Common Mistakes:
Plan Review & Inspection
March 8, 2022
Providing effective energy strategies for buildings and communities
ICC Preferred Provider # 2396
ICC Course # 31439
1. Understand the important details to look for during plan review
2. Understand what needs to be included in inspections
3. Learn good practice for communicating critical details to verify
during inspection
4. Understand commonly observed mistakes during inspections
Learning Objectives
Questions
The Smart Energy Design Assistance Center (SEDAC) is an applied
research program at University of Illinois.
Our mission: Reduce the energy footprint of Illinois and beyond.
Who We Are
SEDAC is the Illinois Energy
Conservation Code Training Provider
This training program is sponsored by
Illinois State Energy Office
Energy Code Training Program
Technical support
energycode@illinois.edu
800.214.7954
Online resources at
smartenergy.illinois.edu/energy-code
www.smartenergy.Illinois.edu/energy-code/
Access to 2018 IECC, Illinois Amendments & Chicago Energy Conservation Code
https://www2.illinois.gov/cdb/business/cod
es/IllinoisAccessibilityCode/Documents/20
18%20Illinois%20Specific%20Amendment
s%20with%20Modifications%20Shown.pdf
https://codes.iccsafe.org/content/
CHIEC2019P2
https://codes.iccsafe.org/content/IECC2018P4
https://codes.iccsafe.org/content/IECC2021P2
https://learn.smartenergy.illinois.edu/
https://smartenergy.illinois.edu/bee_fundamentals/
Plan Review Details
Section Summary
1. Energy Code Required Documentation
2. Key Items for Plan Review
1. Envelope checks
2. Lighting/Electrical checks
3. HVAC checks
4. Service hot water checks
Identify compliance path used:
• Prescriptive
• UA Tradeoff (Also Prescriptive)
• Energy Cost Budget/Simulated Performance
• ASHRAE 90.1 (Commercial Only)
• Energy Rating Index (Residential Only)
• Passive House (Coming summer 2022)
1. Compliance Path Changes Documentation
• Insulation materials and R-value
• Fenestration U-factor and SHGC (Area weighted factors if used)
• Mechanical design criteria
• Mechanical and hot water system details
• Economizer description(s)
• Controls narrative
• Fan power and controls
• Duct and pipe details including sealing, insulation, and location
• Lighting fixture schedule with wattage and controls
• Daylight zone depictions
• Air sealing details
1. C103 Construction Documents
1. R103.2 Construction Documents
• Insulation materials and their R-values
• Fenestration U-factors and SHGC
• Area-weighted U-factors and SHGC calculations
• Mechanical System design criteria
• Mechanical and service water-heating systems and
equipment types, sizes and efficiencies
• Equipment and system controls
• Duct sealing, duct and pipe insulation and location
• Air sealing details
1. Referencing Between Drawings and Specifications
Best to have in a single source (prints or specifications) to avoid
missing or conflicting data.
If in both, include cross references to aid in speed of review. Also
good to have a summary table of locations
1. Insulation levels
2. Air barrier compliance
3. Skylights (>2,500 SF >15’ tall)
4. Vestibules
5. Lighting power density
6. Daylight responsive controls
7. Occupant lighting controls
8. HVAC load calculations
9. HVAC energy recovery
10.Service water heating controls
2. Top 10 Commercial Plan review items
1. Air barrier (air control layer) location
2. Air infiltration level (default is 4 ACH50)
3. Insulation levels or total UA
4. Fenestration criteria (U-factor, SHGC, air tightness)
5. Table R402.4.1.1
6. High Efficacy lighting
7. Ventilation system
8. Manual J / Manual S / Manual D
9. Hot water circulation controls
10.Duct/pipe insulation for unconditioned spaces
2. Top 10 Residential Plan review items
2.1 Plan Review – Insulation Summary
In architectural plan summary page, include table with insulation summary
• Code required R-value/U-factor, Design values, and applicable areas
• For fenestration, also include code and design SHGC.
For UA trade-offs, include minimally compliant UA vs. calculated UA
2.1 Plan Review – Insulation Summary
In architectural plan summary page, include table with insulation summary
• Code required R-value/U-factor, Design values, and applicable areas
• For fenestration, also include code and design SHGC.
For UA trade-offs, include minimally compliant UA vs. calculated UA
2.1 Check Alignment of Control Layers
Alignment of thermal barrier between wall and above-deck roof
insulation often a difficult detail. Again, call out sealing between
differing materials and joints between assemblies.
Source: https://www.buildingenclosureonline.com/articles/88782‐ceu‐parapetscontinuity‐of‐control‐layers
2.1 Plan Review – Air & Thermal Barrier Details
Section views of walls and details of joints between dissimilar materials
should show the continuity of the thermal and air barriers clearly. Show
sealing compounds between joints/materials, too.
Image Source:  https://basc.pnnl.gov/cad‐files
Air 
Barrier
2.1 R402.4 Air Barrier Review Checklist
The sealing methods between dissimilar materials shall allow for
differential expansion and contraction.
Be sure to include appropriate detailing for building joints and
fenestration. (See table R402.4.1.1)
2.2 Plan Drawing Showing Daylit Zones
2.2 Required Documentation for R404
Lighting fixture schedule with lumens, wattage, and quantities.
Helpful to include lumens per watt
R404.1 calls out 90% or more of fixtures shall contain high-efficacy lamps.
• Note it is fixture-based 90% requirement, not bulb-count based.
Helpful to have fixture count in summary table as above so reviewer doesn’t
have to count fixture types in lighting floor-plan drawings.
Fixture Lumens Wattage Lm/W Fixture Quantity % of total
A 1100 12 92 50 35%
