www.ignitetribes.com
LEVEL 5 LEVEL 6
UPSTREAM WBS EXAMPLE < WELL HEAD PLATFORM,RISER PLATFORM,FPSO,FLNG,SUBSEA FACITIY >
ENGINEERING
1.2.1 GENERAL
1.2.1.1 SPECIFICATION/ PROCEDURES / REPORTS
1.2.1.2 CALCULATIONS
1.2.1.3 DATA SHEETS
1.2.1.4 DRAWINGS
1.2.1.5 MATERIAL REQUISITIONS
1.2.1.6 TECHNICAL BID EVALUATION (TBE)
1.2.1.7 VENDOR DOCUMENTS
1.2.2 PROCESS
1.2.2.1 SPECIFICATION/ PROCEDURES / REPORTS
1.2.2.2 CALCULATIONS
1.2.2.3 DATA SHEETS
1.2.2.4 DRAWINGS
1.2.2.5 MATERIAL REQUISITIONS
1.2.2.6 TECHNICAL BID EVALUATION (TBE)
1.2.2.7 VENDOR DOCUMENTS
1.2.2.8 HAZOP REVIEW
1.2.3 STRUCTURAL
1.2.3.1 SPECIFICATION/ PROCEDURES / REPORTS
1.2.3.2 CALCULATIONS
1.2.3.3 DATA SHEETS
1.2.3.4 DRAWINGS
1.2.3.5 MATERIAL REQUISITIONS
1.2.3.6 TECHNICAL BID EVALUATION (TBE)
1.2.3.7 VENDOR DOCUMENTS
1.2.4 MECHANICAL
1.2.4.1 SPECIFICATION/ PROCEDURES / REPORTS
1.2.4.2 CALCULATIONS
1.2.4.3 DATA SHEETS
1.2.4.4 DRAWINGS
1.2.4.5 MATERIAL REQUISITIONS
1.2.4.6 TECHNICAL BID EVALUATION (TBE)
1.2.4.7 VENDOR DOCUMENTS
1.2.5 PIPING
1.2.5.1 SPECIFICATION/ PROCEDURES / REPORTS
1.2.5.2 MODELLING AND MODEL REVIEW
1.2.5.3 CALCULATIONS
1.2.5.4 DATA SHEETS
1.2.5.5 DRAWINGS
1.2.5.6 MATERIAL REQUISITIONS
1.2.5.7 TECHNICAL BID EVALUATION (TBE)
1.2.5.8 VENDOR DOCUMENTS
1.2.5.9 MTO
1.2.6 ELECTRICAL
1.2.6.1 SPECIFICATION/ PROCEDURES / REPORTS
1.2.6.2 CALCULATIONS
1.2.6.3 DATA SHEETS
1.2.6.4 DRAWINGS
1.2.6.5 MATERIAL REQUISITIONS
1.2.6.6 TECHNICAL BID EVALUATION (TBE)
1.2.6.7 VENDOR DOCUMENTS
1.2.7 INSTRUMENT AND TELECOMMUNICATION
1.2.7.1 SPECIFICATION/ PROCEDURES / REPORTS
1.2.7.2 CALCULATIONS
1.2.7.3 DATA SHEETS
1.2.7.4 DRAWINGS
1.2.7.5 MATERIAL REQUISITIONS
1.2.7.6 TECHNICAL BID EVALUATION (TBE)
1.2.7.7 VENDOR DOCUMENTS
1.2.8 CIVIL
1.2.8.1 SPECIFICATION/ PROCEDURES / REPORTS
1.2.8.2 CALCULATIONS
1.2.8.3 DATA SHEETS
1.2.8.4 DRAWINGS
1.2.8.5 MATERIAL REQUISITIONS
1.2.8.6 TECHNICAL BID EVALUATION (TBE)
1.2.8.7 VENDOR DOCUMENTS
1.2.9 PIPELINES
1.2.9.1 SPECIFICATION/ PROCEDURES / REPORTS
1.2.9.2 CALCULATIONS
1.2.9.3 DATA SHEETS
1.2.9.4 DRAWINGS
1.2.9.5 MATERIAL REQUISITIONS
1.2.9.6 TECHNICAL BID EVALUATION (TBE)
1.2.9.7 VENDOR DOCUMENTS
1.2.10 ARCHITECTURE
1.2.1O.1 SPECIFICATION/ PROCEDURES / REPORTS
1.2.1O.2 CALCULATIONS
1.2.1O.3 DATA SHEETS
1.2.1O.4 DRAWINGS
1.2.1O.5 MATERIAL REQUISITIONS
1.2.1O.6 TECHNICAL BID EVALUATION (TBE)
1.2.1O.7 VENDOR DOCUMENTS
1.2.11 HSE (FIRE AND SAFETY)
1.2.12 FINAL DOCUMENTATION
1.2.13 OTHERS
LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4
REFERTODELIVERABLESLISTANDPROGRESSMEASUREMENTSYSTEM
REFERTODELIVERABLESLISTANDPROGRESSMEASUREMENTSYSTEM
LEVEL 5 LEVEL 6LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4
1.3 PROCUREMENT
1.3.1 MECHANICAL
MECHANICAL EQUIPMENT
1.3.1.1 COLUMN, VESSELS, DRUMS
1.3.1.2 HEAT EXCHANGER, CONDENSER
1.3.1.3 BOILER, HEATER & FURNACES
1.3.1.4 TANKS
1.3.1.5 GAS TURBINE DRIVEN BOOSTER COMPRESSOR
1.3.1.6 OTHER COMPRESSORS, FAN AND BLOWERS
1.3.1.7 PUMPS
1.3.1.8 FILTER/ COALESCER
1.3.1.9 PIG LAUNCHER/RECEIVER
1.3.1.10 HOIST /CRANE
1.3.1.11 OTHER MECHANICAL EQUIPMENT
MECHANICAL PACKAGE
1.3.1.12 FLARE PACKAGE
1.3.1.13 NITROGEN PACKAGE
1.3.1.14 CHEMICAL INJECTION PACKAGE
1.3.1.15 MEG REGENERATION PACKAGE
1.3.1.16 ACID GAS REMOVAL UNIIT
1.3.1.17 GAS TURBINE GENERATOR
1.3.1.18 MICRO TURBINE GENERATOR
1.3.1.19 EFFLUENT TREATMENT PACKAGE
1.3.1.20 DEHYDRATION PACKAGE
1.3.1.21 WATER TREATMENT PACKAGE
1.3.1.22 HVAC EQUIPMENT PACKAGE
1.3.1.23 CONDENSATE DESALTER
1.3.1.24 SULPHUR RECOVERY PACKAGE
1.3.1.25 OTHER PACKAGE EQUIPMENT
1.3.2 PIPING AND VALVES
1.3.2.1 PIPES
1.3.2.2 FITTING & FLANGES
1.3.2.3 BALL VALVE
1.3.2.4 BUTTERFLY VALVE
1.3.2.5 CHECK VALVE
