Construction Quality
Control Plan
Non-Public Properties
Newhall Street
Neighborhood Site
Hamden, Connecticut
Revision 0
Prepared for:
Olin Corporation
Cleveland, Tennessee
February 2009
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
TABLE OF CONTENTS
February 2009
i
PAGE
1. INTRODUCTION .............................................................................................................................1
2. SITE DESCRIPTION .......................................................................................................................1
3. PROJECT ORGANIZATION..........................................................................................................2
4. QUALITY CONTROL METHODS ................................................................................................6
5. INSPECTIONS ..................................................................................................................................7
6. FIELD TESTING PROCEDURES..................................................................................................9
7. SUBMITTALS...................................................................................................................................9
8. DOCUMENTATION ......................................................................................................................10
9. REVISIONS TO WORK.................................................................................................................10
10. DEFINABLE FEATURES OF WORK .........................................................................................10
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
LIST OF APPENDICES
February 2009
ii
APPENDIX
CONCEPTUAL PROJECT ORGANIZATIONAL CHART ................................................................. A-1
RESUMES OF KEY PERSONNEL.......................................................................................................... A-2
PREPARATORY PHASE CHECKLIST ..................................................................................................B-1
INITIAL/FOLLOW-UP PHASE INSPECTION CHECKLIST..............................................................B-3
FINAL PHASE INSPECTION CHECKLIST...........................................................................................B-5
SUBMITTAL REGISTER......................................................................................................................... C-1
QUALITY CONTROL DAILY REPORT................................................................................................ D-1
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
February 2009
1
1. INTRODUCTION
This Construction Quality Control Plan (CQCP) will be implemented to ensure remedial and
construction procedures are performed in compliance with the plans and specifications under this
contract. This CQCP will provide a means to maintain effective quality control at the Non-Public
Properties (NPP) Newhall Street Neighborhood Site (the Site). The quality control measures as
presented herein include quality control organization; methods of performing, documenting, and
enforcing quality control operations of both the primary Contractor and their subcontractors
(including inspection and testing); inspections to be performed; and protocol describing corrective
actions.
Overall management of the CQCP will be the responsibility of the Contractor’s Quality Control
Manager (QCM). The QCM will have the authority to act in all construction quality control CQC
matters and will be responsible for ensuring that all materials and work comply with the contract
specifications. All inspection and testing firms will be at the disposal of the QCM to ensure that all
aspects of work are compliant with the contract. The QCM will report any deviations from the
CQCP independently to the On-site Project Manager. The resume of the Contractor’s designated
QCM will be submitted for approval prior to mobilization to the Site.
2. SITE DESCRIPTION
The Newhall Street Neighborhood (Site) is located in the southern part of Hamden, Connecticut,
east of Dixwell Avenue and just north of New Haven. The Newhall Street Neighborhood comprises
an area that historically consisted of wetlands and low-lying areas. Waste materials were used to
fill these areas from the late 1800s to the mid-1900s. Subsequently, homes, public buildings, and
parks were built on and next to the historic fill areas.
The primary potential human health risk associated with the Site is from direct exposure to the fill.
The Site contains contaminated fill material known to contain contaminants consisting primarily of
metals (lead and arsenic), polynuclear aromatic hydrocarbons (PAHs) and polychlorinated
biphenyls (PCBs). The underlying groundwater generally does not pose a health risk to the
residents because the area has a public water source, and the Site groundwater is not used for
drinking or other domestic purposes.
The NPP consent order includes an 18-block area (approximately) consisting of approximately of
230 residential properties. In October 2007, the Connecticut Department of Environmental
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
February 2009
2
Protection (CTDEP) issued a final Remedy Selection Plan. The selected remedy for the residential
properties (and other Non-Public Properties) located inside the Consent Order boundary is as
follows:
• Excavation of fill within the top 4 feet and off-site disposal at authorized facilities.
• Backfill with clean soil.
• Restoration of pre-existing features (landscaping, patios, fencing, driveways, etc.) if
disturbed during construction.
3. PROJECT ORGANIZATION
The Contractor’s key personnel assigned to this project should possess a broad range of remedial
action experience and skills. All should have experience dealing with the handling of contaminated
wastes and should be familiar with requirements of day-to-day work under this contract.
The Contractor’s proposed project organization for this project and the resumes of key personnel,
along with their job titles, should be submitted for review and approval. A conceptual project
Organizational Chart is included in Appendix A.
The functional responsibilities of key technical personnel are summarized as follows.
3.1 HOME OFFICE PERSONNEL
Contractor – President and Chief Executive Officer
The Contractor’s President and Chief Executive Officer (CEO) will ultimately be responsible for
the project's success. He will provide the required resources to ensure that the project is
successfully executed. He will be kept informed of the project's progress and maintain that the
project is meeting its goals. The President and CEO will resolve problems that cannot be resolved
by the On-site Project Manager or Corporate Project Manager.
Contractor – Vice President
The Contractor’s Vice President will oversee the project at the corporate level and report directly
to the President/Chief Executive Officer. He will communicate with the On-site Project Manager
regarding all aspects of the project including, but not limited to, project problems, progress,
payments, schedules, administrative duties, and QCM oversight. He will also resolve problems that
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
February 2009
3
cannot be resolved by the On-site Project Manager and will periodically visit the site and be
acquainted with personnel and procedures.
Contractor - Certified Industrial Hygienist (CIH) - Corporate Director of Health and Safety
Regarding safety and occupational health, the Contractor will:
• Maintain overall responsibility of Site safety.
• Be responsible for assigning Site Safety and Health Officer (SSHO) responsibilities.
• Ensure that all activities are carried out in compliance with the approved site Health
and Safety Plan.
The Contractor’s CIH and/or Corporate Director of Health and Safety is responsible for the
preparation, implementation, and enforcement of the site-specific Health and Safety Plan (HASP).
The Contractor’s SSHO will report site safety activities to the CIH and/or Corporate Director of
Health and Safety on a regular basis, including all safety and occupational health issues. All job
safety records generated will be thoroughly reviewed by the CIH and/or Corporate Director of
Health and Safety, who will also perform quarterly job-site safety inspections. He will prepare an
audit report of findings for each inspection, including identification of deficiencies requiring
corrective action.
The CIH and/or Corporate Director of Health and Safety will supervise the SSHO and develop the
air-monitoring program. He will make periodic trips to the site to conduct safety audits, observe
the administration of this plan, and make any necessary modifications to the program.
Contractor - CHMM – Regulatory Specialist
The Regulatory Specialist is responsible for regulatory compliance matters, including oversight of
all field sampling and chemical data acquisition plans and correspondence with off-site
laboratories. He will review laboratory reports with the selected lab in order to ensure compliance
with project specifications and all required protocols. He will coordinate all off-site waste removal
with Olin’s designated site representative, including transport, disposal, manifests, waste profiles,
regulatory compliance, and disposal requirements (as required).
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
February 2009
4
3.2 FIELD PERSONNEL
Contractor - On-site Project Manager
The Contractor’s On-site Project Manager, will be the primary contact person at the site with
whom MACTEC/Olin will interact with on a daily basis under this contract.
The Contractor’s On-site Project Manager will ensure that:
• Appropriate resources are allocated to the project and balanced to ensure best value to
Olin.
• All cost tracking and reporting is carried out in a manner compliant with Olin’s
Contract Management Procedures.
• All tasks are conducted in accordance with the site HASP and project specifications.
The Contractor’s field personnel should rely on home office support throughout the course of the
project. The Contractor’s Vice President and on-site Project Manager will become and remain
personally involved until each problem is resolved and appropriate corrective measures are
implemented. They will typically communicate at least once daily on the progress of the project.
The Project Manager will be present on the jobsite, to ensure that the project is progressing as
scheduled.
The On-site Project Manager is responsible for implementation and support of the Contractor’s
CQCP and will oversee all aspects of work under this contract for remediation at the site,
including:
• All procurements.
• Qualified Contractor and subcontractor resources are assigned to the project and
balanced to ensure jobs are aligned with project needs.
• The Site is maintained and secure.
• All tasks are carried out safely and in compliance with the project specifications.
His responsibilities include:
• Contractor coordination.
• Acting as site liaison between the Contractor and MACTEC/Olin.
• Maintaining charge of all field operations.
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
February 2009
5
Contractor - Quality Control Manager (QCM)
The Quality Control Manager will report directly to the On-site Project Manager with matters
concerning quality control. He will have both the authority and the duty to halt any operation
appearing to be out of compliance with contract specifications.
The QCM is responsible for keeping and maintaining all records related to personnel, supplies,
equipment use, and equipment calibration and sampling. His function will be to ensure
compliance with the contract plans and specifications.
QCM responsibilities include:
• Performing and documenting field inspections.
• Preparing daily Quality Control Reports.
• Scheduling, reviewing, certifying, and managing project submittals.
• Maintaining the Submittal Register.
• Providing coordination of required quality control testing, reviewing results, and
submitting.
• Coordinating, documenting, and tracking preparatory, initial, and follow-up
inspections.
• Tracking construction deficiencies and ensuring timely corrective action.
• Coordinating field sampling activities (as required).
• Reviewing calibration of test equipment (as necessary).
• Preparing addenda to the CQCP as necessary when additional phases of work are
added.
• Maintenance of as-built drawings.
• Coordinating responses to vendors’ requests for information and technical issues.
• Serving as main point of contact at the site for MACTEC/Olin questions and
discussions on quality and technical issues.
• Delegating duties to alternate QCMs and notifying MACTEC/Olin to whom what
duties have been delegated.
The QCM or an alternate will be on-site when work is being performed.
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
February 2009
6
Contractor - Site Safety and Health Officer (SSHO)
The Site Safety and Health Officer will report to the Certified Industrial Hygienist and be
responsible for the implementation of the approved Site Health and Safety Plan; including
conducting required safety inspections, safety briefings, and reports of safety-related activities. He
has received 40-hour HAZWOPER training per 29 CFR 1910.120(e), and possesses current Red
Cross First Aid and CPR training.
Contractor - Superintendent
The project Superintendent will be responsible for supervising all field activities. His duties
include supervision of the craft labor (equipment operators, truck drivers, and laborers), technical
staff (survey crew), and all subcontractors. The designated Superintendent is also responsible for
the maintenance of all on-site construction equipment.
Contractor – Transportation and Disposal Coordinator
The Transportation and Disposal Coordinator will be experienced in gathering and analyzing data,
and developing and implementing sampling plans and quality control programs. The designated
Contractor representative will be responsible for the coordination of transportation and disposal at
the Site.
4. QUALITY CONTROL METHODS
The CQCP will be implemented in order to ensure compliance with the specifications for remedial
action construction as detailed in the contract specifications. The basis of the CQCP is nationally
recognized standards published by the American Society for Testing and Materials (ASTM) and
the Project Specifications. In addition, procedures utilized within the CQCP should reflect the
experience gained by the prime Contractor in completing construction projects similar to the
Newhall Street Neighborhood Project.
Quality control measures will extend to field sampling procedures; staffing; types of material and
equipment to be used; and methods of performing, documenting, and enforcing quality control
operations of both the Contractor and subcontractors (including inspection and testing).
As previously stated, maintenance of the CQCP will be the responsibility of the QCM. The QCM
will be responsible for ensuring that all materials and work comply with the contract specifications.
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
February 2009
7
The QCM may have a field engineer at his disposal to assist him with the on-site inspections.
