SlideShare a Scribd company logo
1 of 86
1
Cost of Capital
Unit III
Sri Ramakrishna College of Arts & Science,
Coimbatore.
M.VADIVEL
Assistant Professor
Sri Ramakrishna College of Arts & Science, CBE.
3
Required Rates on Projects
An important part of capital budgeting is setting the
required rate for the individual project
4
Required Rates on Projects
An important part of capital budgeting is setting the
required rate for the individual project
0 1
Example: Consider the following project
+1,100
-1,000
5
Required Rates on Projects
An important part of capital budgeting is setting the
required rate for the individual project
0 1
Example: Consider the following project
+1,100
-1,000
If Required Rate = 9%: NPV = -1,000 + 1,100
(1+ .09 )
= $9.17
6
Required Rates on Projects
An important part of capital budgeting is setting the
required rate for the individual project
0 1
Example: Consider the following project
+1,100
-1,000
If Required Rate = 9%: NPV = -1,000 + 1,100
(1+ .09 )
= $9.17
Accept Project since NPV > 0
7
Required Rates on Projects
An important part of capital budgeting is setting the
required rate for the individual project
0 1
Example: Consider the following project
+1,100
-1,000
If Required Rate = 9%: NPV = -1,000 + 1,100
(1+ .09 )
= $9.17
Accept Project since NPV > 0
If Required Rate = 11%: NPV = -1,000 + 1,100
(1+ .11 )
= –$9.01
8
Required Rates on Projects
An important part of capital budgeting is setting the
required rate for the individual project
0 1
Example: Consider the following project
+1,100
-1,000
If Required Rate = 9%: NPV = -1,000 + 1,100
(1+ .09 )
= $9.17
Accept Project since NPV > 0
If Required Rate = 11%: NPV = -1,000 + 1,100
(1+ .11 )
= –$9.01
Reject Project since NPV < 0
9
Required Rates on Projects
An important part of capital budgeting is setting the
required rate for the individual project
0 1
Example: Consider the following project
+1,100
-1,000
If Required Rate = 9%: NPV = -1,000 + 1,100
(1+ .09 )
= $9.17
Accept Project since NPV > 0
If Required Rate = 11%: NPV = -1,000 + 1,100
(1+ .11 )
= –$9.01
In order to estimate correct required rate, companies
must find their own unique cost of raising capital
10
Factors Affecting Cost of Capital
General Economic Conditions--inflation, investment
opportunities
Affect interest rates
The Following Factors affect risk premium
Market Conditions
Operating and Financing Decisions
Affect business risk
Affect financial risk
Amount of Financing
Affect flotation costs and market price of security
11
Model Assumptions
Here, we determine the average cost of capital of a
firm by assuming that the firm continues with its
business, financing and dividend policies.
Weighted Average Cost of Capital Model
12
Computing Weighted Cost of Capital
Average cost of capital of the firm.
To find WACC
1. Compute the cost of each source of capital
2. Determine percentage of each source of capital
3. Calculate Weighted Average Cost of Capital
Weighted Average Cost of Capital (WACC)
13
Computing Cost of Each Source
Required rate of return for creditors
Same cost found in Chapter 7 as “required rate for
debtholders (kd) = YTM”
1. Compute Cost of Debt
14
Computing Cost of Each Source
Required rate of return for creditors
Same cost found in Chapter 7 as “required rate for
debtholders (kd)”
1. Compute Cost of Debt
P0 = +
I
k
t
d
n
t
n
( )
1
1 

 $M
(1+kd)n
where:
It = Dollar Interest Payment
Po = Market Price of Debt
M = Maturity Value of Debt
15
Computing Cost of Each Source
Example
Investors are willing to pay $985 for a bond that pays
$90 a year for 10 years. Fees for issuing the bonds
bring the net price (NP0) down to $938.55. What is the
before tax cost of debt?
1. Compute Cost of Debt
16
Computing Cost of Each Source
Example
Investors are willing to pay $985 for a bond that pays
$90 a year for 10 years. Fees for issuing the bonds
bring the net price (NP0) down to $938.55. What is the
before tax cost of debt?
1. Compute Cost of Debt
P0 = +
I
k
t
d
n
t
n
( )
1
1 

 $M
(1+kd)n
17
Computing Cost of Each Source
Example
Investors are willing to pay $985 for a bond that pays
$90 a year for 10 years. Fees for issuing the bonds
bring the net price (NP0) down to $938.55. What is the
before tax cost of debt?
1. Compute Cost of Debt
938.55 = +
$90
( )
1 12
1
12