1.3.2.6 CHOKE VALVE
1.3.2.7 GATE VALVE
1.3.2.8 OTHER MANUAL VALVES
1.3.2.9 PIPE SUPPORT
1.3.2.10 OTHER PIPING MATERIALS
1.3.3 ELECTRICAL
1.3.3.1 HV, MV & LV Switchgears
1.3.3.2 Power Transformers
1.3.3.3 Distribution Board
1.3.3.4 MCC
1.3.3.5 Cabling System
1.3.3.6 Lighting System
1.3.3.7 Grounding System
1.3.3.8 Cathodic Protection
1.3.3.9 Batteries
1.3.3.10 Electrical Motors
1.3.3.11 Electrical Generators
1.3.3.12 Electrical Bulk Material
1.3.3.13 Other Electrical Equipment
1.3.4 INSTRUMENT
1.3.4.1 GAUGES
1.3.4.2 CONTROL VALVE
1.3.4.3 OTHER ACTUATED VALVES
1.3.4.4 GAS & CONDENSATE METERING SYSTEM
1.3.4.5 WELL HEAD CONTROL PANEL
1.3.4.6 MULTIPHASE FLOW METER
1.3.4.7 FIELD INSTRUMENTS & TUBING
1.3.4.8 SHUTDOWN SYSTEM
1.3.4.9 CONTROL SYSTEM
1.3.4.10 TELEMETRY SYSTEM
1.3.4.11 DCS & SCADA SYSTEM
1.3.4.12 CABLING SYSTEM (INCL. FIBER OPTIC)
1.3.4.13 TRANSMITTERS
1.3.4.14 INSTRUMENT BULK MATERIAL
1.3.4.15 OTHER INSTRUMENT EQUIPMENT
1.3.5 TELECOMMUNICATION
1.3.5.1 TELEPHONE & FAX SYSTEM
1.3.5.2 RADIO & RADAR SYSTEM
1.3.5.3 SATELLITE SYSTEM
1.3.5.4 PUBLIC ADDRESS, SIGNALING, ALARM & SECURITY SYSTEM
1.3.5.5 CABLING SYSTEM
1.3.5.6 OTHER TELECOMM. EQUIPMENT
1.3.6 SUBSEA
1.3.6.1 CHRISTMAS TREE
1.3.6.2 MANIFOLD / PLEM
1.3.6.3 UMBILICAL SYSTEM
1.3.6.4 HFL SYSTEM
1.3.6.5 EFL SYSTEM
1.3.6.6 OTHER MECHANICAL EQUIPMENT
1.3.6.7 OTHER E&I EQUIPMENT
1.3.7 CIVIL
1.3.7.1 BUILDING MATERIALS
1.3.7.2 PILING / FOUNDATION MATERIALS
1.3.7.3 OTHER CIVIL BULK MATERIALS
1.3.8 STRUCTURAL STEEL
1.3.8.1 STRUCTURAL BEAM
1.3.8.2 STRUCTURAL PLATE
1.3.8.3 STRUCTURAL TUBULAR
1.3.8.4 OTHER STEEL STRUCTURE MATERIALS
1.3.9 PAINTING AND COATING
1.3.9.1 PAINT AND COATING
1.3.9.2 OTHER COATIG MATERIAL
REFERTODELIVERABLESLISTANDPROGRESSMEASUREMENTSYSTEM
REFERTODELIVERABLESLISTANDPROGRESSMEASUREMENTSYSTEM
LEVEL 5 LEVEL 6LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4
1.4
FABRICATION /
CONSTRUCTION
1.4.1 FRONT END ACTIVITIES /MOBILIZATION
1.1.1.1 YARD PREPARATIONS (OFFICE,AMENITIES, ETC)
1.1.1.2 FABRICATION OF FRAMING/SUPPORT FOUNDATION
1.1.1.3 MOBILIZATION OF PROJECT MANAGEMENT TEAM
1.1.1.4 MOBILIZATION OF PROJECT MANAGEMENT TEAM
1.1.1.5 MOBILIZATION OF NDT SOURCE INSPECTION
1.1.1.6 MOBILIZATION OF STRUCTURAL SUB-CONTRACTOR
1.1.1.7 MOBILIZATION OF PIPING/PLUMBING SUB-CONTRACTOR
1.1.1.8 MOBILIZATION OF PIPING/PLUMBING SUB-CONTRACTOR
1.1.1.9 MOBILIZATION OF PAINTING SUB-CONTRACTOR
1.1.1.10 MOBILIZATION OF E&I SUB-CONTRACTOR
1.1.1.11 MOBILIZATION OF E&I HVAC/DUCTING SUB-CONTRACTOR
` 1.1.1.12 MOBILIZATION OF ARCHITECTURAL SUB-CONTRACTOR
1.1.1.13 PROJECT PLANNING AND MONITORING CHART
1.1.1.14
WQT/WPS (NUMBER OF WELDERS/WED(NUMBER OF WELDERS/WELDING
OPERATORS/WPS)
1.1.1.15 TEST PANEL/COATING SYSTEM QUALIFICATION TEST(NUMBER OF TEST PANELS)
1.4.2 PREPARATION
1.1.1.1 YARD PREPARATIONS (OFFICE,AMENITIES, ETC)
1.4.3 ENGINEERING (SHOP DRAWING)
1.4.3.1 GENERAL
1.4.3.2 STRUCTURAL
1.4.3.3 MECHANICAL
1.4.3.4 PIPING
1.4.3.5 ELECTRICAL
1.4.3.6 INSTRUMENT AND TELECOMMUNICATION
1.4.3.7 CIVIL
1.4.3.8 PIPELINES
1.4.3.9 ARCHITECTURE
1.4.3.10 HVAC / DUCTING
1.4.4 YARD PRELIMINARIES / FABRICATION / CONSTRUCTION
1.4.4.1 STRUCTURAL
FABRICATION OF STRUCTURAL MEMBERS
FABRICATION OF MEMBERS
ERECTION
TRIAL FIT/WEIGHING
OTHER STRUCTURAL WORK
1.4.4.2 MECHANICAL
MECHANICAL EQUIPMENT SUPPORT
MECHANICAL EQUIPMENT INSTALLATION
1.4.4.3 PIPING
PIPE SUPPORT FABRICATION
PIPE FABRICATION
PIPE SUPPORT INSTALLATION
LEAK TEST VALVE
VALVE INSTALLATON
FLUSHING, HYDROTEST AND ACID CLEANING
1.4.4.4 PIPELINE
PIPE COATING
PIPE FABRICATION
1.4.4.5 ELECTRICAL
FABRICATION OF ELECTRICAL SUPPORT
INSTALLATION OF ELECTRICAL SUPPORT