Testing firms will be at the disposal of the QCM to ensure contract compliance in all aspects of
work. All reports from testing firms will be forwarded to the QCM for his review and approval.
4.1 IMPLEMENTATION
The QCM will be responsible for implementing the CQC Plan by ensuring that quality materials
and supplies are provided for the proposed project, and that good workmanship is provided in all
aspects of this contract. The QCM will report directly to the On-site Project Manager and will
complete daily site inspections to ensure compliance with the quality control specifications.
Daily reports will be completed listing all field testing and sampling activities. These reports will
be submitted to the MACTEC/Olin representative on a daily basis. The QCM will be responsible
for ensuring that all materials and work comply with the contract plans and specifications, and that
all performance standards are met.
It is anticipated that the MACTEC/Olin representative and the Contractor’s QCM will meet
frequently in order to forecast and/or prevent any potential problems from arising. An on-site
quality control meeting will be conducted on a weekly basis as part of the weekly progress meeting
in order to review performance during the previous one-week period, and prepare for the upcoming
two-week period. It is anticipated that the Contractor’s On-site Project Manager, Health and Safety
Officer, Superintendent and MACTEC/Olin representatives will attend this meeting.
4.2 DOCUMENTING
The QCM will record project activities in a daily quality control report maintained on site at all
times. All site activities, site inspections, and field testing of materials will be recorded on a daily
basis, along with any unacceptable site occurrences or deficiencies and their associated corrective
actions. Each daily entry into the report will be signed by the QCM. Quality control reports will
be submitted on a daily basis during all field construction activities.
5. INSPECTIONS
To ensure that all construction and remedial activities comply with the project specifications, the
QCM will complete, in conjunction with the subcontractors, three phases of site inspections for
each feature of work. These inspections will include the following:
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
February 2009
8
PHASE I - PREPARATORY INSPECTION
Preparatory inspections will be performed prior to beginning work on any definable feature of the
project and will include:
• Review of submittal requirements and all other Contract requirements with the
performance of the work;
• Check to assure that provisions have been made to provide required field quality
control testing;
• Examine the work area to ascertain that all preliminary work has been completed;
• Verify all field dimensions and advise MACTEC/Olin of any discrepancies;
• Perform a physical examination of materials and equipment to assure that they
conform to approved shop drawings or submittal data and that all required materials
and/or equipment are on hand and comply with the Contract requirements.
Subsequent to the preparatory inspection and prior to commencement of work, the Contractor shall
instruct each applicable worker on the level of workmanship required to meet contract
specifications.
PHASE II - INITIAL INSPECTIONS
Initial phase inspections will be performed as soon as a representative portion of the particular
feature of work has been accomplished. Initial inspections include, but are not limited to,
examination of the quality of workmanship; review of control testing for compliance with control
requirements; and identification of defective or damaged materials, omissions, and dimensional
requirements.
The initial phase inspection is the time to discuss and agree on the required level of quality
associated with a given work activity. Any discrepancies relative to work quality should be
addressed at this time.
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
February 2009
9
PHASE III - FOLLOW-UP INSPECTIONS
Follow-up inspections will be performed daily as work progresses to ensure continuing compliance
with contract requirements, including control testing, until completion of the particular feature of
work. Final follow-up inspections will be conducted and deficiencies corrected prior to beginning
new work.
The QCM will notify MACTEC/Olin at least 24 hours in advance of any inspections. Notification
and meeting minutes of all inspections will be recorded in the Daily Quality Control Report.
Examples of the inspection forms to be utilized are presented in Appendix B.
6. FIELD TESTING PROCEDURES
The Contractor will conduct field-testing to verify that control measures are adequate to provide a
product that conforms to contract requirements.
Field testing will be conducted under the auspices of the QCM and he or his designee shall:
• Arrange for, or conduct, field testing in accordance with applicable test parameters (ASTM,
etc).
• Verify that facilities and testing equipment are available and comply with testing standards
and ensure that testing facilities are approved by Olin and are validated.
• Check test equipment calibration data against certified standards.
• Verify that all tests are documented and submitted as part of quality control system reporting.
• Review all test documentation prior to submittal.
7. SUBMITTALS
The QCM will follow standard procedures concerning submittals, including the use of the
MACTEC transmittal form. Each submittal form may contain more than one submittal specific to
that specification section. A submittal register listing major submittals will be prepared by
MACTEC (a sample Submittal Register is included in Appendix C). This register will be
prepared in conjunction with the anticipated progress schedule.
The QCM will be responsible for the review and approval of submittals prior to their submittal to
MACTEC/Olin representative. This includes reviews of materials and suppliers’ catalog cuts, as
well as subcontractor submittals. The QCM will review the submittal for completeness and
compliance with the contract specifications. Variations to a submittal will be noted on the MATEC
transmittal form. The QCM will actively participate during procurement activities to ensure
purchase orders and subcontracts comply with the contract.
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
February 2009
10
8. DOCUMENTATION
All testing results will be recorded on the daily quality control report. A sample Daily QC report is
included in Appendix D. Any concerns or deviations from the required material specifications and
the actions taken to correct the problems will be noted on the report. Information recorded on the
daily quality control report will include:
• Definable features of work that was addressed.
• Description of trades working on the project.
• Numbers of personnel.
• Weather conditions.
• Types and numbers of tests performed.
• Results of testing.
• Nature of defects or cause for rejection.
• Proposed corrective action(s).
• Corrective action taken and date.
• Delays encountered.
• Directions received from the Engineer and actions
taken.
• Health and safety issues or deficiencies and how
they were resolved.
• Deficiencies.
9. REVISIONS TO WORK
The Contractor will be responsible for ensuring total compliance of field work to the project
specifications. Should modifications or revisions to the specifications become necessary, the
Contractor will make the request, in writing, to MACTEC/Olin. Approval from MACTEC/Olin
must be received prior to allowing the modifications or revisions to be made in the field. The
QCM will be informed of and record all such requests in his daily log and on the daily quality
control report.
10. DEFINABLE FEATURES OF WORK
Listed below are the general categories and types of work that will be performed under this
contract. These items, known as Definable Features of Work, have been grouped into the various
categories in which work will be performed, and correlate to measurement and payment. Suitable
quality control methods and procedures will be utilized in order to ensure that all work is
performed to the standards and quality required by the specifications.
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
February 2009
11
The following are the definable features of work that will be performed under this contract:
• Pre-Construction Preparation Activities
• Mobilization
• Site Preparation
• Tire Pond Management
• Clearing and Grubbing
• Demolition and Removal of Above Ground
Items
• Excavation of Impacted Fill Material
• Transportation and Disposal of Impacted Fill
Material
• Backfill/Utility Replacement
• Restoration
• Demobilization
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
APPENDIX A
February 2009
A-1
NPP Newhall Street Neighborhood - Olin Site
Conceptual Project Organizational Chart
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
APPENDIX A
February 2009
A-2
Resumes of Key Personnel
-To be added by Contractor
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
APPENDIX B
February 2009
B-1
Preparatory Phase Checklist
NPP Newhall Street Neighborhood-Olin Site
Contract: Date Preparatory Held:
Spec. Section & Paragraph Definable Feature of Work:
Drawing Sheet Numbers Major Definable Feature:
1) Personnel Present
Name Position Company
2) Has each spec. paragraph, drawing, and shop drawing detail been studied?
Yes___ No___
3) Transmittals Involved
Number and Item Code Contractor Approval
C-1Have all items involved been approved? Yes No
1. Are all materials on-hand? Yes No .
Are the materials on the job-site to be incorporated the same as those
approved?
Yes No
Have all materials been checked for contract compliance against approved shop
drawings?
Yes No
Equipment to be Used in Executing the Work:
Items not on-hand or not in compliance with transmittals:
2. Tests required in accordance with contract requirements:
Test Paragraph
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
APPENDIX B
February 2009
B-2
Accident Prevention Planning - Hazard Control Measures:
Activity Hazard Analyses (Job Hazard Analyses)
F-1Applicable Outlines (Attach completed copies)
Activity Hazard Analysis
Activity Hazard(s) Controls
F-2Operational Equipment Checklist
Attached For:
On File For:
3. Have procedures for accomplishing work been reviewed with appropriate people?
Yes No ___
Scope of Work/Method of Construction:
Safety Issues:
Spill Prevention Issues:
4. Has all preliminary work been accomplished in accord with contract requirements
and is this segment of work ready to start? Yes No ___
H-1Explain any problems:
1. Remarks:
CQCSM Comments:
Contractor’s Comments:
Quality Control Representative
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
APPENDIX B
February 2009
B-3
Initial/Follow-Up Phase Inspection Checklist
NPP Newhall Street Neighborhood-Olin Site
Inspection Type: Initial Phase Follow-Up Phase
Date: Specifications Paragraph:
Description and Location of Work Inspected:
Reference Contract Drawings:
A. Personnel Present
Name Position Company
B. Materials Being Used Are In Strict Compliance With The Contract Plans and
Specifications
YES NO _____
If not, explain:
C. Procedures And/Or Work Methods Witnessed Are In Strict Compliance With The
Requirements Of The Contract Specifications: YES NO _____
If not, explain:
D. Workmanship Is Acceptable. YES NO State Areas Where
Improvement Is Needed:
E. Safety Violations and Corrective Actions Taken:
F. Remarks:
Quality Control Representative
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
APPENDIX B
February 2009
B-4
Final Phase Inspection Checklist
NPP Newhall Street Neighborhood-Olin Site
Date: Specifications Paragraph:
Definable Feature of Work:
Description and Location of Work Inspected:
Reference Contract Drawings:
A. Personnel Present
Name Position Company
B. Materials Used In Strict Compliance With The Contract Plans and Specifications
YES NO _____
If not, explain:
C. Procedures And/Or Work Methods Witnessed Are In Strict Compliance With The
Requirements Of The Contract Specifications: YES NO _____
If not, explain:
C. Workmanship is Acceptable: YES NO _____
State Areas Where Improvement is Needed:
E. Remarks:
Quality Control Representative
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
APPENDIX C
February 2009
C-1
SUBMITTAL STATUS CODES
A – Reviewed
B – Reviewed as Noted
C – Reviewed as Noted, Resubmission Requested
D- Revise and Resubmit
SUBMITTAL REGISTER
OLIN, NPP Newhall Street Neighborhood, Hamden, Connecticut
REQUIRED SUBMITTALS
Anticipated
Submittal Date
Date
Submitted to
Engineer
Date Submittal
Returned from
Engineer and
status (see
codes below for
status)
Date
Resubmitted to
Engineer
Date Submittal
Returned from
Engineer and
status (see
codes below for
status)
Date
Resubmitted to
Engineer
Date Submittal
Returned from
Engineer and
status (see
codes below for
status)
Section No. Spec Description
Contractor/
Vendor
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
APPENDIX D
February 2009
D-1
Conceptual Contractor
Quality Control Daily Report
REPORT NO.: JOB NO.: DATE:
PROJECT TITLE: NPP NEWHALL STREET NEIGHBORHOOD
Location: Hamden, Connecticut
Max Min
WEATHER: RAINFALL: TEMP:
____________________________________________________________________________
1. Work performed by Prime Contractor (Include Plant and Labor Breakdown)
*See attachment for Labor and Equipment Breakdown
- None
2. Work performed by Sub-Contractors (Include “Number of Personnel” Breakdown)
- None
3. Material and/ or Equipment delivered to site
- None
4. Type and Results of Inspections
- None
5. Type and Location of Tests performed and results
- None
6. Verbal instructions received from Engineer or Olin, on construction deficiencies or
retesting required (include corrective action to be taken)
- None
7. Health and Safety observations or actions taken
- None
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
APPENDIX D
February 2009
D-2
8. Delays / Problems/Deficiencies
- None
9. Planned Activities
- None
10. Attachments
- None
11. Clarifications to Daily Reports
- None
12. Remarks
- None
Certification: I certify that the above report is complete and correct and that I, or my
representative, have inspected the work performed this day by the Prime Contractor and
each Subcontractor and have determined that all materials, equipment, and
workmanship are in strict compliance with the Contract Documents, Plans and
Specifications. Any exceptions to these contract requirements will be noted above.
______________________________________
Contractor’s Quality Control Manager
SUBMITTAL STATUS CODES
A – Reviewed C – Reviewed as Noted, Resubmission Requested
B – Reviewed as Noted D- Revise and Resubmit
CONSTRUCTION QUALITY CONTROL PLAN
NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD
HAMDEN, CONNECTICUT
APPENDIX D
February 2009
D-3
COMPANY EQUIPMENT WORKING
TODAY
RENTAL EQUIPMENT WORKING
TODAY
TYPE OF
EQUIPMENT
EQUIPMENT
NUMBER
TYPE OF EQUIPMENT VENDOR
MATERIALS AND/OR SERVICES RECEIVED TODAY
VENDOR NAME DESCRIPTION
EQUIPMENT LIST
EQUIPMENT EQUIPMENT
NUMBER
DATE
MOBILIZE TO SITE
DATE
DEMOBILIZED FROM
SITE
RENTAL EQUIPMENT
EQUIPMENT VENDOR DATE
MOBILIZE TO SITE
DATE
DEMOBILIZED FROM
SITE
SUBMITTAL STATUS CODES
A – Reviewed C – Reviewed as Noted, Resubmission Requested
B – Reviewed as Noted D- Revise and Resubmit

