The Cost
of Capital
Learning Goals
• Sources of capital
• Cost of each type of funding
• Calculation of the weighted average cost of capital
(WACC)
• Construction and use of the marginal cost of capital
schedule (MCC)
2
Factors Affecting the Cost of Capital
• General Economic Conditions
– Affect interest rates
• Market Conditions
– Affect risk premiums
• Operating Decisions
– Affect business risk
• Financial Decisions
– Affect financial risk
• Amount of Financing
– Affect flotation costs and market price of security
3
• Compute the cost of each source of capital
• Determine percentage of each source of
capital in the optimal capital structure
• Calculate Weighted Average Cost of Capital
(WACC)
4
Weighted Cost of Capital Model
• Required rate of return for creditors
• Same cost found in Chapter 12 as yield to maturity
on bonds (kd).
• e.g. Suppose that a company issues bonds with a
before tax cost of 10%.
• Since interest payments are tax deductible, the true
cost of the debt is the after tax cost.
• If the company’s tax rate (state and federal
combined) is 40%, the after tax cost of debt
• AT kd = 10%(1-.4) = 6%.
5
1. Compute Cost of Debt
• Cost to raise a dollar of preferred stock.
6
11.90%
$5.00
$42.00
kp = =
The cost of preferred stock:
Example: You can issue preferred stock for a net
price of $42 and the preferred stock pays a
$5 dividend.
Dividend (Dp)
Market Price (PP) - F
Required rate kp =
2. Compute Cost Preferred Stock
• Two Types of Common Equity Financing
– Retained Earnings (internal common equity)
– Issuing new shares of common stock (external
common equity)
7
3. Compute Cost of Common
Equity
• Cost of Internal Common Equity
– Management should retain earnings only
if they earn as much as stockholder’s
next best investment opportunity of the
same risk.
– Cost of Internal Equity = opportunity
cost of common stockholders’ funds.
– Two methods to determine
• Dividend Growth Model
• Capital Asset Pricing Model
8
3. Compute Cost of Common Equity
• Cost of Internal Common Stock Equity
– Dividend Growth Model
9
D1
P0
kS = + g
3. Compute Cost of Common Equity
• Cost of Internal Common Stock Equity
– Dividend Growth Model
10
Example:
The market price of a share of common stock is
$60. The dividend just paid is $3, and the expected
growth rate is 10%.
3. Compute Cost of Common Equity
D1
P0
kS = + g
• Cost of Internal Common Stock Equity
– Dividend Growth Model
11
3(1+0.10)
60
kS = + .10 =.155 = 15.5%
Example:
The market price of a share of common stock is $60.
The dividend just paid is $3, and the expected growth
rate is 10%.
3. Compute Cost of Common Equity
D1
P0
kS = + g
• Cost of Internal Common Stock Equity
– Capital Asset Pricing Model (Chapter 7)
12
kS = kRF + (kM – kRF)
3. Compute Cost of Common Equity
• Cost of Internal Common Stock Equity
– Capital Asset Pricing Model (Chapter 7)
13
Example:
The estimated Beta of a stock is 1.2. The risk-free rate
is 5% and the expected market return is 13%.
3. Compute Cost of Common Equity
kS = kRF + (kM – kRF)
• Cost of Internal Common Stock Equity
– Capital Asset Pricing Model (Chapter 7)
14
kS = 5% + 1.2(13% – 5%) 14.6%
3. Compute Cost of Common Equity
=
Example:
The estimated Beta of a stock is 1.2. The risk-free rate
is 5% and the expected market return is 13%.
kS = kRF + (kM – kRF)
• Cost of New Common Stock
– Must adjust the Dividend Growth Model equation for
floatation costs of the new common shares.
15
3. Compute Cost of Common Equity
D1
P0 - F
kn = + g
• Cost of New Common Stock
– Must adjust the Dividend Growth Model equation
for floatation costs of the new common shares.
16
3. Compute Cost of Common Equity
Example:
If additional shares are issued floatation costs
will be 12%. D0 = $3.00 and estimated growth
is 10%, Price is $60 as before.
D1
P0 - F
kn = + g
• Cost of New Common Stock
– Must adjust the Dividend Growth Model equation for
floatation costs of the new common shares.
17
3. Compute Cost of Common Equity
3(1+0.10)
52.80
kn = + .10 = .1625 =
D1
P0 - F
kn = + g
16.25%
Example:
If additional shares are issued floatation costs will
be 12%. D0 = $3.00 and estimated growth is 10%,
Price is $60 as before.
18
Weighted Average Cost of Capital
Gallagher Corporation estimates the following
costs for each component in its capital structure:
Gallagher’s tax rate is 40%
Source of Capital Cost
Bonds kd = 10%
Preferred Stock kp = 11.9%
Common Stock
Retained Earnings ks = 15%
New Shares kn = 16.25%
19
Weighted Average Cost of Capital
 If using retained earnings to finance the
common stock portion the capital structure:
WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)
20
If using retained earnings to finance the
common stock portion the capital structure:
Weighted Average Cost of Capital
 Assume that Gallagher’s desired capital
structure is 40% debt, 10% preferred and
50% common equity.
WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)
21
Weighted Average Cost of Capital
WACC = .40 x 10% (1-.4) + .10 x 11.9%
+ .50 x 15% = 11.09%
WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)
If using retained earnings to finance the
common stock portion the capital structure:
 Assume that Gallagher’s desired capital
structure is 40% debt, 10% preferred and
50% common equity.
22
If using a new equity issue to finance the
common stock portion the capital structure:
Weighted Average Cost of Capital
WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)
23
Weighted Average Cost of Capital
WACC = .40 x 10% (1-.4) + .10 x 11.9%
+ .50 x 16.25% = 11.72%
If using a new equity issue to finance the
common stock portion the capital structure:
WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)
Marginal Cost of Capital
• Gallagher’s weighted average cost will change if
one component cost of capital changes.
• This may occur when a firm raises a particularly
large amount of capital such that investors think
that the firm is riskier.
• The WACC of the next dollar of capital raised in
called the marginal cost of capital (MCC).
24
Graphing the MCC curve
• Assume now that Gallagher Corporation has
$100,000 in retained earnings with which to
finance its capital budget.
• We can calculate the point at which they will
need to issue new equity since we know that
Gallagher’s desired capital structure calls for
50% common equity.
25
Graphing the MCC curve
• Assume now that Gallagher Corporation has
$100,000 in retained earnings with which to
finance its capital budget.
• We can calculate the point at which they will
need to issue new equity since we know that
Gallagher’s desired capital structure calls for
50% common equity.
26
Breakpoint = Available Retained Earnings
Percentage of Total
Graphing the MCC curve
27
Breakpoint = ($100,000)/.5 = $200,000
Making Decisions Using MCC
28
Weighted
Cost
of
Capital
Total Financing
10%
11%
12%
13%
0 100,000 200,000 300,000 400,000
Marginal weighted cost of capital curve:
Using internal
common equity
Using new
common equity
11.72%
11.09%
Making Decisions Using MCC
• Graph MIRRs of potential projects
29
Weighted
Cost
of
Capital
Total Financing
9%
10%
11%
12%
0 100,000 200,000 300,000 400,000
Marginal weighted cost of capital curve:
Project 1
MIRR =
12.4%
Project 2
MIRR =
12.1%
Project 3
MIRR =
11.5%
Making Decisions Using MCC
• Graph IRRs of potential projects
30
Weighted
Cost
of
Capital
Total Financing
9%
10%
11%
12%
0 100,000 200,000 300,000 400,000
Marginal weighted cost of capital curve:
Project 1
IRR =
12.4%
Project 2
IRR =
12.1%
Project 3
IRR =
11.5%
Graph MCC Curve
11.09%
11.72%
Making Decisions Using MCC
• Graph IRRs of potential projects
• Graph MCC Curve
31
Weighted
Cost
of
Capital
Total Financing
9%
10%
11%
12%
0 100,000 200,000 300,000 400,000
Marginal weighted cost of capital curve:
Project 1
IRR = 12.4% Project 2
IRR = 12.1%
Project 3
IRR = 11.5%
Accept Projects #1 & #2
 Choose projects whose IRR is above the weighted
marginal cost of capital
11.72%
11.09%
32
Answer the following questions and do the following
problems and include them in you ECP Notes.
If the cost of new common equity is higher than the cost of internal equity, why would a
firm choose to issue new common stock?
Why is it important to use a firm’s MCC and not a firm’s initial WACC to evaluate
investments?
Calculate the AT kd, ks, kn for the following information:
Loan rates for this firm = 9%
Growth rate of dividends = 4%
Tax rate = 30%
Common Dividends at t1 = $ 4.00
Price of Common Stock = $35.00
Flotation costs = 6%
Your firm’s ks is 10%, the cost of debt is 6% before taxes, and the tax rate is 40%.
Given the following balance sheet, calculate the firm’s after tax WACC:
Total assets = $25,000
Total debt = 15,000
Total equity = 10,000
33
Your firm is in the 30% tax bracket with a before-tax required rate of return on its
equity of 13% and on its debt of 10%. If the firm uses 60% equity and 40% debt
financing, calculate its after-tax WACC.
Would a firm use WACC or MCC to identify which new capital budgeting projects
should be selected? Why?
A firm's before tax cost of debt on any new issue is 9%; the cost to issue new
preferred stock is 8%. This appears to conflict with the risk/return relationship.
How can this pricing exist?
What determines whether to use the dividend growth model approach or the CAPM
approach to calculate the cost of equity?
Capital Budgeting
Decision Methods
1
• The capital budgeting process.
• Calculation of payback, NPV, IRR, and MIRR for
proposed projects.
• Capital rationing.
• Measurement of risk in capital budgeting and
how to deal with it.
Learning Objectives
2
• Capital Budgeting is the process of
evaluating proposed investment projects for
a firm.
• Managers must determine which projects
are acceptable and must rank mutually
exclusive projects by order of desirability to
the firm.
The Capital Budgeting Process
3
Four methods:
• Payback Period
– years to recoup the initial investment
• Net Present Value (NPV)
– change in value of firm if project is under taken
• Internal Rate of Return (IRR)
– projected percent rate of return project will earn
• Modified Internal Rate of Return (MIRR)
The Accept/Reject Decision
4
• Consider Projects A and B that have the
following expected cashflows?
Capital Budgeting Methods
5
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
• What is the payback for Project A?
Capital Budgeting Methods
6
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
• What is the payback for Project A?
Capital Budgeting Methods
0 1 2 3 4
3,500
-6,500
3,500
-3,000
3,500
+500
3,500
(10,000)
Cumulative CF
7
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
• What is the payback for Project A?
Capital Budgeting Methods
Payback in
2.9 years
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
8
0 1 2 3 4
3,500
-6,500
3,500
-3,000
3,500
+500
3,500
(10,000)
Cumulative CF
0 1 2 3 4
3,500
-6,500
3,500
-3,000
3,500
+500
3,500
(10,000)
Cumulative CF
• What is the payback for Project B?
Capital Budgeting Methods
9
0 1 2 3 4
500 500 4,600 10,000
(10,000)
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
Payback in
3.4 years
• What is the payback for Project B?
Capital Budgeting Methods
10
0 1 2 3 4
500
-9,500
500
-9,000
4,600
-4,400
10,000
+5,600
(10,000)
Cumulative CF
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
• Accept project if payback is less than the
company’s predetermined maximum.
• If company has determined that it requires
payback in three years or less, then you
would:
– accept Project A
– reject Project B
Payback Decision Rule
11
• Present Value of all costs and benefits
(measured in terms of incremental cash
flows) of a project.
• Concept is similar to Discounted Cashflow
model for valuing securities but subtracts
the cost of the project.
Capital Budgeting Methods
Net Present Value
12
• Present Value of all costs and benefits (measured in
terms of incremental cash flows) of a project.
• Concept is similar to Discounted Cashflow model for
valuing securities but subtracts of cost of project.
Capital Budgeting Methods
Net Present Value
NPV = PV of Inflows - Initial Investment
NPV = + + – Initial
Investment
CF1
(1+ k)1
CF2
(1+ k)2 ….
CFn
(1+ k )n
13
What is the
NPV for
Project B?
14
P R O J E C T
Time A B
0 (10,000) (10,000)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
k=10%
0 1 2 3 4
500 500 4,600 10,000
(10,000)
Capital Budgeting Methods
455
$500
(1.10)1
What is the
NPV for
Project B?
15
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
k=10%
0 1 2 3 4
500 500 4,600 10,000
(10,000)
Capital Budgeting Methods
413
$500
(1.10) 2
What is the
NPV for
Project B?
16
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
455
k=10%
0 1 2 3 4
500 500 4,600 10,000
(10,000)
Capital Budgeting Methods
3,456
$4,600
(1.10) 3
What is the
NPV for
Project B?
17
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
413
$500
(1.10) 2
455
k=10%
0 1 2 3 4
500 500 4,600 10,000
(10,000)
Capital Budgeting Methods
6,830
$10,000
(1.10) 4
What is the
NPV for
Project B?
18
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
3,456
$4,600
(1.10) 3
413
$500
(1.10) 2
455
k=10%
0 1 2 3 4
500 500 4,600 10,000
(10,000)
Capital Budgeting Methods
$11,154
What is the
NPV for
Project B?
19
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
6,830
3,456
413
455
k=10%
0 1 2 3 4
500 500 4,600 10,000
(10,000)
Capital Budgeting Methods
PV Benefits > PV Costs
$11,154 > $ 10,000
What is the
NPV for
Project B?
20
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
$11,154
6,830
3,456
413
455
k=10%
0 1 2 3 4
500 500 4,600 10,000
(10,000)
NPV > $0
$1,154 > $0
- $10,000 = $1,154 = NPV
What is the
NPV for
Project B?
21
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
PV Benefits > PV Costs
$11,154 > $ 10,000
$11,154
6,830
3,456
413
455
k=10%
0 1 2 3 4
500 500 4,600 10,000
(10,000)
22
• Additional Keys used to enter
Cash Flows and compute the
Net Present Value (NPV)
Financial Calculator:
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Key used to enter expected cash flows in order of
their receipt.
Note: the initial investment (CF0) must be
entered as a negative number since it is an outflow.
23
• Additional Keys used to
enter Cash Flows and
compute the Net
Present Value (NPV)
Financial Calculator:
NPV IRR
P/YR
CF
N I/Y PV PMT FV
• Additional Keys used to
enter Cash Flows and
compute the Net Present
Value (NPV)
Financial Calculator:
Key used to calculate the net present value of
the cashflows that have been entered in the
calculator.
24
NPV IRR
P/YR
CF
N I/Y PV PMT FV
• Additional Keys used
to enter Cash Flows
and compute the Net
Present Value (NPV)
Financial Calculator:
Key used to calculate the internal rate of return
for the cashflows that have been entered in
the calculator. 25
Calculate the NPV for Project B with calculator.
26
NPV IRR
P/YR
CF
N I/Y PV PMT FV
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the NPV for Project B with calculator.
Keystrokes for TI BAII PLUS:
CF0 = -10,000
27
CF 10000 +/- ENTER
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the NPV for Project B with calculator.
C01 = 500
500 ENTER
28
CF 10000 +/- ENTER
Keystrokes for TI BAII PLUS:
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the NPV for Project B with calculator.
F01 = 2
F stands for “frequency”. Enter 2 since there
are two adjacent payments of 500 in periods 1 and 2.
29
2 ENTER
500 ENTER
CF 10000 +/- ENTER
Keystrokes for TI BAII PLUS:
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the NPV for Project B with calculator.
C02 = 4600
4600 ENTER
30
2 ENTER
500 ENTER
CF 10000 +/- ENTER
Keystrokes for TI BAII PLUS:
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the NPV for Project B with calculator.
