Progress to Date
East-At Grade: Activities Underway
4
Activities Areas & Impacts Duration Tentative Date
Guideway work Victoria Park Avenue to Pharmacy Avenue
• Eglinton Square intersection to be re-opened as early as April
8,2019.
• Series of duct bank pours completed, more to follow.
• Track welding activities commenced late March.
• Stop construction work to commence after Guideway
5-6 months Underway as of
November 2018
Civil Road work Victoria Park Avenue to Birchmount Road
• Intermittent lane reductions.
• Temporary driveway access restrictions.
Ongoing Underway since mid 2018
Guideway work Warden Avenue to Sinnott/Thermos Road then on to Birchmount
Road
• New traffic configuration implemented the weekend of
March 16, 2019.
• Thermos-Sinott to be closed as early as April 15, 2019.
• Work zone is in the center of Eglinton Avenue East.
• Work will be conducted in stages.
8 months March 18, 2019
Massey Creek Culvert Located at the signalized intersection of Eglinton Avenue East and
Rosemount Drive
• New traffic configuration implemented the weekend of
March 16, 2019.
• Preparatory work began late February 2019 includes: tree
removals, dewatering of wells and deep excavation.
9 months Late February 2019
Telecommunications
relocation work
Victoria Park Avenue to Birchmount Road
• Intermittent lane reductions along Eglinton Avenue East.
• There may be occurrences where a shoulder is narrowed and
traffic protection barrier placed.
Ongoing Commenced in 2018
• Weekend through access prohibitions- right in, right out between Victoria Park Avenue and
Birchmount Road.
The series started in November will continue into 2019. More details to follow
– Intersection Paving at Pharmacy Avenue to commence as early as March 30-31 and April 13-14.
• Guideway reconstruction work Pharmacy Avenue to Ionview Road.
– Thermos/Sinnott Road will be closed as early as April 15, 2019 and lasting for approximately six (6) weeks
• At-grade, four Traction Power Sub-Stations will be free-standing structures on City of Toronto
approved sites.
– Building underground or lowering the grade does not meet regulatory requirements.
– It would not be compliant with Toronto Hydro’s ‘Requirements for Customer Owned Sub-Stations’
or the City of Toronto’s storm water management guidelines: ‘Wet Weather Management Flow
Guidelines.
What’s coming in 2019
5
Progress to Date
• Kennedy team accomplished one of its major milestones on March 18, which is the completion of the
vertical piles.
• Latest traffic flip implemented on January 26, 2019 this phase will last until end of May 2019.
• GO East platform restoration completed and handed over to GO Transit on February 9th, 2019.
• Storm and Sanitary activities as well as support of excavation (SOE) at the West Intersection is
completed.
Activities Underway
• Utility upgrades and relocations (THESL and telecom) within the Kennedy Station zone of influence
(ZOI).
• Wet utility upgrades and relocations continue within the Kennedy Station ZOI .
• Support of excavation for the Kennedy Portal and Main Station Box and tail track underway.
• TTC: West Ped Tunnel, East Ped Tunnel, TPSS; Support of excavation activities within TTC ZOI
underway, SRT underpinning activities.
• GO: GIMP Monitoring, SOE at Tail Track- North East platform, Rebar, formwork, concrete at West
Platform.
Kennedy Station: Progress to Date and Activities underway
12
Current Traffic Staging at Kennedy Road and Eglinton
Intersection
14
The current traffic configuration at Kennedy Station was implemented January 26,2019. This
phase is expected to last until the end of May 2019.
• The north-south crosswalk on the west side
of Kennedy Road and Eglinton Avenue East
intersection will be closed for the duration of
this stage.
• The crosswalks on the north, south, and east
side of the intersection will remain open for
the duration of this stage.
• Temporary sidewalk access to Kennedy
Station only located at the south side of
Kennedy Road, pedestrians will need to cross
to north side to continue on Eglinton Avenue
East.
• A minimum of two lanes of traffic in each
direction on Eglinton Avenue East will be
maintained.
• One through lane southbound traffic on
Kennedy Road will be maintained.
• Left turn restrictions westbound at Ionview
Road and Eglinton Avenue East.
• New traffic signals will be installed 160m
east of Kennedy Road and Eglinton Avenue
East
• Completion of the West Portal by summer 2019.
• Kennedy Station will have an antenna (telecommunications tower) after the
project is completed ( more details to follow).
What’s coming in 2019 and beyond
15
Kennedy Station-Construction Progress Photos
M&E and Mud-Slab Main Entrance Compound
Forming walls at West Portal
Kennedy Team- Vertical Pile Milestone Pile installation at Main Station Box