 kd
t
$1,000
(1+kd)10
P0 = +
I
k
t
d
n
t
n
( )
1
1 

 $M
(1+kd)n
18
Computing Cost of Each Source
Example
Investors are willing to pay $985 for a bond that pays
$90 a year for 10 years. Fees for issuing the bonds
bring the net price (NP0) down to $938.55. What is the
before tax cost of debt?
1. Compute Cost of Debt
The before tax cost of debt is 10%
Interest is tax deductible
19
Computing Cost of Each Source
Example
Investors are willing to pay $985 for a bond that pays
$90 a year for 10 years. Fees for issuing the bonds
bring the net price (NP0) down to $938.55. What is the
before tax cost of debt?
1. Compute Cost of Debt
The before tax cost of debt is 10%
Interest is tax deductible
After tax cost of bonds = kd(1 - T)
Marginal Tax Rate = 40%
20
Computing Cost of Each Source
Example
Investors are willing to pay $985 for a bond that pays
$90 a year for 10 years. Fees for issuing the bonds
bring the net price (NP0) down to $938.55. What is the
before tax cost of debt?
1. Compute Cost of Debt
The before tax cost of debt is 10%
Interest is tax deductible
After tax cost of bonds = kd(1 - T)
= 10.0%(1– 0.40) = 6 %
Marginal Tax Rate = 40%
21
Computing Cost of Each Source
Cost to raise a dollar of preferred stock.
2. Compute Cost Preferred Stock
22
Computing Cost of Each Source
Cost to raise a dollar of preferred stock.
2. Compute Cost Preferred Stock
From Chapter 8:
Dividend (D)
Market Price (P0)
Required rate kps =
23
Computing Cost of Each Source
Cost to raise a dollar of preferred stock.
2. Compute Cost Preferred Stock
From Chapter 8:
Dividend (D)
Market Price (P0)
Required rate kps =
However, there are floatation costs of issuing preferred stock:
24
Computing Cost of Each Source
Cost to raise a dollar of preferred stock.
2. Compute Cost Preferred Stock
Cost of Preferred Stock with floatation costs
Dividend (D)
Net Price (NP0)
From Chapter 8:
Dividend (D)
Market Price (P0)
Required rate kps =
However, there are floatation costs of issuing preferred stock:
kps =
25
Computing Cost of Each Source
Example
Your company can issue preferred stock for a price of
$45, but it only receives $42 after floatation costs. The
preferred stock pays a $5 dividend.
2. Compute Cost Preferred Stock
26
Computing Cost of Each Source
Example
Your company can issue preferred stock for a price of
$45, but it only receives $42 after floatation costs. The
preferred stock pays a $5 dividend.
2. Compute Cost Preferred Stock
Cost of Preferred Stock
$5.00
$42.00
kps =
27
Computing Cost of Each Source
Example
Your company can issue preferred stock for a price of
$45, but it only receives $42 after floatation costs. The
preferred stock pays a $5 dividend.
2. Compute Cost Preferred Stock
Cost of Preferred Stock
$5.00
$42.00
= 11.90%
kps =
28
Computing Cost of Each Source
Example
Your company can issue preferred stock for a price of
$45, but it only receives $42 after floatation costs. The
preferred stock pays a $5 dividend.
2. Compute Cost Preferred Stock
Cost of Preferred Stock
$5.00
$42.00
= 11.90%
kps =
No adjustment is made for taxes as
dividends are not tax deductible.
29
Computing Cost of Each Source
Two kinds of Common Equity
Retained Earnings (internal common equity)
Issuing new shares of common stock
3. Compute Cost of Common Equity
30
Computing Cost of Each Source
Cost of Internal Common Equity
Management should retain earnings only if they earn
as much as stockholder’s next best investment
opportunity.
3. Compute Cost of Common Equity
31
Computing Cost of Each Source
Cost of Internal Common Equity
Management should retain earnings only if they earn
as much as stockholder’s next best investment
opportunity.
Cost of Internal Equity = opportunity cost of common
stockholders’ funds.
3. Compute Cost of Common Equity
32
Computing Cost of Each Source
Cost of Internal Common Equity
Management should retain earnings only if they earn
as much as stockholder’s next best investment
opportunity.
Cost of Internal Equity = opportunity cost of common
stockholders’ funds.
Cost of internal equity must equal common
stockholders’ required rate of return.
3. Compute Cost of Common Equity
33
Computing Cost of Each Source
Cost of Internal Common Equity
Management should retain earnings only if they earn
as much as stockholder’s next best investment
opportunity.
Cost of Internal Equity = opportunity cost of common
stockholders’ funds.
Cost of internal equity must equal common
stockholders’ required rate of return.
Three methods to determine
Dividend Growth Model
Capital Asset Pricing Model
Risk Premium Model
3. Compute Cost of Common Equity
34
Computing Cost of Each Source
Cost of Internal Common Equity
Dividend Growth Model
Assume constant growth in dividends (Chap. 8)
3. Compute Cost of Common Equity
35
Computing Cost of Each Source
Cost of Internal Common Equity
Dividend Growth Model
Assume constant growth in dividends (Chap. 8)
3. Compute Cost of Common Equity
Cost of internal equity--dividend growth model
D1
P0
kcs = + g
36
Computing Cost of Each Source
Cost of Internal Common Equity
Dividend Growth Model
Assume constant growth in dividends (Chap. 8)
3. Compute Cost of Common Equity
Cost of internal equity--dividend growth model
D1
P0
kcs = + g
Example
The market price of a share of common stock is $60. The
dividend just paid is $3, and the expected growth rate is 10%.
37
Computing Cost of Each Source
Cost of Internal Common Equity
Dividend Growth Model
Assume constant growth in dividends (Chap. 8)
3. Compute Cost of Common Equity
Cost of internal equity--dividend growth model
D1
P0
kcs = + g
Example
The market price of a share of common stock is $60. The
dividend just paid is $3, and the expected growth rate is 10%.
3(1+0.10)
60
kcs = + .10
38
Computing Cost of Each Source
Cost of Internal Common Equity
Dividend Growth Model
Assume constant growth in dividends (Chap. 8)
3. Compute Cost of Common Equity
Cost of internal equity--dividend growth model
D1
P0
kcs = + g
Example
The market price of a share of common stock is $60. The
dividend just paid is $3, and the expected growth rate is 10%.
3(1+0.10)
60
kcs = + .10 = .155 = 15.5%
39
Computing Cost of Each Source
Cost of Internal Common Equity
Dividend Growth Model
Assume constant growth in dividends (Chap. 8)
3. Compute Cost of Common Equity
Cost of internal equity--dividend growth model
D1
P0
kcs = + g
Example
The market price of a share of common stock is $60. The
dividend just paid is $3, and the expected growth rate is 10%.
3(1+0.10)
60
kcs = + .10 = .155 = 15.5%
The main limitation in this method is estimating growth accurately.
40
Computing Cost of Each Source
Cost of Internal Common Equity
Capital Asset Pricing Model
Estimate the cost of equity from the CAPM (Chap. 6)
3. Compute Cost of Common Equity
41
Computing Cost of Each Source
Cost of Internal Common Equity
Capital Asset Pricing Model
Estimate the cost of equity from the CAPM (Chap. 6)
3. Compute Cost of Common Equity
kcs = krf + b(km – krf)
Cost of internal equity--CAPM
42
Computing Cost of Each Source
Cost of Internal Common Equity
Capital Asset Pricing Model
Estimate the cost of equity from the CAPM (Chap. 6)
3. Compute Cost of Common Equity
Example
The estimated Beta of a stock is 1.2. The risk-free rate is 5%
and the expected market return is 13%.
kcs = krf + b(km – krf)
Cost of internal equity--CAPM
43
Computing Cost of Each Source
Cost of Internal Common Equity
Capital Asset Pricing Model
Estimate the cost of equity from the CAPM (Chap. 6)
3. Compute Cost of Common Equity
Example
The estimated Beta of a stock is 1.2. The risk-free rate is 5%
and the expected market return is 13%.
kcs = krf + b(km – krf)
Cost of internal equity--CAPM
kcs = 5% + 1.2(13% – 5%)
44
Computing Cost of Each Source
Cost of Internal Common Equity
Capital Asset Pricing Model
Estimate the cost of equity from the CAPM (Chap. 6)
3. Compute Cost of Common Equity
Example
The estimated Beta of a stock is 1.2. The risk-free rate is 5%
and the expected market return is 13%.
kcs = krf + b(km – krf)
Cost of internal equity--CAPM
kcs = 5% + 1.2(13% – 5%) = 14.6%
45
Computing Cost of Each Source
Cost of Internal Common Equity
Risk Premium Approach
Adds a risk premium to the bondholder’s required rate of
return.
3. Compute Cost of Common Equity
46
Computing Cost of Each Source
Cost of Internal Common Equity
Risk Premium Approach
Adds a risk premium to the bondholder’s required rate of
return.
3. Compute Cost of Common Equity
kcs = kd + RPc
Cost of internal equity--Risk Premium
Where:
RPc = Common stock
risk premium
47
Computing Cost of Each Source
Cost of Internal Common Equity
Risk Premium Approach
Adds a risk premium to the bondholder’s required rate of
return.
3. Compute Cost of Common Equity
Example
If the risk premium is 5% and kd is 10%
kcs = kd + RPc
Cost of internal equity--Risk Premium
Where:
RPc = Common stock
risk premium
48
Computing Cost of Each Source
Cost of Internal Common Equity
Risk Premium Approach
Adds a risk premium to the bondholder’s required rate of
return.
3. Compute Cost of Common Equity
Example
If the risk premium is 5% and kd is 10%
kcs = kd + RPc
Cost of internal equity--Risk Premium
kcs = 10% + 5%
Where:
RPc = Common stock
risk premium
49
Computing Cost of Each Source
Cost of Internal Common Equity
Risk Premium Approach
Adds a risk premium to the bondholder’s required rate of
return.
3. Compute Cost of Common Equity
Example
If the risk premium is 5% and kd is 10%
kcs = kd + RPc
Cost of internal equity--Risk Premium
kcs = 10% + 5% = 15%
Where:
RPc = Common stock
risk premium
50
Computing Cost of Each Source
Cost of New Common Stock
If retained earnings cannot provide all the equity
capital that is needed, firms may issue new shares of
common stock.
3. Compute Cost of Common Equity
51
Computing Cost of Each Source
Cost of New Common Stock
If retained earnings cannot provide all the equity
capital that is needed, firms may issue new shares of
common stock.
Dividend Growth Model--Must adjust for floatation
costs of the new common shares.
3. Compute Cost of Common Equity
52
Computing Cost of Each Source
Cost of New Common Stock
If retained earnings cannot provide all the equity
capital that is needed, firms may issue new shares of
common stock.
Dividend Growth Model--must adjust for floatation
costs of the new common shares.
3. Compute Cost of Common Equity
Cost of new common stock
D1
NP0
kcs = + g
53
Computing Cost of Each Source
Cost of New Common Stock
3. Compute Cost of Common Equity
Cost of new common stock
D1
NP0
knc = + g
54
Computing Cost of Each Source
Cost of New Common Stock
3. Compute Cost of Common Equity
Cost of new common stock
D1
NP0
knc = + g
Example
Using the above example. Common stock price is currently $60.
If additional shares are issued floatation costs will be 12%. D0 =
$3.00 and estimated growth is 10%.
55
Computing Cost of Each Source
Cost of New Common Stock
3. Compute Cost of Common Equity
Cost of new common stock
D1
NP0
knc = + g
Example
Using the above example. Common stock price is currently $60.