F02 = 1
1 ENTER
31
4600 ENTER
2 ENTER
500 ENTER
CF 10000 +/- ENTER
Keystrokes for TI BAII PLUS:
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the NPV for Project B with calculator.
C03 = 10000
10000 ENTER
32
1 ENTER
4600 ENTER
2 ENTER
500 ENTER
CF 10000 +/- ENTER
Keystrokes for TI BAII PLUS:
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the NPV for Project B with calculator.
F03 = 1
1 ENTER
33
10000 ENTER
1 ENTER
4600 ENTER
2 ENTER
500 ENTER
CF 10000 +/- ENTER
Keystrokes for TI BAII PLUS:
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the NPV for Project B with calculator.
I = 10
k = 10%
34
Keystrokes for TI BAII PLUS:
10 ENTER
NPV
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the NPV for Project B with calculator.
NPV = 1,153.95
CPT
The net present value of Project B = $1,154
as we calculated previously.
35
10 ENTER
NPV
Keystrokes for TI BAII PLUS:
• Accept the project if the NPV is greater
than or equal to 0.
Example:
NPVA = $1,095
NPVB = $1,154
NPV Decision Rule
> 0
> 0
Accept
Accept
•If projects are independent, accept both projects.
•If projects are mutually exclusive, accept the project
with the higher NPV.
36
• IRR (Internal Rate of Return)
– IRR is the discount rate that forces the NPV to equal
zero.
– It is the rate of return on the project given its initial
investment and future cash flows.
• The IRR is the rate earned only if all CFs are reinvested at the
IRR rate.
Capital Budgeting Methods
37
Calculate the IRR for Project B with calculator.
39
NPV IRR
P/YR
CF
N I/Y PV PMT FV
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
Enter CFs as for NPV
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the IRR for Project B with calculator.
IRR = 13.5%
40
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
IRR CPT
• Accept the project if the IRR is greater than or
equal to the required rate of return (k).
• Reject the project if the IRR is less than the
required rate of return (k).
Example:
k = 10%
IRRA = 14.96%
IRRB = 13.50%
IRR Decision Rule
> 10%
> 10%
Accept
Accept
41
• MIRR (Modified Internal Rate of Return)
– This is the discount rate which causes the project’s PV of
the outflows to equal the project’s TV (terminal value) of
the inflows.
– Assumes cash inflows are reinvested at k, the safe re-
investment rate.
– MIRR avoids the problem of multiple IRRs.
– We accept if MIRR > the required rate of return.
Capital Budgeting Methods
PVoutflow = TVinflows
(1 + MIRR)n
42
What is the
MIRR for
Project B?
P R O J E C T
Time A B
0 (10,000.) (10,000.)
1 3,500 500
2 3,500 500
3 3,500 4,600
4 3,500 10,000
Safe =2%
0 1 2 3 4
500 500 4,600 10,000
(10,000)
(10,000)
10,000(1.02)0
10,000
4,600(1.02)1
500(1.02)2
500(1.02)3
4,692
520
531
15,743
10,000 =
15,743
(1 + MIRR)4
(10,000)/(1.02)0
MIRR = .12 = 12%
43
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the MIRR for Project B with calculator.
10000 ENTER
1 ENTER
1 ENTER
4600 ENTER
2 ENTER
500 ENTER
CF 0 +/- ENTER
Keystrokes for TI BAII PLUS:
Step 1. Calculate NPV using cash inflows
44
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the MIRR for Project B with calculator.
NPV = 14,544
CPT
The net present value of Project B cash inflows = $14,544
(use as PV)
45
2 ENTER
NPV
Keystrokes for TI BAII PLUS:
Step 1. Calculate NPV using cash inflows
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the MIRR for Project B with calculator.
FV = 15,743
46
Step 2. Calculate FV of cash inflows using previous NPV
This is the Terminal Value
Calculator Enter:
N = 4
I/YR = 2
PV = -14544
PMT= 0
CPT FV = ?
NPV IRR
P/YR
CF
N I/Y PV PMT FV
Calculate the MIRR for Project B with calculator.
MIRR 12.01
47
Step 3. Calculate MIRR using PV of outflows and calculated
Terminal Value.
Calculator Enter:
N = 4
PV = -10000
PMT = 0
FV = 15,743
CPT I/YR = ??
• Capital rationing is the practice of placing
a dollar limit on the total size of the
capital budget.
• This practice may not be consistent with
maximizing shareholder value but may be
necessary for other reasons.
• Choose between projects by selecting the
combination of projects that yields the
highest total NPV without exceeding the
capital budget limit.
What is capital rationing?
54
• Calculate the coefficient of variation of returns
of the firm’s asset portfolio with the project
and without it.
• This can be done by following a five step
process. Observe the following example.
Measurement of Project Risk
55
• Step 1: Find the CV of the Existing Portfolio
– Assume Company X has an existing rate of return
of 6% and standard deviation of 2%.
Measurement of Project Risk
56
Standard Deviation
Mean, or expected value
CV=
= .02
.06
= .3333, or 33.33%
• Step 2: Find the Expected return of the New
Portfolio (Existing plus Proposed)
– Assume the New Project (Y) has an IRR of 5.71%
and a Standard Deviation of 2.89%
– Assume further that Project Y will account for 10%
of X’s overall investment.
Measurement of Project Risk
57
(wx x E(Rx)) + (wy x E(Ry))
= (.10 x .0571) + (.90 x .06)
= .00571 + .05400
= .05971, or 5.971%
E(Rp) =
• Step 3: Find the Standard Deviation of the New
Portfolio (Existing plus Proposed).
– Assume the proposed is uncorrelated with the
existing project. rxy = 0
Measurement of Project Risk
58
[wx
2σx
2 + wy
2σy
2 + 2wxwyrxyσxσy]1/2
= [(.102)(.02892) + (.902)(.022) + (2)(.10)(.90)(0.0)(.0289)(02)]1/2
= [(.01)(.000835) + (.81)(.0004) + 0]1/2
= .0182, or 1.82%
= [.00000835 + .000324]1/2
= [.00033235]1/2
σp =
• Step 4: Find the CV of the New Portfolio
(Existing plus Proposed)
Measurement of Project Risk
59
Standard Deviation
Mean, or expected value
CV=
= .0182
.05971
= .3048, or 30.48%
• Step 5: Compare the CV of the portfolio
with and without the Proposed Project.
– The difference between the two coefficients
of variation is the measure of risk of the
capital budgeting project.
Measurement of Project Risk
60
CV without Y Change in CV
CV with Y
33.33% -2.85
30.48%
• Firms often compensate for risk by
adjusting the discount rate used to
calculate NPV.
– Higher risk, use a higher discount rate.
– Lower risk, use a lower discount rate
• The risk adjusted discount rate (RADR) can
also be used as a risk adjusted hurdle rate
for IRR comparisons.
Comparing risky projects using risk
adjusted discount rates (RADRs)
61
• Non-simple projects have one or
more negative future cash flows
after the initial investment.
Non-simple Projects
62
• How would a negative cash flow in year 4
affect Project Z’s NPV?
Non-simple projects
Project Z should be rejected in this case.
63
8,336
-4,098
3,757
4,132
4,545
k=10%
0 1 2 3 4
5,000 5,000 5,000 -6,000
(10,000)
- $10,000 = -$1,664 NPV
• Mutually exclusive projects with unequal
project lives can be compared by using two
methods:
– Replacement Chain
– Equivalent Annual Annuity
Mutually Exclusive Projects With
Unequal Lives
68
• Assumes each project can be replicated until a
common period of time has passed, allowing
the projects to be compared.
• Example
– Project Cheap Talk has a 3-year life, with an NPV
of $4,424.
– Project Rolles Voice has a 12-year life, with an NPV
of $4,510.
Replacement Chain Approach
69
• Project Cheap Talk could be repeated four
times during the life of Project Rolles Voice.
• The NPVs of Project Cheap Talk, in years t3, t6,
and t9, are discounted back to year t0.
Replacement Chain Approach
70
• The NPVs of Project Cheap Talk, in years t3,
t6, and t9, are discounted back to year t0,
which results in an NPV of $12,121.
Replacement Chain Approach
3,324
12,121
2,497
1,876
0 3 6 9
4,424 4,424 4,424
4,424
k=10%
71
• Amount of the annuity payment that
would equal the same NPV as the actual
future cash flows of a project.
• EAA = NPV
PVIFAk,n
Equivalent Annual Annuity
72
Equivalent Annual Annuity
73
Project Rolles Voice
$4,510
((1-(1.1)-12) / .1)
= $661.90
• Project Cheap Talk
$4,244
((1-(1.1)-3) / .1)
= $1778.96
ECP Homework
1. The following net cash flows are projected for two separate projects. Your required rate
of return is 12%.
Year Project A Project B
0 ($150,000) ($400,000)
1 $30,000 $100,000
2 $30,000 $100,000
3 $30,000 $100,000
4 $30,000 $100,000
5 $30,000 $100,000
6 $30,000 $100,000
a. Calculate the payback period for each project.
b. Calculate the NPV of each project.
c. Calculate the MIRR of each project.
d. Which project(s) would you accept and why?
2. What is meant by risk adjusted discount rates?
3. Explain why the NPV method of capital budgeting is preferable over the payback method.
4. A firm has a net present value of zero. Should the project be rejected? Explain.
5. You have estimated the MIRR for a new project with the following probabilities:
Possible MIRR Value Probability
4% 5%
7% 15%
10% 15%
11% 50%
14% 15%
a. Calculate the expected MIRR of the project.
b. Calculate the standard deviation of the project.
c. Calculate the coefficient of variation.
d. Calculate the expected MIRR of the new portfolio with the new project. The current
portfolio has an expected MIRR of 9% and a standard deviation of 3% and will
represent 60% of the total portfolio.
ECP Homework
98
Business
Valuation
Learning Objectives
• Understand the importance of business valuation.
• Understand the importance of stock and bond
valuation.
• Learn to compute the value and yield to maturity of
bonds.
• Learn to compute the value and expected yield on
preferred stock and common stock.
• Learn to compute the value of a complete business.
99
General Valuation Model
• To develop a general model for valuing a business,
we consider three factors that affect future
earnings:
– Size of cash flows
– Timing of cash flows
– Risk
• We then apply the factors to the Discounted Cash
Flow (DCF) Model (Equation 12-1)
100
Bond Valuation Model
• Bond Valuation is an application of time value
model introduced in chapter 8.
• The value of the bond is the present value of
the cash flows the investor expects to receive.
• What are the cashflows from a bond
investment?
101
Bond Valuation Model
• 3 Types of Cash Flows
– Amount paid to buy the bond (PV)
– Coupon interest payments made to the
bondholders (PMT)
– Repayment of Par value at end of Bond’s life
(FV).
102
Bond Valuation Model
• 3 Types of Cash Flows
– Amount paid to buy the bond (PV)
– Coupon interest payments made to the
bondholders (PMT)
– Repayment of Par value at end of Bond’s life
(FV).
103
Discount rate (I/YR)
• Bond’s time to maturity (N)
104
Cur Net
Bonds Yld Vol Close Chg
AMR 6¼24 cv 6 91¼ -1½
ATT 8.35s25 8.3 110 102¾ +¼
IBM 63/8 05 6.6 228 965/8 -1/8
Kroger 9s99 8.8 74 1017/8 -¼
IBM 63/8 09 6.6 228 965/8 -1/8
IBM Bond Wall Street Journal Information:
105
Suppose IBM makes annual coupon payments. The person
who buys the bond at the beginning of 2005 for $966.25
will receive 5 annual coupon payments of $63.75 each and
a $1,000 principal payment in 5 years (at the end of 2009).
Assume t0 is the beginning of 2005.
IBM Bond Wall Street Journal
Information:
Cur Net
Bonds Yld Vol Close Chg
AMR 6¼24 cv 6 91¼ -1½
ATT 8.35s25 8.3 110 102¾ +¼
IBM 63/8 05 6.6 228 965/8 -1/8
Kroger 9s99 8.8 74 1017/8 -¼
IBM 63/8 09 6.6 228 965/8 -1/8
106
IBM Bond Timeline:
0 1 2 3 4 5
2005 2006 2007 2008 2009
63.75 63.75 63.75 63.75 63.75
1000.00
Suppose IBM makes annual coupon payments. The person
who buys the bond at the beginning of 2005 for $966.25 will
receive 5 annual coupon payments of $63.75 each and a
$1,000 principal payment in 5 years (at the end of 2009).
Cur Net
Bonds Yld Vol Close Chg
AMR 6¼24 cv 6 91¼ -1½
ATT 8.35s25 8.3 110 102¾ +¼
IBM 63/8 05 6.6 228 965/8 -1/8
Kroger 9s99 8.8 74 1017/8 -¼
IBM 63/8 09 6.6 228 965/8 -1/8
107
Compute the Value for the IBM Bond given that you require an
8% return on your investment.
0 1 2 3 4 5
2005 2006 2007 2008 2009
63.75 63.75 63.75 63.75 63.75
1000.00
IBM Bond Timeline:
108
$63.75 Annuity for 5 years
VB = (INT x PVIFAk,n) + (M x PVIFk,n )
$1000 Lump Sum in 5 years
0 1 2 3 4 5
2005 2006 2007 2008 2009
63.75 63.75 63.75 63.75 63.75
1000.00
IBM Bond Timeline:
109
VB = (INT x PVIFAk,n) + (M x PVIFk,n )
= 63.75(3.9927) + 1000(.6806)
= 254.53 + 680.60 = 935.13
$63.75 Annuity for 5 years $1000 Lump Sum in 5 years
0 1 2 3 4 5
2005 2006 2007 2008 2009
63.75 63.75 63.75 63.75 63.75
1000.00
IBM Bond Timeline:
110
.01 rounding
difference
N I/YR PV PMT FV
–935.12
5 8 ? 63.75 1,000
IBM Bond Timeline:
$63.75 Annuity for 5 years
0 1 2 3 4 5
2005 2006 2007 2008 2009
63.75 63.75 63.75 63.75 63.75
1000.00
$1000 Lump Sum in 5 years
111
Most Bonds Pay Interest Semi-Annually:
e.g. semiannual coupon bond with 5 years
to maturity, 9% annual coupon rate.
Instead of 5 annual payments of $90, the bondholder
receives 10 semiannual payments of $45.
0 1 2 3 4 5
2005 2006 2007 2008 2009
45 45
1000
45 45 45 45 45 45 45 45
112
Compute the value of the bond given that you
require a 10% return on your investment.
Since interest is received every 6 months, we need to use
semiannual compounding
VB = 45( PVIFA10 periods,5%) + 1000(PVIF10 periods, 5%)
10%
2
Semi-Annual
Compounding
Most Bonds Pay Interest Semi-Annually:
0 1 2 3 4 5
2005 2006 2007 2008 2009
45 45
1000
45 45 45 45 45 45 45 45
113
Most Bonds Pay Interest Semi-Annually:
= 45(7.7217) + 1000(.6139)
= 347.48 + 613.90 = 961.38
Compute the value of the bond given that you
require a 10% return on your investment.
Since interest is received every 6 months, we need to use
semiannual compounding
VB = 45( PVIFA10 periods,5%) + 1000(PVIF10 periods, 5%)
0 1 2 3 4 5
2005 2006 2007 2008 2009
45 45
1000
45 45 45 45 45 45 45 45
114
Calculator Solution:
N I/YR PV PMT FV
–961.38
10 5 ? 45 1,000
0 1 2 3 4 5
2005 2006 2007 2008 2009
45 45
1000
45 45 45 45 45 45 45 45
Yield to Maturity
• If an investor purchases a 6.375% annual coupon
bond today for $966.25 and holds it until maturity
(5 years), what is the expected annual rate of
return ?
115
-966.25
??
0 1 2 3 4 5
2005 2006 2007 2008 2009
63.75 63.75 63.75 63.75 63.75
1000.00
+ ??
966.25
Yield to Maturity
116
VB = 63.75(PVIFA5, x%) + 1000(PVIF5,x%)
Solve by trial and error.
• If an investor purchases a 6.375% annual coupon
bond today for $966.25 and holds it until maturity
(5 years), what is the expected annual rate of
return ?
-966.25
??
0 1 2 3 4 5
2005 2006 2007 2008 2009
63.75 63.75 63.75 63.75 63.75
1000.00
+ ??
966.25
Yield to Maturity
7.203%
117
Calculator Solution:
N I/YR PV PMT FV
5 ? -966.25 63.75 1,000
-966.25
0 1 2 3 4 5
2005 2006 2007 2008 2009
63.75 63.75 63.75 63.75 63.75
1000.00
Yield to Maturity
118
 If YTM > Coupon Rate bond Sells at a DISCOUNT
 If YTM < Coupon Rate bond Sells at a PREMIUM
-966.25
0 1 2 3 4 5
2005 2006 2007 2008 2009
63.75 63.75 63.75 63.75 63.75
1000.00
Interest Rate Risk
• Bond Prices fluctuate over Time
– As interest rates in the economy change,
required rates on bonds will also change
resulting in changing market prices.
119
Interest
Rates
VB
Interest Rate Risk
120
• Bond Prices fluctuate over Time
– As interest rates in the economy change,
required rates on bonds will also change
resulting in changing market prices.
Interest
Rates
VB
Interest
Rates VB
Valuing Preferred Stock
121
P0 = Value of Preferred Stock
= PV of ALL dividends discounted at investor’s
Required Rate of Return
52 Weeks Yld Vol Net
Hi Lo Stock Sym Div % PE 100s Hi Lo Close Chg
s 42½ 29 QuakerOats OAT 1.14 3.3 24 5067 35 34¼ 34¼ -¾
s 36¼ 25 RJR Nabisco RN .08p ... 12 6263 29¾ 285/8 287/8 -¾
237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8
23¾ ...
7¼ 5½RJR Nab pfC .60 9.4 ... 2248 6½ 6¼ 63/8 -
1/8
0 1 2 3 
P0=23.75 D1=2.31 D2=2.31 D3=2.31 D=2.31
237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8 23¾ ...
Valuing Preferred Stock
122
P0 = + + +···
2.31
(1+ kp)
2.31
(1+ kp)2
2.31
(1+ kp)3

