SlideShare a Scribd company logo
132kV Connection
A First for N.S.W Coal Mining
Introduction
• Where is Boggabri – Situated between Gunnedah and Narrabri in north west
N.S.W approx. 115km West from Tamworth.
• Boggabri Coal Operations commenced mining in 2006
• A significant expansion of site infrastructure was undertaken in 2014/2015
• The 132kV connection was a joint project by Transgrid and Boggabri Coal
Operations.
• Included was 15kM of single structure, double circuit, 132kV transmission line,
132kV switching station and the 132kv/11kV substation.
Overview
• Boggabri Coal Operations were an LV customer (HV was
managed by the utility) at inception.
• Site demand was below 2MVA
• An 11kV rural feeder from Boggabri Substation was the
only mine supply source. The service extended over 25kM
(voltage regulation was required).
• Expansion of site infrastructure required power system
demand exceeding the 11kV capability.
• Overall site demand increased to 8MVA (design capacity)
• Local services could not meet the demand – Transmission
was the only option.
Why 132kV Connection
?
A first for Mining and Transgrid
Network Layout
Network Connection
Boggabri Coal
Substation
Network Connection
Protection Schemes
Inter tripping
• 132kV trip signals are duplicated through protection relays from
Boggabri Coal to Transgrid
– Zone Protection (overcurrent, short circuit etc)
– TX Differential
– Emergency stops
– Fire system
– Back up Earth Leakage
– Neutral Earth Resistor failure via NER monitor.
– Transformer Protection (Oil temp, explosion, winding temp, over pressure)
– Arc Fault Detection (11kv Bus)
• Protection devices, Circuit breakers, are in Transgrids Switching Station.
• Faults are cleared by transgrid for all 132kV primary protection or
Intertrip faults
Logic Diagram Example
Load shed Arrangements
• Transmission systems demand stability
• Transgrid Load shed scheme means exactly what is
sounds like
• 4 Tiers are implemented which shed different load
blocks
• Bus voltage is monitored at the switching station for
trip signal initiations
EARTHING
• Common earthing system between Transgrid and Boggabri Coal
• Design requirements - Allowable touch and step voltages were
derived from different standards
• Transgrid – AS2067 ( Calculated)
• Boggabri Coal – AS3007 (step/touch potentials v’s clearance times)
• Transfer voltage levels required separation between
“mine infrastructure area” and the 132kV facility. A
164M exclusion zone has been established for earthed
services entering this zone.
EARTHING
Challenges
• Design was completed by Transmission orientated Engineers with a different approach to mining
“Risk management base”
• Design review was undertaken by a QLD based engineering company
• Disconnect between project team and the end user of the facility
• System operation – original design philosophy was to run 2 x 10MVA TX’s in parallel which allowed
for a 65kA fault level on the 415V system (terminals of the 3MVA TX supply)
• Fundamental protection schemes, secondary systems, required further development prior to
energistaion.
• HV and LV services crossing operational boundaries. Boggabri Coal and Transgrid share HV and LV
services originating on both sides of the installation.
• Differences in isolation procedures, including hardware between both Transgrid and Boggabri Coal
• Transgrid having a major facility “next door” to the mine substation.
• Unrestricted earth fault levels on the 132kV connection (max 15kA) – transfer voltages
• Reliance of primary protection clearing faults is by the utility – No 132kV protective devices are
owned or operated by Boggabri Coal Operations.
Advantages
• Transgrid monitoring
• Transgrid system control monitor the status of Transgrid equipment, including the 132kV circuit breakers,
24/7
• Remote operation of 132kV circuit breakers from Transgrid system control
• Stability of Supply
• The 132kV connection is part of the overall, north west area “Ring Main”. This means the system is very
stable and subject to minimal outages or faults.
• Reduced Arc Flash Categories
• Increased equipment clearances (above 3M) and protection schemes allow for arc
flash categories to be reduced
Key Outcomes
• Transgrid and Boggabri Coal Operating agreement implemented
This document identifies
– Equipment isolation instructions, each piece of equipment has an agreed isolation procedure
– Communication protocol’s
– Key contacts for events
– Use and transaction of “High Voltage Equipment Outage” permits.
• Connection Agreement
– Highlights the obligations of each party
– Deals with access and safety scenarios .
– Modifications to the agreed installation and protection settings are dealt with here
• Operational and Maintenance, hazard identification and risk analysis via
consultation with designer, supplier, installer, operator and utility (Transgrid).
– This process expedited the risk mitigation process due to designer information being supplied by key engineers
• Designer based training for operational staff
– Maintenance, Isolation and Operational documents were developed and used as training material
for electrical staff by the designer. Training was delivered onsite.
Recommendations
• Where plant and installations are being
constructed, for the purpose of mining
operations, statutory functions should be
involved in the key decisions.
• Collaboration with mining and transmission
industries requires further development.
Mindsets are differing around system
operations and protection functions.
Thank You!

