
domain
3
Team not skilled for gathering
requirements
2
Team resists any change 4
Team does not follow processes 1
Customer not clear on the
requirements
4
Delay due to vendor 3
Human Resources not available 3
Phases Weight (B)
Initiation 0.25
Planning 0.25
Requirements 1
Design 2
CUT 2
Testing 3
Factor Table (1)
Phase Table (2)
Plan A Plan B Plan C……how far ?
17
Step 1b. Define benchmarks
Benchmarks are decided on the basis of data gathered from past projects
with similar characteristics
• Identify completed project
• Identify the constraints that were faced by this project
– Note the corresponding weights for the Factors (refer Factor Table) - A
• Identify the phases in which they were identified
– Note the corresponding weight for the Phases (refer Phase Table) - B
• Final Weight for each phase = ( A * B )
• Count the number of Alternate Plans prepared during these phases of the
project to handle the constraints
• Repeat this process with various projects which are complete and take the
average value
• Benchmark this count against the weight ranges – Benchmark Table
Plan A Plan B Plan C……how far ?
18
Benchmark Table for a typical IT
Development Project ( An Example)
Weight
Range
Recommended number of Alternate Plans
Initiation Planning Req. Design CUT Testing
0-1 0 0 0 0 0 0
2-10 1 1 2 2 3 3
11-20 2 2 3 3 4 4
>20 3 3 4 4 5 5
Plan A Plan B Plan C……how far ?
Benchmark Table (3)
19
Step 2a. Calculate total weight in case of a
new project
• Identify the Factors in the new project
– Note the corresponding weights (refer Factor Table) -- A
• Identify the Phase in which they have maximum probability of
identification
– Note the corresponding weight (refer Phase Table) -- B
• Total Weight = ( A * B)
Plan A Plan B Plan C……how far ?
20
Calculation of Total Weight for a new IT
Development Project ( An Example )
Factors effecting the current
project
Weight
based on
Factor
Table (A)
Phase
when this
factor
may be
identified
Weight
based on
Phase
Table (B)
Total
Weight
(A * B)
Team not experienced in the
domain
3 Initiation 0.25 0.75
Team not clear on the
requirements
2 Design 2 4
Team does not follow processes 1 Req. 1 1
Multiple stakeholders 4 Planning 0.25 1
Delay in query resolution by
customer
4 Planning 0.25 1
Competitors launching similar
product
5 Design
2 10
Plan A Plan B Plan C……how far ?
Total Weight Table (4)
21
Step 2b. Derive the number of alternate
plans required for a phase
• Calculate the sum of the total weights for each of the phases
separately
• Look up in the Benchmark Table
• Find the number of alternate plans corresponding to the total
weight for that phase
• Prepare Alternate Plans accordingly for each phase
Plan A Plan B Plan C……how far ?
22
Number of Alternate Plans for a new IT
Development Project ( Example contd.)
Phase(s) Total weight
Calculated from
Table 4
Alternate Plans to
be prepared based
on Benchmark Table
Initiation 0.75 0
Planning 2 1
Requirements 1 0
Design 14 3
Plan A Plan B Plan C……how far ?
Number of Alternate Plans Table (5)
23
Critical factors for success
The success of this methodology depends on
• Experience of the person/team preparing the guidelines
• Reliability of the data received from past projects
• Clear understanding of the project
• Updating & improving the guidelines
• Proper use of the guidelines & benchmarks
• Different set of guidelines and benchmarks to be used for
different types of projects
Plan A Plan B Plan C……how far ?
24
Benefits of using Alt-PM
• Planning for eventualities in advance
• Saving project effort & time leading to cost saving
• Enhancing knowledge sharing and reducing person dependency
• Showcasing proactive Project Management
• Achieving higher customer satisfaction scores
• High project flexibility
• Higher team motivation
Plan A Plan B Plan C……how far ?
25
Alt-PM
A methodology to face the challenges in a more
structured & organized manner
HAPPY PROJECT MANAGEMENT 
Plan A Plan B Plan C……how far ?
26
Thank You
Plan A Plan B Plan C……how far ?

