The document evaluates the sustainability of community-based water projects in Sudan, revealing that only 40% of these projects exhibit fair sustainability, largely due to insufficient financial support and poor organizational performance. It emphasizes the necessity of community participation in project management while also highlighting that mere community involvement does not guarantee project sustainability. The study advocates for enhanced post-implementation strategies and external assistance to improve the effectiveness and longevity of water projects.