If additional shares are issued floatation costs will be 12%. D0 =
$3.00 and estimated growth is 10%.
NP0 = $60.00 – (.12x 60) = $52.80
Floatation
Costs
56
Computing Cost of Each Source
Cost of New Common Stock
3. Compute Cost of Common Equity
Cost of new common stock
D1
NP0
knc = + g
Example
Using the above example. Common stock price is currently $60.
If additional shares are issued floatation costs will be 12%. D0 =
$3.00 and estimated growth is 10%.
NP0 = $60.00 – (.12x 60) = $52.80
3(1+0.10)
52.80
kcs = + .10
57
Computing Cost of Each Source
Cost of New Common Stock
3. Compute Cost of Common Equity
Cost of new common stock
D1
NP0
knc = + g
Example
Using the above example. Common stock price is currently $60.
If additional shares are issued floatation costs will be 12%. D0 =
$3.00 and estimated growth is 10%.
NP0 = $60.00 – (.12x 60) = $52.80
3(1+0.10)
52.80
kcs = + .10 = .1625 = 16.25%
58
Capital Structure Weights
Long Term Liabilities and Equity
Weights of each source should reflect expected
financing mix
Assume a stable financial mix–so use Balance Sheet
percentages to calculate the weighted average cost
of capital.
59
Capital Structure Weights
Long Term Liabilities and Equity
Balance Sheet Green Apple Company
Current Assets $5,000 Current Liabilities $2,000
Plant & Equipment 7,000 Bonds 4,000
Total Assets $12,000 Preferred Stock 1,000
Common Stock 5,000
Total Liabilities and
Owners Equity $12,000
Assets Liabilities
Firm Raises $10,000 of capital from long term sources
60
Capital Structure Weights
Long Term Liabilities and Equity
Current Assets $5,000 Current Liabilities $2,000
Plant & Equipment 7,000 Bonds 4,000
Total Assets $12,000 Preferred Stock 1,000
Common Stock 5,000
Total Liabilities and
Owners Equity $12,000
Assets Liabilities
Compute Firm’s Capital Structure (% of each source)
Bonds:
4,000
10,000
= 40%
Amount of Bonds
Total Capital Sources
Balance Sheet Green Apple Company
61
Capital Structure Weights
Long Term Liabilities and Equity
Current Assets $5,000 Current Liabilities $2,000
Plant & Equipment 7,000 Bonds 4,000
Total Assets $12,000 Preferred Stock 1,000
Common Stock 5,000
Total Liabilities and
Owners Equity $12,000
Assets Liabilities
Compute Firm’s Capital Structure (% of each source)
Amount of Preferred Stock
Total Capital Sources
Preferred Stock:
1,000
10,000
= 10%
Balance Sheet Green Apple Company
62
Capital Structure Weights
Long Term Liabilities and Equity
Current Assets $5,000 Current Liabilities $2,000
Plant & Equipment 7,000 Bonds 4,000
Total Assets $12,000 Preferred Stock 1,000
Common Stock 5,000
Total Liabilities and
Owners Equity $12,000
Assets Liabilities
Compute Firm’s Capital Structure (% of each source)
Amount of Common Stock
Total Capital Sources
Common Stock:
5,000
10,000
= 50%
Balance Sheet Green Apple Company
63
Capital Structure Weights
Long Term Liabilities and Equity
Current Assets $5,000 Current Liabilities $2,000
Plant & Equipment 7,000 Bonds 4,000
Total Assets $12,000 Preferred Stock 1,000
Common Stock 5,000
Total Liabilities and
Owners Equity $12,000
Assets Liabilities
40%
10%
50%
When money is raised for capital projects, approximately
40% of the money comes from selling bonds, 10%
comes from selling preferred stock and 50% comes from
retaining earnings or selling common stock
Balance Sheet Green Apple Company
64
Computing WACC
Green Apple Company estimates the following costs
for each component in its capital structure:
Source of Capital Cost
Bonds kd = 10%
Preferred Stock kps = 11.9%
Common Stock
Retained Earnings kcs = 15%
New Shares knc = 16.25%
Green Apple’s tax rate is 40%
65
Computing WACC
If using retained earnings to finance the common
stock portion the capital structure
WACC= k0 = %Bonds x Cost of Bonds x (1-T)
+ %Preferred x Cost of Preferred
+ %Common x Cost of Common Stock
66
Balance Sheet
Current Assets $5,000 Current Liabilities $2,000
Plant & Equipment 7,000 Bonds (9%) 4,000
Total Assets $12,000 Preferred Stock (10%) 1,000
Common Stock(13%) 5,000
Tax Rate = 40% Total Liabilities and
Owners Equity $12,000
Assets Liabilities
40%
10%
50%
WACC= k0 = %Bonds x Cost of Bonds x (1-T)
+ %Preferred x Cost of Preferred
+ %Common x Cost of Common Stock
Computing WACC - using Retained Earnings
67
Balance Sheet
Current Assets $5,000 Current Liabilities $2,000
Plant & Equipment 7,000 Bonds (10%) 4,000
Total Assets $12,000 Preferred Stock (11.9%)1,000
Common Stock(15%) 5,000
Tax Rate = 40% Total Liabilities and
Owners Equity $12,000
Assets Liabilities
40%
10%
50%
WACC= k0 = %Bonds x Cost of Bonds x (1-T)
+ %Preferred x Cost of Preferred
+ %Common x Cost of Common Stock
Computing WACC - using Retained Earnings
WACC = .40 x 10% (1-.4)
68
Balance Sheet
Assets Liabilities
40%
10%
50%
WACC= k0 = %Bonds x Cost of Bonds x (1-T)
+ %Preferred x Cost of Preferred
+ %Common x Cost of Common Stock
Computing WACC - using Retained Earnings
WACC = .40 x 10% (1-.4)
+ .10 x 11.9%
Current Assets $5,000 Current Liabilities $2,000
Plant & Equipment 7,000 Bonds (10%) 4,000
Total Assets $12,000 Preferred Stock (11.9%)1,000
Common Stock(15%) 5,000
Tax Rate = 40% Total Liabilities and
Owners Equity $12,000
69
Balance Sheet
Assets Liabilities
40%
10%
50%
WACC= k0 = %Bonds x Cost of Bonds x (1-T)
+ %Preferred x Cost of Preferred
+ %Common x Cost of Common Stock
Computing WACC - using Retained Earnings
WACC = .40 x 10% (1-.4)
+ .10 x 11.9%
+ .50 x 15%
Current Assets $5,000 Current Liabilities $2,000
Plant & Equipment 7,000 Bonds (10%) 4,000
Total Assets $12,000 Preferred Stock (11.9%)1,000
Common Stock(15%) 5,000
Tax Rate = 40% Total Liabilities and
Owners Equity $12,000
70
Balance Sheet
Assets Liabilities
40%
10%
50%
WACC = .40 x 10% (1-.4)
+ .10 x 11.9%
+ .50 x 15% = 11.09%
WACC= k0 = %Bonds x Cost of Bonds x (1-T)
+ %Preferred x Cost of Preferred
+ %Common x Cost of Common Stock
Computing WACC - using Retained Earnings
Current Assets $5,000 Current Liabilities $2,000
Plant & Equipment 7,000 Bonds (10%) 4,000
Total Assets $12,000 Preferred Stock (11.9%)1,000
Common Stock(15%) 5,000
Tax Rate = 40% Total Liabilities and
Owners Equity $12,000
71
Computing WACC
If use newly issued common stock, use knc rather
than kcs for the cost of the equity portion.
WACC= k0 = %Bonds x Cost of Bonds x (1-T)
+ %Preferred x Cost of Preferred
+ %Common x Cost of Common Stock
knc
72
Balance Sheet
Assets Liabilities
WACC = .40 x 10% (1-.4)
+ .10 x 11.9%
+ .50 x 16.25% = 11.72%
WACC= k0 = %Bonds x Cost of Bonds x (1-T)
+ %Preferred x Cost of Preferred
+ %Common x Cost of Common Stock
Computing WACC - using New Common Shares
Current Assets $5,000 Current Liabilities $2,000
Plant & Equipment 7,000 Bonds (10%) 4,000
Total Assets $12,000 Preferred Stock (11.9%)1,000
Common Stock(16.25%)5,000
Tax Rate = 40% Total Liabilities and
Owners Equity $12,000
73
Weighted Marginal Cost of Capital
A firm’s cost of capital will change as it is raises more
and more capital
Retained earnings will be used up at some level
The cost of other sources may rise beyond a certain
amount of money has been raised
74
Weighted Marginal Cost of Capital
A firm’s cost of capital will changes as it is raising more
and more capital
Retained earnings will be used up at some level
The cost of other sources may rise beyond a certain
amount of money raised
Therefore, beyond a point, the WACC will rise.
Calculate the point at which the cost of capital
increases
75
Weighted Marginal Cost of Capital
A firm’s cost of capital will changes as it is raising more
and more capital
Retained earnings will be used up at some level
The cost of other sources may rise beyond a certain
amount of money raised
Calculate the point at which the cost of capital
increases
Break in cost
of capital curve
Amt of lower cost capital that can
be raised before component cost rises
Weight of this kind of capital
in the capital structure
=
76
Weighted Marginal Cost of Capital
Break in cost
of capital curve
Retained earnings
available for reinvesting
Percentage of
common financing
=
If Green Apple Company has $100,000 of internally
generated common:
77
Weighted Marginal Cost of Capital
Break in cost
of capital curve
Retained earnings
available for reinvesting
Percentage of
common financing
=
If Green Apple Company has $100,000 of internally
generated common:
Break in cost
of capital curve
$100,000
.50
=
78
Weighted Marginal Cost of Capital
Break in cost
of capital curve
Retained earnings
available for reinvesting
Percentage of
common financing
=
If Green Apple Company has $100,000 of internally
generated common:
Break in cost
of capital curve
$100,000
.50
= = $200,000
79
Weighted Marginal Cost of Capital
Break in cost
of capital curve
Retained earnings
available for reinvesting
Percentage of
common financing
=
If Green Apple Company has $100,000 of internally
generated common:
Break in cost
of capital curve
$100,000
.50
= = $200,000
Once $200,000 is raised from all sources, the
cost of capital will rise because all the lower
cost retained earnings will be used up.
80
Weighted Marginal Cost of Capital
Weighted
Cost
of
Capital
Total Financing
9%
10%
11%
12%
0 100,000 200,000 300,000 400,000
Marginal weighted cost of capital curve:
11.09%
Cost of Capital
using internal
common stock
81
Weighted Marginal Cost of Capital
Weighted
Cost
of
Capital
Total Financing
9%
10%
11%
12%
0 100,000 200,000 300,000 400,000
Marginal weighted cost of capital curve:
11.09%
Break-Point for
common equity
82
Weighted Marginal Cost of Capital
Weighted
Cost
of
Capital
Total Financing
9%
10%
11%
12%
0 100,000 200,000 300,000 400,000
Marginal weighted cost of capital curve:
11.09%
Cost of Capital
using internal
common stock
11.72%
Cost of Capital using
new common equity
83
Weighted Marginal Cost of Capital
Weighted
Cost
of
Capital
Total Financing
9%
10%
11%
12%
0 100,000 200,000 300,000 400,000
Marginal weighted cost of capital curve:
11.09%
11.72%
84
Making Decisions
Choosing Projects Using Weighted Marginal Cost of Capital
Graph IRR’s of potential projects
Weighted
Cost
of
Capital
Total Financing
9%
10%
11%
12%
0 100,000 200,000 300,000 400,000
Marginal weighted cost of capital curve:
Project 1
IRR = 12.4%
Project 2
IRR = 12.1% Project 3
IRR = 11.5%
85
Making Decisions
Choosing Projects Using Weighted Marginal Cost of Capital
Graph IRR’s of potential projects
Graph Weighted Marginal Cost of Capital
Weighted
Cost
of
Capital
Total Financing
9%
10%
11%
12%
0 100,000 200,000 300,000 400,000
Marginal weighted cost of capital curve:
Project 1
IRR = 12.4%
Project 2
IRR = 12.1% Project 3
IRR = 11.5%
86
Making Decisions
Choosing Projects Using Weighted Marginal Cost of Capital
Graph IRR’s of potential projects
Graph Weighted Marginal Cost of Capital
Choose projects whose IRR is above the weighted
marginal cost of capital
Weighted
Cost
of
Capital
Total Financing
9%
10%
11%
12%
0 100,000 200,000 300,000 400,000
Marginal weighted cost of capital curve:
Project 1
IRR = 12.4%
Project 2
IRR = 12.1% Project 3
IRR = 11.5%
Accept Projects #1 & #2
87
Thank You…….