More Related Content

What's hot

Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
Jatindra Malik
 
Project planning
Project planningProject planning
Project planning
Shaikh Zain
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projects
haroldtaylor1113
 

What's hot (18)

Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Project Management 4 Schedule Management
Project Management 4 Schedule ManagementProject Management 4 Schedule Management
Project Management 4 Schedule Management
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
Conveyor belt project
Conveyor belt projectConveyor belt project
Conveyor belt project
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
1 b, evaluation of project
1 b, evaluation of project1 b, evaluation of project
1 b, evaluation of project
 
Project managemen PERT VS CPM
Project managemen  PERT VS CPMProject managemen  PERT VS CPM
Project managemen PERT VS CPM
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Project milestone
Project milestoneProject milestone
Project milestone
 
Project planning
Project planningProject planning
Project planning
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projects
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 

Viewers also liked

Bhavesh 20-pmi-20final-131008015751-phpapp01
Bhavesh 20-pmi-20final-131008015751-phpapp01Bhavesh 20-pmi-20final-131008015751-phpapp01
Bhavesh 20-pmi-20final-131008015751-phpapp01
PMI_IREP_TP
 
Jagadeeshdv abhaydesai-131008015757-phpapp02
Jagadeeshdv abhaydesai-131008015757-phpapp02Jagadeeshdv abhaydesai-131008015757-phpapp02
Jagadeeshdv abhaydesai-131008015757-phpapp02
PMI_IREP_TP
 
Presentation by mangesh sardesai
Presentation by mangesh sardesaiPresentation by mangesh sardesai
Presentation by mangesh sardesai
PMI_IREP_TP
 
Presentation by shubham vyas
Presentation by shubham vyasPresentation by shubham vyas
Presentation by shubham vyas
PMI_IREP_TP
 
Finalchakradharpurohithproposalmilieuanalysiswithoutaccountdata unpublished-1...
Finalchakradharpurohithproposalmilieuanalysiswithoutaccountdata unpublished-1...Finalchakradharpurohithproposalmilieuanalysiswithoutaccountdata unpublished-1...
Finalchakradharpurohithproposalmilieuanalysiswithoutaccountdata unpublished-1...
PMI_IREP_TP
 
Presentation by j v rao.doc
Presentation by j v rao.docPresentation by j v rao.doc
Presentation by j v rao.doc
PMI_IREP_TP
 
Presentation by beebejan valiyakath
Presentation by beebejan valiyakathPresentation by beebejan valiyakath
Presentation by beebejan valiyakath
PMI_IREP_TP
 
Presentation by somdatta banerjee
Presentation by somdatta banerjeePresentation by somdatta banerjee
Presentation by somdatta banerjee
PMI_IREP_TP
 
Presentation by pranal dongare
Presentation by pranal dongarePresentation by pranal dongare
Presentation by pranal dongare
PMI_IREP_TP
 
Presentation by pavan adipuram
Presentation by pavan adipuramPresentation by pavan adipuram
Presentation by pavan adipuram
PMI_IREP_TP
 
Presentation by saurabh chandra
Presentation by saurabh chandraPresentation by saurabh chandra
Presentation by saurabh chandra
PMI_IREP_TP
 
Presentation by dhruva sen
Presentation by dhruva senPresentation by dhruva sen
Presentation by dhruva sen
PMI_IREP_TP
 
Presentation by subhajit bhattacharya1
Presentation by subhajit bhattacharya1Presentation by subhajit bhattacharya1
Presentation by subhajit bhattacharya1
PMI_IREP_TP
 
Presentation by dattatraya pathak
Presentation by dattatraya pathakPresentation by dattatraya pathak
Presentation by dattatraya pathak
PMI_IREP_TP
 
Presentation by suhail qadir
Presentation by suhail qadirPresentation by suhail qadir
Presentation by suhail qadir
PMI_IREP_TP
 
Presentation by jv rao
Presentation by jv raoPresentation by jv rao
Presentation by jv rao
PMI_IREP_TP
 

Viewers also liked (18)