CABLE TRAY/CABLE LADDER INSTALLATION
CABLE PULLING
FIELD ELECTRICAL DEVICE INSTALLATION
ELECTRICAL EQUIPMENT INSTALLATION
CALIBRATE ELECTRICAL EQUIPMENT
DRESSING/GLANDING/TAGGING
1.4.4.6 INSTRUMENT AND TELECOMMUNICATION
FABRICATION O F INSTRUMENT SUPPORT
INSTRUMENT CABLE TRAY/LADDER/CONDUITS
INSTALLATION
INSTRUMENT CABLE PULLING
INSTRUMENT LIGHTING AND FIXTURES
INSTRUMENT EQUIPMENT INSTALLATION
INSTALLATION OF PIPE SUPPORT
INSTALLATION OF TUBING/AIR SUPPL
INSTRUMENT TUBING / LEAK TEST
TELEPHONE AND LAN INSTALLATION
CCTV
RADIO SYS
DRESSING / GLANDING / TAGGING/ TERMINATION
CALIBRATE INSTRUMENT
1.4.4.7 ARCHITECTURE
WALL PARTITION AND PANEL INSTALLATION
DOORS AND WINDOW
INSTALL FLOOR PEDESTAL
INSTALL HANGERS AND FALSE CEILING
REFERTODELIVERABLESLISTANDPROGRESSMEASUREMENTSYSTEM
LEVEL 5 LEVEL 6LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4
1.4.4.8 HVAC / DUCTING
FABRICATION OF DUCTING SUPPORT
INSTALLATION OF DUCTING SUPPORT
HVAC DUCTING FABRICATION AND INSTALLATION
FABRICATION OF ELECTRICAL / INSTRUMENT
SUPPORT
INSTALLATION OF ELECTRICAL / INSTRUMENT
SUPPORT
TUBING TRAY/ CABLE TRAY/ LADDER
INSTALLATION
FIELD HVAC DEVICE INSTALLATION
HVAC EQUIPMENT INSTALLATION
CALIBRATE HVAC EQUIPMENT
DRESSING, GLANDING, TAGGING AND
TERMINATION
1.4.4.9 BLAST AND PAINTING
EQUIPMENT PAINTING
PIPE BLASTING AND PAINTING
1.4.4.10 INSULATION EQUIPMENT INSULATION
PIPE INSULATION
1.4.5 TESTING AND COMMISSIONING
1.4.5.1 ELECTRICAL *NUMBER OF SYSTEMS
1.4.5.2 INSTRUMENT AND COMMUNICATION *NUMBER OF SYSTEMS
1.4.5.3 PIPING AND PLUMBING *NUMBER OF SYSTEMS
1.4.5.4 PIPELINE *NUMBER OF SYSTEMS
1.4.5.5 MECHANICAL *NUMBER OF SYSTEMS
1.4.5.6 HVAC *NUMBER OF SYSTEMS
1.4.5.7 SYSTEM TESTING *NUMBER OF SYSTEMS
1.4.6 LOAD-OUT AND SEA FASTEING
1.4.6.1 DRAWINGS
1.4.6.2 MATERIALS
1.4.6.3 WEIGHING
1.4.6.4 SEA FASTENING FABRICAION
1.4.6.5 LOAD-OUT AND POSITIONING
1.4.6.6 TIE-DOWN ARRANGEMENT
1.4.7 FINAL DOCUMENTATION
1.4.7.1 QA/QC DOCUMENTS
1.4.7.2 EQUIPMENT DOSSIER
1.4.7.3 MATERIAL DOCUMENTS
1.4.7.4 TESTING AND PRE-COMMISSIONING DOCUMENTS
1.4.7.5 DESIGN DATA
1.4.7.6 AS-BUILT DRAWING
1.4.7.7 NDT RECORDS AND RADIOGRAPHS
1.5 INSTALLATION
1.5.1 PRE-INSTALL ENGINEERING AND PROCUREMENT
1.5.1.1 SHOP DRAWING
1.5.1.2 PROCEDURE
1.5.1.3 PROCUREMENT OF INSTALLATION MATERIALS
1.5.2 MARINE SPREAD MOBILIZATION
1.5.2.1 PREPARATION ACTIVITIES
1.5.2.2 MOBILIZATION OF BARGE AT YARD
1.5.3 TRANSPORTATION
1.5.3.1 SAIL AWAY AND ARRIVE AT SITE
1.5.4 INSTALLATION
1.5.4.1 PREPARATION ACTIVITIES
1.5.4.2 TOPSIDE INSTALLATION (TOPSIDE AS EX)
1.5.4.3 WELD AND NDT OF TOPSIDE
1.5.5 MARINE SPREAD DEMOB
1.5.5.1 DEMOB OF MARINE SPREAD
1.5.5.2 FINAL DOCUMENTATION
LEVEL 5 LEVEL 6LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4
1.6
HUC (HOOK-UP AND
COMMISSIONING)
1.6.1 COMMISSIONING ENGINERING
1.6.1.1 SHOP DRAWING
1.6.1.2 PROCEDURE
1.6.2 COMMISSIONING PROCUREMENT
1.6.2.1 PROCUREMENT FOR HUC MATERIALS
1.6.3 PRE-FABRICATION
1.6.3.1 PREPARATION ACTIVITIES
1.6.3.2 PRE-FABRICATION
1.6.4 OFSHORE-HUC
PREPARATION ACTIVITIES
MOBILIZATION OF WORK BOAT
SET-UP ANCHOR
FACILITIES HOOK-UP
POST-DRILLING HOOK-UP
FLOW LINE TIE-IN
REINSTATEMENT WORKS
HOST TIE-IN
COMMISSIONING SYSTEM #1
WORKBOAT DEMOB
FINAL DOCUMENTATION
ON-SHORE COMMISSIONING
COMMISSIONING OF SYSTEM #1
DEMOBILIZATION OF EQUIPMENT
FINAL DOCUMENTATION
PRE-SHUTDOWN ACTIVITIES
STRUCTURAL AND CIVIL
PIPING
PIPELINE
MECHANICAL
ELECTRICAL
INSTRUMENT AND COMMUNICATION
HVAC AND DUCTING
ARCHITECTURAL
BLAST AND PAINTING
SHUT-DOWN ACTIVITIES
STRUCTURAL AND CIVIL
PIPING
PIPELINE
MECHANICAL
ELECTRICAL
INSTRUMENT AND COMMUNICATION
HVAC AND DUCTING
ARCHITECTURAL
BLAST AND PAINTING
POST SHUT-DOWN ACTIVITIES