More Related Content

Similar to Cost of Capital and its different types of cost of capital

FM CH 4.pptx best presentation for financial management
FM CH 4.pptx best presentation for financial managementFM CH 4.pptx best presentation for financial management
FM CH 4.pptx best presentation for financial management
Kalkaye
 
UNIT-3.pptx FINANCIAL MGT FGSRTSRFGBEDRTWE
UNIT-3.pptx FINANCIAL MGT FGSRTSRFGBEDRTWEUNIT-3.pptx FINANCIAL MGT FGSRTSRFGBEDRTWE
UNIT-3.pptx FINANCIAL MGT FGSRTSRFGBEDRTWE
DrSurabhiBharti
 
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docxSheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
lesleyryder69361
 

Similar to Cost of Capital and its different types of cost of capital (20)

FM CH 4.pptx best presentation for financial management
FM CH 4.pptx best presentation for financial managementFM CH 4.pptx best presentation for financial management
FM CH 4.pptx best presentation for financial management
 
Cost Of Capital
Cost Of CapitalCost Of Capital
Cost Of Capital
 
Cost of capital
Cost of capitalCost of capital
Cost of capital
 
UNIT-3.pptx FINANCIAL MGT FGSRTSRFGBEDRTWE
UNIT-3.pptx FINANCIAL MGT FGSRTSRFGBEDRTWEUNIT-3.pptx FINANCIAL MGT FGSRTSRFGBEDRTWE
UNIT-3.pptx FINANCIAL MGT FGSRTSRFGBEDRTWE
 
CHAPTER 9 PPT.ppt
CHAPTER 9 PPT.pptCHAPTER 9 PPT.ppt
CHAPTER 9 PPT.ppt
 
Bba 2204 fin mgt week 9 cost of capital
Bba 2204 fin mgt week 9 cost of capitalBba 2204 fin mgt week 9 cost of capital
Bba 2204 fin mgt week 9 cost of capital
 
Cost of Capital
Cost of CapitalCost of Capital
Cost of Capital
 
Chapter 10.The Cost of Capital(WACC)
Chapter 10.The Cost of Capital(WACC)Chapter 10.The Cost of Capital(WACC)
Chapter 10.The Cost of Capital(WACC)
 
Ch. 6ed Cost of Capital.ppt.ppt
Ch. 6ed Cost of Capital.ppt.pptCh. 6ed Cost of Capital.ppt.ppt
Ch. 6ed Cost of Capital.ppt.ppt
 
3- Cost of Capital-update.pptx
3- Cost of Capital-update.pptx3- Cost of Capital-update.pptx
3- Cost of Capital-update.pptx
 
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docxSheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
 
Chapter 3 Cost of Capital.pptx
Chapter 3 Cost of Capital.pptxChapter 3 Cost of Capital.pptx
Chapter 3 Cost of Capital.pptx
 
Cost of capital
Cost of capitalCost of capital
Cost of capital
 
BlueBookAcademy.com - Value companies using Discounted Cash Flow Valuation
BlueBookAcademy.com - Value companies using Discounted Cash Flow ValuationBlueBookAcademy.com - Value companies using Discounted Cash Flow Valuation
BlueBookAcademy.com - Value companies using Discounted Cash Flow Valuation
 
Cost of capital ppt @ bec doms on finance
Cost of capital ppt @ bec doms on financeCost of capital ppt @ bec doms on finance
Cost of capital ppt @ bec doms on finance
 
Ch14
Ch14Ch14
Ch14
 
4(1).pptx
4(1).pptx4(1).pptx
4(1).pptx
 
4464-Chapter-08 (1).ppt
4464-Chapter-08 (1).ppt4464-Chapter-08 (1).ppt
4464-Chapter-08 (1).ppt
 
Fin 2732 cost of capital
Fin 2732 cost of capitalFin 2732 cost of capital
Fin 2732 cost of capital
 
ch 10; cost of capital
ch 10; cost of capitalch 10; cost of capital
ch 10; cost of capital
 

More from VadivelM9

Capital Asset Pricing Model (CAPM) Model
Capital Asset Pricing Model (CAPM) ModelCapital Asset Pricing Model (CAPM) Model
Capital Asset Pricing Model (CAPM) Model
VadivelM9
 
Technical Analysis with different types of charts
Technical Analysis with different types of chartsTechnical Analysis with different types of charts
Technical Analysis with different types of charts
VadivelM9
 
Fundamental Analysis including Economy, Industry Company Analysis
Fundamental Analysis including Economy, Industry Company AnalysisFundamental Analysis including Economy, Industry Company Analysis
Fundamental Analysis including Economy, Industry Company Analysis
VadivelM9
 
1. Risk and its different types of risk .
1. Risk and its different types of risk .1. Risk and its different types of risk .
1. Risk and its different types of risk .
VadivelM9
 