Bhavesh 20-pmi-20final-131008015751-phpapp01
Bhavesh 20-pmi-20final-131008015751-phpapp01Bhavesh 20-pmi-20final-131008015751-phpapp01
Bhavesh 20-pmi-20final-131008015751-phpapp01
 
Jagadeeshdv abhaydesai-131008015757-phpapp02
Jagadeeshdv abhaydesai-131008015757-phpapp02Jagadeeshdv abhaydesai-131008015757-phpapp02
Jagadeeshdv abhaydesai-131008015757-phpapp02
 
Presentation by mangesh sardesai
Presentation by mangesh sardesaiPresentation by mangesh sardesai
Presentation by mangesh sardesai
 
Presentation by shubham vyas
Presentation by shubham vyasPresentation by shubham vyas
Presentation by shubham vyas
 
Finalchakradharpurohithproposalmilieuanalysiswithoutaccountdata unpublished-1...
Finalchakradharpurohithproposalmilieuanalysiswithoutaccountdata unpublished-1...Finalchakradharpurohithproposalmilieuanalysiswithoutaccountdata unpublished-1...
Finalchakradharpurohithproposalmilieuanalysiswithoutaccountdata unpublished-1...
 
Presentation by j v rao.doc
Presentation by j v rao.docPresentation by j v rao.doc
Presentation by j v rao.doc
 
Presentation by beebejan valiyakath
Presentation by beebejan valiyakathPresentation by beebejan valiyakath
Presentation by beebejan valiyakath
 
Presentation by somdatta banerjee
Presentation by somdatta banerjeePresentation by somdatta banerjee
Presentation by somdatta banerjee
 
Presentation by pranal dongare
Presentation by pranal dongarePresentation by pranal dongare
Presentation by pranal dongare
 
Enterprise Day 2015 - JIRA for field work (ReSight)
Enterprise Day 2015 - JIRA for field work (ReSight)Enterprise Day 2015 - JIRA for field work (ReSight)
Enterprise Day 2015 - JIRA for field work (ReSight)
 
Presentation by pavan adipuram
Presentation by pavan adipuramPresentation by pavan adipuram
Presentation by pavan adipuram
 
Presentation by saurabh chandra
Presentation by saurabh chandraPresentation by saurabh chandra
Presentation by saurabh chandra
 
Presentation by dhruva sen
Presentation by dhruva senPresentation by dhruva sen
Presentation by dhruva sen
 
Presentation by subhajit bhattacharya1
Presentation by subhajit bhattacharya1Presentation by subhajit bhattacharya1
Presentation by subhajit bhattacharya1
 
Presentation by dattatraya pathak
Presentation by dattatraya pathakPresentation by dattatraya pathak
Presentation by dattatraya pathak
 
Presentation by suhail qadir
Presentation by suhail qadirPresentation by suhail qadir
Presentation by suhail qadir
 
Driving engagement in the digital workplace
Driving engagement in the digital workplaceDriving engagement in the digital workplace
Driving engagement in the digital workplace
 
Presentation by jv rao
Presentation by jv raoPresentation by jv rao
Presentation by jv rao
 

Similar to Day 202-20-201135-20-201220-20-20-20maple-20-20paramita-20mukerji-131008015752-phpapp02

Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
alfred4lewis58146
 
Software Project Management lecture 9
Software Project Management lecture 9Software Project Management lecture 9
Software Project Management lecture 9
Syed Muhammad Hammad
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
IRESH3
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx
dorishigh
 
Motorola Advaced Project Portfolio Management
Motorola Advaced Project Portfolio ManagementMotorola Advaced Project Portfolio Management
Motorola Advaced Project Portfolio Management
Aras
 

Similar to Day 202-20-201135-20-201220-20-20-20maple-20-20paramita-20mukerji-131008015752-phpapp02 (20)

Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
 
Software Project Management lecture 9
Software Project Management lecture 9Software Project Management lecture 9
Software Project Management lecture 9
 
Investment Planning: Meeting today's challenges and planning for the future
Investment Planning: Meeting today's challenges and planning for the futureInvestment Planning: Meeting today's challenges and planning for the future
Investment Planning: Meeting today's challenges and planning for the future
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
 