More Related Content

What's hot

Presentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapperPresentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapper
Jyoti Rawat
 
Gagan
GaganGagan
Kulekhani I hydropower ,Nepal
Kulekhani I hydropower ,NepalKulekhani I hydropower ,Nepal
Kulekhani I hydropower ,Nepal
Bishal Rimal
 
Critical Power: Generators and Generator System Design
Critical Power: Generators and Generator System DesignCritical Power: Generators and Generator System Design
Critical Power: Generators and Generator System Design
ConsultingSpecifyingEngineer
 
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Gensol Engineering Limited
 
Wind farm planning and commissioning
Wind farm planning and commissioningWind farm planning and commissioning
Wind farm planning and commissioning
Preet_patel
 
Construction of PCC Parapet
Construction of PCC Parapet Construction of PCC Parapet
Construction of PCC Parapet
Himanshu Chakravarti
 
lift ppt
lift pptlift ppt
lift ppt
smartraja1991
 
Paralleling Switchgear
Paralleling SwitchgearParalleling Switchgear
Paralleling Switchgear
michaeljmack
 
Modern substation design
Modern substation designModern substation design
Modern substation design
rajesh18001 R
 
Bangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants OverviewBangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants Overview
Ridwanul Hoque
 
Automotive Driver Requirements Topologies & Applications
Automotive Driver Requirements Topologies & ApplicationsAutomotive Driver Requirements Topologies & Applications
Automotive Driver Requirements Topologies & Applications
ON Semiconductor
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
michaeljmack
 
Critical power: Transfer switches and switchgear
Critical power: Transfer switches and switchgearCritical power: Transfer switches and switchgear
Critical power: Transfer switches and switchgear
ConsultingSpecifyingEngineer
 
Ward leonard method & Characteristics of series motor
Ward leonard method & Characteristics of series motorWard leonard method & Characteristics of series motor
Ward leonard method & Characteristics of series motor
Pavithran Selvam
 
Switch yard pp 2 kanti thermal power station
Switch yard pp 2 kanti thermal power stationSwitch yard pp 2 kanti thermal power station
Switch yard pp 2 kanti thermal power station
neeraj prasad
 

What's hot (20)

Presentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapperPresentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapper
 
My report vfd
My  report vfdMy  report vfd
My report vfd
 
Gagan
GaganGagan
Gagan
 
Kulekhani I hydropower ,Nepal
Kulekhani I hydropower ,NepalKulekhani I hydropower ,Nepal
Kulekhani I hydropower ,Nepal
 
Critical Power: Generators and Generator System Design
Critical Power: Generators and Generator System DesignCritical Power: Generators and Generator System Design
Critical Power: Generators and Generator System Design
 
ppt
pptppt
ppt
 
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
 
Wind farm planning and commissioning
Wind farm planning and commissioningWind farm planning and commissioning
Wind farm planning and commissioning
 
Construction of PCC Parapet
Construction of PCC Parapet Construction of PCC Parapet
Construction of PCC Parapet
 
lift ppt
lift pptlift ppt
lift ppt
 
Paralleling Switchgear
Paralleling SwitchgearParalleling Switchgear
Paralleling Switchgear
 
PM Ahmed Abdelhady CV
PM Ahmed Abdelhady CVPM Ahmed Abdelhady CV
PM Ahmed Abdelhady CV
 
Modern substation design
Modern substation designModern substation design
Modern substation design
 