More Related Content

What's hot

Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002Minh Bui Si
 
Project management planning
Project management planningProject management planning
Project management planningAlvin Niere
 
Sample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_projectSample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_projectignitetribes
 
Overview to contract management
Overview to contract managementOverview to contract management
Overview to contract managementPriyesh Nair
 
The Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementThe Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementMilind_jagtap_
 
Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5pankajsh10
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksPankaj K Sinha
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction Thanigaivel Asokan
 
Value management presentation slides
Value management presentation slidesValue management presentation slides
Value management presentation slidesDoreen Yeo
 
USACE Construction Quality Management manual
USACE Construction Quality Management manualUSACE Construction Quality Management manual
USACE Construction Quality Management manualJerico Awat
 
13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder EngagementDavidMcLachlan1
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02Minh Bui Si
 
Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)Jayson Narito
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1Ho Yen Liang
 
project Scope management
project Scope management project Scope management
project Scope management Mohamed , PMP
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 

What's hot (20)

Quality management
Quality managementQuality management
Quality management
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
 
Project management planning
Project management planningProject management planning
Project management planning
 
Managing & Supervising Projects, Consultants & Contractors
Managing & Supervising Projects, Consultants & ContractorsManaging & Supervising Projects, Consultants & Contractors
Managing & Supervising Projects, Consultants & Contractors
 
Sample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_projectSample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_project
 
Overview to contract management
Overview to contract managementOverview to contract management
Overview to contract management
 
The Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementThe Chunnel Project - Quality Management
The Chunnel Project - Quality Management
 
Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
Chunnel Project
Chunnel ProjectChunnel Project
Chunnel Project
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction
 
Value management presentation slides
Value management presentation slidesValue management presentation slides
Value management presentation slides
 
USACE Construction Quality Management manual
USACE Construction Quality Management manualUSACE Construction Quality Management manual
USACE Construction Quality Management manual
 
13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)
 
Project scope management 2
Project scope management 2Project scope management 2
Project scope management 2
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1
 
project Scope management
project Scope management project Scope management
project Scope management
 
Construction project management
Construction project managementConstruction project management
Construction project management
 

Viewers also liked

Quality control in construction site
Quality control in construction siteQuality control in construction site
Quality control in construction siteMohamed Saber
 
Houston Commercial Cooling Tower Case Study - Aug. 22 2016
Houston Commercial Cooling Tower Case Study - Aug. 22 2016Houston Commercial Cooling Tower Case Study - Aug. 22 2016
Houston Commercial Cooling Tower Case Study - Aug. 22 2016Bevan Brinkley
 
livepool-john-lennon-airport-case-study
livepool-john-lennon-airport-case-studylivepool-john-lennon-airport-case-study
livepool-john-lennon-airport-case-studyCourtney Jowsey
 
Stansted Airport Case Study
Stansted Airport Case StudyStansted Airport Case Study
Stansted Airport Case StudySteve Carter
 
Birmingham Airport Case Study
Birmingham Airport Case StudyBirmingham Airport Case Study
Birmingham Airport Case StudyCristina Calleja
 