B 840 9 93 72 50%
C 635 65 10 12 8%
D 450 6 75 8 6%
E 536 12 45 2 1%
2.3 Verify Ventilation Strategy
Type: Negative Positive Balanced
Relies on: Infiltration Exfiltration Neither
2.3 Control Narratives and Sensor Graphics
Control Graphic
Control Narrative
Usually in a controls drawing 
section  or sub‐section of 
mechanical, satisfies C103.2 
information requirements for 
controls, economizer 
description, etc.
2.3 What about Rules of Thumb?
Common old rule-of-thumb for residential HVAC sizing was 1 ton of
cooling for every 500sf - 600sf.
https://www.energyvanguard.com/blog/air‐conditioner‐sizing‐rules‐of‐thumb‐must‐die
Source :
2.3 Mechanical System Design Process
ACCA Technical manuals cover
design, installation and
maintenance for residential and light
commercial HVAC systems.
HVAC Design Impacts
• 1st construction costs
• Comfort
• Indoor air quality
• Building durability
• Energy efficiency
• Higher customer satisfaction/
lower call backs
https://www.acca.org/standards/technical-manuals
2.3 Verify Outdoor Design Conditions
https://farm-energy.extension.org/wp-content/uploads/2019/04/7.-Outdoor_Design_Conditions_508.pdf
Ranges:  ‐4‐10     88‐93
2.4 Circulation Systems & Demand Recirculation Systems
• “Controls…shall start the pump based on the identification of a demand for hot 
water within the occupancy. The controls shall automatically turn off the pump 
when the water in the circulation loop is at the desired temperature and when 
there is not a demand for hot water.”
• “The controls shall start the pump upon receiving a signal from the action of a 
user of a fixture or appliance…The controls shall limit the temperature of the 
water entering the cold‐water piping to ≤ 104 °F.”
2.4 R403.8 Systems serving multiple units
Service Water Heating or HVAC
Systems serving multiple dwelling units shall comply with
Sections C403 and C404 of the IECC – Commercial Provisions
instead of R403
Inspections
Site Inspections Summary
1. Footing and Foundation Inspection
2. Framing and Rough-in Inspection
1. Insulation Installation Quality
2. Window Details
3. Air Sealing Testing
3. Plumbing Rough-in Inspection
4. Mechanical Rough-in Inspection
5. Final Inspection
1. C105.2.1 / R105.2.1 Footing and foundation
Checking R-value, location, thickness, depth of burial and
protection of insulation
https://foundationhandbook.ornl.gov/handbook/ 
1. R105.2.1 Footing and foundation
Checking depth of burial
• Does it go down far enough? (2’, 4’, 10’, within 6” of
basement slab, etc.)
• Part may be horizontal
1.1 C105.2.5 / R105.2.5 Framing and rough-in
Can be two parts – Framing structural & air sealing, followed by
insulation inspection (insulation makes air sealing harder to inspect)
Can also be single inspection, depending on building department
1.1 C105.2.5/R105.2.2 Thermal Envelope
Checking other thermal envelope air leakage controls
• Are the joints of dis-similar materials sealed?
• Are the joints of similar materials sealed?
1.1 C105.2.5 Thermal Envelope
Checking proper installation
• Fills the cavity
• Uncompressed
1.2 R105.2.5 / C105.2.5 Framing and rough-in
Checking fenestration properties such as U-factor and SHGC,
proper installation, and air leakage controls
1.2 R105.2.5 Framing and rough-in
Checking fenestration for proper installation
• Adequate space for air sealing around window
• Bottom flange not caulked to allow water out
1.3 R402.4.1.2 Blower Door Testing
Mandatory for residential construction
Residential air leakage rate not to exceed 4
air changes per hour @ 50 pascals
Where required by code official, testing shall
be conducted by an approved third party.
Testing performed after creation of all
penetrations of the building thermal
envelope
1.3 Bloor Door Testing for Multifamily Housing
Low-rise multifamily
Air leakage not exceeding 0.25 cubic feet per minute of
enclosure area (all six sides) at 50 Pascal.
Sampling methodology available for buildings >7 units
https://www.mncee.org/blog/may-2019/research-sidesteps-obstacles-measuring-air-tightne/
2. R105.2.3 / C105.2.3 Plumbing system
Types of insulation, corresponding R-value, protection, required
controls, and heat traps
3. R105.2.4 / C105.2.4 Mechanical system
HVAC equipment type, size, required controls, system
insulation, and corresponding R-value, system and damper air
leakage control, minimum fan efficiency, energy recovery, and
economizer
3. Mechanical rough-in
HVAC equipment size
• Does it match the design?
• Larger or smaller is a problem
• Commissioning process should start early in building process – design
drawings!
• Initial commissioning report may be reviewed during rough-in inspections
for HVAC systems – check some progress put into functional testing as
systems installed and brought online
• Verify there is a testing plan in place for controls required in C403
through C405 for HVAC, service hot water, and electrical.
3. C408 Commissioning
3. R105.2.4 / C105.2.4 Mechanical system
HVAC system air leakage control
• Duct sealing completed (UL tape, mastic, etc)?
• Damper air leakage rates or duct testing?
3. R105.2.4 Mechanical rough-in
whole-house ventilation system/controls
• System present?
• Designed controls installed?
4. C105.2.5 Electrical System
Lighting system controls, components, and meters
*Meters for Group R‐2
4. C105.2.6 Final
Installation and proper operation of all required building controls, and
documentation verifying activities associated with required building
commissioning have been conducted in accordance with Section C408
4. R105.2.5 Final
Any required remaining building systems, equipment, and controls and
their operation and the required number of high efficacy fixtures
Questions?
energycode@illinois.edu
800-214-7954