Ppt
PptPpt
Ppt
 
Bangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants OverviewBangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants Overview
 
Automotive Driver Requirements Topologies & Applications
Automotive Driver Requirements Topologies & ApplicationsAutomotive Driver Requirements Topologies & Applications
Automotive Driver Requirements Topologies & Applications
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
Critical power: Transfer switches and switchgear
Critical power: Transfer switches and switchgearCritical power: Transfer switches and switchgear
Critical power: Transfer switches and switchgear
 
Ward leonard method & Characteristics of series motor
Ward leonard method & Characteristics of series motorWard leonard method & Characteristics of series motor
Ward leonard method & Characteristics of series motor
 
Switch yard pp 2 kanti thermal power station
Switch yard pp 2 kanti thermal power stationSwitch yard pp 2 kanti thermal power station
Switch yard pp 2 kanti thermal power station
 

Viewers also liked

What is agile marketing?
What is agile marketing? What is agile marketing?
What is agile marketing?
Femi Deji Olajiga
 
Presentation english2
Presentation english2Presentation english2
Presentation english2
Giangi Romano
 
Blake aden ppp_slides
Blake aden ppp_slidesBlake aden ppp_slides
Blake aden ppp_slides
Aden Blake
 
Sistema operativo
Sistema operativoSistema operativo
Sistema operativo
DamarisK
 
CFU Kitchens - International Menus
CFU Kitchens - International MenusCFU Kitchens - International Menus
CFU Kitchens - International MenusTony Joseph
 
LC Intro 7/8
LC Intro 7/8LC Intro 7/8
LC Intro 7/8
ebmccall
 
Cooperative Drilling
Cooperative DrillingCooperative Drilling
Cooperative Drilling
NSW Environment and Planning
 
Qalam w maidan final
Qalam w maidan final Qalam w maidan final
Qalam w maidan final
قلم وميدان
 
2.Israel Tourism Brand Guidelines
2.Israel Tourism Brand Guidelines2.Israel Tourism Brand Guidelines
2.Israel Tourism Brand GuidelinesRuochen CHENG
 
Clean Energy Finance Corporation
Clean Energy Finance CorporationClean Energy Finance Corporation
Clean Energy Finance Corporation
NSW Environment and Planning
 
2014 Regulatory Team Work
2014 Regulatory Team Work2014 Regulatory Team Work
2014 Regulatory Team WorkMichael Youth
 
Nmdl final project express-kate schild
Nmdl final project express-kate schildNmdl final project express-kate schild
Nmdl final project express-kate schild
kateschild94
 
Prevention of vehicle interaction collisions
Prevention of vehicle interaction collisionsPrevention of vehicle interaction collisions
Prevention of vehicle interaction collisions
NSW Environment and Planning
 
Rojas cárdenas juan_manuel_colaborativa_i
Rojas cárdenas juan_manuel_colaborativa_iRojas cárdenas juan_manuel_colaborativa_i
Rojas cárdenas juan_manuel_colaborativa_i
Juanma_rojas
 

Viewers also liked (20)

What is agile marketing?
What is agile marketing? What is agile marketing?
What is agile marketing?
 
Presentation english2
Presentation english2Presentation english2
Presentation english2
 
Deveco
DevecoDeveco
Deveco
 
Blake aden ppp_slides
Blake aden ppp_slidesBlake aden ppp_slides
Blake aden ppp_slides
 
Sistema operativo
Sistema operativoSistema operativo
Sistema operativo
 
to Edit
to Editto Edit
to Edit
 
FERMÁQUINAS
FERMÁQUINASFERMÁQUINAS
FERMÁQUINAS
 
CFU Kitchens - International Menus
CFU Kitchens - International MenusCFU Kitchens - International Menus
CFU Kitchens - International Menus
 
LC Intro 7/8
LC Intro 7/8LC Intro 7/8
LC Intro 7/8
 
portfolio
portfolioportfolio
portfolio
 
Cooperative Drilling
Cooperative DrillingCooperative Drilling
Cooperative Drilling
 
Qalam w maidan final
Qalam w maidan final Qalam w maidan final
Qalam w maidan final
 