More Related Content

What's hot

Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryPMI Chennai Chapter
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technipignitetribes
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draftignitetribes
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoignitetribes
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksPankaj K Sinha
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baronignitetribes
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
Onshore modules construction – a fabricator’s view
Onshore modules construction – a fabricator’s viewOnshore modules construction – a fabricator’s view
Onshore modules construction – a fabricator’s viewMerrylyn Yeo
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsNam N.N Tran M.Eng, PMP
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Saurabh Shah Piping Engineer CV
Saurabh Shah Piping Engineer CVSaurabh Shah Piping Engineer CV
Saurabh Shah Piping Engineer CVSaurabh Shah
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docxSharad Naik
 
Front End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control TrainingFront End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control TrainingDEVELOP
 

What's hot (20)

Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technip
 
Basic engineering_Checklist
Basic engineering_ChecklistBasic engineering_Checklist
Basic engineering_Checklist
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
Onshore modules construction – a fabricator’s view
Onshore modules construction – a fabricator’s viewOnshore modules construction – a fabricator’s view
Onshore modules construction – a fabricator’s view
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
 
Project Schedule - Level IV Schedule
Project Schedule - Level IV ScheduleProject Schedule - Level IV Schedule
Project Schedule - Level IV Schedule
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Saurabh Shah Piping Engineer CV
Saurabh Shah Piping Engineer CVSaurabh Shah Piping Engineer CV
Saurabh Shah Piping Engineer CV
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Epc overview
Epc  overviewEpc  overview
Epc overview
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 
Front End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control TrainingFront End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control Training
 

Similar to Sample wbs for_upstream_epcic_project

Arburg practical guide to injection moulding.pdf
Arburg practical guide to injection moulding.pdfArburg practical guide to injection moulding.pdf
Arburg practical guide to injection moulding.pdfMarufSaiyad
 
Pressure Relief Systems Vol 2
Pressure Relief Systems   Vol 2Pressure Relief Systems   Vol 2
Pressure Relief Systems Vol 2Gerard B. Hawkins
 
Petronas drilling operations guideline
Petronas drilling operations guidelinePetronas drilling operations guideline
Petronas drilling operations guidelineEaswaran Kanason
 
DCES_Classroom_Building_100_CDs.pdf
DCES_Classroom_Building_100_CDs.pdfDCES_Classroom_Building_100_CDs.pdf
DCES_Classroom_Building_100_CDs.pdfRoshelleStahl1
 
GAS DISPERSION - A Definitive Guide to Accidental Releases of Heavy Gases
GAS DISPERSION -  A Definitive Guide to Accidental Releases of Heavy GasesGAS DISPERSION -  A Definitive Guide to Accidental Releases of Heavy Gases
GAS DISPERSION - A Definitive Guide to Accidental Releases of Heavy GasesGerard B. Hawkins
 
Manual 48GC-4-6-03SI.pdf
Manual 48GC-4-6-03SI.pdfManual 48GC-4-6-03SI.pdf
Manual 48GC-4-6-03SI.pdfDiego839645
 
Tunnel_lining_design_guide_The_British_T.pdf
Tunnel_lining_design_guide_The_British_T.pdfTunnel_lining_design_guide_The_British_T.pdf
Tunnel_lining_design_guide_The_British_T.pdfHugoPaulin1
 
Variable Area Flow Meters Basics and Practices
Variable Area Flow Meters Basics and PracticesVariable Area Flow Meters Basics and Practices
Variable Area Flow Meters Basics and PracticesThompson Equipment Company
 
2010 polaris 600 rush pro ride snowmobile service repair manual
2010 polaris 600 rush pro ride snowmobile service repair manual2010 polaris 600 rush pro ride snowmobile service repair manual
2010 polaris 600 rush pro ride snowmobile service repair manualfjjskejdmdn
 
2010 POLARIS 600 RUSH PRO-RIDE SNOWMOBILE Service Repair Manual
2010 POLARIS 600 RUSH PRO-RIDE SNOWMOBILE Service Repair Manual2010 POLARIS 600 RUSH PRO-RIDE SNOWMOBILE Service Repair Manual
2010 POLARIS 600 RUSH PRO-RIDE SNOWMOBILE Service Repair Manualplopoi drert
 
2002 polaris octane personal watercraft service repair manual
2002 polaris octane personal watercraft service repair manual2002 polaris octane personal watercraft service repair manual
2002 polaris octane personal watercraft service repair manualfjkskemmdmm
 

Similar to Sample wbs for_upstream_epcic_project (20)

OPS2
OPS2OPS2
OPS2
 
Arburg practical guide to injection moulding.pdf
Arburg practical guide to injection moulding.pdfArburg practical guide to injection moulding.pdf
Arburg practical guide to injection moulding.pdf
 
Pressure Relief Systems Vol 2
Pressure Relief Systems   Vol 2Pressure Relief Systems   Vol 2
Pressure Relief Systems Vol 2
 
Petronas drilling operations guideline
Petronas drilling operations guidelinePetronas drilling operations guideline
Petronas drilling operations guideline
 
DCES_Classroom_Building_100_CDs.pdf
DCES_Classroom_Building_100_CDs.pdfDCES_Classroom_Building_100_CDs.pdf
DCES_Classroom_Building_100_CDs.pdf
 
Interior coating of welded steel water tanks
Interior coating of welded steel water tanksInterior coating of welded steel water tanks
Interior coating of welded steel water tanks
 
GAS DISPERSION - A Definitive Guide to Accidental Releases of Heavy Gases
GAS DISPERSION -  A Definitive Guide to Accidental Releases of Heavy GasesGAS DISPERSION -  A Definitive Guide to Accidental Releases of Heavy Gases
GAS DISPERSION - A Definitive Guide to Accidental Releases of Heavy Gases
 
UC-0212-FCR
UC-0212-FCRUC-0212-FCR
UC-0212-FCR
 
Manual 48GC-4-6-03SI.pdf
Manual 48GC-4-6-03SI.pdfManual 48GC-4-6-03SI.pdf
Manual 48GC-4-6-03SI.pdf
 
Acetic Acid Process Plant Design
Acetic Acid Process Plant DesignAcetic Acid Process Plant Design
Acetic Acid Process Plant Design
 
Tunnel_lining_design_guide_The_British_T.pdf
Tunnel_lining_design_guide_The_British_T.pdfTunnel_lining_design_guide_The_British_T.pdf
Tunnel_lining_design_guide_The_British_T.pdf
 
Variable Area Flow Meters Basics and Practices
Variable Area Flow Meters Basics and PracticesVariable Area Flow Meters Basics and Practices
Variable Area Flow Meters Basics and Practices
 
Patel dhaval
Patel dhaval Patel dhaval
Patel dhaval
 
2010 polaris 600 rush pro ride snowmobile service repair manual
2010 polaris 600 rush pro ride snowmobile service repair manual2010 polaris 600 rush pro ride snowmobile service repair manual
2010 polaris 600 rush pro ride snowmobile service repair manual
 
2010 POLARIS 600 RUSH PRO-RIDE SNOWMOBILE Service Repair Manual
2010 POLARIS 600 RUSH PRO-RIDE SNOWMOBILE Service Repair Manual2010 POLARIS 600 RUSH PRO-RIDE SNOWMOBILE Service Repair Manual
2010 POLARIS 600 RUSH PRO-RIDE SNOWMOBILE Service Repair Manual
 