More Related Content

What's hot

Ventilation in Multi-Family Buildings - Summer Camp 2015
Ventilation in Multi-Family Buildings - Summer Camp 2015Ventilation in Multi-Family Buildings - Summer Camp 2015
Ventilation in Multi-Family Buildings - Summer Camp 2015
Lorne Ricketts
 
2015 IECC Key Highlights & Updates
2015 IECC Key Highlights & Updates2015 IECC Key Highlights & Updates
2015 IECC Key Highlights & Updates
Michael Brown
 
Genge, kerr assessing the effects of climate change on buildings using the pi...
Genge, kerr assessing the effects of climate change on buildings using the pi...Genge, kerr assessing the effects of climate change on buildings using the pi...
Genge, kerr assessing the effects of climate change on buildings using the pi...
Gerald R. (Jerry) Genge
 
HVAC Project
HVAC ProjectHVAC Project
HVAC Project
Tarek Shaker
 
Heating and ac
Heating and acHeating and ac
Heating and ac
Craig Kielb
 
Irjet v3 i12235
Irjet v3 i12235Irjet v3 i12235
Irjet v3 i12235
btlitm99
 
Corridor Pressurization System Performance in MURBS
Corridor Pressurization System Performance in MURBSCorridor Pressurization System Performance in MURBS
Corridor Pressurization System Performance in MURBS
RDH Building Science
 
Especificando um sistema de traço a vapor
Especificando um sistema de traço a vaporEspecificando um sistema de traço a vapor
Especificando um sistema de traço a vapor
Paulo Costa
 
NBEC 2014 - Airflow in Mid to High-rise Multi-Unit Residential Buildings
NBEC 2014 - Airflow in Mid to High-rise Multi-Unit Residential BuildingsNBEC 2014 - Airflow in Mid to High-rise Multi-Unit Residential Buildings
NBEC 2014 - Airflow in Mid to High-rise Multi-Unit Residential Buildings
RDH Building Science
 
Stimulus Package Energy Efficiency Credits White Paper
Stimulus Package Energy Efficiency Credits White PaperStimulus Package Energy Efficiency Credits White Paper
Stimulus Package Energy Efficiency Credits White Paper
Marky Moore
 
Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...
Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...
Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...
lizzabel
 
NBEC 2014 - MURB Airtightness Study
NBEC 2014 - MURB Airtightness StudyNBEC 2014 - MURB Airtightness Study
NBEC 2014 - MURB Airtightness Study
RDH Building Science
 
Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi...
 Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi... Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi...
Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi...
BREEZE Software
 
Manual de dimensionamento de Traço a Vapor
Manual de dimensionamento de Traço a VaporManual de dimensionamento de Traço a Vapor
Manual de dimensionamento de Traço a Vapor
Paulo Costa
 
2009 IECC: Residential Provisions
2009 IECC: Residential Provisions2009 IECC: Residential Provisions
2009 IECC: Residential Provisions
G Communications 360
 
South Carolina Research Authority 2010 M2G Certification
South Carolina Research Authority 2010 M2G CertificationSouth Carolina Research Authority 2010 M2G Certification
South Carolina Research Authority 2010 M2G Certification
Charles Rice
 
SEAI - Non Domestic Webinar #1 Domestic Hot Water Systems in NEAP
SEAI - Non Domestic Webinar #1 Domestic Hot Water Systems in NEAPSEAI - Non Domestic Webinar #1 Domestic Hot Water Systems in NEAP
SEAI - Non Domestic Webinar #1 Domestic Hot Water Systems in NEAP
SustainableEnergyAut
 
New Code Requirements for Fenestration Energy Performance
New Code Requirements for Fenestration Energy PerformanceNew Code Requirements for Fenestration Energy Performance
New Code Requirements for Fenestration Energy Performance
RDH Building Science
 