52 Weeks Yld Vol Net
Hi Lo Stock Sym Div % PE 100s Hi Lo Close Chg
s 42½ 29 QuakerOats OAT 1.14 3.3 24 5067 35 34¼ 34¼ -¾
s 36¼ 25 RJR Nabisco RN .08p ... 12 6263 29¾ 285/8 287/8 -¾
237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8
23¾ ...
7¼ 5½RJR Nab pfC .60 9.4 ... 2248 6½ 6¼ 63/8 -
1/8
0 1 2 3 
P0=23.75 D1=2.31 D2=2.31 D3=2.31 D=2.31
237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8 23¾ ...
Valuing Preferred Stock
123
P0 =
Dp
kp
=
2.31
.10 = $23.10
P0 = + + +···
2.31
(1+ kp)
2.31
(1+ kp )2
2.31
(1+ kp )3

52 Weeks Yld Vol Net
Hi Lo Stock Sym Div % PE 100s Hi Lo Close Chg
s 42½ 29 QuakerOats OAT 1.14 3.3 24 5067 35 34¼ 34¼ -¾
s 36¼ 25 RJR Nabisco RN .08p ... 12 6263 29¾ 285/8 287/8 -¾
237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8
23¾ ...
7¼ 5½RJR Nab pfC .60 9.4 ... 2248 6½ 6¼ 63/8 -
1/8
0 1 2 3 
P0=23.75 D1=2.31 D2=2.31 D3=2.31 D=2.31
237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8 23¾ ...
Valuing Individual Shares of Common
Stock
124
P0 = PV of ALL expected dividends discounted at investor’s
Required Rate of Return
Not like Preferred Stock since D0 = D1 = D2 = D3 = DN , therefore the cash
flows are no longer an annuity.
P0 = + + +···
D1
(1+ ks )
D2
(1+ ks )2
D3
(1+ ks )3
D1 D2 D3
P0 D
0 1 2 3 
Valuing Individual Shares of Common
Stock
125
P0 = PV of ALL expected dividends discounted at investor’s
Required Rate of Return
Investors do not know the values of
D1, D2, .... , DN. The future dividends must be
estimated.
D1 D2 D3
P0 D
0 1 2 3 
P0 = + + +···
D1
(1+ ks )
D2
(1+ ks )2
D3
(1+ ks )3
Constant Growth Dividend Model
126
Assume that dividends grow at a constant rate (g).
D1=D0 (1+g)
D0
D2=D0 (1+g)2D3=D0 (1+g)3 D=D0 (1+g)
0 1 2 3 
Constant Growth Dividend Model
127
Requires ks
> g
Reduces to:
P0 = + + + ···
+
D0 (1+ g)
(1+ ks )
D0 (1+ g)2
(1+ ks )2
D0 (1+ g)3
(1+ ks )3 
P0 = =
D0(1+g)
ks – g
D1
ks – g
Assume that dividends grow at a constant rate (g).
D1=D0 (1+g)
D0
D2=D0 (1+g)2D3=D0 (1+g)3 D=D0 (1+g)
0 1 2 3 
Constant Growth Dividend Model
128
P0 = = $30.50
1.14(1+.07)
.11 – .07
What is the value of a share of common stock if the
most recently paid dividend (D0) was $1.14 per share and
dividends are expected to grow at a rate of 7%?
Assume that you require a rate of return of 11%
on this investment.
P0 = =
D0(1+g)
ks – g
D1
ks – g
Valuing Total Stockholders’ Equity
• The Investor’s Cash Flow DCF Model
– Investor’s Cash Flow is the amount that is
“free” to be distributed to debt holders,
preferred stockholders and common
stockholders.
– Cash remaining after accounting for
expenses, taxes, capital expenditures and
new net working capital.
129
130
Calculating Intrinsic Value
Coca Cola Example
131
ECP Homework
1. Indicate which of the following bonds seems to be reported incorrectly with respect to discount, premium,
or par and explain why.
Bond Price Coupon Rate Yield to Maturity
A 105 9% 8%
B 100 6% 6%
C 101 5% 4.5%
D 102 0% 5%
2. What is the price of a ten-year $1,000 par-value bond with a 9% annual coupon rate and a 10% annual
yield to maturity assuming semi-annual coupon payments?
3. You have an issue of preferred stock that is paying a $3 annual dividend. A fair rate of return on this
investment is calculated to be 13.5%. What is the value of this preferred stock issue?
4. Total assets of a firm are $1,000,000 and the total liabilities are $400,000. 500,000 shares of common
stock have been issued and 250,000 shares are outstanding. The market price of the stock is $15 and net
income for the past year was $150,000.
a.. Calculate the book value of the firm.
b. Calculate the book value per share.
c. Calculate the P/E ratio.
5. A firm’s common stock is currently selling for $12.50 per share. The required rate of return is 9% and the
company will pay an annual dividend of $.50 per share one year from now which will grow at a constant rate
for the next several years. What is the growth rate?