Scope of work
Scope of workScope of work
Scope of work
 
2002 polaris octane personal watercraft service repair manual
2002 polaris octane personal watercraft service repair manual2002 polaris octane personal watercraft service repair manual
2002 polaris octane personal watercraft service repair manual
 
3404 tm workshop
3404 tm workshop3404 tm workshop
3404 tm workshop
 
Ufgs 33 11 23
Ufgs 33 11 23Ufgs 33 11 23
Ufgs 33 11 23
 
Inspection and Test Plan_D.pdf
Inspection and Test Plan_D.pdfInspection and Test Plan_D.pdf
Inspection and Test Plan_D.pdf
 

More from ignitetribes

Primavera Activity ID Coding
Primavera Activity ID CodingPrimavera Activity ID Coding
Primavera Activity ID Codingignitetribes
 
Headed Towards Burnout
Headed Towards BurnoutHeaded Towards Burnout
Headed Towards Burnoutignitetribes
 
The Leadership Qualities of Elon Musk
The Leadership Qualities of Elon MuskThe Leadership Qualities of Elon Musk
The Leadership Qualities of Elon Muskignitetribes
 
Improving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganImproving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganignitetribes
 
101 toughest interviews_questions
101 toughest interviews_questions101 toughest interviews_questions
101 toughest interviews_questionsignitetribes
 
Technip case study
Technip case studyTechnip case study
Technip case studyignitetribes
 
Project planning and control training with lego
Project planning and control training with legoProject planning and control training with lego
Project planning and control training with legoignitetribes
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement ignitetribes
 

More from ignitetribes (8)

Primavera Activity ID Coding
Primavera Activity ID CodingPrimavera Activity ID Coding
Primavera Activity ID Coding
 
Headed Towards Burnout
Headed Towards BurnoutHeaded Towards Burnout
Headed Towards Burnout
 
The Leadership Qualities of Elon Musk
The Leadership Qualities of Elon MuskThe Leadership Qualities of Elon Musk
The Leadership Qualities of Elon Musk
 
Improving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganImproving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dungan
 
101 toughest interviews_questions
101 toughest interviews_questions101 toughest interviews_questions
101 toughest interviews_questions
 
Technip case study
Technip case studyTechnip case study
Technip case study
 
Project planning and control training with lego
Project planning and control training with legoProject planning and control training with lego
Project planning and control training with lego
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 

Recently uploaded

Multivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptxMultivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptxalijaker017
 
ANSI(ST)-III_Manufacturing-I_05052020.pdf
ANSI(ST)-III_Manufacturing-I_05052020.pdfANSI(ST)-III_Manufacturing-I_05052020.pdf
ANSI(ST)-III_Manufacturing-I_05052020.pdfBertinKamsipa1
 
Filters for Electromagnetic Compatibility Applications
Filters for Electromagnetic Compatibility ApplicationsFilters for Electromagnetic Compatibility Applications
Filters for Electromagnetic Compatibility ApplicationsMathias Magdowski
 
"United Nations Park" Site Visit Report.
"United Nations Park" Site  Visit Report."United Nations Park" Site  Visit Report.
"United Nations Park" Site Visit Report.MdManikurRahman
 
ChatGPT Prompt Engineering for project managers.pdf
ChatGPT Prompt Engineering for project managers.pdfChatGPT Prompt Engineering for project managers.pdf
ChatGPT Prompt Engineering for project managers.pdfqasastareekh
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxwendy cai
 
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...Roi Lipman
 
Theory for How to calculation capacitor bank
Theory for How to calculation capacitor bankTheory for How to calculation capacitor bank
Theory for How to calculation capacitor banktawat puangthong
 
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas SachpazisSeismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas SachpazisDr.Costas Sachpazis
 
Introduction to Artificial Intelligence and History of AI
Introduction to Artificial Intelligence and History of AIIntroduction to Artificial Intelligence and History of AI
Introduction to Artificial Intelligence and History of AISheetal Jain
 
Low rpm Generator for efficient energy harnessing from a two stage wind turbine
Low rpm Generator for efficient energy harnessing from a two stage wind turbineLow rpm Generator for efficient energy harnessing from a two stage wind turbine
Low rpm Generator for efficient energy harnessing from a two stage wind turbineAftabkhan575376
 
solid state electronics ktu module 5 slides
solid state electronics ktu module 5 slidessolid state electronics ktu module 5 slides
solid state electronics ktu module 5 slidesARUN AV
 
Lab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docxLab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docxRashidFaridChishti
 
School management system project report.pdf
School management system project report.pdfSchool management system project report.pdf
School management system project report.pdfKamal Acharya
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationDr. Radhey Shyam
 
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfInvolute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfJNTUA
 
Paint shop management system project report.pdf
Paint shop management system project report.pdfPaint shop management system project report.pdf
Paint shop management system project report.pdfKamal Acharya
 
Electrical shop management system project report.pdf
Electrical shop management system project report.pdfElectrical shop management system project report.pdf
Electrical shop management system project report.pdfKamal Acharya
 
Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdfKamal Acharya
 
Electrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineElectrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineJulioCesarSalazarHer1
 

Recently uploaded (20)

Multivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptxMultivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptx
 
ANSI(ST)-III_Manufacturing-I_05052020.pdf
ANSI(ST)-III_Manufacturing-I_05052020.pdfANSI(ST)-III_Manufacturing-I_05052020.pdf
ANSI(ST)-III_Manufacturing-I_05052020.pdf
 
Filters for Electromagnetic Compatibility Applications
Filters for Electromagnetic Compatibility ApplicationsFilters for Electromagnetic Compatibility Applications
Filters for Electromagnetic Compatibility Applications
 
"United Nations Park" Site Visit Report.
"United Nations Park" Site  Visit Report."United Nations Park" Site  Visit Report.
"United Nations Park" Site Visit Report.
 