06 project time management
06  project time management06  project time management
06 project time management
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.ppt
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
 
Intro to PM.ppt
Intro to PM.pptIntro to PM.ppt
Intro to PM.ppt
 
2015 Toronto Section Presentation
2015 Toronto Section Presentation2015 Toronto Section Presentation
2015 Toronto Section Presentation
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
The Role of the Business Case in Public Investment Management and Project Por...
The Role of the Business Case in Public Investment Management and Project Por...The Role of the Business Case in Public Investment Management and Project Por...
The Role of the Business Case in Public Investment Management and Project Por...
 
lec11.ppt
lec11.pptlec11.ppt
lec11.ppt
 
PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0
 
Project Planning
Project PlanningProject Planning
Project Planning
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx
 
Motorola Advaced Project Portfolio Management
Motorola Advaced Project Portfolio ManagementMotorola Advaced Project Portfolio Management
Motorola Advaced Project Portfolio Management
 
Planning.ppt
Planning.pptPlanning.ppt
Planning.ppt
 
5-ProjPlanning.ppt
5-ProjPlanning.ppt5-ProjPlanning.ppt
5-ProjPlanning.ppt
 

More from PMI_IREP_TP

Presentation by vikas dubey
Presentation by vikas dubeyPresentation by vikas dubey
Presentation by vikas dubey
PMI_IREP_TP
 
Presentation by anjali mogre
Presentation by anjali mogrePresentation by anjali mogre
Presentation by anjali mogre
PMI_IREP_TP
 
Presentation by shreyas bhargave
Presentation by shreyas bhargavePresentation by shreyas bhargave
Presentation by shreyas bhargave
PMI_IREP_TP
 
Presentation by anipriya p
Presentation by anipriya pPresentation by anipriya p
Presentation by anipriya p
PMI_IREP_TP
 
Presentation by dhruba jyoti chaudhuri
Presentation by dhruba jyoti chaudhuriPresentation by dhruba jyoti chaudhuri
Presentation by dhruba jyoti chaudhuri
PMI_IREP_TP
 
Presentation by rahul ghodke
Presentation by rahul ghodkePresentation by rahul ghodke
Presentation by rahul ghodke
PMI_IREP_TP
 
Presentation by dakshinamoorthi g
Presentation by dakshinamoorthi  gPresentation by dakshinamoorthi  g
Presentation by dakshinamoorthi g
PMI_IREP_TP
 
Presentation by Rajesh Kumar Mudiakal
Presentation by Rajesh Kumar MudiakalPresentation by Rajesh Kumar Mudiakal
Presentation by Rajesh Kumar Mudiakal
PMI_IREP_TP
 
Presentation by Gaurav Sapra
Presentation by Gaurav SapraPresentation by Gaurav Sapra
Presentation by Gaurav Sapra
PMI_IREP_TP
 
Presentation by Ruchika Wadhwa
Presentation by Ruchika WadhwaPresentation by Ruchika Wadhwa
Presentation by Ruchika Wadhwa
PMI_IREP_TP
 
Presentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPresentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajan
PMI_IREP_TP
 
Presentation by sameer murdeshwar
Presentation by sameer murdeshwarPresentation by sameer murdeshwar
Presentation by sameer murdeshwar
PMI_IREP_TP
 
Presentation by prameela kumar
Presentation by prameela kumarPresentation by prameela kumar
Presentation by prameela kumar
PMI_IREP_TP
 
Presentation by lavika upadhyay
Presentation by lavika upadhyayPresentation by lavika upadhyay
Presentation by lavika upadhyay
PMI_IREP_TP
 
Presentation by lakshmi varagan d
Presentation by lakshmi varagan dPresentation by lakshmi varagan d
Presentation by lakshmi varagan d
PMI_IREP_TP
 
Presentation by parag saha
Presentation by parag sahaPresentation by parag saha
Presentation by parag saha
PMI_IREP_TP
 