P.Timmins Resume 2015
P.Timmins Resume 2015P.Timmins Resume 2015
P.Timmins Resume 2015
 
2.Israel Tourism Brand Guidelines
2.Israel Tourism Brand Guidelines2.Israel Tourism Brand Guidelines
2.Israel Tourism Brand Guidelines
 
Clean Energy Finance Corporation
Clean Energy Finance CorporationClean Energy Finance Corporation
Clean Energy Finance Corporation
 
2014 Regulatory Team Work
2014 Regulatory Team Work2014 Regulatory Team Work
2014 Regulatory Team Work
 
Limbajultrupului(cOp)
Limbajultrupului(cOp)Limbajultrupului(cOp)
Limbajultrupului(cOp)
 
Nmdl final project express-kate schild
Nmdl final project express-kate schildNmdl final project express-kate schild
Nmdl final project express-kate schild
 
Prevention of vehicle interaction collisions
Prevention of vehicle interaction collisionsPrevention of vehicle interaction collisions
Prevention of vehicle interaction collisions
 
Rojas cárdenas juan_manuel_colaborativa_i
Rojas cárdenas juan_manuel_colaborativa_iRojas cárdenas juan_manuel_colaborativa_i
Rojas cárdenas juan_manuel_colaborativa_i
 

Similar to Complex connections Rick Chorley

Zinfra Renewables Capability Statement
Zinfra Renewables Capability StatementZinfra Renewables Capability Statement
Zinfra Renewables Capability Statement
Zinfra Group
 
Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Abdul Alim Dewan
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptx
TalhaAbdulRehman2
 
Zinfra Group Australia: Power Brochure
Zinfra Group Australia: Power BrochureZinfra Group Australia: Power Brochure
Zinfra Group Australia: Power Brochure
Zinfra Group
 
Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Sarthak Panigrahi
 
CESC LTD. TRAINING REPORT
CESC LTD. TRAINING REPORTCESC LTD. TRAINING REPORT
CESC LTD. TRAINING REPORT
MAINAK SINGHA BARMA
 
1.3. MCAGCC 29 Palms Microgrid_Morrissett_EPRI/SNL Microgrid
1.3. MCAGCC 29 Palms Microgrid_Morrissett_EPRI/SNL Microgrid1.3. MCAGCC 29 Palms Microgrid_Morrissett_EPRI/SNL Microgrid
1.3. MCAGCC 29 Palms Microgrid_Morrissett_EPRI/SNL Microgrid
Sandia National Laboratories: Energy & Climate: Renewables
 
Ultra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVACUltra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVAC
Aravind Panasa
 
Operational ANM Schmes in the UK and America
Operational ANM Schmes in the UK and AmericaOperational ANM Schmes in the UK and America
Operational ANM Schmes in the UK and America
Smarter Grid Solutions
 
10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium
10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium
10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium
Sandia National Laboratories: Energy & Climate: Renewables
 
Planning a successful microgrid
Planning a successful microgridPlanning a successful microgrid
Planning a successful microgrid
TRC Companies, Inc.
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And Commisioning
Suraj Naik
 
20170727 angledc project, mvdc
20170727 angledc project, mvdc20170727 angledc project, mvdc
20170727 angledc project, mvdc
Chao Long
 
Engage with...Network Rail
Engage with...Network RailEngage with...Network Rail
Engage with...Network Rail
KTN
 
MES Case Study - Carlton Park Substation
MES Case Study - Carlton Park SubstationMES Case Study - Carlton Park Substation
MES Case Study - Carlton Park SubstationSteve Sadler
 
Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.
Avirup Ghosh
 
Power Factor correction of Toitskraal 11kV feeder
Power Factor correction of Toitskraal 11kV feederPower Factor correction of Toitskraal 11kV feeder
Power Factor correction of Toitskraal 11kV feederKruger Greyvenstein
 
Power conversion in wind turbine.ppt
Power conversion in wind turbine.pptPower conversion in wind turbine.ppt
Power conversion in wind turbine.ppt
vimal46140
 
resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986sheik syedali
 

Similar to Complex connections Rick Chorley (20)

Zinfra Renewables Capability Statement
Zinfra Renewables Capability StatementZinfra Renewables Capability Statement
Zinfra Renewables Capability Statement
 
Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptx
 
Zinfra Group Australia: Power Brochure
Zinfra Group Australia: Power BrochureZinfra Group Australia: Power Brochure
Zinfra Group Australia: Power Brochure
 
Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Rourkela Steel Pant Power System
Rourkela Steel Pant Power System
 
CESC LTD. TRAINING REPORT
CESC LTD. TRAINING REPORTCESC LTD. TRAINING REPORT
CESC LTD. TRAINING REPORT
 
Wind Power EPCM
Wind Power EPCMWind Power EPCM
Wind Power EPCM
 
1.3. MCAGCC 29 Palms Microgrid_Morrissett_EPRI/SNL Microgrid
1.3. MCAGCC 29 Palms Microgrid_Morrissett_EPRI/SNL Microgrid1.3. MCAGCC 29 Palms Microgrid_Morrissett_EPRI/SNL Microgrid
1.3. MCAGCC 29 Palms Microgrid_Morrissett_EPRI/SNL Microgrid
 
Ultra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVACUltra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVAC
 
Operational ANM Schmes in the UK and America
Operational ANM Schmes in the UK and AmericaOperational ANM Schmes in the UK and America
Operational ANM Schmes in the UK and America
 
10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium
10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium
10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium
 
Planning a successful microgrid
Planning a successful microgridPlanning a successful microgrid
Planning a successful microgrid
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And Commisioning
 
20170727 angledc project, mvdc
20170727 angledc project, mvdc20170727 angledc project, mvdc
20170727 angledc project, mvdc
 
Engage with...Network Rail
Engage with...Network RailEngage with...Network Rail
Engage with...Network Rail
 
MES Case Study - Carlton Park Substation
MES Case Study - Carlton Park SubstationMES Case Study - Carlton Park Substation
MES Case Study - Carlton Park Substation
 
Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.
 
Power Factor correction of Toitskraal 11kV feeder
Power Factor correction of Toitskraal 11kV feederPower Factor correction of Toitskraal 11kV feeder
Power Factor correction of Toitskraal 11kV feeder
 
Power conversion in wind turbine.ppt
Power conversion in wind turbine.pptPower conversion in wind turbine.ppt
Power conversion in wind turbine.ppt
 
resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986
 

More from NSW Environment and Planning

12 Small mines report card 2020
12 Small mines report card 202012 Small mines report card 2020
12 Small mines report card 2020
NSW Environment and Planning
 
11 occupational hygiene monitoring of dust
11 occupational hygiene monitoring of dust11 occupational hygiene monitoring of dust
11 occupational hygiene monitoring of dust
NSW Environment and Planning
 
09 learning from disasters
09 learning from disasters09 learning from disasters
09 learning from disasters
NSW Environment and Planning
 
13 explosives awareness
13 explosives awareness13 explosives awareness
13 explosives awareness
NSW Environment and Planning
 
10 incident reporting to the regulator 2020
10 incident reporting to the regulator 202010 incident reporting to the regulator 2020
10 incident reporting to the regulator 2020
NSW Environment and Planning
 
08 dust safety and health surveillance
08 dust safety and health surveillance08 dust safety and health surveillance
08 dust safety and health surveillance
NSW Environment and Planning
 
07 feedback and consultation
07 feedback and consultation07 feedback and consultation
07 feedback and consultation
NSW Environment and Planning
 
06. how the regulator communicates with the industry
06. how the regulator communicates with the industry06. how the regulator communicates with the industry
06. how the regulator communicates with the industry
NSW Environment and Planning
 
05 reviewing your SMS
05 reviewing your SMS05 reviewing your SMS
05 reviewing your SMS
NSW Environment and Planning
 
04. slinging and lifting equipment
04. slinging and lifting equipment04. slinging and lifting equipment
04. slinging and lifting equipment
NSW Environment and Planning
 
Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)
NSW Environment and Planning
 
Central assessment unit CAU(Steve Bentham)
Central assessment unit CAU(Steve Bentham)Central assessment unit CAU(Steve Bentham)
Central assessment unit CAU(Steve Bentham)
NSW Environment and Planning
 