ChatGPT Prompt Engineering for project managers.pdf
ChatGPT Prompt Engineering for project managers.pdfChatGPT Prompt Engineering for project managers.pdf
ChatGPT Prompt Engineering for project managers.pdf
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
 
Theory for How to calculation capacitor bank
Theory for How to calculation capacitor bankTheory for How to calculation capacitor bank
Theory for How to calculation capacitor bank
 
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas SachpazisSeismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
 
Introduction to Artificial Intelligence and History of AI
Introduction to Artificial Intelligence and History of AIIntroduction to Artificial Intelligence and History of AI
Introduction to Artificial Intelligence and History of AI
 
Low rpm Generator for efficient energy harnessing from a two stage wind turbine
Low rpm Generator for efficient energy harnessing from a two stage wind turbineLow rpm Generator for efficient energy harnessing from a two stage wind turbine
Low rpm Generator for efficient energy harnessing from a two stage wind turbine
 
solid state electronics ktu module 5 slides
solid state electronics ktu module 5 slidessolid state electronics ktu module 5 slides
solid state electronics ktu module 5 slides
 
Lab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docxLab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docx
 
School management system project report.pdf
School management system project report.pdfSchool management system project report.pdf
School management system project report.pdf
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
 
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfInvolute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
 
Paint shop management system project report.pdf
Paint shop management system project report.pdfPaint shop management system project report.pdf
Paint shop management system project report.pdf
 
Electrical shop management system project report.pdf
Electrical shop management system project report.pdfElectrical shop management system project report.pdf
Electrical shop management system project report.pdf
 
Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdf
 
Electrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineElectrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission line
 