More Related Content

Similar to the cost of capital all detail about WACC.

BlueBookAcademy.com - Value companies using Discounted Cash Flow Valuation
BlueBookAcademy.com - Value companies using Discounted Cash Flow ValuationBlueBookAcademy.com - Value companies using Discounted Cash Flow Valuation
BlueBookAcademy.com - Value companies using Discounted Cash Flow Valuationbluebookacademy
 
Chapter 12 Cost Of Capital
Chapter 12 Cost Of CapitalChapter 12 Cost Of Capital
Chapter 12 Cost Of CapitalAlamgir Alwani
 
3- Cost of Capital-update.pptx
3- Cost of Capital-update.pptx3- Cost of Capital-update.pptx
3- Cost of Capital-update.pptxMohamedKamal236980
 
Cost of capital
Cost of capitalCost of capital
Cost of capitalViquaco
 
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docxSheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docxlesleyryder69361
 
Ch. 6ed Cost of Capital.ppt.ppt
Ch. 6ed Cost of Capital.ppt.pptCh. 6ed Cost of Capital.ppt.ppt
Ch. 6ed Cost of Capital.ppt.pptHudaElMaghraby1
 
FM CH 4.pptx best presentation for financial management
FM CH 4.pptx best presentation for financial managementFM CH 4.pptx best presentation for financial management
FM CH 4.pptx best presentation for financial managementKalkaye
 
Costofcapital 100114234212-phpapp02
Costofcapital 100114234212-phpapp02Costofcapital 100114234212-phpapp02
Costofcapital 100114234212-phpapp02yaser_alakhras
 
Risk & capital budgeting
Risk & capital  budgetingRisk & capital  budgeting
Risk & capital budgetinglubnasadiyah
 
Capital structure theories 1
Capital structure theories  1Capital structure theories  1
Capital structure theories 1vijay lahri
 
Module-5-Assigned-Problems (1).pdf
Module-5-Assigned-Problems (1).pdfModule-5-Assigned-Problems (1).pdf
Module-5-Assigned-Problems (1).pdfRiaBago
 
The Cost of Capital/abshor.marantika/Aulia Riskafina-Jeremy Haposan-Rizki Bhi...
The Cost of Capital/abshor.marantika/Aulia Riskafina-Jeremy Haposan-Rizki Bhi...The Cost of Capital/abshor.marantika/Aulia Riskafina-Jeremy Haposan-Rizki Bhi...
The Cost of Capital/abshor.marantika/Aulia Riskafina-Jeremy Haposan-Rizki Bhi...Aulia Riskafina Kusuma
 
adavanced financial management materials
adavanced financial management materialsadavanced financial management materials
adavanced financial management materialsSunil Kumar
 
Bba 2204 fin mgt week 9 cost of capital
Bba 2204 fin mgt week 9 cost of capitalBba 2204 fin mgt week 9 cost of capital
Bba 2204 fin mgt week 9 cost of capitalStephen Ong
 
Fin 2732 cost of capital
Fin 2732 cost of capitalFin 2732 cost of capital
Fin 2732 cost of capitalYashGupta744
 
capital sturcture.ppt
capital sturcture.pptcapital sturcture.ppt
capital sturcture.pptMIshtiaq6
 

Similar to the cost of capital all detail about WACC. (20)

BlueBookAcademy.com - Value companies using Discounted Cash Flow Valuation
BlueBookAcademy.com - Value companies using Discounted Cash Flow ValuationBlueBookAcademy.com - Value companies using Discounted Cash Flow Valuation
BlueBookAcademy.com - Value companies using Discounted Cash Flow Valuation
 
Cost of Capital
Cost of CapitalCost of Capital
Cost of Capital
 
Chapter 12 Cost Of Capital
Chapter 12 Cost Of CapitalChapter 12 Cost Of Capital
Chapter 12 Cost Of Capital
 
3- Cost of Capital-update.pptx
3- Cost of Capital-update.pptx3- Cost of Capital-update.pptx
3- Cost of Capital-update.pptx
 
Cost of capital
Cost of capitalCost of capital
Cost of capital
 
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docxSheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
 
Ch14
Ch14Ch14
Ch14
 
Ch. 6ed Cost of Capital.ppt.ppt
Ch. 6ed Cost of Capital.ppt.pptCh. 6ed Cost of Capital.ppt.ppt
Ch. 6ed Cost of Capital.ppt.ppt
 
FM CH 4.pptx best presentation for financial management
FM CH 4.pptx best presentation for financial managementFM CH 4.pptx best presentation for financial management
FM CH 4.pptx best presentation for financial management
 
Costofcapital 100114234212-phpapp02
Costofcapital 100114234212-phpapp02Costofcapital 100114234212-phpapp02
Costofcapital 100114234212-phpapp02
 
Cost Of Capital
Cost Of CapitalCost Of Capital
Cost Of Capital
 
Risk & capital budgeting
Risk & capital  budgetingRisk & capital  budgeting
Risk & capital budgeting
 
Capital structure theories 1
Capital structure theories  1Capital structure theories  1
Capital structure theories 1
 
MBA 8480 - Valuation Principles
MBA 8480 - Valuation PrinciplesMBA 8480 - Valuation Principles
MBA 8480 - Valuation Principles
 
Module-5-Assigned-Problems (1).pdf
Module-5-Assigned-Problems (1).pdfModule-5-Assigned-Problems (1).pdf
Module-5-Assigned-Problems (1).pdf
 