Presentation by somdatta banerjee
Presentation by somdatta banerjeePresentation by somdatta banerjee
Presentation by somdatta banerjee
PMI_IREP_TP
 
Presentation by meghna jadhav
Presentation by meghna jadhavPresentation by meghna jadhav
Presentation by meghna jadhav
PMI_IREP_TP
 
Presentation by bhavesh thakkar
Presentation by bhavesh thakkarPresentation by bhavesh thakkar
Presentation by bhavesh thakkar
PMI_IREP_TP
 
Presentation by vignesh swamidurai
Presentation by vignesh swamiduraiPresentation by vignesh swamidurai
Presentation by vignesh swamidurai
PMI_IREP_TP
 

More from PMI_IREP_TP (20)

Presentation by vikas dubey
Presentation by vikas dubeyPresentation by vikas dubey
Presentation by vikas dubey
 
Presentation by anjali mogre
Presentation by anjali mogrePresentation by anjali mogre
Presentation by anjali mogre
 
Presentation by shreyas bhargave
Presentation by shreyas bhargavePresentation by shreyas bhargave
Presentation by shreyas bhargave
 
Presentation by anipriya p
Presentation by anipriya pPresentation by anipriya p
Presentation by anipriya p
 
Presentation by dhruba jyoti chaudhuri
Presentation by dhruba jyoti chaudhuriPresentation by dhruba jyoti chaudhuri
Presentation by dhruba jyoti chaudhuri
 
Presentation by rahul ghodke
Presentation by rahul ghodkePresentation by rahul ghodke
Presentation by rahul ghodke
 
Presentation by dakshinamoorthi g
Presentation by dakshinamoorthi  gPresentation by dakshinamoorthi  g
Presentation by dakshinamoorthi g
 
Presentation by Rajesh Kumar Mudiakal
Presentation by Rajesh Kumar MudiakalPresentation by Rajesh Kumar Mudiakal
Presentation by Rajesh Kumar Mudiakal
 
Presentation by Gaurav Sapra
Presentation by Gaurav SapraPresentation by Gaurav Sapra
Presentation by Gaurav Sapra
 
Presentation by Ruchika Wadhwa
Presentation by Ruchika WadhwaPresentation by Ruchika Wadhwa
Presentation by Ruchika Wadhwa
 
Presentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPresentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajan
 
Presentation by sameer murdeshwar
Presentation by sameer murdeshwarPresentation by sameer murdeshwar
Presentation by sameer murdeshwar
 
Presentation by prameela kumar
Presentation by prameela kumarPresentation by prameela kumar
Presentation by prameela kumar
 
Presentation by lavika upadhyay
Presentation by lavika upadhyayPresentation by lavika upadhyay
Presentation by lavika upadhyay
 
Presentation by lakshmi varagan d
Presentation by lakshmi varagan dPresentation by lakshmi varagan d
Presentation by lakshmi varagan d
 
Presentation by parag saha
Presentation by parag sahaPresentation by parag saha
Presentation by parag saha
 
Presentation by somdatta banerjee
Presentation by somdatta banerjeePresentation by somdatta banerjee
Presentation by somdatta banerjee
 
Presentation by meghna jadhav
Presentation by meghna jadhavPresentation by meghna jadhav
Presentation by meghna jadhav
 
Presentation by bhavesh thakkar
Presentation by bhavesh thakkarPresentation by bhavesh thakkar
Presentation by bhavesh thakkar
 
Presentation by vignesh swamidurai
Presentation by vignesh swamiduraiPresentation by vignesh swamidurai
Presentation by vignesh swamidurai
 

Recently uploaded

Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
lizamodels9
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
dlhescort
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Anamikakaur10
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
lizamodels9
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 

Recently uploaded (20)

Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 

Day 202-20-201135-20-201220-20-20-20maple-20-20paramita-20mukerji-131008015752-phpapp02