Sample wbs for_upstream_epcic_project

  • 1. www.ignitetribes.com LEVEL 5 LEVEL 6 UPSTREAM WBS EXAMPLE < WELL HEAD PLATFORM,RISER PLATFORM,FPSO,FLNG,SUBSEA FACITIY > ENGINEERING 1.2.1 GENERAL 1.2.1.1 SPECIFICATION/ PROCEDURES / REPORTS 1.2.1.2 CALCULATIONS 1.2.1.3 DATA SHEETS 1.2.1.4 DRAWINGS 1.2.1.5 MATERIAL REQUISITIONS 1.2.1.6 TECHNICAL BID EVALUATION (TBE) 1.2.1.7 VENDOR DOCUMENTS 1.2.2 PROCESS 1.2.2.1 SPECIFICATION/ PROCEDURES / REPORTS 1.2.2.2 CALCULATIONS 1.2.2.3 DATA SHEETS 1.2.2.4 DRAWINGS 1.2.2.5 MATERIAL REQUISITIONS 1.2.2.6 TECHNICAL BID EVALUATION (TBE) 1.2.2.7 VENDOR DOCUMENTS 1.2.2.8 HAZOP REVIEW 1.2.3 STRUCTURAL 1.2.3.1 SPECIFICATION/ PROCEDURES / REPORTS 1.2.3.2 CALCULATIONS 1.2.3.3 DATA SHEETS 1.2.3.4 DRAWINGS 1.2.3.5 MATERIAL REQUISITIONS 1.2.3.6 TECHNICAL BID EVALUATION (TBE) 1.2.3.7 VENDOR DOCUMENTS 1.2.4 MECHANICAL 1.2.4.1 SPECIFICATION/ PROCEDURES / REPORTS 1.2.4.2 CALCULATIONS 1.2.4.3 DATA SHEETS 1.2.4.4 DRAWINGS 1.2.4.5 MATERIAL REQUISITIONS 1.2.4.6 TECHNICAL BID EVALUATION (TBE) 1.2.4.7 VENDOR DOCUMENTS 1.2.5 PIPING 1.2.5.1 SPECIFICATION/ PROCEDURES / REPORTS 1.2.5.2 MODELLING AND MODEL REVIEW 1.2.5.3 CALCULATIONS 1.2.5.4 DATA SHEETS 1.2.5.5 DRAWINGS 1.2.5.6 MATERIAL REQUISITIONS 1.2.5.7 TECHNICAL BID EVALUATION (TBE) 1.2.5.8 VENDOR DOCUMENTS 1.2.5.9 MTO 1.2.6 ELECTRICAL 1.2.6.1 SPECIFICATION/ PROCEDURES / REPORTS 1.2.6.2 CALCULATIONS 1.2.6.3 DATA SHEETS 1.2.6.4 DRAWINGS 1.2.6.5 MATERIAL REQUISITIONS 1.2.6.6 TECHNICAL BID EVALUATION (TBE) 1.2.6.7 VENDOR DOCUMENTS 1.2.7 INSTRUMENT AND TELECOMMUNICATION 1.2.7.1 SPECIFICATION/ PROCEDURES / REPORTS 1.2.7.2 CALCULATIONS 1.2.7.3 DATA SHEETS 1.2.7.4 DRAWINGS 1.2.7.5 MATERIAL REQUISITIONS 1.2.7.6 TECHNICAL BID EVALUATION (TBE) 1.2.7.7 VENDOR DOCUMENTS 1.2.8 CIVIL 1.2.8.1 SPECIFICATION/ PROCEDURES / REPORTS 1.2.8.2 CALCULATIONS 1.2.8.3 DATA SHEETS 1.2.8.4 DRAWINGS 1.2.8.5 MATERIAL REQUISITIONS 1.2.8.6 TECHNICAL BID EVALUATION (TBE) 1.2.8.7 VENDOR DOCUMENTS 1.2.9 PIPELINES 1.2.9.1 SPECIFICATION/ PROCEDURES / REPORTS 1.2.9.2 CALCULATIONS 1.2.9.3 DATA SHEETS 1.2.9.4 DRAWINGS 1.2.9.5 MATERIAL REQUISITIONS 1.2.9.6 TECHNICAL BID EVALUATION (TBE) 1.2.9.7 VENDOR DOCUMENTS 1.2.10 ARCHITECTURE 1.2.1O.1 SPECIFICATION/ PROCEDURES / REPORTS 1.2.1O.2 CALCULATIONS 1.2.1O.3 DATA SHEETS 1.2.1O.4 DRAWINGS 1.2.1O.5 MATERIAL REQUISITIONS 1.2.1O.6 TECHNICAL BID EVALUATION (TBE) 1.2.1O.7 VENDOR DOCUMENTS 1.2.11 HSE (FIRE AND SAFETY) 1.2.12 FINAL DOCUMENTATION 1.2.13 OTHERS LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4 REFERTODELIVERABLESLISTANDPROGRESSMEASUREMENTSYSTEM REFERTODELIVERABLESLISTANDPROGRESSMEASUREMENTSYSTEM
  • 2. LEVEL 5 LEVEL 6LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4 1.3 PROCUREMENT 1.3.1 MECHANICAL MECHANICAL EQUIPMENT 1.3.1.1 COLUMN, VESSELS, DRUMS 1.3.1.2 HEAT EXCHANGER, CONDENSER 1.3.1.3 BOILER, HEATER & FURNACES 1.3.1.4 TANKS 1.3.1.5 GAS TURBINE DRIVEN BOOSTER COMPRESSOR 1.3.1.6 OTHER COMPRESSORS, FAN AND BLOWERS 1.3.1.7 PUMPS 1.3.1.8 FILTER/ COALESCER 1.3.1.9 PIG LAUNCHER/RECEIVER 1.3.1.10 HOIST /CRANE 1.3.1.11 OTHER MECHANICAL EQUIPMENT MECHANICAL PACKAGE 1.3.1.12 FLARE PACKAGE 1.3.1.13 NITROGEN PACKAGE 1.3.1.14 CHEMICAL INJECTION PACKAGE 1.3.1.15 MEG REGENERATION PACKAGE 1.3.1.16 ACID GAS REMOVAL UNIIT 1.3.1.17 GAS TURBINE GENERATOR 1.3.1.18 MICRO TURBINE GENERATOR 1.3.1.19 EFFLUENT TREATMENT PACKAGE 1.3.1.20 DEHYDRATION PACKAGE 1.3.1.21 WATER TREATMENT PACKAGE 1.3.1.22 HVAC EQUIPMENT PACKAGE 1.3.1.23 CONDENSATE DESALTER 1.3.1.24 SULPHUR RECOVERY PACKAGE 1.3.1.25 OTHER PACKAGE EQUIPMENT 1.3.2 PIPING AND VALVES 1.3.2.1 PIPES 1.3.2.2 FITTING & FLANGES 1.3.2.3 BALL VALVE 1.3.2.4 BUTTERFLY VALVE 1.3.2.5 CHECK VALVE 1.3.2.6 CHOKE VALVE 1.3.2.7 GATE VALVE 1.3.2.8 OTHER MANUAL VALVES 1.3.2.9 PIPE SUPPORT 1.3.2.10 OTHER PIPING MATERIALS 1.3.3 ELECTRICAL 1.3.3.1 HV, MV & LV Switchgears 1.3.3.2 Power Transformers 1.3.3.3 Distribution Board 1.3.3.4 MCC 1.3.3.5 Cabling System 1.3.3.6 Lighting System 1.3.3.7 Grounding System 1.3.3.8 Cathodic Protection 1.3.3.9 Batteries 1.3.3.10 Electrical Motors 1.3.3.11 Electrical Generators 1.3.3.12 Electrical Bulk Material 1.3.3.13 Other Electrical Equipment 1.3.4 INSTRUMENT 1.3.4.1 GAUGES 1.3.4.2 CONTROL VALVE 1.3.4.3 OTHER ACTUATED VALVES 1.3.4.4 GAS & CONDENSATE METERING SYSTEM 1.3.4.5 WELL HEAD CONTROL PANEL 1.3.4.6 MULTIPHASE FLOW METER 1.3.4.7 FIELD INSTRUMENTS & TUBING 1.3.4.8 SHUTDOWN SYSTEM 1.3.4.9 CONTROL SYSTEM 1.3.4.10 TELEMETRY SYSTEM 1.3.4.11 DCS & SCADA SYSTEM 1.3.4.12 CABLING SYSTEM (INCL. FIBER OPTIC) 1.3.4.13 TRANSMITTERS 1.3.4.14 INSTRUMENT BULK MATERIAL 1.3.4.15 OTHER INSTRUMENT EQUIPMENT 1.3.5 TELECOMMUNICATION 1.3.5.1 TELEPHONE & FAX SYSTEM 1.3.5.2 RADIO & RADAR SYSTEM 1.3.5.3 SATELLITE SYSTEM 1.3.5.4 PUBLIC ADDRESS, SIGNALING, ALARM & SECURITY SYSTEM 1.3.5.5 CABLING SYSTEM 1.3.5.6 OTHER TELECOMM. EQUIPMENT 1.3.6 SUBSEA 1.3.6.1 CHRISTMAS TREE 1.3.6.2 MANIFOLD / PLEM 1.3.6.3 UMBILICAL SYSTEM 1.3.6.4 HFL SYSTEM 1.3.6.5 EFL SYSTEM 1.3.6.6 OTHER MECHANICAL EQUIPMENT 1.3.6.7 OTHER E&I EQUIPMENT 1.3.7 CIVIL 1.3.7.1 BUILDING MATERIALS 1.3.7.2 PILING / FOUNDATION MATERIALS 1.3.7.3 OTHER CIVIL BULK MATERIALS 1.3.8 STRUCTURAL STEEL 1.3.8.1 STRUCTURAL BEAM 1.3.8.2 STRUCTURAL PLATE 1.3.8.3 STRUCTURAL TUBULAR 1.3.8.4 OTHER STEEL STRUCTURE MATERIALS 1.3.9 PAINTING AND COATING 1.3.9.1 PAINT AND COATING 1.3.9.2 OTHER COATIG MATERIAL REFERTODELIVERABLESLISTANDPROGRESSMEASUREMENTSYSTEM REFERTODELIVERABLESLISTANDPROGRESSMEASUREMENTSYSTEM