4. Investment Avenues in India . Different investment
4. Investment Avenues in India . Different investment4. Investment Avenues in India . Different investment
4. Investment Avenues in India . Different investment
VadivelM9
 
3. Difference between Investment vs Speculation
3. Difference between Investment vs Speculation3. Difference between Investment vs Speculation
3. Difference between Investment vs Speculation
VadivelM9
 
2. Speculation and speculator in investment
2. Speculation and speculator in investment2. Speculation and speculator in investment
2. Speculation and speculator in investment
VadivelM9
 

More from VadivelM9 (20)

Performance Evaluation in Portfolio Management
Performance Evaluation in Portfolio ManagementPerformance Evaluation in Portfolio Management
Performance Evaluation in Portfolio Management
 
Formula Plans in portfolio management Selection
Formula Plans in portfolio management SelectionFormula Plans in portfolio management Selection
Formula Plans in portfolio management Selection
 
Capital Asset Pricing Model (CAPM) Model
Capital Asset Pricing Model (CAPM) ModelCapital Asset Pricing Model (CAPM) Model
Capital Asset Pricing Model (CAPM) Model
 
Security Valuation in Bond, Equity, Pref. Share Valuation
Security Valuation in Bond, Equity, Pref. Share ValuationSecurity Valuation in Bond, Equity, Pref. Share Valuation
Security Valuation in Bond, Equity, Pref. Share Valuation
 
Security Valuation in Investment Management
Security Valuation in Investment ManagementSecurity Valuation in Investment Management
Security Valuation in Investment Management
 
Bond Value Theorems in investment management
Bond Value Theorems in investment  managementBond Value Theorems in investment  management
Bond Value Theorems in investment management
 
Technical Analysis with different types of charts
Technical Analysis with different types of chartsTechnical Analysis with different types of charts
Technical Analysis with different types of charts
 
Fundamental Analysis including Economy, Industry Company Analysis
Fundamental Analysis including Economy, Industry Company AnalysisFundamental Analysis including Economy, Industry Company Analysis
Fundamental Analysis including Economy, Industry Company Analysis
 
1. Risk and its different types of risk .
1. Risk and its different types of risk .1. Risk and its different types of risk .
1. Risk and its different types of risk .
 
Process of Investment in investment management
Process of Investment in investment managementProcess of Investment in investment management
Process of Investment in investment management
 
Nature of Investment and Investment Analysis
Nature of Investment and Investment AnalysisNature of Investment and Investment Analysis
Nature of Investment and Investment Analysis
 
Gambling and its different types of gambling
Gambling and its different types of gamblingGambling and its different types of gambling
Gambling and its different types of gambling
 
4. Investment Avenues in India . Different investment
4. Investment Avenues in India . Different investment4. Investment Avenues in India . Different investment
4. Investment Avenues in India . Different investment
 
3. Difference between Investment vs Speculation
3. Difference between Investment vs Speculation3. Difference between Investment vs Speculation
3. Difference between Investment vs Speculation
 
2. Speculation and speculator in investment
2. Speculation and speculator in investment2. Speculation and speculator in investment
2. Speculation and speculator in investment
 
1. Investment and concept of investment.
1. Investment and concept of investment.1. Investment and concept of investment.
1. Investment and concept of investment.
 
Capital Bugeting - Discounted Cash Flow Methods.pptx
Capital Bugeting - Discounted Cash Flow Methods.pptxCapital Bugeting - Discounted Cash Flow Methods.pptx
Capital Bugeting - Discounted Cash Flow Methods.pptx
 
Capital Bugeting - Traditional Methods.pptx
Capital Bugeting - Traditional Methods.pptxCapital Bugeting - Traditional Methods.pptx
Capital Bugeting - Traditional Methods.pptx
 
Working Capital Management and its Elements
Working Capital Management and its ElementsWorking Capital Management and its Elements
Working Capital Management and its Elements
 
Analysis of Leverage and its types of leverage analysis.
Analysis of Leverage and its types of leverage analysis.Analysis of Leverage and its types of leverage analysis.
Analysis of Leverage and its types of leverage analysis.
 

Recently uploaded

QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
httgc7rh9c
 

Recently uploaded (20)

How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17
 
AIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptAIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.ppt
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Introduction to TechSoup’s Digital Marketing Services and Use Cases
Introduction to TechSoup’s Digital Marketing  Services and Use CasesIntroduction to TechSoup’s Digital Marketing  Services and Use Cases
Introduction to TechSoup’s Digital Marketing Services and Use Cases
 
Play hard learn harder: The Serious Business of Play
Play hard learn harder:  The Serious Business of PlayPlay hard learn harder:  The Serious Business of Play
Play hard learn harder: The Serious Business of Play
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
dusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learningdusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learning
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Economic Importance Of Fungi In Food Additives
Economic Importance Of Fungi In Food AdditivesEconomic Importance Of Fungi In Food Additives
Economic Importance Of Fungi In Food Additives
 
Tatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf artsTatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf arts
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
 
Our Environment Class 10 Science Notes pdf
Our Environment Class 10 Science Notes pdfOur Environment Class 10 Science Notes pdf
Our Environment Class 10 Science Notes pdf
 