Gander Airport Case Study
Gander Airport Case StudyGander Airport Case Study
Gander Airport Case Studyjtaylorireland
 
Case study brookfield airport
Case study brookfield airportCase study brookfield airport
Case study brookfield airportColo_cr
 
Bts Construction Building Specs Template 20090220 Tipo
Bts   Construction Building Specs Template 20090220 TipoBts   Construction Building Specs Template 20090220 Tipo
Bts Construction Building Specs Template 20090220 Tipoguestae22559
 
Cqm student study guide
Cqm student study guideCqm student study guide
Cqm student study guideRobert Rodgers
 
Gatwick Airport Disruption 2013 - A Case Study
Gatwick Airport Disruption 2013 - A Case StudyGatwick Airport Disruption 2013 - A Case Study
Gatwick Airport Disruption 2013 - A Case StudySteelhenge
 
Project Plan for Construction of School in Africa (Congo)
Project Plan for Construction of School in Africa (Congo)Project Plan for Construction of School in Africa (Congo)
Project Plan for Construction of School in Africa (Congo)Alex Osborne
 
Total Quality Management for Improved Project Success - Construction Claims M...
Total Quality Management for Improved Project Success - Construction Claims M...Total Quality Management for Improved Project Success - Construction Claims M...
Total Quality Management for Improved Project Success - Construction Claims M...The Frisby Group - Construction Consultants
 
VoIP Project Request For Proposal Presentation
VoIP Project Request For Proposal PresentationVoIP Project Request For Proposal Presentation
VoIP Project Request For Proposal Presentationbrianbish10795
 
EPC Construction CQA Program
EPC Construction CQA ProgramEPC Construction CQA Program
EPC Construction CQA ProgramDan Stehling
 

Viewers also liked (20)

Quality control in construction site
Quality control in construction siteQuality control in construction site
Quality control in construction site
 
Project plan overview
Project plan overviewProject plan overview
Project plan overview
 
Houston Commercial Cooling Tower Case Study - Aug. 22 2016
Houston Commercial Cooling Tower Case Study - Aug. 22 2016Houston Commercial Cooling Tower Case Study - Aug. 22 2016
Houston Commercial Cooling Tower Case Study - Aug. 22 2016
 
Birmingham Airport Case study
Birmingham Airport Case studyBirmingham Airport Case study
Birmingham Airport Case study
 
livepool-john-lennon-airport-case-study
livepool-john-lennon-airport-case-studylivepool-john-lennon-airport-case-study
livepool-john-lennon-airport-case-study
 
Prince 2 project managment Document,Project quality plan
Prince 2 project managment Document,Project quality planPrince 2 project managment Document,Project quality plan
Prince 2 project managment Document,Project quality plan
 
Stansted Airport Case Study
Stansted Airport Case StudyStansted Airport Case Study
Stansted Airport Case Study
 
Birmingham Airport Case Study
Birmingham Airport Case StudyBirmingham Airport Case Study
Birmingham Airport Case Study
 
Gander Airport Case Study
Gander Airport Case StudyGander Airport Case Study
Gander Airport Case Study
 
Case study brookfield airport
Case study brookfield airportCase study brookfield airport
Case study brookfield airport
 
RFP-Doc-Final
RFP-Doc-FinalRFP-Doc-Final
RFP-Doc-Final
 
Hitachi case study
Hitachi case studyHitachi case study
Hitachi case study
 
Bts Construction Building Specs Template 20090220 Tipo
Bts   Construction Building Specs Template 20090220 TipoBts   Construction Building Specs Template 20090220 Tipo
Bts Construction Building Specs Template 20090220 Tipo
 
Cqm student study guide
Cqm student study guideCqm student study guide
Cqm student study guide
 
Challenges airport planning
Challenges airport planningChallenges airport planning
Challenges airport planning
 
Gatwick Airport Disruption 2013 - A Case Study
Gatwick Airport Disruption 2013 - A Case StudyGatwick Airport Disruption 2013 - A Case Study
Gatwick Airport Disruption 2013 - A Case Study
 
Project Plan for Construction of School in Africa (Congo)
Project Plan for Construction of School in Africa (Congo)Project Plan for Construction of School in Africa (Congo)
Project Plan for Construction of School in Africa (Congo)
 
Total Quality Management for Improved Project Success - Construction Claims M...
Total Quality Management for Improved Project Success - Construction Claims M...Total Quality Management for Improved Project Success - Construction Claims M...
Total Quality Management for Improved Project Success - Construction Claims M...
 
VoIP Project Request For Proposal Presentation
VoIP Project Request For Proposal PresentationVoIP Project Request For Proposal Presentation
VoIP Project Request For Proposal Presentation
 
EPC Construction CQA Program
EPC Construction CQA ProgramEPC Construction CQA Program
EPC Construction CQA Program
 

Similar to Construction quality control plan draft rev0 27_feb09

CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016Ali Issa
 
Quality Control Program Proposal Final Draft
Quality Control Program Proposal Final DraftQuality Control Program Proposal Final Draft
Quality Control Program Proposal Final DraftThomas Smith
 
Erection method statement
Erection method statementErection method statement
Erection method statementkanalbiru
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTmustafa hussain
 
Eia of township and area development projects
Eia of township and area development projectsEia of township and area development projects
Eia of township and area development projectsSandeep Kumar
 
Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Khalid Abdel Naser Abdel Rahim
 
Human waste bank proposal,
Human  waste  bank  proposal,Human  waste  bank  proposal,
Human waste bank proposal,Eliud Kiogora
 
Ici final project
Ici final projectIci final project
Ici final projectkongzc
 
PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx
PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptxPRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx
PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptxBachtiar Candra
 
Project management plan
Project management planProject management plan
Project management planDonny Olson
 
Do You Need A Construction Phase Plan
Do You Need A Construction Phase PlanDo You Need A Construction Phase Plan
Do You Need A Construction Phase PlanLen Foster
 
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdfARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdfFaruq42
 
Summary of NBC 2016
Summary of NBC 2016Summary of NBC 2016
Summary of NBC 2016ssuserfa2cfd
 
Environmental Management Process-david leung
Environmental Management Process-david leungEnvironmental Management Process-david leung
Environmental Management Process-david leungicablearning
 
Guidelines for Santee Water Efficient Landscape
Guidelines for Santee Water Efficient LandscapeGuidelines for Santee Water Efficient Landscape
Guidelines for Santee Water Efficient LandscapeFujita64g
 
EMP Report of a Hospital
EMP Report of a HospitalEMP Report of a Hospital
EMP Report of a HospitalNirob Ahmed
 
Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)Palash Mehar
 

Similar to Construction quality control plan draft rev0 27_feb09 (20)

CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
Quality Control Program Proposal Final Draft
Quality Control Program Proposal Final DraftQuality Control Program Proposal Final Draft
Quality Control Program Proposal Final Draft
 
Erection method statement
Erection method statementErection method statement
Erection method statement
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENT
 
Eia of township and area development projects
Eia of township and area development projectsEia of township and area development projects
Eia of township and area development projects
 
Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...
 
Human waste bank proposal,
Human  waste  bank  proposal,Human  waste  bank  proposal,
Human waste bank proposal,
 
Ici final project
Ici final projectIci final project
Ici final project
 
Short termim workplan_20100602_part3
Short termim workplan_20100602_part3Short termim workplan_20100602_part3
Short termim workplan_20100602_part3
 
PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx
PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptxPRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx
PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx
 
Ici final project
Ici final projectIci final project
Ici final project
 
Project management plan
Project management planProject management plan
Project management plan
 
Do You Need A Construction Phase Plan
Do You Need A Construction Phase PlanDo You Need A Construction Phase Plan
Do You Need A Construction Phase Plan
 
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdfARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdf
 
Summary of NBC 2016
Summary of NBC 2016Summary of NBC 2016
Summary of NBC 2016
 
Environmental Management Process-david leung
Environmental Management Process-david leungEnvironmental Management Process-david leung
Environmental Management Process-david leung
 
Ici individual
Ici individualIci individual
Ici individual
 
Guidelines for Santee Water Efficient Landscape
Guidelines for Santee Water Efficient LandscapeGuidelines for Santee Water Efficient Landscape
Guidelines for Santee Water Efficient Landscape
 
EMP Report of a Hospital
EMP Report of a HospitalEMP Report of a Hospital
EMP Report of a Hospital
 
Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)
 

Recently uploaded

Sonam +91-9537192988-Mind-blowing skills and techniques of Ahmedabad Call Girls
Sonam +91-9537192988-Mind-blowing skills and techniques of Ahmedabad Call GirlsSonam +91-9537192988-Mind-blowing skills and techniques of Ahmedabad Call Girls
Sonam +91-9537192988-Mind-blowing skills and techniques of Ahmedabad Call GirlsNiya Khan
 
Low Rate Call Girls Gorakhpur Anika 8250192130 Independent Escort Service Gor...
Low Rate Call Girls Gorakhpur Anika 8250192130 Independent Escort Service Gor...Low Rate Call Girls Gorakhpur Anika 8250192130 Independent Escort Service Gor...
Low Rate Call Girls Gorakhpur Anika 8250192130 Independent Escort Service Gor...Suhani Kapoor
 