How to Design Mechanical Building Services
How to Design Mechanical Building ServicesHow to Design Mechanical Building Services
How to Design Mechanical Building Services
David Seymour M.Eng, C.Eng, MCIBSE, MCIPHE
 
Indoor Air Quality & HVAC SYSTEMS
Indoor Air Quality & HVAC SYSTEMSIndoor Air Quality & HVAC SYSTEMS
Indoor Air Quality & HVAC SYSTEMS
debbiezp
 

What's hot (20)

Ventilation in Multi-Family Buildings - Summer Camp 2015
Ventilation in Multi-Family Buildings - Summer Camp 2015Ventilation in Multi-Family Buildings - Summer Camp 2015
Ventilation in Multi-Family Buildings - Summer Camp 2015
 
2015 IECC Key Highlights & Updates
2015 IECC Key Highlights & Updates2015 IECC Key Highlights & Updates
2015 IECC Key Highlights & Updates
 
Genge, kerr assessing the effects of climate change on buildings using the pi...
Genge, kerr assessing the effects of climate change on buildings using the pi...Genge, kerr assessing the effects of climate change on buildings using the pi...
Genge, kerr assessing the effects of climate change on buildings using the pi...
 
HVAC Project
HVAC ProjectHVAC Project
HVAC Project
 
Heating and ac
Heating and acHeating and ac
Heating and ac
 
Irjet v3 i12235
Irjet v3 i12235Irjet v3 i12235
Irjet v3 i12235
 
Corridor Pressurization System Performance in MURBS
Corridor Pressurization System Performance in MURBSCorridor Pressurization System Performance in MURBS
Corridor Pressurization System Performance in MURBS
 
Especificando um sistema de traço a vapor
Especificando um sistema de traço a vaporEspecificando um sistema de traço a vapor
Especificando um sistema de traço a vapor
 
NBEC 2014 - Airflow in Mid to High-rise Multi-Unit Residential Buildings
NBEC 2014 - Airflow in Mid to High-rise Multi-Unit Residential BuildingsNBEC 2014 - Airflow in Mid to High-rise Multi-Unit Residential Buildings
NBEC 2014 - Airflow in Mid to High-rise Multi-Unit Residential Buildings
 
Stimulus Package Energy Efficiency Credits White Paper
Stimulus Package Energy Efficiency Credits White PaperStimulus Package Energy Efficiency Credits White Paper
Stimulus Package Energy Efficiency Credits White Paper
 
Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...
Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...
Oct. 24 Webinar/Seminar: Is ASHRAE 90.1 2012 or iecc-2012 the right energy co...
 
NBEC 2014 - MURB Airtightness Study
NBEC 2014 - MURB Airtightness StudyNBEC 2014 - MURB Airtightness Study
NBEC 2014 - MURB Airtightness Study
 
Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi...
 Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi... Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi...
Performing Safety Modeling Analysis To Comply With LNG Facility Siting Requi...
 
Manual de dimensionamento de Traço a Vapor
Manual de dimensionamento de Traço a VaporManual de dimensionamento de Traço a Vapor
Manual de dimensionamento de Traço a Vapor
 
2009 IECC: Residential Provisions
2009 IECC: Residential Provisions2009 IECC: Residential Provisions
2009 IECC: Residential Provisions
 
South Carolina Research Authority 2010 M2G Certification
South Carolina Research Authority 2010 M2G CertificationSouth Carolina Research Authority 2010 M2G Certification
South Carolina Research Authority 2010 M2G Certification
 
SEAI - Non Domestic Webinar #1 Domestic Hot Water Systems in NEAP
SEAI - Non Domestic Webinar #1 Domestic Hot Water Systems in NEAPSEAI - Non Domestic Webinar #1 Domestic Hot Water Systems in NEAP
SEAI - Non Domestic Webinar #1 Domestic Hot Water Systems in NEAP
 
New Code Requirements for Fenestration Energy Performance
New Code Requirements for Fenestration Energy PerformanceNew Code Requirements for Fenestration Energy Performance
New Code Requirements for Fenestration Energy Performance
 
How to Design Mechanical Building Services
How to Design Mechanical Building ServicesHow to Design Mechanical Building Services
How to Design Mechanical Building Services
 
Indoor Air Quality & HVAC SYSTEMS
Indoor Air Quality & HVAC SYSTEMSIndoor Air Quality & HVAC SYSTEMS
Indoor Air Quality & HVAC SYSTEMS
 

Similar to Common Mistakes: Plan Review & Inspection

IECC 2009 Training
IECC 2009 TrainingIECC 2009 Training
IECC 2009 Training
G Communications 360
 
2009 IECC: Commercial
2009 IECC: Commercial2009 IECC: Commercial
2009 IECC: Commercial
G Communications 360
 
Climate change paper genge and kerr
Climate change paper genge and kerrClimate change paper genge and kerr
Climate change paper genge and kerr
Gerald R. (Jerry) Genge
 
Final Report Condensed
Final Report CondensedFinal Report Condensed
Final Report Condensed
Austin Christianson
 