Autonomous mining equipment (Owen Barry)
Autonomous mining equipment (Owen Barry)Autonomous mining equipment (Owen Barry)
Autonomous mining equipment (Owen Barry)
NSW Environment and Planning
 
Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)
NSW Environment and Planning
 
Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)
NSW Environment and Planning
 
Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)
NSW Environment and Planning
 
Airborne dust update (Mark Shepherd)
Airborne dust update (Mark Shepherd)Airborne dust update (Mark Shepherd)
Airborne dust update (Mark Shepherd)
NSW Environment and Planning
 
Emergency planning (Matt U'Brien)
Emergency planning (Matt U'Brien)Emergency planning (Matt U'Brien)
Emergency planning (Matt U'Brien)
NSW Environment and Planning
 
Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)
NSW Environment and Planning
 
Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...
NSW Environment and Planning
 

More from NSW Environment and Planning (20)

12 Small mines report card 2020
12 Small mines report card 202012 Small mines report card 2020
12 Small mines report card 2020
 
11 occupational hygiene monitoring of dust
11 occupational hygiene monitoring of dust11 occupational hygiene monitoring of dust
11 occupational hygiene monitoring of dust
 
09 learning from disasters
09 learning from disasters09 learning from disasters
09 learning from disasters
 
13 explosives awareness
13 explosives awareness13 explosives awareness
13 explosives awareness
 
10 incident reporting to the regulator 2020
10 incident reporting to the regulator 202010 incident reporting to the regulator 2020
10 incident reporting to the regulator 2020
 
08 dust safety and health surveillance
08 dust safety and health surveillance08 dust safety and health surveillance
08 dust safety and health surveillance
 
07 feedback and consultation
07 feedback and consultation07 feedback and consultation
07 feedback and consultation
 
06. how the regulator communicates with the industry
06. how the regulator communicates with the industry06. how the regulator communicates with the industry
06. how the regulator communicates with the industry
 
05 reviewing your SMS
05 reviewing your SMS05 reviewing your SMS
05 reviewing your SMS
 
04. slinging and lifting equipment
04. slinging and lifting equipment04. slinging and lifting equipment
04. slinging and lifting equipment
 
Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)
 
Central assessment unit CAU(Steve Bentham)
Central assessment unit CAU(Steve Bentham)Central assessment unit CAU(Steve Bentham)
Central assessment unit CAU(Steve Bentham)
 
Autonomous mining equipment (Owen Barry)
Autonomous mining equipment (Owen Barry)Autonomous mining equipment (Owen Barry)
Autonomous mining equipment (Owen Barry)
 
Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)
 
Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)
 
Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)
 
Airborne dust update (Mark Shepherd)
Airborne dust update (Mark Shepherd)Airborne dust update (Mark Shepherd)
Airborne dust update (Mark Shepherd)
 
Emergency planning (Matt U'Brien)
Emergency planning (Matt U'Brien)Emergency planning (Matt U'Brien)
Emergency planning (Matt U'Brien)
 
Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)
 
Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...
 

Recently uploaded

Government Service OPSI Playbook FINAL.pdf
Government Service OPSI Playbook FINAL.pdfGovernment Service OPSI Playbook FINAL.pdf
Government Service OPSI Playbook FINAL.pdf
MoffatNyamadzawo2
 
2017 Omnibus Rules on Appointments and Other Human Resource Actions, As Amended
2017 Omnibus Rules on Appointments and Other Human Resource Actions, As Amended2017 Omnibus Rules on Appointments and Other Human Resource Actions, As Amended
2017 Omnibus Rules on Appointments and Other Human Resource Actions, As Amended
johnmarimigallon
 
CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054
CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054
CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054
Congressional Budget Office
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
850fcj96
 
2024: The FAR - Federal Acquisition Regulations, Part 38
2024: The FAR - Federal Acquisition Regulations, Part 382024: The FAR - Federal Acquisition Regulations, Part 38
2024: The FAR - Federal Acquisition Regulations, Part 38
JSchaus & Associates
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
GrantManagementInsti
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
ClaudioTebaldi2
 
kupon sample qurban masjid indonesia terbaru.pptx
kupon sample qurban masjid indonesia terbaru.pptxkupon sample qurban masjid indonesia terbaru.pptx
kupon sample qurban masjid indonesia terbaru.pptx
viderakai
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
850fcj96
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
RIDPRO11
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
SERUDS INDIA
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
AjayVejendla3
 