Dubai Call Girls Demons O525547819 Call Girls IN DUbai Natural Big Boody
Dubai Call Girls Demons O525547819 Call Girls IN DUbai Natural Big BoodyDubai Call Girls Demons O525547819 Call Girls IN DUbai Natural Big Boody
Dubai Call Girls Demons O525547819 Call Girls IN DUbai Natural Big Boodykojalkojal131
 
VIP Call Girls Service Saharanpur Aishwarya 8250192130 Independent Escort Ser...
VIP Call Girls Service Saharanpur Aishwarya 8250192130 Independent Escort Ser...VIP Call Girls Service Saharanpur Aishwarya 8250192130 Independent Escort Ser...
VIP Call Girls Service Saharanpur Aishwarya 8250192130 Independent Escort Ser...Suhani Kapoor
 
Preventing and ending sexual harassment in the workplace.pptx
Preventing and ending sexual harassment in the workplace.pptxPreventing and ending sexual harassment in the workplace.pptx
Preventing and ending sexual harassment in the workplace.pptxGry Tina Tinde
 
Neha +91-9537192988-Friendly Ahmedabad Call Girls has Complete Authority for ...
Neha +91-9537192988-Friendly Ahmedabad Call Girls has Complete Authority for ...Neha +91-9537192988-Friendly Ahmedabad Call Girls has Complete Authority for ...
Neha +91-9537192988-Friendly Ahmedabad Call Girls has Complete Authority for ...Niya Khan
 
Internshala Student Partner 6.0 Jadavpur University Certificate
Internshala Student Partner 6.0 Jadavpur University CertificateInternshala Student Partner 6.0 Jadavpur University Certificate
Internshala Student Partner 6.0 Jadavpur University CertificateSoham Mondal
 
Call Girl in Low Price Delhi Punjabi Bagh 9711199012
Call Girl in Low Price Delhi Punjabi Bagh  9711199012Call Girl in Low Price Delhi Punjabi Bagh  9711199012
Call Girl in Low Price Delhi Punjabi Bagh 9711199012sapnasaifi408
 
Business Development and Product Strategy for a SME named SARL based in Leban...
Business Development and Product Strategy for a SME named SARL based in Leban...Business Development and Product Strategy for a SME named SARL based in Leban...
Business Development and Product Strategy for a SME named SARL based in Leban...Soham Mondal
 
The Impact of Socioeconomic Status on Education.pdf
The Impact of Socioeconomic Status on Education.pdfThe Impact of Socioeconomic Status on Education.pdf
The Impact of Socioeconomic Status on Education.pdftheknowledgereview1
 
VIP Call Girls Firozabad Aaradhya 8250192130 Independent Escort Service Firoz...
VIP Call Girls Firozabad Aaradhya 8250192130 Independent Escort Service Firoz...VIP Call Girls Firozabad Aaradhya 8250192130 Independent Escort Service Firoz...
VIP Call Girls Firozabad Aaradhya 8250192130 Independent Escort Service Firoz...Suhani Kapoor
 
加利福尼亚艺术学院毕业证文凭证书( 咨询 )证书双学位
加利福尼亚艺术学院毕业证文凭证书( 咨询 )证书双学位加利福尼亚艺术学院毕业证文凭证书( 咨询 )证书双学位
加利福尼亚艺术学院毕业证文凭证书( 咨询 )证书双学位obuhobo
 
CALL ON ➥8923113531 🔝Call Girls Husainganj Lucknow best Female service 🧳
CALL ON ➥8923113531 🔝Call Girls Husainganj Lucknow best Female service  🧳CALL ON ➥8923113531 🔝Call Girls Husainganj Lucknow best Female service  🧳
CALL ON ➥8923113531 🔝Call Girls Husainganj Lucknow best Female service 🧳anilsa9823
 
Dubai Call Girls Starlet O525547819 Call Girls Dubai Showen Dating
Dubai Call Girls Starlet O525547819 Call Girls Dubai Showen DatingDubai Call Girls Starlet O525547819 Call Girls Dubai Showen Dating
Dubai Call Girls Starlet O525547819 Call Girls Dubai Showen Datingkojalkojal131
 
Employee of the Month - Samsung Semiconductor India Research
Employee of the Month - Samsung Semiconductor India ResearchEmployee of the Month - Samsung Semiconductor India Research
Employee of the Month - Samsung Semiconductor India ResearchSoham Mondal
 
VIP Call Girl Bhiwandi Aashi 8250192130 Independent Escort Service Bhiwandi
VIP Call Girl Bhiwandi Aashi 8250192130 Independent Escort Service BhiwandiVIP Call Girl Bhiwandi Aashi 8250192130 Independent Escort Service Bhiwandi
VIP Call Girl Bhiwandi Aashi 8250192130 Independent Escort Service BhiwandiSuhani Kapoor
 
Call Girls In Bhikaji Cama Place 24/7✡️9711147426✡️ Escorts Service
Call Girls In Bhikaji Cama Place 24/7✡️9711147426✡️ Escorts ServiceCall Girls In Bhikaji Cama Place 24/7✡️9711147426✡️ Escorts Service
Call Girls In Bhikaji Cama Place 24/7✡️9711147426✡️ Escorts Servicejennyeacort
 
Dubai Call Girls Naija O525547819 Call Girls In Dubai Home Made
Dubai Call Girls Naija O525547819 Call Girls In Dubai Home MadeDubai Call Girls Naija O525547819 Call Girls In Dubai Home Made
Dubai Call Girls Naija O525547819 Call Girls In Dubai Home Madekojalkojal131
 
VIP Russian Call Girls in Bhilai Deepika 8250192130 Independent Escort Servic...
VIP Russian Call Girls in Bhilai Deepika 8250192130 Independent Escort Servic...VIP Russian Call Girls in Bhilai Deepika 8250192130 Independent Escort Servic...
VIP Russian Call Girls in Bhilai Deepika 8250192130 Independent Escort Servic...Suhani Kapoor
 
VIP Call Girls in Cuttack Aarohi 8250192130 Independent Escort Service Cuttack
VIP Call Girls in Cuttack Aarohi 8250192130 Independent Escort Service CuttackVIP Call Girls in Cuttack Aarohi 8250192130 Independent Escort Service Cuttack
VIP Call Girls in Cuttack Aarohi 8250192130 Independent Escort Service CuttackSuhani Kapoor
 

Recently uploaded (20)

Sonam +91-9537192988-Mind-blowing skills and techniques of Ahmedabad Call Girls
Sonam +91-9537192988-Mind-blowing skills and techniques of Ahmedabad Call GirlsSonam +91-9537192988-Mind-blowing skills and techniques of Ahmedabad Call Girls
Sonam +91-9537192988-Mind-blowing skills and techniques of Ahmedabad Call Girls
 
Low Rate Call Girls Gorakhpur Anika 8250192130 Independent Escort Service Gor...
Low Rate Call Girls Gorakhpur Anika 8250192130 Independent Escort Service Gor...Low Rate Call Girls Gorakhpur Anika 8250192130 Independent Escort Service Gor...
Low Rate Call Girls Gorakhpur Anika 8250192130 Independent Escort Service Gor...
 
Dubai Call Girls Demons O525547819 Call Girls IN DUbai Natural Big Boody
Dubai Call Girls Demons O525547819 Call Girls IN DUbai Natural Big BoodyDubai Call Girls Demons O525547819 Call Girls IN DUbai Natural Big Boody
Dubai Call Girls Demons O525547819 Call Girls IN DUbai Natural Big Boody
 
VIP Call Girls Service Saharanpur Aishwarya 8250192130 Independent Escort Ser...
VIP Call Girls Service Saharanpur Aishwarya 8250192130 Independent Escort Ser...VIP Call Girls Service Saharanpur Aishwarya 8250192130 Independent Escort Ser...
VIP Call Girls Service Saharanpur Aishwarya 8250192130 Independent Escort Ser...
 
Preventing and ending sexual harassment in the workplace.pptx
Preventing and ending sexual harassment in the workplace.pptxPreventing and ending sexual harassment in the workplace.pptx
Preventing and ending sexual harassment in the workplace.pptx
 
Neha +91-9537192988-Friendly Ahmedabad Call Girls has Complete Authority for ...
Neha +91-9537192988-Friendly Ahmedabad Call Girls has Complete Authority for ...Neha +91-9537192988-Friendly Ahmedabad Call Girls has Complete Authority for ...
Neha +91-9537192988-Friendly Ahmedabad Call Girls has Complete Authority for ...
 
Internshala Student Partner 6.0 Jadavpur University Certificate
Internshala Student Partner 6.0 Jadavpur University CertificateInternshala Student Partner 6.0 Jadavpur University Certificate
Internshala Student Partner 6.0 Jadavpur University Certificate
 
Call Girl in Low Price Delhi Punjabi Bagh 9711199012
Call Girl in Low Price Delhi Punjabi Bagh  9711199012Call Girl in Low Price Delhi Punjabi Bagh  9711199012
Call Girl in Low Price Delhi Punjabi Bagh 9711199012
 
Business Development and Product Strategy for a SME named SARL based in Leban...
Business Development and Product Strategy for a SME named SARL based in Leban...Business Development and Product Strategy for a SME named SARL based in Leban...
Business Development and Product Strategy for a SME named SARL based in Leban...
 