HVAC Cent vs decent ac systems
HVAC Cent vs decent ac systemsHVAC Cent vs decent ac systems
HVAC Cent vs decent ac systems
varunsingh383
 
Australian indoor environment rating tools, and the future of building health...
Australian indoor environment rating tools, and the future of building health...Australian indoor environment rating tools, and the future of building health...
Australian indoor environment rating tools, and the future of building health...
Michael Taranto
 
Insulated metal panels edc1
Insulated metal panels edc1Insulated metal panels edc1
Insulated metal panels edc1
Derrick Teal
 
IPC 7711/7721 Revision B Rework, Modification & Repair of Electronic Assemblies
IPC 7711/7721 Revision B Rework, Modification & Repair of Electronic AssembliesIPC 7711/7721 Revision B Rework, Modification & Repair of Electronic Assemblies
IPC 7711/7721 Revision B Rework, Modification & Repair of Electronic Assemblies
imagination
 
Project report1
Project report1Project report1
Project report1
SAMALIS_SOFTWARES.Inc.
 
Energy Efficient Building Enclosure Design Guidelines for Wood-Frame Buildings
Energy Efficient Building Enclosure Design Guidelines for Wood-Frame BuildingsEnergy Efficient Building Enclosure Design Guidelines for Wood-Frame Buildings
Energy Efficient Building Enclosure Design Guidelines for Wood-Frame Buildings
RDH Building Science
 
ASHRAE Standard 100
ASHRAE Standard 100ASHRAE Standard 100
ASHRAE Standard 100
Illinois ASHRAE
 
Hvac manpreet singh naroo
Hvac  manpreet singh narooHvac  manpreet singh naroo
Hvac manpreet singh naroo
Manpreet Singh Naroo
 
WoodWorks 2013 Vancouver - Energy-Efficient Building Enclosure Design Guideli...
WoodWorks 2013 Vancouver - Energy-Efficient Building Enclosure Design Guideli...WoodWorks 2013 Vancouver - Energy-Efficient Building Enclosure Design Guideli...
WoodWorks 2013 Vancouver - Energy-Efficient Building Enclosure Design Guideli...
Graham Finch
 
X472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leedX472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leed
michaeljmack
 
Utilizing Energy Recovery and Optimizing Air
Utilizing Energy Recovery and Optimizing AirUtilizing Energy Recovery and Optimizing Air
Utilizing Energy Recovery and Optimizing Air
CannonDesign
 
SB-12 Energy Star Training
SB-12 Energy Star TrainingSB-12 Energy Star Training
SB-12 Energy Star Training
tboyko
 
Do Trade-Offs Improve Energy Efficiency
Do Trade-Offs Improve Energy EfficiencyDo Trade-Offs Improve Energy Efficiency
Do Trade-Offs Improve Energy Efficiency
Brett Dillon
 
05 - IEC 61400-15 Update, Jason Fields (NREL).pptx
05 - IEC 61400-15 Update, Jason Fields (NREL).pptx05 - IEC 61400-15 Update, Jason Fields (NREL).pptx
05 - IEC 61400-15 Update, Jason Fields (NREL).pptx
ZaidMasoodKhan
 
2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems
michaeljmack
 
High performance buildings & rating tools
High performance buildings & rating toolsHigh performance buildings & rating tools
High performance buildings & rating tools
Ken Thomson
 

Similar to Common Mistakes: Plan Review & Inspection (20)

IECC 2009 Training
IECC 2009 TrainingIECC 2009 Training
IECC 2009 Training
 
2009 IECC: Commercial
2009 IECC: Commercial2009 IECC: Commercial
2009 IECC: Commercial
 
Climate change paper genge and kerr
Climate change paper genge and kerrClimate change paper genge and kerr
Climate change paper genge and kerr
 
Final Report Condensed
Final Report CondensedFinal Report Condensed
Final Report Condensed
 
HVAC Cent vs decent ac systems
HVAC Cent vs decent ac systemsHVAC Cent vs decent ac systems
HVAC Cent vs decent ac systems
 
Australian indoor environment rating tools, and the future of building health...
Australian indoor environment rating tools, and the future of building health...Australian indoor environment rating tools, and the future of building health...
Australian indoor environment rating tools, and the future of building health...
 
Insulated metal panels edc1
Insulated metal panels edc1Insulated metal panels edc1
Insulated metal panels edc1
 
IPC 7711/7721 Revision B Rework, Modification & Repair of Electronic Assemblies
IPC 7711/7721 Revision B Rework, Modification & Repair of Electronic AssembliesIPC 7711/7721 Revision B Rework, Modification & Repair of Electronic Assemblies
IPC 7711/7721 Revision B Rework, Modification & Repair of Electronic Assemblies
 
Project report1
Project report1Project report1
Project report1
 
Energy Efficient Building Enclosure Design Guidelines for Wood-Frame Buildings
Energy Efficient Building Enclosure Design Guidelines for Wood-Frame BuildingsEnergy Efficient Building Enclosure Design Guidelines for Wood-Frame Buildings
Energy Efficient Building Enclosure Design Guidelines for Wood-Frame Buildings
 
ASHRAE Standard 100
ASHRAE Standard 100ASHRAE Standard 100
ASHRAE Standard 100
 
Hvac manpreet singh naroo
Hvac  manpreet singh narooHvac  manpreet singh naroo
Hvac manpreet singh naroo
 
WoodWorks 2013 Vancouver - Energy-Efficient Building Enclosure Design Guideli...
WoodWorks 2013 Vancouver - Energy-Efficient Building Enclosure Design Guideli...WoodWorks 2013 Vancouver - Energy-Efficient Building Enclosure Design Guideli...
WoodWorks 2013 Vancouver - Energy-Efficient Building Enclosure Design Guideli...
 