Transit-Oriented Development Study Working Group Meeting
Transit-Oriented Development Study Working Group MeetingTransit-Oriented Development Study Working Group Meeting
Transit-Oriented Development Study Working Group Meeting
Cuyahoga County Planning Commission
 
State crafting: Changes and challenges for managing the public finances
State crafting: Changes and challenges for managing the public financesState crafting: Changes and challenges for managing the public finances
State crafting: Changes and challenges for managing the public finances
ResolutionFoundation
 
A proposed request for information on LIHTC
A proposed request for information on LIHTCA proposed request for information on LIHTC
A proposed request for information on LIHTC
Roger Valdez
 
Donate to charity during this holiday season
Donate to charity during this holiday seasonDonate to charity during this holiday season
Donate to charity during this holiday season
SERUDS INDIA
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
ARCResearch
 
Monitoring Health for the SDGs - Global Health Statistics 2024 - WHO
Monitoring Health for the SDGs - Global Health Statistics 2024 - WHOMonitoring Health for the SDGs - Global Health Statistics 2024 - WHO
Monitoring Health for the SDGs - Global Health Statistics 2024 - WHO
Christina Parmionova
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
Saeed Al Dhaheri
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Congressional Budget Office
 

Recently uploaded (20)

Government Service OPSI Playbook FINAL.pdf
Government Service OPSI Playbook FINAL.pdfGovernment Service OPSI Playbook FINAL.pdf
Government Service OPSI Playbook FINAL.pdf
 
2017 Omnibus Rules on Appointments and Other Human Resource Actions, As Amended
2017 Omnibus Rules on Appointments and Other Human Resource Actions, As Amended2017 Omnibus Rules on Appointments and Other Human Resource Actions, As Amended
2017 Omnibus Rules on Appointments and Other Human Resource Actions, As Amended
 
CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054
CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054
CBO’s Outlook for U.S. Fertility Rates: 2024 to 2054
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
 
2024: The FAR - Federal Acquisition Regulations, Part 38
2024: The FAR - Federal Acquisition Regulations, Part 382024: The FAR - Federal Acquisition Regulations, Part 38
2024: The FAR - Federal Acquisition Regulations, Part 38
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
 
kupon sample qurban masjid indonesia terbaru.pptx
kupon sample qurban masjid indonesia terbaru.pptxkupon sample qurban masjid indonesia terbaru.pptx
kupon sample qurban masjid indonesia terbaru.pptx
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
 
Transit-Oriented Development Study Working Group Meeting
Transit-Oriented Development Study Working Group MeetingTransit-Oriented Development Study Working Group Meeting
Transit-Oriented Development Study Working Group Meeting
 
State crafting: Changes and challenges for managing the public finances
State crafting: Changes and challenges for managing the public financesState crafting: Changes and challenges for managing the public finances
State crafting: Changes and challenges for managing the public finances
 
A proposed request for information on LIHTC
A proposed request for information on LIHTCA proposed request for information on LIHTC
A proposed request for information on LIHTC
 
Donate to charity during this holiday season
Donate to charity during this holiday seasonDonate to charity during this holiday season
Donate to charity during this holiday season
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
 
Monitoring Health for the SDGs - Global Health Statistics 2024 - WHO
Monitoring Health for the SDGs - Global Health Statistics 2024 - WHOMonitoring Health for the SDGs - Global Health Statistics 2024 - WHO
Monitoring Health for the SDGs - Global Health Statistics 2024 - WHO
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
 