Cost of Capital and its different types of cost of capital

  • 1. 1 Cost of Capital Unit III Sri Ramakrishna College of Arts & Science, Coimbatore. M.VADIVEL Assistant Professor Sri Ramakrishna College of Arts & Science, CBE.
  • 2. 3 Required Rates on Projects An important part of capital budgeting is setting the required rate for the individual project
  • 3. 4 Required Rates on Projects An important part of capital budgeting is setting the required rate for the individual project 0 1 Example: Consider the following project +1,100 -1,000
  • 4. 5 Required Rates on Projects An important part of capital budgeting is setting the required rate for the individual project 0 1 Example: Consider the following project +1,100 -1,000 If Required Rate = 9%: NPV = -1,000 + 1,100 (1+ .09 ) = $9.17
  • 5. 6 Required Rates on Projects An important part of capital budgeting is setting the required rate for the individual project 0 1 Example: Consider the following project +1,100 -1,000 If Required Rate = 9%: NPV = -1,000 + 1,100 (1+ .09 ) = $9.17 Accept Project since NPV > 0
  • 6. 7 Required Rates on Projects An important part of capital budgeting is setting the required rate for the individual project 0 1 Example: Consider the following project +1,100 -1,000 If Required Rate = 9%: NPV = -1,000 + 1,100 (1+ .09 ) = $9.17 Accept Project since NPV > 0 If Required Rate = 11%: NPV = -1,000 + 1,100 (1+ .11 ) = –$9.01
  • 7. 8 Required Rates on Projects An important part of capital budgeting is setting the required rate for the individual project 0 1 Example: Consider the following project +1,100 -1,000 If Required Rate = 9%: NPV = -1,000 + 1,100 (1+ .09 ) = $9.17 Accept Project since NPV > 0 If Required Rate = 11%: NPV = -1,000 + 1,100 (1+ .11 ) = –$9.01 Reject Project since NPV < 0
  • 8. 9 Required Rates on Projects An important part of capital budgeting is setting the required rate for the individual project 0 1 Example: Consider the following project +1,100 -1,000 If Required Rate = 9%: NPV = -1,000 + 1,100 (1+ .09 ) = $9.17 Accept Project since NPV > 0 If Required Rate = 11%: NPV = -1,000 + 1,100 (1+ .11 ) = –$9.01 In order to estimate correct required rate, companies must find their own unique cost of raising capital
  • 9. 10 Factors Affecting Cost of Capital General Economic Conditions--inflation, investment opportunities Affect interest rates The Following Factors affect risk premium Market Conditions Operating and Financing Decisions Affect business risk Affect financial risk Amount of Financing Affect flotation costs and market price of security
  • 10. 11 Model Assumptions Here, we determine the average cost of capital of a firm by assuming that the firm continues with its business, financing and dividend policies. Weighted Average Cost of Capital Model
  • 11. 12 Computing Weighted Cost of Capital Average cost of capital of the firm. To find WACC 1. Compute the cost of each source of capital 2. Determine percentage of each source of capital 3. Calculate Weighted Average Cost of Capital Weighted Average Cost of Capital (WACC)
  • 12. 13 Computing Cost of Each Source Required rate of return for creditors Same cost found in Chapter 7 as “required rate for debtholders (kd) = YTM” 1. Compute Cost of Debt
  • 13. 14 Computing Cost of Each Source Required rate of return for creditors Same cost found in Chapter 7 as “required rate for debtholders (kd)” 1. Compute Cost of Debt P0 = + I k t d n t n ( ) 1 1    $M (1+kd)n where: It = Dollar Interest Payment Po = Market Price of Debt M = Maturity Value of Debt
  • 14. 15 Computing Cost of Each Source Example Investors are willing to pay $985 for a bond that pays $90 a year for 10 years. Fees for issuing the bonds bring the net price (NP0) down to $938.55. What is the before tax cost of debt? 1. Compute Cost of Debt
  • 15. 16 Computing Cost of Each Source Example Investors are willing to pay $985 for a bond that pays $90 a year for 10 years. Fees for issuing the bonds bring the net price (NP0) down to $938.55. What is the before tax cost of debt? 1. Compute Cost of Debt P0 = + I k t d n t n ( ) 1 1    $M (1+kd)n
  • 16. 17 Computing Cost of Each Source Example Investors are willing to pay $985 for a bond that pays $90 a year for 10 years. Fees for issuing the bonds bring the net price (NP0) down to $938.55. What is the before tax cost of debt? 1. Compute Cost of Debt 938.55 = + $90 ( ) 1 12 1 12    kd t $1,000 (1+kd)10 P0 = + I k t d n t n ( ) 1 1    $M (1+kd)n
  • 17. 18 Computing Cost of Each Source Example Investors are willing to pay $985 for a bond that pays $90 a year for 10 years. Fees for issuing the bonds bring the net price (NP0) down to $938.55. What is the before tax cost of debt? 1. Compute Cost of Debt The before tax cost of debt is 10% Interest is tax deductible
  • 18. 19 Computing Cost of Each Source Example Investors are willing to pay $985 for a bond that pays $90 a year for 10 years. Fees for issuing the bonds bring the net price (NP0) down to $938.55. What is the before tax cost of debt? 1. Compute Cost of Debt The before tax cost of debt is 10% Interest is tax deductible After tax cost of bonds = kd(1 - T) Marginal Tax Rate = 40%
  • 19. 20 Computing Cost of Each Source Example Investors are willing to pay $985 for a bond that pays $90 a year for 10 years. Fees for issuing the bonds bring the net price (NP0) down to $938.55. What is the before tax cost of debt? 1. Compute Cost of Debt The before tax cost of debt is 10% Interest is tax deductible After tax cost of bonds = kd(1 - T) = 10.0%(1– 0.40) = 6 % Marginal Tax Rate = 40%
  • 20. 21 Computing Cost of Each Source Cost to raise a dollar of preferred stock. 2. Compute Cost Preferred Stock
  • 21. 22 Computing Cost of Each Source Cost to raise a dollar of preferred stock. 2. Compute Cost Preferred Stock From Chapter 8: Dividend (D) Market Price (P0) Required rate kps =
  • 22. 23 Computing Cost of Each Source Cost to raise a dollar of preferred stock. 2. Compute Cost Preferred Stock From Chapter 8: Dividend (D) Market Price (P0) Required rate kps = However, there are floatation costs of issuing preferred stock:
  • 23. 24 Computing Cost of Each Source Cost to raise a dollar of preferred stock. 2. Compute Cost Preferred Stock Cost of Preferred Stock with floatation costs Dividend (D) Net Price (NP0) From Chapter 8: Dividend (D) Market Price (P0) Required rate kps = However, there are floatation costs of issuing preferred stock: kps =
  • 24. 25 Computing Cost of Each Source Example Your company can issue preferred stock for a price of $45, but it only receives $42 after floatation costs. The preferred stock pays a $5 dividend. 2. Compute Cost Preferred Stock
  • 25. 26 Computing Cost of Each Source Example Your company can issue preferred stock for a price of $45, but it only receives $42 after floatation costs. The preferred stock pays a $5 dividend. 2. Compute Cost Preferred Stock Cost of Preferred Stock $5.00 $42.00 kps =
  • 26. 27 Computing Cost of Each Source Example Your company can issue preferred stock for a price of $45, but it only receives $42 after floatation costs. The preferred stock pays a $5 dividend. 2. Compute Cost Preferred Stock Cost of Preferred Stock $5.00 $42.00 = 11.90% kps =
  • 27. 28 Computing Cost of Each Source Example Your company can issue preferred stock for a price of $45, but it only receives $42 after floatation costs. The preferred stock pays a $5 dividend. 2. Compute Cost Preferred Stock Cost of Preferred Stock $5.00 $42.00 = 11.90% kps = No adjustment is made for taxes as dividends are not tax deductible.
  • 28. 29 Computing Cost of Each Source Two kinds of Common Equity Retained Earnings (internal common equity) Issuing new shares of common stock 3. Compute Cost of Common Equity
  • 29. 30 Computing Cost of Each Source Cost of Internal Common Equity Management should retain earnings only if they earn as much as stockholder’s next best investment opportunity. 3. Compute Cost of Common Equity
  • 30. 31 Computing Cost of Each Source Cost of Internal Common Equity Management should retain earnings only if they earn as much as stockholder’s next best investment opportunity. Cost of Internal Equity = opportunity cost of common stockholders’ funds. 3. Compute Cost of Common Equity
  • 31. 32 Computing Cost of Each Source Cost of Internal Common Equity Management should retain earnings only if they earn as much as stockholder’s next best investment opportunity. Cost of Internal Equity = opportunity cost of common stockholders’ funds. Cost of internal equity must equal common stockholders’ required rate of return. 3. Compute Cost of Common Equity
  • 32. 33 Computing Cost of Each Source Cost of Internal Common Equity Management should retain earnings only if they earn as much as stockholder’s next best investment opportunity. Cost of Internal Equity = opportunity cost of common stockholders’ funds. Cost of internal equity must equal common stockholders’ required rate of return. Three methods to determine Dividend Growth Model Capital Asset Pricing Model Risk Premium Model 3. Compute Cost of Common Equity