The Impact of Socioeconomic Status on Education.pdf
The Impact of Socioeconomic Status on Education.pdfThe Impact of Socioeconomic Status on Education.pdf
The Impact of Socioeconomic Status on Education.pdf
 
VIP Call Girls Firozabad Aaradhya 8250192130 Independent Escort Service Firoz...
VIP Call Girls Firozabad Aaradhya 8250192130 Independent Escort Service Firoz...VIP Call Girls Firozabad Aaradhya 8250192130 Independent Escort Service Firoz...
VIP Call Girls Firozabad Aaradhya 8250192130 Independent Escort Service Firoz...
 
加利福尼亚艺术学院毕业证文凭证书( 咨询 )证书双学位
加利福尼亚艺术学院毕业证文凭证书( 咨询 )证书双学位加利福尼亚艺术学院毕业证文凭证书( 咨询 )证书双学位
加利福尼亚艺术学院毕业证文凭证书( 咨询 )证书双学位
 
CALL ON ➥8923113531 🔝Call Girls Husainganj Lucknow best Female service 🧳
CALL ON ➥8923113531 🔝Call Girls Husainganj Lucknow best Female service  🧳CALL ON ➥8923113531 🔝Call Girls Husainganj Lucknow best Female service  🧳
CALL ON ➥8923113531 🔝Call Girls Husainganj Lucknow best Female service 🧳
 
Dubai Call Girls Starlet O525547819 Call Girls Dubai Showen Dating
Dubai Call Girls Starlet O525547819 Call Girls Dubai Showen DatingDubai Call Girls Starlet O525547819 Call Girls Dubai Showen Dating
Dubai Call Girls Starlet O525547819 Call Girls Dubai Showen Dating
 
Employee of the Month - Samsung Semiconductor India Research
Employee of the Month - Samsung Semiconductor India ResearchEmployee of the Month - Samsung Semiconductor India Research
Employee of the Month - Samsung Semiconductor India Research
 
VIP Call Girl Bhiwandi Aashi 8250192130 Independent Escort Service Bhiwandi
VIP Call Girl Bhiwandi Aashi 8250192130 Independent Escort Service BhiwandiVIP Call Girl Bhiwandi Aashi 8250192130 Independent Escort Service Bhiwandi
VIP Call Girl Bhiwandi Aashi 8250192130 Independent Escort Service Bhiwandi
 
Call Girls In Bhikaji Cama Place 24/7✡️9711147426✡️ Escorts Service
Call Girls In Bhikaji Cama Place 24/7✡️9711147426✡️ Escorts ServiceCall Girls In Bhikaji Cama Place 24/7✡️9711147426✡️ Escorts Service
Call Girls In Bhikaji Cama Place 24/7✡️9711147426✡️ Escorts Service
 
Dubai Call Girls Naija O525547819 Call Girls In Dubai Home Made
Dubai Call Girls Naija O525547819 Call Girls In Dubai Home MadeDubai Call Girls Naija O525547819 Call Girls In Dubai Home Made
Dubai Call Girls Naija O525547819 Call Girls In Dubai Home Made
 
VIP Russian Call Girls in Bhilai Deepika 8250192130 Independent Escort Servic...
VIP Russian Call Girls in Bhilai Deepika 8250192130 Independent Escort Servic...VIP Russian Call Girls in Bhilai Deepika 8250192130 Independent Escort Servic...
VIP Russian Call Girls in Bhilai Deepika 8250192130 Independent Escort Servic...
 
VIP Call Girls in Cuttack Aarohi 8250192130 Independent Escort Service Cuttack
VIP Call Girls in Cuttack Aarohi 8250192130 Independent Escort Service CuttackVIP Call Girls in Cuttack Aarohi 8250192130 Independent Escort Service Cuttack
VIP Call Girls in Cuttack Aarohi 8250192130 Independent Escort Service Cuttack
 