The Cost of Capital/abshor.marantika/Aulia Riskafina-Jeremy Haposan-Rizki Bhi...
The Cost of Capital/abshor.marantika/Aulia Riskafina-Jeremy Haposan-Rizki Bhi...The Cost of Capital/abshor.marantika/Aulia Riskafina-Jeremy Haposan-Rizki Bhi...
The Cost of Capital/abshor.marantika/Aulia Riskafina-Jeremy Haposan-Rizki Bhi...
 
adavanced financial management materials
adavanced financial management materialsadavanced financial management materials
adavanced financial management materials
 
Bba 2204 fin mgt week 9 cost of capital
Bba 2204 fin mgt week 9 cost of capitalBba 2204 fin mgt week 9 cost of capital
Bba 2204 fin mgt week 9 cost of capital
 
Fin 2732 cost of capital
Fin 2732 cost of capitalFin 2732 cost of capital
Fin 2732 cost of capital
 
capital sturcture.ppt
capital sturcture.pptcapital sturcture.ppt
capital sturcture.ppt
 

Recently uploaded

Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...Pooja Nehwal
 
Interimreport1 January–31 March2024 Elo Mutual Pension Insurance Company
Interimreport1 January–31 March2024 Elo Mutual Pension Insurance CompanyInterimreport1 January–31 March2024 Elo Mutual Pension Insurance Company
Interimreport1 January–31 March2024 Elo Mutual Pension Insurance CompanyTyöeläkeyhtiö Elo
 
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
The Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfThe Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfGale Pooley
 
The Economic History of the U.S. Lecture 20.pdf
The Economic History of the U.S. Lecture 20.pdfThe Economic History of the U.S. Lecture 20.pdf
The Economic History of the U.S. Lecture 20.pdfGale Pooley
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...makika9823
 
Solution Manual for Principles of Corporate Finance 14th Edition by Richard B...
Solution Manual for Principles of Corporate Finance 14th Edition by Richard B...Solution Manual for Principles of Corporate Finance 14th Edition by Richard B...
Solution Manual for Principles of Corporate Finance 14th Edition by Richard B...ssifa0344
 
The Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdfThe Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdfGale Pooley
 
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...ssifa0344
 
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service AizawlVip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawlmakika9823
 
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...Pooja Nehwal
 
Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]Commonwealth
 
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...ssifa0344
 
The Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdfThe Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdfGale Pooley
 
Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex
 
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdf20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdfAdnet Communications
 
05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx
05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx
05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptxFinTech Belgium
 
Lundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdfLundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdfAdnet Communications
 

Recently uploaded (20)

Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
Independent Call Girl Number in Kurla Mumbai📲 Pooja Nehwal 9892124323 💞 Full ...
 
Veritas Interim Report 1 January–31 March 2024
Veritas Interim Report 1 January–31 March 2024Veritas Interim Report 1 January–31 March 2024
Veritas Interim Report 1 January–31 March 2024
 
Interimreport1 January–31 March2024 Elo Mutual Pension Insurance Company
Interimreport1 January–31 March2024 Elo Mutual Pension Insurance CompanyInterimreport1 January–31 March2024 Elo Mutual Pension Insurance Company
Interimreport1 January–31 March2024 Elo Mutual Pension Insurance Company
 
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Maya 7001305949 Independent Escort Service Nashik
 
The Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfThe Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdf
 
The Economic History of the U.S. Lecture 20.pdf
The Economic History of the U.S. Lecture 20.pdfThe Economic History of the U.S. Lecture 20.pdf
The Economic History of the U.S. Lecture 20.pdf
 
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
Independent Lucknow Call Girls 8923113531WhatsApp Lucknow Call Girls make you...
 
Solution Manual for Principles of Corporate Finance 14th Edition by Richard B...
Solution Manual for Principles of Corporate Finance 14th Edition by Richard B...Solution Manual for Principles of Corporate Finance 14th Edition by Richard B...
Solution Manual for Principles of Corporate Finance 14th Edition by Richard B...
 
The Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdfThe Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdf
 
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
 
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service AizawlVip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
Vip B Aizawl Call Girls #9907093804 Contact Number Escorts Service Aizawl
 
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
Dharavi Russian callg Girls, { 09892124323 } || Call Girl In Mumbai ...
 
Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]
 
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
TEST BANK For Corporate Finance, 13th Edition By Stephen Ross, Randolph Weste...
 
The Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdfThe Economic History of the U.S. Lecture 19.pdf
The Economic History of the U.S. Lecture 19.pdf
 
Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024
 
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
 
20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdf20240417-Calibre-April-2024-Investor-Presentation.pdf
20240417-Calibre-April-2024-Investor-Presentation.pdf
 
05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx
05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx
05_Annelore Lenoir_Docbyte_MeetupDora&Cybersecurity.pptx
 
Lundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdfLundin Gold April 2024 Corporate Presentation v4.pdf
Lundin Gold April 2024 Corporate Presentation v4.pdf
 

the cost of capital all detail about WACC.