X472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leedX472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leed
 
Utilizing Energy Recovery and Optimizing Air
Utilizing Energy Recovery and Optimizing AirUtilizing Energy Recovery and Optimizing Air
Utilizing Energy Recovery and Optimizing Air
 
SB-12 Energy Star Training
SB-12 Energy Star TrainingSB-12 Energy Star Training
SB-12 Energy Star Training
 
Do Trade-Offs Improve Energy Efficiency
Do Trade-Offs Improve Energy EfficiencyDo Trade-Offs Improve Energy Efficiency
Do Trade-Offs Improve Energy Efficiency
 
05 - IEC 61400-15 Update, Jason Fields (NREL).pptx
05 - IEC 61400-15 Update, Jason Fields (NREL).pptx05 - IEC 61400-15 Update, Jason Fields (NREL).pptx
05 - IEC 61400-15 Update, Jason Fields (NREL).pptx
 
2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems
 
High performance buildings & rating tools
High performance buildings & rating toolsHigh performance buildings & rating tools
High performance buildings & rating tools
 

More from Meghan Knudson

2016 Code Memorandum Roofing Requirements
2016 Code Memorandum Roofing Requirements2016 Code Memorandum Roofing Requirements
2016 Code Memorandum Roofing Requirements
Meghan Knudson
 
Village of Hanover Park Plan Reviewer/Project Coordinator
Village of Hanover Park Plan Reviewer/Project CoordinatorVillage of Hanover Park Plan Reviewer/Project Coordinator
Village of Hanover Park Plan Reviewer/Project Coordinator
Meghan Knudson
 
Village of La Grange Director of Building and Inspectional Services
Village of La Grange Director of Building and Inspectional ServicesVillage of La Grange Director of Building and Inspectional Services
Village of La Grange Director of Building and Inspectional Services
Meghan Knudson
 
City of Crystal Lake Development Service Representative
City of Crystal Lake Development Service RepresentativeCity of Crystal Lake Development Service Representative
City of Crystal Lake Development Service Representative
Meghan Knudson
 
Illinois Energy Conservation Advisory Council Local Code Official
 Illinois Energy Conservation Advisory Council Local Code Official Illinois Energy Conservation Advisory Council Local Code Official
Illinois Energy Conservation Advisory Council Local Code Official
Meghan Knudson
 
Addison Building Division Supervisor
Addison Building Division SupervisorAddison Building Division Supervisor
Addison Building Division Supervisor
Meghan Knudson
 
Winnetka Building & Code Enforcement Manager
Winnetka Building & Code Enforcement ManagerWinnetka Building & Code Enforcement Manager
Winnetka Building & Code Enforcement Manager
Meghan Knudson
 
Glendale Heights Code Enforcement Inspector
Glendale Heights Code Enforcement InspectorGlendale Heights Code Enforcement Inspector
Glendale Heights Code Enforcement Inspector
Meghan Knudson
 
South Holland Building Inspector
South Holland Building InspectorSouth Holland Building Inspector
South Holland Building Inspector
Meghan Knudson
 
Schaumburg Building Official (Community Development)
Schaumburg Building Official (Community Development)Schaumburg Building Official (Community Development)
Schaumburg Building Official (Community Development)
Meghan Knudson
 
Evaston Director of Community Development
Evaston Director of Community DevelopmentEvaston Director of Community Development
Evaston Director of Community Development
Meghan Knudson
 
Palatine Customer Service Representative
Palatine Customer Service RepresentativePalatine Customer Service Representative
Palatine Customer Service Representative
Meghan Knudson
 
Algonquin Building Commissioner
Algonquin Building CommissionerAlgonquin Building Commissioner
Algonquin Building Commissioner
Meghan Knudson
 
Palatine Part-Time Fire Inspector
Palatine Part-Time Fire InspectorPalatine Part-Time Fire Inspector
Palatine Part-Time Fire Inspector
Meghan Knudson
 
Pace Facilities Maintenance Specialist
Pace Facilities Maintenance SpecialistPace Facilities Maintenance Specialist
Pace Facilities Maintenance Specialist
Meghan Knudson
 
Pace Construction Project Manager
Pace Construction Project ManagerPace Construction Project Manager
Pace Construction Project Manager
Meghan Knudson
 