Construction quality control plan draft rev0 27_feb09

  • 1. Draft Construction Quality Control Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut Revision 0 Prepared for: Olin Corporation Cleveland, Tennessee February 2009
  • 2. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT TABLE OF CONTENTS February 2009 i PAGE 1. INTRODUCTION .............................................................................................................................1 2. SITE DESCRIPTION .......................................................................................................................1 3. PROJECT ORGANIZATION..........................................................................................................2 4. QUALITY CONTROL METHODS ................................................................................................6 5. INSPECTIONS ..................................................................................................................................7 6. FIELD TESTING PROCEDURES..................................................................................................9 7. SUBMITTALS...................................................................................................................................9 8. DOCUMENTATION ......................................................................................................................10 9. REVISIONS TO WORK.................................................................................................................10 10. DEFINABLE FEATURES OF WORK .........................................................................................10
  • 3. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT LIST OF APPENDICES February 2009 ii APPENDIX CONCEPTUAL PROJECT ORGANIZATIONAL CHART ................................................................. A-1 RESUMES OF KEY PERSONNEL.......................................................................................................... A-2 PREPARATORY PHASE CHECKLIST ..................................................................................................B-1 INITIAL/FOLLOW-UP PHASE INSPECTION CHECKLIST..............................................................B-3 FINAL PHASE INSPECTION CHECKLIST...........................................................................................B-5 SUBMITTAL REGISTER......................................................................................................................... C-1 QUALITY CONTROL DAILY REPORT................................................................................................ D-1
  • 4. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT February 2009 1 1. INTRODUCTION This Construction Quality Control Plan (CQCP) will be implemented to ensure remedial and construction procedures are performed in compliance with the plans and specifications under this contract. This CQCP will provide a means to maintain effective quality control at the Non-Public Properties (NPP) Newhall Street Neighborhood Site (the Site). The quality control measures as presented herein include quality control organization; methods of performing, documenting, and enforcing quality control operations of both the primary Contractor and their subcontractors (including inspection and testing); inspections to be performed; and protocol describing corrective actions. Overall management of the CQCP will be the responsibility of the Contractor’s Quality Control Manager (QCM). The QCM will have the authority to act in all construction quality control CQC matters and will be responsible for ensuring that all materials and work comply with the contract specifications. All inspection and testing firms will be at the disposal of the QCM to ensure that all aspects of work are compliant with the contract. The QCM will report any deviations from the CQCP independently to the On-site Project Manager. The resume of the Contractor’s designated QCM will be submitted for approval prior to mobilization to the Site. 2. SITE DESCRIPTION The Newhall Street Neighborhood (Site) is located in the southern part of Hamden, Connecticut, east of Dixwell Avenue and just north of New Haven. The Newhall Street Neighborhood comprises an area that historically consisted of wetlands and low-lying areas. Waste materials were used to fill these areas from the late 1800s to the mid-1900s. Subsequently, homes, public buildings, and parks were built on and next to the historic fill areas. The primary potential human health risk associated with the Site is from direct exposure to the fill. The Site contains contaminated fill material known to contain contaminants consisting primarily of metals (lead and arsenic), polynuclear aromatic hydrocarbons (PAHs) and polychlorinated biphenyls (PCBs). The underlying groundwater generally does not pose a health risk to the residents because the area has a public water source, and the Site groundwater is not used for drinking or other domestic purposes. The NPP consent order includes an 18-block area (approximately) consisting of approximately of 230 residential properties. In October 2007, the Connecticut Department of Environmental
  • 5. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT February 2009 2 Protection (CTDEP) issued a final Remedy Selection Plan. The selected remedy for the residential properties (and other Non-Public Properties) located inside the Consent Order boundary is as follows: • Excavation of fill within the top 4 feet and off-site disposal at authorized facilities. • Backfill with clean soil. • Restoration of pre-existing features (landscaping, patios, fencing, driveways, etc.) if disturbed during construction. 3. PROJECT ORGANIZATION The Contractor’s key personnel assigned to this project should possess a broad range of remedial action experience and skills. All should have experience dealing with the handling of contaminated wastes and should be familiar with requirements of day-to-day work under this contract. The Contractor’s proposed project organization for this project and the resumes of key personnel, along with their job titles, should be submitted for review and approval. A conceptual project Organizational Chart is included in Appendix A. The functional responsibilities of key technical personnel are summarized as follows. 3.1 HOME OFFICE PERSONNEL Contractor – President and Chief Executive Officer The Contractor’s President and Chief Executive Officer (CEO) will ultimately be responsible for the project's success. He will provide the required resources to ensure that the project is successfully executed. He will be kept informed of the project's progress and maintain that the project is meeting its goals. The President and CEO will resolve problems that cannot be resolved by the On-site Project Manager or Corporate Project Manager. Contractor – Vice President The Contractor’s Vice President will oversee the project at the corporate level and report directly to the President/Chief Executive Officer. He will communicate with the On-site Project Manager regarding all aspects of the project including, but not limited to, project problems, progress, payments, schedules, administrative duties, and QCM oversight. He will also resolve problems that
  • 6. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT February 2009 3 cannot be resolved by the On-site Project Manager and will periodically visit the site and be acquainted with personnel and procedures. Contractor - Certified Industrial Hygienist (CIH) - Corporate Director of Health and Safety Regarding safety and occupational health, the Contractor will: • Maintain overall responsibility of Site safety. • Be responsible for assigning Site Safety and Health Officer (SSHO) responsibilities. • Ensure that all activities are carried out in compliance with the approved site Health and Safety Plan. The Contractor’s CIH and/or Corporate Director of Health and Safety is responsible for the preparation, implementation, and enforcement of the site-specific Health and Safety Plan (HASP). The Contractor’s SSHO will report site safety activities to the CIH and/or Corporate Director of Health and Safety on a regular basis, including all safety and occupational health issues. All job safety records generated will be thoroughly reviewed by the CIH and/or Corporate Director of Health and Safety, who will also perform quarterly job-site safety inspections. He will prepare an audit report of findings for each inspection, including identification of deficiencies requiring corrective action. The CIH and/or Corporate Director of Health and Safety will supervise the SSHO and develop the air-monitoring program. He will make periodic trips to the site to conduct safety audits, observe the administration of this plan, and make any necessary modifications to the program. Contractor - CHMM – Regulatory Specialist The Regulatory Specialist is responsible for regulatory compliance matters, including oversight of all field sampling and chemical data acquisition plans and correspondence with off-site laboratories. He will review laboratory reports with the selected lab in order to ensure compliance with project specifications and all required protocols. He will coordinate all off-site waste removal with Olin’s designated site representative, including transport, disposal, manifests, waste profiles, regulatory compliance, and disposal requirements (as required).
  • 7. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT February 2009 4 3.2 FIELD PERSONNEL Contractor - On-site Project Manager The Contractor’s On-site Project Manager, will be the primary contact person at the site with whom MACTEC/Olin will interact with on a daily basis under this contract. The Contractor’s On-site Project Manager will ensure that: • Appropriate resources are allocated to the project and balanced to ensure best value to Olin. • All cost tracking and reporting is carried out in a manner compliant with Olin’s Contract Management Procedures. • All tasks are conducted in accordance with the site HASP and project specifications. The Contractor’s field personnel should rely on home office support throughout the course of the project. The Contractor’s Vice President and on-site Project Manager will become and remain personally involved until each problem is resolved and appropriate corrective measures are implemented. They will typically communicate at least once daily on the progress of the project. The Project Manager will be present on the jobsite, to ensure that the project is progressing as scheduled. The On-site Project Manager is responsible for implementation and support of the Contractor’s CQCP and will oversee all aspects of work under this contract for remediation at the site, including: • All procurements. • Qualified Contractor and subcontractor resources are assigned to the project and balanced to ensure jobs are aligned with project needs. • The Site is maintained and secure. • All tasks are carried out safely and in compliance with the project specifications. His responsibilities include: • Contractor coordination. • Acting as site liaison between the Contractor and MACTEC/Olin. • Maintaining charge of all field operations.
  • 8. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT February 2009 5 Contractor - Quality Control Manager (QCM) The Quality Control Manager will report directly to the On-site Project Manager with matters concerning quality control. He will have both the authority and the duty to halt any operation appearing to be out of compliance with contract specifications. The QCM is responsible for keeping and maintaining all records related to personnel, supplies, equipment use, and equipment calibration and sampling. His function will be to ensure compliance with the contract plans and specifications. QCM responsibilities include: • Performing and documenting field inspections. • Preparing daily Quality Control Reports. • Scheduling, reviewing, certifying, and managing project submittals. • Maintaining the Submittal Register. • Providing coordination of required quality control testing, reviewing results, and submitting. • Coordinating, documenting, and tracking preparatory, initial, and follow-up inspections. • Tracking construction deficiencies and ensuring timely corrective action. • Coordinating field sampling activities (as required). • Reviewing calibration of test equipment (as necessary). • Preparing addenda to the CQCP as necessary when additional phases of work are added. • Maintenance of as-built drawings. • Coordinating responses to vendors’ requests for information and technical issues. • Serving as main point of contact at the site for MACTEC/Olin questions and discussions on quality and technical issues. • Delegating duties to alternate QCMs and notifying MACTEC/Olin to whom what duties have been delegated. The QCM or an alternate will be on-site when work is being performed.
  • 9. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT February 2009 6 Contractor - Site Safety and Health Officer (SSHO) The Site Safety and Health Officer will report to the Certified Industrial Hygienist and be responsible for the implementation of the approved Site Health and Safety Plan; including conducting required safety inspections, safety briefings, and reports of safety-related activities. He has received 40-hour HAZWOPER training per 29 CFR 1910.120(e), and possesses current Red Cross First Aid and CPR training. Contractor - Superintendent The project Superintendent will be responsible for supervising all field activities. His duties include supervision of the craft labor (equipment operators, truck drivers, and laborers), technical staff (survey crew), and all subcontractors. The designated Superintendent is also responsible for the maintenance of all on-site construction equipment. Contractor – Transportation and Disposal Coordinator The Transportation and Disposal Coordinator will be experienced in gathering and analyzing data, and developing and implementing sampling plans and quality control programs. The designated Contractor representative will be responsible for the coordination of transportation and disposal at the Site. 4. QUALITY CONTROL METHODS The CQCP will be implemented in order to ensure compliance with the specifications for remedial action construction as detailed in the contract specifications. The basis of the CQCP is nationally recognized standards published by the American Society for Testing and Materials (ASTM) and the Project Specifications. In addition, procedures utilized within the CQCP should reflect the experience gained by the prime Contractor in completing construction projects similar to the Newhall Street Neighborhood Project. Quality control measures will extend to field sampling procedures; staffing; types of material and equipment to be used; and methods of performing, documenting, and enforcing quality control operations of both the Contractor and subcontractors (including inspection and testing). As previously stated, maintenance of the CQCP will be the responsibility of the QCM. The QCM will be responsible for ensuring that all materials and work comply with the contract specifications.