  • 33. 34 Computing Cost of Each Source Cost of Internal Common Equity Dividend Growth Model Assume constant growth in dividends (Chap. 8) 3. Compute Cost of Common Equity
  • 34. 35 Computing Cost of Each Source Cost of Internal Common Equity Dividend Growth Model Assume constant growth in dividends (Chap. 8) 3. Compute Cost of Common Equity Cost of internal equity--dividend growth model D1 P0 kcs = + g
  • 35. 36 Computing Cost of Each Source Cost of Internal Common Equity Dividend Growth Model Assume constant growth in dividends (Chap. 8) 3. Compute Cost of Common Equity Cost of internal equity--dividend growth model D1 P0 kcs = + g Example The market price of a share of common stock is $60. The dividend just paid is $3, and the expected growth rate is 10%.
  • 36. 37 Computing Cost of Each Source Cost of Internal Common Equity Dividend Growth Model Assume constant growth in dividends (Chap. 8) 3. Compute Cost of Common Equity Cost of internal equity--dividend growth model D1 P0 kcs = + g Example The market price of a share of common stock is $60. The dividend just paid is $3, and the expected growth rate is 10%. 3(1+0.10) 60 kcs = + .10
  • 37. 38 Computing Cost of Each Source Cost of Internal Common Equity Dividend Growth Model Assume constant growth in dividends (Chap. 8) 3. Compute Cost of Common Equity Cost of internal equity--dividend growth model D1 P0 kcs = + g Example The market price of a share of common stock is $60. The dividend just paid is $3, and the expected growth rate is 10%. 3(1+0.10) 60 kcs = + .10 = .155 = 15.5%
  • 38. 39 Computing Cost of Each Source Cost of Internal Common Equity Dividend Growth Model Assume constant growth in dividends (Chap. 8) 3. Compute Cost of Common Equity Cost of internal equity--dividend growth model D1 P0 kcs = + g Example The market price of a share of common stock is $60. The dividend just paid is $3, and the expected growth rate is 10%. 3(1+0.10) 60 kcs = + .10 = .155 = 15.5% The main limitation in this method is estimating growth accurately.
  • 39. 40 Computing Cost of Each Source Cost of Internal Common Equity Capital Asset Pricing Model Estimate the cost of equity from the CAPM (Chap. 6) 3. Compute Cost of Common Equity
  • 40. 41 Computing Cost of Each Source Cost of Internal Common Equity Capital Asset Pricing Model Estimate the cost of equity from the CAPM (Chap. 6) 3. Compute Cost of Common Equity kcs = krf + b(km – krf) Cost of internal equity--CAPM
  • 41. 42 Computing Cost of Each Source Cost of Internal Common Equity Capital Asset Pricing Model Estimate the cost of equity from the CAPM (Chap. 6) 3. Compute Cost of Common Equity Example The estimated Beta of a stock is 1.2. The risk-free rate is 5% and the expected market return is 13%. kcs = krf + b(km – krf) Cost of internal equity--CAPM
  • 42. 43 Computing Cost of Each Source Cost of Internal Common Equity Capital Asset Pricing Model Estimate the cost of equity from the CAPM (Chap. 6) 3. Compute Cost of Common Equity Example The estimated Beta of a stock is 1.2. The risk-free rate is 5% and the expected market return is 13%. kcs = krf + b(km – krf) Cost of internal equity--CAPM kcs = 5% + 1.2(13% – 5%)
  • 43. 44 Computing Cost of Each Source Cost of Internal Common Equity Capital Asset Pricing Model Estimate the cost of equity from the CAPM (Chap. 6) 3. Compute Cost of Common Equity Example The estimated Beta of a stock is 1.2. The risk-free rate is 5% and the expected market return is 13%. kcs = krf + b(km – krf) Cost of internal equity--CAPM kcs = 5% + 1.2(13% – 5%) = 14.6%
  • 44. 45 Computing Cost of Each Source Cost of Internal Common Equity Risk Premium Approach Adds a risk premium to the bondholder’s required rate of return. 3. Compute Cost of Common Equity
  • 45. 46 Computing Cost of Each Source Cost of Internal Common Equity Risk Premium Approach Adds a risk premium to the bondholder’s required rate of return. 3. Compute Cost of Common Equity kcs = kd + RPc Cost of internal equity--Risk Premium Where: RPc = Common stock risk premium
  • 46. 47 Computing Cost of Each Source Cost of Internal Common Equity Risk Premium Approach Adds a risk premium to the bondholder’s required rate of return. 3. Compute Cost of Common Equity Example If the risk premium is 5% and kd is 10% kcs = kd + RPc Cost of internal equity--Risk Premium Where: RPc = Common stock risk premium
  • 47. 48 Computing Cost of Each Source Cost of Internal Common Equity Risk Premium Approach Adds a risk premium to the bondholder’s required rate of return. 3. Compute Cost of Common Equity Example If the risk premium is 5% and kd is 10% kcs = kd + RPc Cost of internal equity--Risk Premium kcs = 10% + 5% Where: RPc = Common stock risk premium
  • 48. 49 Computing Cost of Each Source Cost of Internal Common Equity Risk Premium Approach Adds a risk premium to the bondholder’s required rate of return. 3. Compute Cost of Common Equity Example If the risk premium is 5% and kd is 10% kcs = kd + RPc Cost of internal equity--Risk Premium kcs = 10% + 5% = 15% Where: RPc = Common stock risk premium
  • 49. 50 Computing Cost of Each Source Cost of New Common Stock If retained earnings cannot provide all the equity capital that is needed, firms may issue new shares of common stock. 3. Compute Cost of Common Equity
  • 50. 51 Computing Cost of Each Source Cost of New Common Stock If retained earnings cannot provide all the equity capital that is needed, firms may issue new shares of common stock. Dividend Growth Model--Must adjust for floatation costs of the new common shares. 3. Compute Cost of Common Equity
  • 51. 52 Computing Cost of Each Source Cost of New Common Stock If retained earnings cannot provide all the equity capital that is needed, firms may issue new shares of common stock. Dividend Growth Model--must adjust for floatation costs of the new common shares. 3. Compute Cost of Common Equity Cost of new common stock D1 NP0 kcs = + g
  • 52. 53 Computing Cost of Each Source Cost of New Common Stock 3. Compute Cost of Common Equity Cost of new common stock D1 NP0 knc = + g
  • 53. 54 Computing Cost of Each Source Cost of New Common Stock 3. Compute Cost of Common Equity Cost of new common stock D1 NP0 knc = + g Example Using the above example. Common stock price is currently $60. If additional shares are issued floatation costs will be 12%. D0 = $3.00 and estimated growth is 10%.
  • 54. 55 Computing Cost of Each Source Cost of New Common Stock 3. Compute Cost of Common Equity Cost of new common stock D1 NP0 knc = + g Example Using the above example. Common stock price is currently $60. If additional shares are issued floatation costs will be 12%. D0 = $3.00 and estimated growth is 10%. NP0 = $60.00 – (.12x 60) = $52.80 Floatation Costs
  • 55. 56 Computing Cost of Each Source Cost of New Common Stock 3. Compute Cost of Common Equity Cost of new common stock D1 NP0 knc = + g Example Using the above example. Common stock price is currently $60. If additional shares are issued floatation costs will be 12%. D0 = $3.00 and estimated growth is 10%. NP0 = $60.00 – (.12x 60) = $52.80 3(1+0.10) 52.80 kcs = + .10
  • 56. 57 Computing Cost of Each Source Cost of New Common Stock 3. Compute Cost of Common Equity Cost of new common stock D1 NP0 knc = + g Example Using the above example. Common stock price is currently $60. If additional shares are issued floatation costs will be 12%. D0 = $3.00 and estimated growth is 10%. NP0 = $60.00 – (.12x 60) = $52.80 3(1+0.10) 52.80 kcs = + .10 = .1625 = 16.25%
  • 57. 58 Capital Structure Weights Long Term Liabilities and Equity Weights of each source should reflect expected financing mix Assume a stable financial mix–so use Balance Sheet percentages to calculate the weighted average cost of capital.
  • 58. 59 Capital Structure Weights Long Term Liabilities and Equity Balance Sheet Green Apple Company Current Assets $5,000 Current Liabilities $2,000 Plant & Equipment 7,000 Bonds 4,000 Total Assets $12,000 Preferred Stock 1,000 Common Stock 5,000 Total Liabilities and Owners Equity $12,000 Assets Liabilities Firm Raises $10,000 of capital from long term sources
  • 59. 60 Capital Structure Weights Long Term Liabilities and Equity Current Assets $5,000 Current Liabilities $2,000 Plant & Equipment 7,000 Bonds 4,000 Total Assets $12,000 Preferred Stock 1,000 Common Stock 5,000 Total Liabilities and Owners Equity $12,000 Assets Liabilities Compute Firm’s Capital Structure (% of each source) Bonds: 4,000 10,000 = 40% Amount of Bonds Total Capital Sources Balance Sheet Green Apple Company
  • 60. 61 Capital Structure Weights Long Term Liabilities and Equity Current Assets $5,000 Current Liabilities $2,000 Plant & Equipment 7,000 Bonds 4,000 Total Assets $12,000 Preferred Stock 1,000 Common Stock 5,000 Total Liabilities and Owners Equity $12,000 Assets Liabilities Compute Firm’s Capital Structure (% of each source) Amount of Preferred Stock Total Capital Sources Preferred Stock: 1,000 10,000 = 10% Balance Sheet Green Apple Company