  • 2. Learning Goals • Sources of capital • Cost of each type of funding • Calculation of the weighted average cost of capital (WACC) • Construction and use of the marginal cost of capital schedule (MCC) 2
  • 3. Factors Affecting the Cost of Capital • General Economic Conditions – Affect interest rates • Market Conditions – Affect risk premiums • Operating Decisions – Affect business risk • Financial Decisions – Affect financial risk • Amount of Financing – Affect flotation costs and market price of security 3
  • 4. • Compute the cost of each source of capital • Determine percentage of each source of capital in the optimal capital structure • Calculate Weighted Average Cost of Capital (WACC) 4 Weighted Cost of Capital Model
  • 5. • Required rate of return for creditors • Same cost found in Chapter 12 as yield to maturity on bonds (kd). • e.g. Suppose that a company issues bonds with a before tax cost of 10%. • Since interest payments are tax deductible, the true cost of the debt is the after tax cost. • If the company’s tax rate (state and federal combined) is 40%, the after tax cost of debt • AT kd = 10%(1-.4) = 6%. 5 1. Compute Cost of Debt
  • 6. • Cost to raise a dollar of preferred stock. 6 11.90% $5.00 $42.00 kp = = The cost of preferred stock: Example: You can issue preferred stock for a net price of $42 and the preferred stock pays a $5 dividend. Dividend (Dp) Market Price (PP) - F Required rate kp = 2. Compute Cost Preferred Stock
  • 7. • Two Types of Common Equity Financing – Retained Earnings (internal common equity) – Issuing new shares of common stock (external common equity) 7 3. Compute Cost of Common Equity
  • 8. • Cost of Internal Common Equity – Management should retain earnings only if they earn as much as stockholder’s next best investment opportunity of the same risk. – Cost of Internal Equity = opportunity cost of common stockholders’ funds. – Two methods to determine • Dividend Growth Model • Capital Asset Pricing Model 8 3. Compute Cost of Common Equity
  • 9. • Cost of Internal Common Stock Equity – Dividend Growth Model 9 D1 P0 kS = + g 3. Compute Cost of Common Equity
  • 10. • Cost of Internal Common Stock Equity – Dividend Growth Model 10 Example: The market price of a share of common stock is $60. The dividend just paid is $3, and the expected growth rate is 10%. 3. Compute Cost of Common Equity D1 P0 kS = + g
  • 11. • Cost of Internal Common Stock Equity – Dividend Growth Model 11 3(1+0.10) 60 kS = + .10 =.155 = 15.5% Example: The market price of a share of common stock is $60. The dividend just paid is $3, and the expected growth rate is 10%. 3. Compute Cost of Common Equity D1 P0 kS = + g
  • 12. • Cost of Internal Common Stock Equity – Capital Asset Pricing Model (Chapter 7) 12 kS = kRF + (kM – kRF) 3. Compute Cost of Common Equity
  • 13. • Cost of Internal Common Stock Equity – Capital Asset Pricing Model (Chapter 7) 13 Example: The estimated Beta of a stock is 1.2. The risk-free rate is 5% and the expected market return is 13%. 3. Compute Cost of Common Equity kS = kRF + (kM – kRF)
  • 14. • Cost of Internal Common Stock Equity – Capital Asset Pricing Model (Chapter 7) 14 kS = 5% + 1.2(13% – 5%) 14.6% 3. Compute Cost of Common Equity = Example: The estimated Beta of a stock is 1.2. The risk-free rate is 5% and the expected market return is 13%. kS = kRF + (kM – kRF)
  • 15. • Cost of New Common Stock – Must adjust the Dividend Growth Model equation for floatation costs of the new common shares. 15 3. Compute Cost of Common Equity D1 P0 - F kn = + g
  • 16. • Cost of New Common Stock – Must adjust the Dividend Growth Model equation for floatation costs of the new common shares. 16 3. Compute Cost of Common Equity Example: If additional shares are issued floatation costs will be 12%. D0 = $3.00 and estimated growth is 10%, Price is $60 as before. D1 P0 - F kn = + g
  • 17. • Cost of New Common Stock – Must adjust the Dividend Growth Model equation for floatation costs of the new common shares. 17 3. Compute Cost of Common Equity 3(1+0.10) 52.80 kn = + .10 = .1625 = D1 P0 - F kn = + g 16.25% Example: If additional shares are issued floatation costs will be 12%. D0 = $3.00 and estimated growth is 10%, Price is $60 as before.
  • 18. 18 Weighted Average Cost of Capital Gallagher Corporation estimates the following costs for each component in its capital structure: Gallagher’s tax rate is 40% Source of Capital Cost Bonds kd = 10% Preferred Stock kp = 11.9% Common Stock Retained Earnings ks = 15% New Shares kn = 16.25%
  • 19. 19 Weighted Average Cost of Capital  If using retained earnings to finance the common stock portion the capital structure: WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)
  • 20. 20 If using retained earnings to finance the common stock portion the capital structure: Weighted Average Cost of Capital  Assume that Gallagher’s desired capital structure is 40% debt, 10% preferred and 50% common equity. WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)
  • 21. 21 Weighted Average Cost of Capital WACC = .40 x 10% (1-.4) + .10 x 11.9% + .50 x 15% = 11.09% WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks) If using retained earnings to finance the common stock portion the capital structure:  Assume that Gallagher’s desired capital structure is 40% debt, 10% preferred and 50% common equity.
  • 22. 22 If using a new equity issue to finance the common stock portion the capital structure: Weighted Average Cost of Capital WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)
  • 23. 23 Weighted Average Cost of Capital WACC = .40 x 10% (1-.4) + .10 x 11.9% + .50 x 16.25% = 11.72% If using a new equity issue to finance the common stock portion the capital structure: WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)
  • 24. Marginal Cost of Capital • Gallagher’s weighted average cost will change if one component cost of capital changes. • This may occur when a firm raises a particularly large amount of capital such that investors think that the firm is riskier. • The WACC of the next dollar of capital raised in called the marginal cost of capital (MCC). 24
  • 25. Graphing the MCC curve • Assume now that Gallagher Corporation has $100,000 in retained earnings with which to finance its capital budget. • We can calculate the point at which they will need to issue new equity since we know that Gallagher’s desired capital structure calls for 50% common equity. 25
  • 26. Graphing the MCC curve • Assume now that Gallagher Corporation has $100,000 in retained earnings with which to finance its capital budget. • We can calculate the point at which they will need to issue new equity since we know that Gallagher’s desired capital structure calls for 50% common equity. 26 Breakpoint = Available Retained Earnings Percentage of Total
  • 27. Graphing the MCC curve 27 Breakpoint = ($100,000)/.5 = $200,000
  • 28. Making Decisions Using MCC 28 Weighted Cost of Capital Total Financing 10% 11% 12% 13% 0 100,000 200,000 300,000 400,000 Marginal weighted cost of capital curve: Using internal common equity Using new common equity 11.72% 11.09%
  • 29. Making Decisions Using MCC • Graph MIRRs of potential projects 29 Weighted Cost of Capital Total Financing 9% 10% 11% 12% 0 100,000 200,000 300,000 400,000 Marginal weighted cost of capital curve: Project 1 MIRR = 12.4% Project 2 MIRR = 12.1% Project 3 MIRR = 11.5%
  • 30. Making Decisions Using MCC • Graph IRRs of potential projects 30 Weighted Cost of Capital Total Financing 9% 10% 11% 12% 0 100,000 200,000 300,000 400,000 Marginal weighted cost of capital curve: Project 1 IRR = 12.4% Project 2 IRR = 12.1% Project 3 IRR = 11.5% Graph MCC Curve 11.09% 11.72%
  • 31. Making Decisions Using MCC • Graph IRRs of potential projects • Graph MCC Curve 31 Weighted Cost of Capital Total Financing 9% 10% 11% 12% 0 100,000 200,000 300,000 400,000 Marginal weighted cost of capital curve: Project 1 IRR = 12.4% Project 2 IRR = 12.1% Project 3 IRR = 11.5% Accept Projects #1 & #2  Choose projects whose IRR is above the weighted marginal cost of capital 11.72% 11.09%
  • 32. 32 Answer the following questions and do the following problems and include them in you ECP Notes. If the cost of new common equity is higher than the cost of internal equity, why would a firm choose to issue new common stock? Why is it important to use a firm’s MCC and not a firm’s initial WACC to evaluate investments? Calculate the AT kd, ks, kn for the following information: Loan rates for this firm = 9% Growth rate of dividends = 4% Tax rate = 30% Common Dividends at t1 = $ 4.00 Price of Common Stock = $35.00 Flotation costs = 6% Your firm’s ks is 10%, the cost of debt is 6% before taxes, and the tax rate is 40%. Given the following balance sheet, calculate the firm’s after tax WACC: Total assets = $25,000 Total debt = 15,000 Total equity = 10,000
  • 33. 33 Your firm is in the 30% tax bracket with a before-tax required rate of return on its equity of 13% and on its debt of 10%. If the firm uses 60% equity and 40% debt financing, calculate its after-tax WACC. Would a firm use WACC or MCC to identify which new capital budgeting projects should be selected? Why? A firm's before tax cost of debt on any new issue is 9%; the cost to issue new preferred stock is 8%. This appears to conflict with the risk/return relationship. How can this pricing exist? What determines whether to use the dividend growth model approach or the CAPM approach to calculate the cost of equity?
  • 35. • The capital budgeting process. • Calculation of payback, NPV, IRR, and MIRR for proposed projects. • Capital rationing. • Measurement of risk in capital budgeting and how to deal with it. Learning Objectives 2
  • 36. • Capital Budgeting is the process of evaluating proposed investment projects for a firm. • Managers must determine which projects are acceptable and must rank mutually exclusive projects by order of desirability to the firm. The Capital Budgeting Process 3
  • 37. Four methods: • Payback Period – years to recoup the initial investment • Net Present Value (NPV) – change in value of firm if project is under taken • Internal Rate of Return (IRR) – projected percent rate of return project will earn • Modified Internal Rate of Return (MIRR) The Accept/Reject Decision 4
  • 38. • Consider Projects A and B that have the following expected cashflows? Capital Budgeting Methods 5 P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000
  • 39. • What is the payback for Project A? Capital Budgeting Methods 6 P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000
  • 40. • What is the payback for Project A? Capital Budgeting Methods 0 1 2 3 4 3,500 -6,500 3,500 -3,000 3,500 +500 3,500 (10,000) Cumulative CF 7 P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000
  • 41. • What is the payback for Project A? Capital Budgeting Methods Payback in 2.9 years P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000 8 0 1 2 3 4 3,500 -6,500 3,500 -3,000 3,500 +500 3,500 (10,000) Cumulative CF 0 1 2 3 4 3,500 -6,500 3,500 -3,000 3,500 +500 3,500 (10,000) Cumulative CF
  • 42. • What is the payback for Project B? Capital Budgeting Methods 9 0 1 2 3 4 500 500 4,600 10,000 (10,000) P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000
  • 43. Payback in 3.4 years • What is the payback for Project B? Capital Budgeting Methods 10 0 1 2 3 4 500 -9,500 500 -9,000 4,600 -4,400 10,000 +5,600 (10,000) Cumulative CF P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000
  • 44. • Accept project if payback is less than the company’s predetermined maximum. • If company has determined that it requires payback in three years or less, then you would: – accept Project A – reject Project B Payback Decision Rule 11
  • 45. • Present Value of all costs and benefits (measured in terms of incremental cash flows) of a project. • Concept is similar to Discounted Cashflow model for valuing securities but subtracts the cost of the project. Capital Budgeting Methods Net Present Value 12