  • 3. LEVEL 5 LEVEL 6LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4 1.4 FABRICATION / CONSTRUCTION 1.4.1 FRONT END ACTIVITIES /MOBILIZATION 1.1.1.1 YARD PREPARATIONS (OFFICE,AMENITIES, ETC) 1.1.1.2 FABRICATION OF FRAMING/SUPPORT FOUNDATION 1.1.1.3 MOBILIZATION OF PROJECT MANAGEMENT TEAM 1.1.1.4 MOBILIZATION OF PROJECT MANAGEMENT TEAM 1.1.1.5 MOBILIZATION OF NDT SOURCE INSPECTION 1.1.1.6 MOBILIZATION OF STRUCTURAL SUB-CONTRACTOR 1.1.1.7 MOBILIZATION OF PIPING/PLUMBING SUB-CONTRACTOR 1.1.1.8 MOBILIZATION OF PIPING/PLUMBING SUB-CONTRACTOR 1.1.1.9 MOBILIZATION OF PAINTING SUB-CONTRACTOR 1.1.1.10 MOBILIZATION OF E&I SUB-CONTRACTOR 1.1.1.11 MOBILIZATION OF E&I HVAC/DUCTING SUB-CONTRACTOR ` 1.1.1.12 MOBILIZATION OF ARCHITECTURAL SUB-CONTRACTOR 1.1.1.13 PROJECT PLANNING AND MONITORING CHART 1.1.1.14 WQT/WPS (NUMBER OF WELDERS/WED(NUMBER OF WELDERS/WELDING OPERATORS/WPS) 1.1.1.15 TEST PANEL/COATING SYSTEM QUALIFICATION TEST(NUMBER OF TEST PANELS) 1.4.2 PREPARATION 1.1.1.1 YARD PREPARATIONS (OFFICE,AMENITIES, ETC) 1.4.3 ENGINEERING (SHOP DRAWING) 1.4.3.1 GENERAL 1.4.3.2 STRUCTURAL 1.4.3.3 MECHANICAL 1.4.3.4 PIPING 1.4.3.5 ELECTRICAL 1.4.3.6 INSTRUMENT AND TELECOMMUNICATION 1.4.3.7 CIVIL 1.4.3.8 PIPELINES 1.4.3.9 ARCHITECTURE 1.4.3.10 HVAC / DUCTING 1.4.4 YARD PRELIMINARIES / FABRICATION / CONSTRUCTION 1.4.4.1 STRUCTURAL FABRICATION OF STRUCTURAL MEMBERS FABRICATION OF MEMBERS ERECTION TRIAL FIT/WEIGHING OTHER STRUCTURAL WORK 1.4.4.2 MECHANICAL MECHANICAL EQUIPMENT SUPPORT MECHANICAL EQUIPMENT INSTALLATION 1.4.4.3 PIPING PIPE SUPPORT FABRICATION PIPE FABRICATION PIPE SUPPORT INSTALLATION LEAK TEST VALVE VALVE INSTALLATON FLUSHING, HYDROTEST AND ACID CLEANING 1.4.4.4 PIPELINE PIPE COATING PIPE FABRICATION 1.4.4.5 ELECTRICAL FABRICATION OF ELECTRICAL SUPPORT INSTALLATION OF ELECTRICAL SUPPORT CABLE TRAY/CABLE LADDER INSTALLATION CABLE PULLING FIELD ELECTRICAL DEVICE INSTALLATION ELECTRICAL EQUIPMENT INSTALLATION CALIBRATE ELECTRICAL EQUIPMENT DRESSING/GLANDING/TAGGING 1.4.4.6 INSTRUMENT AND TELECOMMUNICATION FABRICATION O F INSTRUMENT SUPPORT INSTRUMENT CABLE TRAY/LADDER/CONDUITS INSTALLATION INSTRUMENT CABLE PULLING INSTRUMENT LIGHTING AND FIXTURES INSTRUMENT EQUIPMENT INSTALLATION INSTALLATION OF PIPE SUPPORT INSTALLATION OF TUBING/AIR SUPPL INSTRUMENT TUBING / LEAK TEST TELEPHONE AND LAN INSTALLATION CCTV RADIO SYS DRESSING / GLANDING / TAGGING/ TERMINATION CALIBRATE INSTRUMENT 1.4.4.7 ARCHITECTURE WALL PARTITION AND PANEL INSTALLATION DOORS AND WINDOW INSTALL FLOOR PEDESTAL INSTALL HANGERS AND FALSE CEILING REFERTODELIVERABLESLISTANDPROGRESSMEASUREMENTSYSTEM
  • 4. LEVEL 5 LEVEL 6LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4 1.4.4.8 HVAC / DUCTING FABRICATION OF DUCTING SUPPORT INSTALLATION OF DUCTING SUPPORT HVAC DUCTING FABRICATION AND INSTALLATION FABRICATION OF ELECTRICAL / INSTRUMENT SUPPORT INSTALLATION OF ELECTRICAL / INSTRUMENT SUPPORT TUBING TRAY/ CABLE TRAY/ LADDER INSTALLATION FIELD HVAC DEVICE INSTALLATION HVAC EQUIPMENT INSTALLATION CALIBRATE HVAC EQUIPMENT DRESSING, GLANDING, TAGGING AND TERMINATION 1.4.4.9 BLAST AND PAINTING EQUIPMENT PAINTING PIPE BLASTING AND PAINTING 1.4.4.10 INSULATION EQUIPMENT INSULATION PIPE INSULATION 1.4.5 TESTING AND COMMISSIONING 1.4.5.1 ELECTRICAL *NUMBER OF SYSTEMS 1.4.5.2 INSTRUMENT AND COMMUNICATION *NUMBER OF SYSTEMS 1.4.5.3 PIPING AND PLUMBING *NUMBER OF SYSTEMS 1.4.5.4 PIPELINE *NUMBER OF SYSTEMS 1.4.5.5 MECHANICAL *NUMBER OF SYSTEMS 1.4.5.6 HVAC *NUMBER OF SYSTEMS 1.4.5.7 SYSTEM TESTING *NUMBER OF SYSTEMS 1.4.6 LOAD-OUT AND SEA FASTEING 1.4.6.1 DRAWINGS 1.4.6.2 MATERIALS 1.4.6.3 WEIGHING 1.4.6.4 SEA FASTENING FABRICAION 1.4.6.5 LOAD-OUT AND POSITIONING 1.4.6.6 TIE-DOWN ARRANGEMENT 1.4.7 FINAL DOCUMENTATION 1.4.7.1 QA/QC DOCUMENTS 1.4.7.2 EQUIPMENT DOSSIER 1.4.7.3 MATERIAL DOCUMENTS 1.4.7.4 TESTING AND PRE-COMMISSIONING DOCUMENTS 1.4.7.5 DESIGN DATA 1.4.7.6 AS-BUILT DRAWING 1.4.7.7 NDT RECORDS AND RADIOGRAPHS 1.5 INSTALLATION 1.5.1 PRE-INSTALL ENGINEERING AND PROCUREMENT 1.5.1.1 SHOP DRAWING 1.5.1.2 PROCEDURE 1.5.1.3 PROCUREMENT OF INSTALLATION MATERIALS 1.5.2 MARINE SPREAD MOBILIZATION 1.5.2.1 PREPARATION ACTIVITIES 1.5.2.2 MOBILIZATION OF BARGE AT YARD 1.5.3 TRANSPORTATION 1.5.3.1 SAIL AWAY AND ARRIVE AT SITE 1.5.4 INSTALLATION 1.5.4.1 PREPARATION ACTIVITIES 1.5.4.2 TOPSIDE INSTALLATION (TOPSIDE AS EX) 1.5.4.3 WELD AND NDT OF TOPSIDE 1.5.5 MARINE SPREAD DEMOB 1.5.5.1 DEMOB OF MARINE SPREAD 1.5.5.2 FINAL DOCUMENTATION
  • 5. LEVEL 5 LEVEL 6LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4 1.6 HUC (HOOK-UP AND COMMISSIONING) 1.6.1 COMMISSIONING ENGINERING 1.6.1.1 SHOP DRAWING 1.6.1.2 PROCEDURE 1.6.2 COMMISSIONING PROCUREMENT 1.6.2.1 PROCUREMENT FOR HUC MATERIALS 1.6.3 PRE-FABRICATION 1.6.3.1 PREPARATION ACTIVITIES 1.6.3.2 PRE-FABRICATION 1.6.4 OFSHORE-HUC PREPARATION ACTIVITIES MOBILIZATION OF WORK BOAT SET-UP ANCHOR FACILITIES HOOK-UP POST-DRILLING HOOK-UP FLOW LINE TIE-IN REINSTATEMENT WORKS HOST TIE-IN COMMISSIONING SYSTEM #1 WORKBOAT DEMOB FINAL DOCUMENTATION ON-SHORE COMMISSIONING COMMISSIONING OF SYSTEM #1 DEMOBILIZATION OF EQUIPMENT FINAL DOCUMENTATION PRE-SHUTDOWN ACTIVITIES STRUCTURAL AND CIVIL PIPING PIPELINE MECHANICAL ELECTRICAL INSTRUMENT AND COMMUNICATION HVAC AND DUCTING ARCHITECTURAL BLAST AND PAINTING SHUT-DOWN ACTIVITIES STRUCTURAL AND CIVIL PIPING PIPELINE MECHANICAL ELECTRICAL INSTRUMENT AND COMMUNICATION HVAC AND DUCTING ARCHITECTURAL BLAST AND PAINTING POST SHUT-DOWN ACTIVITIES