  • 61. 62 Capital Structure Weights Long Term Liabilities and Equity Current Assets $5,000 Current Liabilities $2,000 Plant & Equipment 7,000 Bonds 4,000 Total Assets $12,000 Preferred Stock 1,000 Common Stock 5,000 Total Liabilities and Owners Equity $12,000 Assets Liabilities Compute Firm’s Capital Structure (% of each source) Amount of Common Stock Total Capital Sources Common Stock: 5,000 10,000 = 50% Balance Sheet Green Apple Company
  • 62. 63 Capital Structure Weights Long Term Liabilities and Equity Current Assets $5,000 Current Liabilities $2,000 Plant & Equipment 7,000 Bonds 4,000 Total Assets $12,000 Preferred Stock 1,000 Common Stock 5,000 Total Liabilities and Owners Equity $12,000 Assets Liabilities 40% 10% 50% When money is raised for capital projects, approximately 40% of the money comes from selling bonds, 10% comes from selling preferred stock and 50% comes from retaining earnings or selling common stock Balance Sheet Green Apple Company
  • 63. 64 Computing WACC Green Apple Company estimates the following costs for each component in its capital structure: Source of Capital Cost Bonds kd = 10% Preferred Stock kps = 11.9% Common Stock Retained Earnings kcs = 15% New Shares knc = 16.25% Green Apple’s tax rate is 40%
  • 64. 65 Computing WACC If using retained earnings to finance the common stock portion the capital structure WACC= k0 = %Bonds x Cost of Bonds x (1-T) + %Preferred x Cost of Preferred + %Common x Cost of Common Stock
  • 65. 66 Balance Sheet Current Assets $5,000 Current Liabilities $2,000 Plant & Equipment 7,000 Bonds (9%) 4,000 Total Assets $12,000 Preferred Stock (10%) 1,000 Common Stock(13%) 5,000 Tax Rate = 40% Total Liabilities and Owners Equity $12,000 Assets Liabilities 40% 10% 50% WACC= k0 = %Bonds x Cost of Bonds x (1-T) + %Preferred x Cost of Preferred + %Common x Cost of Common Stock Computing WACC - using Retained Earnings
  • 66. 67 Balance Sheet Current Assets $5,000 Current Liabilities $2,000 Plant & Equipment 7,000 Bonds (10%) 4,000 Total Assets $12,000 Preferred Stock (11.9%)1,000 Common Stock(15%) 5,000 Tax Rate = 40% Total Liabilities and Owners Equity $12,000 Assets Liabilities 40% 10% 50% WACC= k0 = %Bonds x Cost of Bonds x (1-T) + %Preferred x Cost of Preferred + %Common x Cost of Common Stock Computing WACC - using Retained Earnings WACC = .40 x 10% (1-.4)
  • 67. 68 Balance Sheet Assets Liabilities 40% 10% 50% WACC= k0 = %Bonds x Cost of Bonds x (1-T) + %Preferred x Cost of Preferred + %Common x Cost of Common Stock Computing WACC - using Retained Earnings WACC = .40 x 10% (1-.4) + .10 x 11.9% Current Assets $5,000 Current Liabilities $2,000 Plant & Equipment 7,000 Bonds (10%) 4,000 Total Assets $12,000 Preferred Stock (11.9%)1,000 Common Stock(15%) 5,000 Tax Rate = 40% Total Liabilities and Owners Equity $12,000
  • 68. 69 Balance Sheet Assets Liabilities 40% 10% 50% WACC= k0 = %Bonds x Cost of Bonds x (1-T) + %Preferred x Cost of Preferred + %Common x Cost of Common Stock Computing WACC - using Retained Earnings WACC = .40 x 10% (1-.4) + .10 x 11.9% + .50 x 15% Current Assets $5,000 Current Liabilities $2,000 Plant & Equipment 7,000 Bonds (10%) 4,000 Total Assets $12,000 Preferred Stock (11.9%)1,000 Common Stock(15%) 5,000 Tax Rate = 40% Total Liabilities and Owners Equity $12,000
  • 69. 70 Balance Sheet Assets Liabilities 40% 10% 50% WACC = .40 x 10% (1-.4) + .10 x 11.9% + .50 x 15% = 11.09% WACC= k0 = %Bonds x Cost of Bonds x (1-T) + %Preferred x Cost of Preferred + %Common x Cost of Common Stock Computing WACC - using Retained Earnings Current Assets $5,000 Current Liabilities $2,000 Plant & Equipment 7,000 Bonds (10%) 4,000 Total Assets $12,000 Preferred Stock (11.9%)1,000 Common Stock(15%) 5,000 Tax Rate = 40% Total Liabilities and Owners Equity $12,000
  • 70. 71 Computing WACC If use newly issued common stock, use knc rather than kcs for the cost of the equity portion. WACC= k0 = %Bonds x Cost of Bonds x (1-T) + %Preferred x Cost of Preferred + %Common x Cost of Common Stock knc
  • 71. 72 Balance Sheet Assets Liabilities WACC = .40 x 10% (1-.4) + .10 x 11.9% + .50 x 16.25% = 11.72% WACC= k0 = %Bonds x Cost of Bonds x (1-T) + %Preferred x Cost of Preferred + %Common x Cost of Common Stock Computing WACC - using New Common Shares Current Assets $5,000 Current Liabilities $2,000 Plant & Equipment 7,000 Bonds (10%) 4,000 Total Assets $12,000 Preferred Stock (11.9%)1,000 Common Stock(16.25%)5,000 Tax Rate = 40% Total Liabilities and Owners Equity $12,000
  • 72. 73 Weighted Marginal Cost of Capital A firm’s cost of capital will change as it is raises more and more capital Retained earnings will be used up at some level The cost of other sources may rise beyond a certain amount of money has been raised
  • 73. 74 Weighted Marginal Cost of Capital A firm’s cost of capital will changes as it is raising more and more capital Retained earnings will be used up at some level The cost of other sources may rise beyond a certain amount of money raised Therefore, beyond a point, the WACC will rise. Calculate the point at which the cost of capital increases
  • 74. 75 Weighted Marginal Cost of Capital A firm’s cost of capital will changes as it is raising more and more capital Retained earnings will be used up at some level The cost of other sources may rise beyond a certain amount of money raised Calculate the point at which the cost of capital increases Break in cost of capital curve Amt of lower cost capital that can be raised before component cost rises Weight of this kind of capital in the capital structure =
  • 75. 76 Weighted Marginal Cost of Capital Break in cost of capital curve Retained earnings available for reinvesting Percentage of common financing = If Green Apple Company has $100,000 of internally generated common:
  • 76. 77 Weighted Marginal Cost of Capital Break in cost of capital curve Retained earnings available for reinvesting Percentage of common financing = If Green Apple Company has $100,000 of internally generated common: Break in cost of capital curve $100,000 .50 =
  • 77. 78 Weighted Marginal Cost of Capital Break in cost of capital curve Retained earnings available for reinvesting Percentage of common financing = If Green Apple Company has $100,000 of internally generated common: Break in cost of capital curve $100,000 .50 = = $200,000
  • 78. 79 Weighted Marginal Cost of Capital Break in cost of capital curve Retained earnings available for reinvesting Percentage of common financing = If Green Apple Company has $100,000 of internally generated common: Break in cost of capital curve $100,000 .50 = = $200,000 Once $200,000 is raised from all sources, the cost of capital will rise because all the lower cost retained earnings will be used up.
  • 79. 80 Weighted Marginal Cost of Capital Weighted Cost of Capital Total Financing 9% 10% 11% 12% 0 100,000 200,000 300,000 400,000 Marginal weighted cost of capital curve: 11.09% Cost of Capital using internal common stock
  • 80. 81 Weighted Marginal Cost of Capital Weighted Cost of Capital Total Financing 9% 10% 11% 12% 0 100,000 200,000 300,000 400,000 Marginal weighted cost of capital curve: 11.09% Break-Point for common equity
  • 81. 82 Weighted Marginal Cost of Capital Weighted Cost of Capital Total Financing 9% 10% 11% 12% 0 100,000 200,000 300,000 400,000 Marginal weighted cost of capital curve: 11.09% Cost of Capital using internal common stock 11.72% Cost of Capital using new common equity
  • 82. 83 Weighted Marginal Cost of Capital Weighted Cost of Capital Total Financing 9% 10% 11% 12% 0 100,000 200,000 300,000 400,000 Marginal weighted cost of capital curve: 11.09% 11.72%
  • 83. 84 Making Decisions Choosing Projects Using Weighted Marginal Cost of Capital Graph IRR’s of potential projects Weighted Cost of Capital Total Financing 9% 10% 11% 12% 0 100,000 200,000 300,000 400,000 Marginal weighted cost of capital curve: Project 1 IRR = 12.4% Project 2 IRR = 12.1% Project 3 IRR = 11.5%
  • 84. 85 Making Decisions Choosing Projects Using Weighted Marginal Cost of Capital Graph IRR’s of potential projects Graph Weighted Marginal Cost of Capital Weighted Cost of Capital Total Financing 9% 10% 11% 12% 0 100,000 200,000 300,000 400,000 Marginal weighted cost of capital curve: Project 1 IRR = 12.4% Project 2 IRR = 12.1% Project 3 IRR = 11.5%
  • 85. 86 Making Decisions Choosing Projects Using Weighted Marginal Cost of Capital Graph IRR’s of potential projects Graph Weighted Marginal Cost of Capital Choose projects whose IRR is above the weighted marginal cost of capital Weighted Cost of Capital Total Financing 9% 10% 11% 12% 0 100,000 200,000 300,000 400,000 Marginal weighted cost of capital curve: Project 1 IRR = 12.4% Project 2 IRR = 12.1% Project 3 IRR = 11.5% Accept Projects #1 & #2