  • 1. 1 Plan A Plan B Plan C……how far ? A new methodology for preparing Alternate Plans Paramita Mukerji 28 September 2013
  • 2. 2Plan A Plan B Plan C……how far ? Agenda Current Scenario in IT projects Why plans change? Constraints in Alt Planning Alt-PM : The Alternate Planning Methodology Prepare Guidelines Define Benchmarks Calculate Total weight Derive the number of alternate plans Critical factors for success Benefits
  • 3. 3 Current Scenario in IT Projects • Plans are prepared by PMs during project planning • All relevant information is taken in consideration • Senior management approval, followed by customer assent BUT THESE PLANS FREQUENTLY CHANGE WHY? Plan A Plan B Plan C……how far ?
  • 4. 4 Why plans change? Plan A Plan B Plan C……how far ?
  • 5. 5 Factors leading to change in plans • Factors Internal to the team – lack of skilled resources – lack of experience – lack of technical competence – processes which are either not defined or not followed • Factors external to the team (in decreasing order of impact) – change in scope – change in timelines – change in final product quality/specifications – change in budget Plan A Plan B Plan C……how far ?
  • 6. 6 Root causes which lead to the failure of the plans Above data based on inputs from people working in various types of IT projects majorly in the role of Project Managers and some in various types of other roles like Project Lead, Analyst, Architect, Tester, Quality Assurance, Developer, vendor side SPOC across organizations. 43% 22% 11% 9% 4% 4% 7% Customer driven Technology related Unavailability of resources In capability of the delivery team Competition driven Statutory regulations Others Plan A Plan B Plan C……how far ?
  • 7. 7 Is there a need for Alternate Plan ? Existing Scenario in IT projects reflect that: • 90% Project Managers feel the need for Alternate Plans • 60% of the Projects do not prepare Alternate Plans • 40% projects have Alternate Plans – BUT they are created post failure of earlier plan • 70% PMs believe Alternate Plans should be made proactively Plan A Plan B Plan C……how far ?
  • 8. 8 Constraints in Alt Planning Plan A Plan B Plan C……how far ?
  • 9. 9 Constraints in proactive planning • Inability to forecast • Unavailability of time (budget) • Unavailability of data • Not part of defined process • Reactive versus Proactive – Hindsight is 20:20 Plan A Plan B Plan C……how far ?
  • 10. 10 Constraints in implementation • Tendency to revert to earlier plan • Revised plan not detailed enough • Unavailability of resources (Human, Hard or Software). • Lack of faith • Frequent changes in the revised plan • Delay in mid-project approval – Customer approval – Senior management approvals Plan A Plan B Plan C……how far ?
  • 11. 11 Recap • Projects will undergo changes • These changes have to be handled • In order to handle changes we should: – Identify the need for Alternate Plans – Prepare Alternate Plans proactively – Implement Alternate Plans appropriately Plan A Plan B Plan C……how far ?
  • 12. 12 Alt-PM Alternate Planning Methodology A reference tool to help projects identify the optimum number of alternate plans required under varying project conditions Plan A Plan B Plan C……how far ?
  • 13. 13 About Alt-PM Methodology Alt-PM is a methodology aimed towards helping the managers identify the alternate plans proactively based on information available. It factors in the challenges with respect to implementation of these plans. It is a simple methodology in which : – Guidelines are prepared by experienced project managers – Projects use these guidelines to prepare Alternate Plans – Guidelines evolve dynamically with usage Plan A Plan B Plan C……how far ?
  • 14. 14 Using Alt-PM The usage of this methodology is a two step process: Step 1: Preparation of the Guidelines & Benchmarks Step 2: Calculating the number of Alternate Plans for a new project Plan A Plan B Plan C……how far ?
  • 15. 15 Step 1a. Prepare guidelines 1. Choose the group of project with similar characteristics 2. Creating the Factor table – List the constraints which are generally faced by such projects. We call them Factors • Assign weight to each factor in a scale of 0-5 (5 means highest impact on plans) – Factor Table 3. Creating the Phase table – Sequence in which these projects get executed. We call them Phases • Arrange phases in chronological order • Assign weight to each phase ( higher weight means change in this phase has higher impact on plans) – Phase Table Plan A Plan B Plan C……how far ?