  • 10. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT February 2009 7 The QCM may have a field engineer at his disposal to assist him with the on-site inspections. Testing firms will be at the disposal of the QCM to ensure contract compliance in all aspects of work. All reports from testing firms will be forwarded to the QCM for his review and approval. 4.1 IMPLEMENTATION The QCM will be responsible for implementing the CQC Plan by ensuring that quality materials and supplies are provided for the proposed project, and that good workmanship is provided in all aspects of this contract. The QCM will report directly to the On-site Project Manager and will complete daily site inspections to ensure compliance with the quality control specifications. Daily reports will be completed listing all field testing and sampling activities. These reports will be submitted to the MACTEC/Olin representative on a daily basis. The QCM will be responsible for ensuring that all materials and work comply with the contract plans and specifications, and that all performance standards are met. It is anticipated that the MACTEC/Olin representative and the Contractor’s QCM will meet frequently in order to forecast and/or prevent any potential problems from arising. An on-site quality control meeting will be conducted on a weekly basis as part of the weekly progress meeting in order to review performance during the previous one-week period, and prepare for the upcoming two-week period. It is anticipated that the Contractor’s On-site Project Manager, Health and Safety Officer, Superintendent and MACTEC/Olin representatives will attend this meeting. 4.2 DOCUMENTING The QCM will record project activities in a daily quality control report maintained on site at all times. All site activities, site inspections, and field testing of materials will be recorded on a daily basis, along with any unacceptable site occurrences or deficiencies and their associated corrective actions. Each daily entry into the report will be signed by the QCM. Quality control reports will be submitted on a daily basis during all field construction activities. 5. INSPECTIONS To ensure that all construction and remedial activities comply with the project specifications, the QCM will complete, in conjunction with the subcontractors, three phases of site inspections for each feature of work. These inspections will include the following:
  • 11. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT February 2009 8 PHASE I - PREPARATORY INSPECTION Preparatory inspections will be performed prior to beginning work on any definable feature of the project and will include: • Review of submittal requirements and all other Contract requirements with the performance of the work; • Check to assure that provisions have been made to provide required field quality control testing; • Examine the work area to ascertain that all preliminary work has been completed; • Verify all field dimensions and advise MACTEC/Olin of any discrepancies; • Perform a physical examination of materials and equipment to assure that they conform to approved shop drawings or submittal data and that all required materials and/or equipment are on hand and comply with the Contract requirements. Subsequent to the preparatory inspection and prior to commencement of work, the Contractor shall instruct each applicable worker on the level of workmanship required to meet contract specifications. PHASE II - INITIAL INSPECTIONS Initial phase inspections will be performed as soon as a representative portion of the particular feature of work has been accomplished. Initial inspections include, but are not limited to, examination of the quality of workmanship; review of control testing for compliance with control requirements; and identification of defective or damaged materials, omissions, and dimensional requirements. The initial phase inspection is the time to discuss and agree on the required level of quality associated with a given work activity. Any discrepancies relative to work quality should be addressed at this time.
  • 12. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT February 2009 9 PHASE III - FOLLOW-UP INSPECTIONS Follow-up inspections will be performed daily as work progresses to ensure continuing compliance with contract requirements, including control testing, until completion of the particular feature of work. Final follow-up inspections will be conducted and deficiencies corrected prior to beginning new work. The QCM will notify MACTEC/Olin at least 24 hours in advance of any inspections. Notification and meeting minutes of all inspections will be recorded in the Daily Quality Control Report. Examples of the inspection forms to be utilized are presented in Appendix B. 6. FIELD TESTING PROCEDURES The Contractor will conduct field-testing to verify that control measures are adequate to provide a product that conforms to contract requirements. Field testing will be conducted under the auspices of the QCM and he or his designee shall: • Arrange for, or conduct, field testing in accordance with applicable test parameters (ASTM, etc). • Verify that facilities and testing equipment are available and comply with testing standards and ensure that testing facilities are approved by Olin and are validated. • Check test equipment calibration data against certified standards. • Verify that all tests are documented and submitted as part of quality control system reporting. • Review all test documentation prior to submittal. 7. SUBMITTALS The QCM will follow standard procedures concerning submittals, including the use of the MACTEC transmittal form. Each submittal form may contain more than one submittal specific to that specification section. A submittal register listing major submittals will be prepared by MACTEC (a sample Submittal Register is included in Appendix C). This register will be prepared in conjunction with the anticipated progress schedule. The QCM will be responsible for the review and approval of submittals prior to their submittal to MACTEC/Olin representative. This includes reviews of materials and suppliers’ catalog cuts, as well as subcontractor submittals. The QCM will review the submittal for completeness and compliance with the contract specifications. Variations to a submittal will be noted on the MATEC transmittal form. The QCM will actively participate during procurement activities to ensure purchase orders and subcontracts comply with the contract.
  • 13. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT February 2009 10 8. DOCUMENTATION All testing results will be recorded on the daily quality control report. A sample Daily QC report is included in Appendix D. Any concerns or deviations from the required material specifications and the actions taken to correct the problems will be noted on the report. Information recorded on the daily quality control report will include: • Definable features of work that was addressed. • Description of trades working on the project. • Numbers of personnel. • Weather conditions. • Types and numbers of tests performed. • Results of testing. • Nature of defects or cause for rejection. • Proposed corrective action(s). • Corrective action taken and date. • Delays encountered. • Directions received from the Engineer and actions taken. • Health and safety issues or deficiencies and how they were resolved. • Deficiencies. 9. REVISIONS TO WORK The Contractor will be responsible for ensuring total compliance of field work to the project specifications. Should modifications or revisions to the specifications become necessary, the Contractor will make the request, in writing, to MACTEC/Olin. Approval from MACTEC/Olin must be received prior to allowing the modifications or revisions to be made in the field. The QCM will be informed of and record all such requests in his daily log and on the daily quality control report. 10. DEFINABLE FEATURES OF WORK Listed below are the general categories and types of work that will be performed under this contract. These items, known as Definable Features of Work, have been grouped into the various categories in which work will be performed, and correlate to measurement and payment. Suitable quality control methods and procedures will be utilized in order to ensure that all work is performed to the standards and quality required by the specifications.
  • 14. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT February 2009 11 The following are the definable features of work that will be performed under this contract: • Pre-Construction Preparation Activities • Mobilization • Site Preparation • Tire Pond Management • Clearing and Grubbing • Demolition and Removal of Above Ground Items • Excavation of Impacted Fill Material • Transportation and Disposal of Impacted Fill Material • Backfill/Utility Replacement • Restoration • Demobilization
  • 15. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT APPENDIX A February 2009 A-1 NPP Newhall Street Neighborhood - Olin Site Conceptual Project Organizational Chart
  • 16. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT APPENDIX A February 2009 A-2 Resumes of Key Personnel -To be added by Contractor
  • 17. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT APPENDIX B February 2009 B-1 Preparatory Phase Checklist NPP Newhall Street Neighborhood-Olin Site Contract: Date Preparatory Held: Spec. Section & Paragraph Definable Feature of Work: Drawing Sheet Numbers Major Definable Feature: 1) Personnel Present Name Position Company 2) Has each spec. paragraph, drawing, and shop drawing detail been studied? Yes___ No___ 3) Transmittals Involved Number and Item Code Contractor Approval C-1Have all items involved been approved? Yes No 1. Are all materials on-hand? Yes No . Are the materials on the job-site to be incorporated the same as those approved? Yes No Have all materials been checked for contract compliance against approved shop drawings? Yes No Equipment to be Used in Executing the Work: Items not on-hand or not in compliance with transmittals: 2. Tests required in accordance with contract requirements: Test Paragraph
  • 18. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT APPENDIX B February 2009 B-2 Accident Prevention Planning - Hazard Control Measures: Activity Hazard Analyses (Job Hazard Analyses) F-1Applicable Outlines (Attach completed copies) Activity Hazard Analysis Activity Hazard(s) Controls F-2Operational Equipment Checklist Attached For: On File For: 3. Have procedures for accomplishing work been reviewed with appropriate people? Yes No ___ Scope of Work/Method of Construction: Safety Issues: Spill Prevention Issues: 4. Has all preliminary work been accomplished in accord with contract requirements and is this segment of work ready to start? Yes No ___ H-1Explain any problems: 1. Remarks: CQCSM Comments: Contractor’s Comments: Quality Control Representative
  • 19. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT APPENDIX B February 2009 B-3 Initial/Follow-Up Phase Inspection Checklist NPP Newhall Street Neighborhood-Olin Site Inspection Type: Initial Phase Follow-Up Phase Date: Specifications Paragraph: Description and Location of Work Inspected: Reference Contract Drawings: A. Personnel Present Name Position Company B. Materials Being Used Are In Strict Compliance With The Contract Plans and Specifications YES NO _____ If not, explain: C. Procedures And/Or Work Methods Witnessed Are In Strict Compliance With The Requirements Of The Contract Specifications: YES NO _____ If not, explain: D. Workmanship Is Acceptable. YES NO State Areas Where Improvement Is Needed: E. Safety Violations and Corrective Actions Taken: F. Remarks: Quality Control Representative
  • 20. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT APPENDIX B February 2009 B-4 Final Phase Inspection Checklist NPP Newhall Street Neighborhood-Olin Site Date: Specifications Paragraph: Definable Feature of Work: Description and Location of Work Inspected: Reference Contract Drawings: A. Personnel Present Name Position Company B. Materials Used In Strict Compliance With The Contract Plans and Specifications YES NO _____ If not, explain: C. Procedures And/Or Work Methods Witnessed Are In Strict Compliance With The Requirements Of The Contract Specifications: YES NO _____ If not, explain: C. Workmanship is Acceptable: YES NO _____ State Areas Where Improvement is Needed: E. Remarks: Quality Control Representative
  • 21. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT APPENDIX C February 2009 C-1 SUBMITTAL STATUS CODES A – Reviewed B – Reviewed as Noted C – Reviewed as Noted, Resubmission Requested D- Revise and Resubmit SUBMITTAL REGISTER OLIN, NPP Newhall Street Neighborhood, Hamden, Connecticut REQUIRED SUBMITTALS Anticipated Submittal Date Date Submitted to Engineer Date Submittal Returned from Engineer and status (see codes below for status) Date Resubmitted to Engineer Date Submittal Returned from Engineer and status (see codes below for status) Date Resubmitted to Engineer Date Submittal Returned from Engineer and status (see codes below for status) Section No. Spec Description Contractor/ Vendor
  • 22. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT APPENDIX D February 2009 D-1 Conceptual Contractor Quality Control Daily Report REPORT NO.: JOB NO.: DATE: PROJECT TITLE: NPP NEWHALL STREET NEIGHBORHOOD Location: Hamden, Connecticut Max Min WEATHER: RAINFALL: TEMP: ____________________________________________________________________________ 1. Work performed by Prime Contractor (Include Plant and Labor Breakdown) *See attachment for Labor and Equipment Breakdown - None 2. Work performed by Sub-Contractors (Include “Number of Personnel” Breakdown) - None 3. Material and/ or Equipment delivered to site - None 4. Type and Results of Inspections - None 5. Type and Location of Tests performed and results - None 6. Verbal instructions received from Engineer or Olin, on construction deficiencies or retesting required (include corrective action to be taken) - None 7. Health and Safety observations or actions taken - None
  • 23. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT APPENDIX D February 2009 D-2 8. Delays / Problems/Deficiencies - None 9. Planned Activities - None 10. Attachments - None 11. Clarifications to Daily Reports - None 12. Remarks - None Certification: I certify that the above report is complete and correct and that I, or my representative, have inspected the work performed this day by the Prime Contractor and each Subcontractor and have determined that all materials, equipment, and workmanship are in strict compliance with the Contract Documents, Plans and Specifications. Any exceptions to these contract requirements will be noted above. ______________________________________ Contractor’s Quality Control Manager SUBMITTAL STATUS CODES A – Reviewed C – Reviewed as Noted, Resubmission Requested B – Reviewed as Noted D- Revise and Resubmit
  • 24. CONSTRUCTION QUALITY CONTROL PLAN NON-PUBLIC PROPERTIES, NEWHALL STREET NEIGHBORHOOD HAMDEN, CONNECTICUT APPENDIX D February 2009 D-3 COMPANY EQUIPMENT WORKING TODAY RENTAL EQUIPMENT WORKING TODAY TYPE OF EQUIPMENT EQUIPMENT NUMBER TYPE OF EQUIPMENT VENDOR MATERIALS AND/OR SERVICES RECEIVED TODAY VENDOR NAME DESCRIPTION EQUIPMENT LIST EQUIPMENT EQUIPMENT NUMBER DATE MOBILIZE TO SITE DATE DEMOBILIZED FROM SITE RENTAL EQUIPMENT EQUIPMENT VENDOR DATE MOBILIZE TO SITE DATE DEMOBILIZED FROM SITE SUBMITTAL STATUS CODES A – Reviewed C – Reviewed as Noted, Resubmission Requested B – Reviewed as Noted D- Revise and Resubmit