Complex connections Rick Chorley

  • 1. 132kV Connection A First for N.S.W Coal Mining
  • 2. Introduction • Where is Boggabri – Situated between Gunnedah and Narrabri in north west N.S.W approx. 115km West from Tamworth. • Boggabri Coal Operations commenced mining in 2006 • A significant expansion of site infrastructure was undertaken in 2014/2015 • The 132kV connection was a joint project by Transgrid and Boggabri Coal Operations. • Included was 15kM of single structure, double circuit, 132kV transmission line, 132kV switching station and the 132kv/11kV substation.
  • 3. Overview • Boggabri Coal Operations were an LV customer (HV was managed by the utility) at inception. • Site demand was below 2MVA • An 11kV rural feeder from Boggabri Substation was the only mine supply source. The service extended over 25kM (voltage regulation was required). • Expansion of site infrastructure required power system demand exceeding the 11kV capability. • Overall site demand increased to 8MVA (design capacity) • Local services could not meet the demand – Transmission was the only option.
  • 4. Why 132kV Connection ? A first for Mining and Transgrid
  • 8.
  • 10. Inter tripping • 132kV trip signals are duplicated through protection relays from Boggabri Coal to Transgrid – Zone Protection (overcurrent, short circuit etc) – TX Differential – Emergency stops – Fire system – Back up Earth Leakage – Neutral Earth Resistor failure via NER monitor. – Transformer Protection (Oil temp, explosion, winding temp, over pressure) – Arc Fault Detection (11kv Bus) • Protection devices, Circuit breakers, are in Transgrids Switching Station. • Faults are cleared by transgrid for all 132kV primary protection or Intertrip faults
  • 12. Load shed Arrangements • Transmission systems demand stability • Transgrid Load shed scheme means exactly what is sounds like • 4 Tiers are implemented which shed different load blocks • Bus voltage is monitored at the switching station for trip signal initiations
  • 13. EARTHING • Common earthing system between Transgrid and Boggabri Coal • Design requirements - Allowable touch and step voltages were derived from different standards • Transgrid – AS2067 ( Calculated) • Boggabri Coal – AS3007 (step/touch potentials v’s clearance times) • Transfer voltage levels required separation between “mine infrastructure area” and the 132kV facility. A 164M exclusion zone has been established for earthed services entering this zone.
  • 15. Challenges • Design was completed by Transmission orientated Engineers with a different approach to mining “Risk management base” • Design review was undertaken by a QLD based engineering company • Disconnect between project team and the end user of the facility • System operation – original design philosophy was to run 2 x 10MVA TX’s in parallel which allowed for a 65kA fault level on the 415V system (terminals of the 3MVA TX supply) • Fundamental protection schemes, secondary systems, required further development prior to energistaion. • HV and LV services crossing operational boundaries. Boggabri Coal and Transgrid share HV and LV services originating on both sides of the installation. • Differences in isolation procedures, including hardware between both Transgrid and Boggabri Coal • Transgrid having a major facility “next door” to the mine substation. • Unrestricted earth fault levels on the 132kV connection (max 15kA) – transfer voltages • Reliance of primary protection clearing faults is by the utility – No 132kV protective devices are owned or operated by Boggabri Coal Operations.
  • 16. Advantages • Transgrid monitoring • Transgrid system control monitor the status of Transgrid equipment, including the 132kV circuit breakers, 24/7 • Remote operation of 132kV circuit breakers from Transgrid system control • Stability of Supply • The 132kV connection is part of the overall, north west area “Ring Main”. This means the system is very stable and subject to minimal outages or faults. • Reduced Arc Flash Categories • Increased equipment clearances (above 3M) and protection schemes allow for arc flash categories to be reduced
  • 17. Key Outcomes • Transgrid and Boggabri Coal Operating agreement implemented This document identifies – Equipment isolation instructions, each piece of equipment has an agreed isolation procedure – Communication protocol’s – Key contacts for events – Use and transaction of “High Voltage Equipment Outage” permits. • Connection Agreement – Highlights the obligations of each party – Deals with access and safety scenarios . – Modifications to the agreed installation and protection settings are dealt with here • Operational and Maintenance, hazard identification and risk analysis via consultation with designer, supplier, installer, operator and utility (Transgrid). – This process expedited the risk mitigation process due to designer information being supplied by key engineers • Designer based training for operational staff – Maintenance, Isolation and Operational documents were developed and used as training material for electrical staff by the designer. Training was delivered onsite.
  • 18. Recommendations • Where plant and installations are being constructed, for the purpose of mining operations, statutory functions should be involved in the key decisions. • Collaboration with mining and transmission industries requires further development. Mindsets are differing around system operations and protection functions.
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.