3. Purpose of the Project
To replace the existing structure with a
bridge that meets the requirements set
forth by the West Virginia Bridge Design
Manual and the Design Directives.
… and in a hurry
7. •Dave Scott
•Ron Klavuhn
•Stanford Mills
•Lora Freeman
•Dave Morgan
•Chad Mann
•OBEC Consultants
Salem, Oregon
Project Team
Owner Agency
WVDOH
District 8
Contractor
C.L. Belt
Construction
Substructure &
Foundation
Engineer
WVDOH
District 8
Superstructure
Designer/
Fabricator
U.S. Bridge
9. ASAP Project
An ASAP Project is a fast-track project
with limited details that is bid as lump
sum. The contractor is responsible to
apply for permits, to arrange for utility
relocations, to make the material
selections with the suppliers, and
construct the project meeting the
requirements, such as waterway opening,
design loading, and general geometry.