Pace Construction Document Controller
Pace Construction Document ControllerPace Construction Document Controller
Pace Construction Document Controller
Meghan Knudson
 
Hanover Park Building Inspector
Hanover Park Building InspectorHanover Park Building Inspector
Hanover Park Building Inspector
Meghan Knudson
 
Lemont Building Inspector/Plans Examiner
Lemont Building Inspector/Plans ExaminerLemont Building Inspector/Plans Examiner
Lemont Building Inspector/Plans Examiner
Meghan Knudson
 
Huntley Combination Plumbing/Building Inspector
Huntley Combination Plumbing/Building InspectorHuntley Combination Plumbing/Building Inspector
Huntley Combination Plumbing/Building Inspector
Meghan Knudson
 

More from Meghan Knudson (20)

2016 Code Memorandum Roofing Requirements
2016 Code Memorandum Roofing Requirements2016 Code Memorandum Roofing Requirements
2016 Code Memorandum Roofing Requirements
 
Village of Hanover Park Plan Reviewer/Project Coordinator
Village of Hanover Park Plan Reviewer/Project CoordinatorVillage of Hanover Park Plan Reviewer/Project Coordinator
Village of Hanover Park Plan Reviewer/Project Coordinator
 
Village of La Grange Director of Building and Inspectional Services
Village of La Grange Director of Building and Inspectional ServicesVillage of La Grange Director of Building and Inspectional Services
Village of La Grange Director of Building and Inspectional Services
 
City of Crystal Lake Development Service Representative
City of Crystal Lake Development Service RepresentativeCity of Crystal Lake Development Service Representative
City of Crystal Lake Development Service Representative
 
Illinois Energy Conservation Advisory Council Local Code Official
 Illinois Energy Conservation Advisory Council Local Code Official Illinois Energy Conservation Advisory Council Local Code Official
Illinois Energy Conservation Advisory Council Local Code Official
 
Addison Building Division Supervisor
Addison Building Division SupervisorAddison Building Division Supervisor
Addison Building Division Supervisor
 
Winnetka Building & Code Enforcement Manager
Winnetka Building & Code Enforcement ManagerWinnetka Building & Code Enforcement Manager
Winnetka Building & Code Enforcement Manager
 
Glendale Heights Code Enforcement Inspector
Glendale Heights Code Enforcement InspectorGlendale Heights Code Enforcement Inspector
Glendale Heights Code Enforcement Inspector
 
South Holland Building Inspector
South Holland Building InspectorSouth Holland Building Inspector
South Holland Building Inspector
 
Schaumburg Building Official (Community Development)
Schaumburg Building Official (Community Development)Schaumburg Building Official (Community Development)
Schaumburg Building Official (Community Development)
 
Evaston Director of Community Development
Evaston Director of Community DevelopmentEvaston Director of Community Development
Evaston Director of Community Development
 
Palatine Customer Service Representative
Palatine Customer Service RepresentativePalatine Customer Service Representative
Palatine Customer Service Representative
 
Algonquin Building Commissioner
Algonquin Building CommissionerAlgonquin Building Commissioner
Algonquin Building Commissioner
 
Palatine Part-Time Fire Inspector
Palatine Part-Time Fire InspectorPalatine Part-Time Fire Inspector
Palatine Part-Time Fire Inspector
 
Pace Facilities Maintenance Specialist
Pace Facilities Maintenance SpecialistPace Facilities Maintenance Specialist
Pace Facilities Maintenance Specialist
 
Pace Construction Project Manager
Pace Construction Project ManagerPace Construction Project Manager
Pace Construction Project Manager
 
Pace Construction Document Controller
Pace Construction Document ControllerPace Construction Document Controller
Pace Construction Document Controller
 
Hanover Park Building Inspector
Hanover Park Building InspectorHanover Park Building Inspector
Hanover Park Building Inspector
 
Lemont Building Inspector/Plans Examiner
Lemont Building Inspector/Plans ExaminerLemont Building Inspector/Plans Examiner
Lemont Building Inspector/Plans Examiner
 
Huntley Combination Plumbing/Building Inspector
Huntley Combination Plumbing/Building InspectorHuntley Combination Plumbing/Building Inspector
Huntley Combination Plumbing/Building Inspector
 

Recently uploaded

原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
3woawyyl
 
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
ssuser05e8f3
 
2024: The FAR - Federal Acquisition Regulations, Part 40
2024: The FAR - Federal Acquisition Regulations, Part 402024: The FAR - Federal Acquisition Regulations, Part 40
2024: The FAR - Federal Acquisition Regulations, Part 40
JSchaus & Associates
 
Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019
Partito democratico
 
United Nations World Oceans Day 2024; June 8th " Awaken new dephts".
United Nations World Oceans Day 2024; June 8th " Awaken new dephts".United Nations World Oceans Day 2024; June 8th " Awaken new dephts".
United Nations World Oceans Day 2024; June 8th " Awaken new dephts".
Christina Parmionova
 