  • 16. 16 Factor & Phase Tables for a typical IT Development Project ( An Example ) Factors Weight (A) Team not experienced in the domain 3 Team not skilled for gathering requirements 2 Team resists any change 4 Team does not follow processes 1 Customer not clear on the requirements 4 Delay due to vendor 3 Human Resources not available 3 Phases Weight (B) Initiation 0.25 Planning 0.25 Requirements 1 Design 2 CUT 2 Testing 3 Factor Table (1) Phase Table (2) Plan A Plan B Plan C……how far ?
  • 17. 17 Step 1b. Define benchmarks Benchmarks are decided on the basis of data gathered from past projects with similar characteristics • Identify completed project • Identify the constraints that were faced by this project – Note the corresponding weights for the Factors (refer Factor Table) - A • Identify the phases in which they were identified – Note the corresponding weight for the Phases (refer Phase Table) - B • Final Weight for each phase = ( A * B ) • Count the number of Alternate Plans prepared during these phases of the project to handle the constraints • Repeat this process with various projects which are complete and take the average value • Benchmark this count against the weight ranges – Benchmark Table Plan A Plan B Plan C……how far ?
  • 18. 18 Benchmark Table for a typical IT Development Project ( An Example) Weight Range Recommended number of Alternate Plans Initiation Planning Req. Design CUT Testing 0-1 0 0 0 0 0 0 2-10 1 1 2 2 3 3 11-20 2 2 3 3 4 4 >20 3 3 4 4 5 5 Plan A Plan B Plan C……how far ? Benchmark Table (3)
  • 19. 19 Step 2a. Calculate total weight in case of a new project • Identify the Factors in the new project – Note the corresponding weights (refer Factor Table) -- A • Identify the Phase in which they have maximum probability of identification – Note the corresponding weight (refer Phase Table) -- B • Total Weight = ( A * B) Plan A Plan B Plan C……how far ?
  • 20. 20 Calculation of Total Weight for a new IT Development Project ( An Example ) Factors effecting the current project Weight based on Factor Table (A) Phase when this factor may be identified Weight based on Phase Table (B) Total Weight (A * B) Team not experienced in the domain 3 Initiation 0.25 0.75 Team not clear on the requirements 2 Design 2 4 Team does not follow processes 1 Req. 1 1 Multiple stakeholders 4 Planning 0.25 1 Delay in query resolution by customer 4 Planning 0.25 1 Competitors launching similar product 5 Design 2 10 Plan A Plan B Plan C……how far ? Total Weight Table (4)
  • 21. 21 Step 2b. Derive the number of alternate plans required for a phase • Calculate the sum of the total weights for each of the phases separately • Look up in the Benchmark Table • Find the number of alternate plans corresponding to the total weight for that phase • Prepare Alternate Plans accordingly for each phase Plan A Plan B Plan C……how far ?
  • 22. 22 Number of Alternate Plans for a new IT Development Project ( Example contd.) Phase(s) Total weight Calculated from Table 4 Alternate Plans to be prepared based on Benchmark Table Initiation 0.75 0 Planning 2 1 Requirements 1 0 Design 14 3 Plan A Plan B Plan C……how far ? Number of Alternate Plans Table (5)
  • 23. 23 Critical factors for success The success of this methodology depends on • Experience of the person/team preparing the guidelines • Reliability of the data received from past projects • Clear understanding of the project • Updating & improving the guidelines • Proper use of the guidelines & benchmarks • Different set of guidelines and benchmarks to be used for different types of projects Plan A Plan B Plan C……how far ?
  • 24. 24 Benefits of using Alt-PM • Planning for eventualities in advance • Saving project effort & time leading to cost saving • Enhancing knowledge sharing and reducing person dependency • Showcasing proactive Project Management • Achieving higher customer satisfaction scores • High project flexibility • Higher team motivation Plan A Plan B Plan C……how far ?
  • 25. 25 Alt-PM A methodology to face the challenges in a more structured & organized manner HAPPY PROJECT MANAGEMENT  Plan A Plan B Plan C……how far ?
  • 26. 26 Thank You Plan A Plan B Plan C……how far ?