  • 46. • Present Value of all costs and benefits (measured in terms of incremental cash flows) of a project. • Concept is similar to Discounted Cashflow model for valuing securities but subtracts of cost of project. Capital Budgeting Methods Net Present Value NPV = PV of Inflows - Initial Investment NPV = + + – Initial Investment CF1 (1+ k)1 CF2 (1+ k)2 …. CFn (1+ k )n 13
  • 47. What is the NPV for Project B? 14 P R O J E C T Time A B 0 (10,000) (10,000) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000 k=10% 0 1 2 3 4 500 500 4,600 10,000 (10,000) Capital Budgeting Methods
  • 48. 455 $500 (1.10)1 What is the NPV for Project B? 15 P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000 k=10% 0 1 2 3 4 500 500 4,600 10,000 (10,000) Capital Budgeting Methods
  • 49. 413 $500 (1.10) 2 What is the NPV for Project B? 16 P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000 455 k=10% 0 1 2 3 4 500 500 4,600 10,000 (10,000) Capital Budgeting Methods
  • 50. 3,456 $4,600 (1.10) 3 What is the NPV for Project B? 17 P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000 413 $500 (1.10) 2 455 k=10% 0 1 2 3 4 500 500 4,600 10,000 (10,000) Capital Budgeting Methods
  • 51. 6,830 $10,000 (1.10) 4 What is the NPV for Project B? 18 P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000 3,456 $4,600 (1.10) 3 413 $500 (1.10) 2 455 k=10% 0 1 2 3 4 500 500 4,600 10,000 (10,000) Capital Budgeting Methods
  • 52. $11,154 What is the NPV for Project B? 19 P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000 6,830 3,456 413 455 k=10% 0 1 2 3 4 500 500 4,600 10,000 (10,000) Capital Budgeting Methods
  • 53. PV Benefits > PV Costs $11,154 > $ 10,000 What is the NPV for Project B? 20 P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000 $11,154 6,830 3,456 413 455 k=10% 0 1 2 3 4 500 500 4,600 10,000 (10,000)
  • 54. NPV > $0 $1,154 > $0 - $10,000 = $1,154 = NPV What is the NPV for Project B? 21 P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000 PV Benefits > PV Costs $11,154 > $ 10,000 $11,154 6,830 3,456 413 455 k=10% 0 1 2 3 4 500 500 4,600 10,000 (10,000)
  • 55. 22 • Additional Keys used to enter Cash Flows and compute the Net Present Value (NPV) Financial Calculator:
  • 56. NPV IRR P/YR CF N I/Y PV PMT FV Key used to enter expected cash flows in order of their receipt. Note: the initial investment (CF0) must be entered as a negative number since it is an outflow. 23 • Additional Keys used to enter Cash Flows and compute the Net Present Value (NPV) Financial Calculator:
  • 57. NPV IRR P/YR CF N I/Y PV PMT FV • Additional Keys used to enter Cash Flows and compute the Net Present Value (NPV) Financial Calculator: Key used to calculate the net present value of the cashflows that have been entered in the calculator. 24
  • 58. NPV IRR P/YR CF N I/Y PV PMT FV • Additional Keys used to enter Cash Flows and compute the Net Present Value (NPV) Financial Calculator: Key used to calculate the internal rate of return for the cashflows that have been entered in the calculator. 25
  • 59. Calculate the NPV for Project B with calculator. 26 NPV IRR P/YR CF N I/Y PV PMT FV P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000
  • 60. NPV IRR P/YR CF N I/Y PV PMT FV Calculate the NPV for Project B with calculator. Keystrokes for TI BAII PLUS: CF0 = -10,000 27 CF 10000 +/- ENTER
  • 61. NPV IRR P/YR CF N I/Y PV PMT FV Calculate the NPV for Project B with calculator. C01 = 500 500 ENTER 28 CF 10000 +/- ENTER Keystrokes for TI BAII PLUS:
  • 62. NPV IRR P/YR CF N I/Y PV PMT FV Calculate the NPV for Project B with calculator. F01 = 2 F stands for “frequency”. Enter 2 since there are two adjacent payments of 500 in periods 1 and 2. 29 2 ENTER 500 ENTER CF 10000 +/- ENTER Keystrokes for TI BAII PLUS:
  • 63. NPV IRR P/YR CF N I/Y PV PMT FV Calculate the NPV for Project B with calculator. C02 = 4600 4600 ENTER 30 2 ENTER 500 ENTER CF 10000 +/- ENTER Keystrokes for TI BAII PLUS:
  • 64. NPV IRR P/YR CF N I/Y PV PMT FV Calculate the NPV for Project B with calculator. F02 = 1 1 ENTER 31 4600 ENTER 2 ENTER 500 ENTER CF 10000 +/- ENTER Keystrokes for TI BAII PLUS:
  • 65. NPV IRR P/YR CF N I/Y PV PMT FV Calculate the NPV for Project B with calculator. C03 = 10000 10000 ENTER 32 1 ENTER 4600 ENTER 2 ENTER 500 ENTER CF 10000 +/- ENTER Keystrokes for TI BAII PLUS:
  • 66. NPV IRR P/YR CF N I/Y PV PMT FV Calculate the NPV for Project B with calculator. F03 = 1 1 ENTER 33 10000 ENTER 1 ENTER 4600 ENTER 2 ENTER 500 ENTER CF 10000 +/- ENTER Keystrokes for TI BAII PLUS:
  • 67. NPV IRR P/YR CF N I/Y PV PMT FV Calculate the NPV for Project B with calculator. I = 10 k = 10% 34 Keystrokes for TI BAII PLUS: 10 ENTER NPV
  • 68. NPV IRR P/YR CF N I/Y PV PMT FV Calculate the NPV for Project B with calculator. NPV = 1,153.95 CPT The net present value of Project B = $1,154 as we calculated previously. 35 10 ENTER NPV Keystrokes for TI BAII PLUS:
  • 69. • Accept the project if the NPV is greater than or equal to 0. Example: NPVA = $1,095 NPVB = $1,154 NPV Decision Rule > 0 > 0 Accept Accept •If projects are independent, accept both projects. •If projects are mutually exclusive, accept the project with the higher NPV. 36
  • 70. • IRR (Internal Rate of Return) – IRR is the discount rate that forces the NPV to equal zero. – It is the rate of return on the project given its initial investment and future cash flows. • The IRR is the rate earned only if all CFs are reinvested at the IRR rate. Capital Budgeting Methods 37
  • 71. Calculate the IRR for Project B with calculator. 39 NPV IRR P/YR CF N I/Y PV PMT FV P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000
  • 72. Enter CFs as for NPV NPV IRR P/YR CF N I/Y PV PMT FV Calculate the IRR for Project B with calculator. IRR = 13.5% 40 P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000 IRR CPT
  • 73. • Accept the project if the IRR is greater than or equal to the required rate of return (k). • Reject the project if the IRR is less than the required rate of return (k). Example: k = 10% IRRA = 14.96% IRRB = 13.50% IRR Decision Rule > 10% > 10% Accept Accept 41
  • 74. • MIRR (Modified Internal Rate of Return) – This is the discount rate which causes the project’s PV of the outflows to equal the project’s TV (terminal value) of the inflows. – Assumes cash inflows are reinvested at k, the safe re- investment rate. – MIRR avoids the problem of multiple IRRs. – We accept if MIRR > the required rate of return. Capital Budgeting Methods PVoutflow = TVinflows (1 + MIRR)n 42
  • 75. What is the MIRR for Project B? P R O J E C T Time A B 0 (10,000.) (10,000.) 1 3,500 500 2 3,500 500 3 3,500 4,600 4 3,500 10,000 Safe =2% 0 1 2 3 4 500 500 4,600 10,000 (10,000) (10,000) 10,000(1.02)0 10,000 4,600(1.02)1 500(1.02)2 500(1.02)3 4,692 520 531 15,743 10,000 = 15,743 (1 + MIRR)4 (10,000)/(1.02)0 MIRR = .12 = 12% 43
  • 76. NPV IRR P/YR CF N I/Y PV PMT FV Calculate the MIRR for Project B with calculator. 10000 ENTER 1 ENTER 1 ENTER 4600 ENTER 2 ENTER 500 ENTER CF 0 +/- ENTER Keystrokes for TI BAII PLUS: Step 1. Calculate NPV using cash inflows 44
  • 77. NPV IRR P/YR CF N I/Y PV PMT FV Calculate the MIRR for Project B with calculator. NPV = 14,544 CPT The net present value of Project B cash inflows = $14,544 (use as PV) 45 2 ENTER NPV Keystrokes for TI BAII PLUS: Step 1. Calculate NPV using cash inflows
  • 78. NPV IRR P/YR CF N I/Y PV PMT FV Calculate the MIRR for Project B with calculator. FV = 15,743 46 Step 2. Calculate FV of cash inflows using previous NPV This is the Terminal Value Calculator Enter: N = 4 I/YR = 2 PV = -14544 PMT= 0 CPT FV = ?
  • 79. NPV IRR P/YR CF N I/Y PV PMT FV Calculate the MIRR for Project B with calculator. MIRR 12.01 47 Step 3. Calculate MIRR using PV of outflows and calculated Terminal Value. Calculator Enter: N = 4 PV = -10000 PMT = 0 FV = 15,743 CPT I/YR = ??
  • 80. • Capital rationing is the practice of placing a dollar limit on the total size of the capital budget. • This practice may not be consistent with maximizing shareholder value but may be necessary for other reasons. • Choose between projects by selecting the combination of projects that yields the highest total NPV without exceeding the capital budget limit. What is capital rationing? 54
  • 81. • Calculate the coefficient of variation of returns of the firm’s asset portfolio with the project and without it. • This can be done by following a five step process. Observe the following example. Measurement of Project Risk 55
  • 82. • Step 1: Find the CV of the Existing Portfolio – Assume Company X has an existing rate of return of 6% and standard deviation of 2%. Measurement of Project Risk 56 Standard Deviation Mean, or expected value CV= = .02 .06 = .3333, or 33.33%
  • 83. • Step 2: Find the Expected return of the New Portfolio (Existing plus Proposed) – Assume the New Project (Y) has an IRR of 5.71% and a Standard Deviation of 2.89% – Assume further that Project Y will account for 10% of X’s overall investment. Measurement of Project Risk 57 (wx x E(Rx)) + (wy x E(Ry)) = (.10 x .0571) + (.90 x .06) = .00571 + .05400 = .05971, or 5.971% E(Rp) =
  • 84. • Step 3: Find the Standard Deviation of the New Portfolio (Existing plus Proposed). – Assume the proposed is uncorrelated with the existing project. rxy = 0 Measurement of Project Risk 58 [wx 2σx 2 + wy 2σy 2 + 2wxwyrxyσxσy]1/2 = [(.102)(.02892) + (.902)(.022) + (2)(.10)(.90)(0.0)(.0289)(02)]1/2 = [(.01)(.000835) + (.81)(.0004) + 0]1/2 = .0182, or 1.82% = [.00000835 + .000324]1/2 = [.00033235]1/2 σp =
  • 85. • Step 4: Find the CV of the New Portfolio (Existing plus Proposed) Measurement of Project Risk 59 Standard Deviation Mean, or expected value CV= = .0182 .05971 = .3048, or 30.48%
  • 86. • Step 5: Compare the CV of the portfolio with and without the Proposed Project. – The difference between the two coefficients of variation is the measure of risk of the capital budgeting project. Measurement of Project Risk 60 CV without Y Change in CV CV with Y 33.33% -2.85 30.48%
  • 87. • Firms often compensate for risk by adjusting the discount rate used to calculate NPV. – Higher risk, use a higher discount rate. – Lower risk, use a lower discount rate • The risk adjusted discount rate (RADR) can also be used as a risk adjusted hurdle rate for IRR comparisons. Comparing risky projects using risk adjusted discount rates (RADRs) 61
  • 88. • Non-simple projects have one or more negative future cash flows after the initial investment. Non-simple Projects 62
  • 89. • How would a negative cash flow in year 4 affect Project Z’s NPV? Non-simple projects Project Z should be rejected in this case. 63 8,336 -4,098 3,757 4,132 4,545 k=10% 0 1 2 3 4 5,000 5,000 5,000 -6,000 (10,000) - $10,000 = -$1,664 NPV
  • 90. • Mutually exclusive projects with unequal project lives can be compared by using two methods: – Replacement Chain – Equivalent Annual Annuity Mutually Exclusive Projects With Unequal Lives 68
  • 91. • Assumes each project can be replicated until a common period of time has passed, allowing the projects to be compared. • Example – Project Cheap Talk has a 3-year life, with an NPV of $4,424. – Project Rolles Voice has a 12-year life, with an NPV of $4,510. Replacement Chain Approach 69
  • 92. • Project Cheap Talk could be repeated four times during the life of Project Rolles Voice. • The NPVs of Project Cheap Talk, in years t3, t6, and t9, are discounted back to year t0. Replacement Chain Approach 70
  • 93. • The NPVs of Project Cheap Talk, in years t3, t6, and t9, are discounted back to year t0, which results in an NPV of $12,121. Replacement Chain Approach 3,324 12,121 2,497 1,876 0 3 6 9 4,424 4,424 4,424 4,424 k=10% 71
  • 94. • Amount of the annuity payment that would equal the same NPV as the actual future cash flows of a project. • EAA = NPV PVIFAk,n Equivalent Annual Annuity 72
  • 95. Equivalent Annual Annuity 73 Project Rolles Voice $4,510 ((1-(1.1)-12) / .1) = $661.90 • Project Cheap Talk $4,244 ((1-(1.1)-3) / .1) = $1778.96
  • 96. ECP Homework 1. The following net cash flows are projected for two separate projects. Your required rate of return is 12%. Year Project A Project B 0 ($150,000) ($400,000) 1 $30,000 $100,000 2 $30,000 $100,000 3 $30,000 $100,000 4 $30,000 $100,000 5 $30,000 $100,000 6 $30,000 $100,000 a. Calculate the payback period for each project. b. Calculate the NPV of each project. c. Calculate the MIRR of each project. d. Which project(s) would you accept and why?
  • 97. 2. What is meant by risk adjusted discount rates? 3. Explain why the NPV method of capital budgeting is preferable over the payback method. 4. A firm has a net present value of zero. Should the project be rejected? Explain. 5. You have estimated the MIRR for a new project with the following probabilities: Possible MIRR Value Probability 4% 5% 7% 15% 10% 15% 11% 50% 14% 15% a. Calculate the expected MIRR of the project. b. Calculate the standard deviation of the project. c. Calculate the coefficient of variation. d. Calculate the expected MIRR of the new portfolio with the new project. The current portfolio has an expected MIRR of 9% and a standard deviation of 3% and will represent 60% of the total portfolio. ECP Homework
  • 99. Learning Objectives • Understand the importance of business valuation. • Understand the importance of stock and bond valuation. • Learn to compute the value and yield to maturity of bonds. • Learn to compute the value and expected yield on preferred stock and common stock. • Learn to compute the value of a complete business. 99
  • 100. General Valuation Model • To develop a general model for valuing a business, we consider three factors that affect future earnings: – Size of cash flows – Timing of cash flows – Risk • We then apply the factors to the Discounted Cash Flow (DCF) Model (Equation 12-1) 100
  • 101. Bond Valuation Model • Bond Valuation is an application of time value model introduced in chapter 8. • The value of the bond is the present value of the cash flows the investor expects to receive. • What are the cashflows from a bond investment? 101
  • 102. Bond Valuation Model • 3 Types of Cash Flows – Amount paid to buy the bond (PV) – Coupon interest payments made to the bondholders (PMT) – Repayment of Par value at end of Bond’s life (FV). 102
  • 103. Bond Valuation Model • 3 Types of Cash Flows – Amount paid to buy the bond (PV) – Coupon interest payments made to the bondholders (PMT) – Repayment of Par value at end of Bond’s life (FV). 103 Discount rate (I/YR) • Bond’s time to maturity (N)
  • 104. 104 Cur Net Bonds Yld Vol Close Chg AMR 6¼24 cv 6 91¼ -1½ ATT 8.35s25 8.3 110 102¾ +¼ IBM 63/8 05 6.6 228 965/8 -1/8 Kroger 9s99 8.8 74 1017/8 -¼ IBM 63/8 09 6.6 228 965/8 -1/8 IBM Bond Wall Street Journal Information:
  • 105. 105 Suppose IBM makes annual coupon payments. The person who buys the bond at the beginning of 2005 for $966.25 will receive 5 annual coupon payments of $63.75 each and a $1,000 principal payment in 5 years (at the end of 2009). Assume t0 is the beginning of 2005. IBM Bond Wall Street Journal Information: Cur Net Bonds Yld Vol Close Chg AMR 6¼24 cv 6 91¼ -1½ ATT 8.35s25 8.3 110 102¾ +¼ IBM 63/8 05 6.6 228 965/8 -1/8 Kroger 9s99 8.8 74 1017/8 -¼ IBM 63/8 09 6.6 228 965/8 -1/8
  • 106. 106 IBM Bond Timeline: 0 1 2 3 4 5 2005 2006 2007 2008 2009 63.75 63.75 63.75 63.75 63.75 1000.00 Suppose IBM makes annual coupon payments. The person who buys the bond at the beginning of 2005 for $966.25 will receive 5 annual coupon payments of $63.75 each and a $1,000 principal payment in 5 years (at the end of 2009). Cur Net Bonds Yld Vol Close Chg AMR 6¼24 cv 6 91¼ -1½ ATT 8.35s25 8.3 110 102¾ +¼ IBM 63/8 05 6.6 228 965/8 -1/8 Kroger 9s99 8.8 74 1017/8 -¼ IBM 63/8 09 6.6 228 965/8 -1/8
  • 107. 107 Compute the Value for the IBM Bond given that you require an 8% return on your investment. 0 1 2 3 4 5 2005 2006 2007 2008 2009 63.75 63.75 63.75 63.75 63.75 1000.00 IBM Bond Timeline:
  • 108. 108 $63.75 Annuity for 5 years VB = (INT x PVIFAk,n) + (M x PVIFk,n ) $1000 Lump Sum in 5 years 0 1 2 3 4 5 2005 2006 2007 2008 2009 63.75 63.75 63.75 63.75 63.75 1000.00 IBM Bond Timeline:
  • 109. 109 VB = (INT x PVIFAk,n) + (M x PVIFk,n ) = 63.75(3.9927) + 1000(.6806) = 254.53 + 680.60 = 935.13 $63.75 Annuity for 5 years $1000 Lump Sum in 5 years 0 1 2 3 4 5 2005 2006 2007 2008 2009 63.75 63.75 63.75 63.75 63.75 1000.00 IBM Bond Timeline:
  • 110. 110 .01 rounding difference N I/YR PV PMT FV –935.12 5 8 ? 63.75 1,000 IBM Bond Timeline: $63.75 Annuity for 5 years 0 1 2 3 4 5 2005 2006 2007 2008 2009 63.75 63.75 63.75 63.75 63.75 1000.00 $1000 Lump Sum in 5 years
  • 111. 111 Most Bonds Pay Interest Semi-Annually: e.g. semiannual coupon bond with 5 years to maturity, 9% annual coupon rate. Instead of 5 annual payments of $90, the bondholder receives 10 semiannual payments of $45. 0 1 2 3 4 5 2005 2006 2007 2008 2009 45 45 1000 45 45 45 45 45 45 45 45
  • 112. 112 Compute the value of the bond given that you require a 10% return on your investment. Since interest is received every 6 months, we need to use semiannual compounding VB = 45( PVIFA10 periods,5%) + 1000(PVIF10 periods, 5%) 10% 2 Semi-Annual Compounding Most Bonds Pay Interest Semi-Annually: 0 1 2 3 4 5 2005 2006 2007 2008 2009 45 45 1000 45 45 45 45 45 45 45 45
  • 113. 113 Most Bonds Pay Interest Semi-Annually: = 45(7.7217) + 1000(.6139) = 347.48 + 613.90 = 961.38 Compute the value of the bond given that you require a 10% return on your investment. Since interest is received every 6 months, we need to use semiannual compounding VB = 45( PVIFA10 periods,5%) + 1000(PVIF10 periods, 5%) 0 1 2 3 4 5 2005 2006 2007 2008 2009 45 45 1000 45 45 45 45 45 45 45 45
  • 114. 114 Calculator Solution: N I/YR PV PMT FV –961.38 10 5 ? 45 1,000 0 1 2 3 4 5 2005 2006 2007 2008 2009 45 45 1000 45 45 45 45 45 45 45 45
  • 115. Yield to Maturity • If an investor purchases a 6.375% annual coupon bond today for $966.25 and holds it until maturity (5 years), what is the expected annual rate of return ? 115 -966.25 ?? 0 1 2 3 4 5 2005 2006 2007 2008 2009 63.75 63.75 63.75 63.75 63.75 1000.00 + ?? 966.25
  • 116. Yield to Maturity 116 VB = 63.75(PVIFA5, x%) + 1000(PVIF5,x%) Solve by trial and error. • If an investor purchases a 6.375% annual coupon bond today for $966.25 and holds it until maturity (5 years), what is the expected annual rate of return ? -966.25 ?? 0 1 2 3 4 5 2005 2006 2007 2008 2009 63.75 63.75 63.75 63.75 63.75 1000.00 + ?? 966.25
  • 117. Yield to Maturity 7.203% 117 Calculator Solution: N I/YR PV PMT FV 5 ? -966.25 63.75 1,000 -966.25 0 1 2 3 4 5 2005 2006 2007 2008 2009 63.75 63.75 63.75 63.75 63.75 1000.00
  • 118. Yield to Maturity 118  If YTM > Coupon Rate bond Sells at a DISCOUNT  If YTM < Coupon Rate bond Sells at a PREMIUM -966.25 0 1 2 3 4 5 2005 2006 2007 2008 2009 63.75 63.75 63.75 63.75 63.75 1000.00
  • 119. Interest Rate Risk • Bond Prices fluctuate over Time – As interest rates in the economy change, required rates on bonds will also change resulting in changing market prices. 119 Interest Rates VB
  • 120. Interest Rate Risk 120 • Bond Prices fluctuate over Time – As interest rates in the economy change, required rates on bonds will also change resulting in changing market prices. Interest Rates VB Interest Rates VB
  • 121. Valuing Preferred Stock 121 P0 = Value of Preferred Stock = PV of ALL dividends discounted at investor’s Required Rate of Return 52 Weeks Yld Vol Net Hi Lo Stock Sym Div % PE 100s Hi Lo Close Chg s 42½ 29 QuakerOats OAT 1.14 3.3 24 5067 35 34¼ 34¼ -¾ s 36¼ 25 RJR Nabisco RN .08p ... 12 6263 29¾ 285/8 287/8 -¾ 237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8 23¾ ... 7¼ 5½RJR Nab pfC .60 9.4 ... 2248 6½ 6¼ 63/8 - 1/8 0 1 2 3  P0=23.75 D1=2.31 D2=2.31 D3=2.31 D=2.31 237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8 23¾ ...
  • 122. Valuing Preferred Stock 122 P0 = + + +··· 2.31 (1+ kp) 2.31 (1+ kp)2 2.31 (1+ kp)3  52 Weeks Yld Vol Net Hi Lo Stock Sym Div % PE 100s Hi Lo Close Chg s 42½ 29 QuakerOats OAT 1.14 3.3 24 5067 35 34¼ 34¼ -¾ s 36¼ 25 RJR Nabisco RN .08p ... 12 6263 29¾ 285/8 287/8 -¾ 237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8 23¾ ... 7¼ 5½RJR Nab pfC .60 9.4 ... 2248 6½ 6¼ 63/8 - 1/8 0 1 2 3  P0=23.75 D1=2.31 D2=2.31 D3=2.31 D=2.31 237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8 23¾ ...
  • 123. Valuing Preferred Stock 123 P0 = Dp kp = 2.31 .10 = $23.10 P0 = + + +··· 2.31 (1+ kp) 2.31 (1+ kp )2 2.31 (1+ kp )3  52 Weeks Yld Vol Net Hi Lo Stock Sym Div % PE 100s Hi Lo Close Chg s 42½ 29 QuakerOats OAT 1.14 3.3 24 5067 35 34¼ 34¼ -¾ s 36¼ 25 RJR Nabisco RN .08p ... 12 6263 29¾ 285/8 287/8 -¾ 237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8 23¾ ... 7¼ 5½RJR Nab pfC .60 9.4 ... 2248 6½ 6¼ 63/8 - 1/8 0 1 2 3  P0=23.75 D1=2.31 D2=2.31 D3=2.31 D=2.31 237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8 23¾ ...
  • 124. Valuing Individual Shares of Common Stock 124 P0 = PV of ALL expected dividends discounted at investor’s Required Rate of Return Not like Preferred Stock since D0 = D1 = D2 = D3 = DN , therefore the cash flows are no longer an annuity. P0 = + + +··· D1 (1+ ks ) D2 (1+ ks )2 D3 (1+ ks )3 D1 D2 D3 P0 D 0 1 2 3 
  • 125. Valuing Individual Shares of Common Stock 125 P0 = PV of ALL expected dividends discounted at investor’s Required Rate of Return Investors do not know the values of D1, D2, .... , DN. The future dividends must be estimated. D1 D2 D3 P0 D 0 1 2 3  P0 = + + +··· D1 (1+ ks ) D2 (1+ ks )2 D3 (1+ ks )3
  • 126. Constant Growth Dividend Model 126 Assume that dividends grow at a constant rate (g). D1=D0 (1+g) D0 D2=D0 (1+g)2D3=D0 (1+g)3 D=D0 (1+g) 0 1 2 3 
  • 127. Constant Growth Dividend Model 127 Requires ks > g Reduces to: P0 = + + + ··· + D0 (1+ g) (1+ ks ) D0 (1+ g)2 (1+ ks )2 D0 (1+ g)3 (1+ ks )3  P0 = = D0(1+g) ks – g D1 ks – g Assume that dividends grow at a constant rate (g). D1=D0 (1+g) D0 D2=D0 (1+g)2D3=D0 (1+g)3 D=D0 (1+g) 0 1 2 3 
  • 128. Constant Growth Dividend Model 128 P0 = = $30.50 1.14(1+.07) .11 – .07 What is the value of a share of common stock if the most recently paid dividend (D0) was $1.14 per share and dividends are expected to grow at a rate of 7%? Assume that you require a rate of return of 11% on this investment. P0 = = D0(1+g) ks – g D1 ks – g
  • 129. Valuing Total Stockholders’ Equity • The Investor’s Cash Flow DCF Model – Investor’s Cash Flow is the amount that is “free” to be distributed to debt holders, preferred stockholders and common stockholders. – Cash remaining after accounting for expenses, taxes, capital expenditures and new net working capital. 129
  • 131. 131 ECP Homework 1. Indicate which of the following bonds seems to be reported incorrectly with respect to discount, premium, or par and explain why. Bond Price Coupon Rate Yield to Maturity A 105 9% 8% B 100 6% 6% C 101 5% 4.5% D 102 0% 5% 2. What is the price of a ten-year $1,000 par-value bond with a 9% annual coupon rate and a 10% annual yield to maturity assuming semi-annual coupon payments? 3. You have an issue of preferred stock that is paying a $3 annual dividend. A fair rate of return on this investment is calculated to be 13.5%. What is the value of this preferred stock issue? 4. Total assets of a firm are $1,000,000 and the total liabilities are $400,000. 500,000 shares of common stock have been issued and 250,000 shares are outstanding. The market price of the stock is $15 and net income for the past year was $150,000. a.. Calculate the book value of the firm. b. Calculate the book value per share. c. Calculate the P/E ratio. 5. A firm’s common stock is currently selling for $12.50 per share. The required rate of return is 9% and the company will pay an annual dividend of $.50 per share one year from now which will grow at a constant rate for the next several years. What is the growth rate?