Texas Water Development Board Updates June 2024
Texas Water Development Board Updates June 2024Texas Water Development Board Updates June 2024
Texas Water Development Board Updates June 2024
Texas Alliance of Groundwater Districts
 
karnataka housing board schemes . all schemes
karnataka housing board schemes . all schemeskarnataka housing board schemes . all schemes
karnataka housing board schemes . all schemes
narinav14
 
Border towns and spaces of (in)visibility.pdf
Border towns and spaces of (in)visibility.pdfBorder towns and spaces of (in)visibility.pdf
Border towns and spaces of (in)visibility.pdf
Scalabrini Institute for Human Mobility in Africa
 
Researching the client.pptxsxssssssssssssssssssssss
Researching the client.pptxsxssssssssssssssssssssssResearching the client.pptxsxssssssssssssssssssssss
Researching the client.pptxsxssssssssssssssssssssss
DanielOliver74
 
Indira awas yojana housing scheme renamed as PMAY
Indira awas yojana housing scheme renamed as PMAYIndira awas yojana housing scheme renamed as PMAY
Indira awas yojana housing scheme renamed as PMAY
narinav14
 
2024: The FAR - Federal Acquisition Regulations, Part 42
2024: The FAR - Federal Acquisition Regulations, Part 422024: The FAR - Federal Acquisition Regulations, Part 42
2024: The FAR - Federal Acquisition Regulations, Part 42
JSchaus & Associates
 
PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)
ahcitycouncil
 
RFP for Reno's Community Assistance Center
RFP for Reno's Community Assistance CenterRFP for Reno's Community Assistance Center
RFP for Reno's Community Assistance Center
This Is Reno
 
China Politics social economic political
China Politics social economic politicalChina Politics social economic political
China Politics social economic political
ajatjamwal123
 
Item # 10 -- Historical Presv. Districts
Item # 10 -- Historical Presv. DistrictsItem # 10 -- Historical Presv. Districts
Item # 10 -- Historical Presv. Districts
ahcitycouncil
 
2024: The FAR - Federal Acquisition Regulations, Part 39
2024: The FAR - Federal Acquisition Regulations, Part 392024: The FAR - Federal Acquisition Regulations, Part 39
2024: The FAR - Federal Acquisition Regulations, Part 39
JSchaus & Associates
 
原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样
原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样
原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样
yemqpj
 
Abiy Berehe - Texas Commission on Environmental Quality Updates
Abiy Berehe - Texas Commission on Environmental Quality UpdatesAbiy Berehe - Texas Commission on Environmental Quality Updates
Abiy Berehe - Texas Commission on Environmental Quality Updates
Texas Alliance of Groundwater Districts
 
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC Charlotte
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC CharlotteA Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC Charlotte
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC Charlotte
Cori Faklaris
 
Practical guide for the celebration of World Environment Day on june 5th.
Practical guide for the  celebration of World Environment Day on  june 5th.Practical guide for the  celebration of World Environment Day on  june 5th.
Practical guide for the celebration of World Environment Day on june 5th.
Christina Parmionova
 

Recently uploaded (20)

原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
 
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
 
2024: The FAR - Federal Acquisition Regulations, Part 40
2024: The FAR - Federal Acquisition Regulations, Part 402024: The FAR - Federal Acquisition Regulations, Part 40
2024: The FAR - Federal Acquisition Regulations, Part 40
 
Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019
 
United Nations World Oceans Day 2024; June 8th " Awaken new dephts".
United Nations World Oceans Day 2024; June 8th " Awaken new dephts".United Nations World Oceans Day 2024; June 8th " Awaken new dephts".
United Nations World Oceans Day 2024; June 8th " Awaken new dephts".
 
Texas Water Development Board Updates June 2024
Texas Water Development Board Updates June 2024Texas Water Development Board Updates June 2024
Texas Water Development Board Updates June 2024
 
karnataka housing board schemes . all schemes
karnataka housing board schemes . all schemeskarnataka housing board schemes . all schemes
karnataka housing board schemes . all schemes
 
Border towns and spaces of (in)visibility.pdf
Border towns and spaces of (in)visibility.pdfBorder towns and spaces of (in)visibility.pdf
Border towns and spaces of (in)visibility.pdf
 
Researching the client.pptxsxssssssssssssssssssssss
Researching the client.pptxsxssssssssssssssssssssssResearching the client.pptxsxssssssssssssssssssssss
Researching the client.pptxsxssssssssssssssssssssss
 
Indira awas yojana housing scheme renamed as PMAY
Indira awas yojana housing scheme renamed as PMAYIndira awas yojana housing scheme renamed as PMAY
Indira awas yojana housing scheme renamed as PMAY
 
2024: The FAR - Federal Acquisition Regulations, Part 42
2024: The FAR - Federal Acquisition Regulations, Part 422024: The FAR - Federal Acquisition Regulations, Part 42
2024: The FAR - Federal Acquisition Regulations, Part 42
 
PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)
 
RFP for Reno's Community Assistance Center
RFP for Reno's Community Assistance CenterRFP for Reno's Community Assistance Center
RFP for Reno's Community Assistance Center
 
China Politics social economic political
China Politics social economic politicalChina Politics social economic political
China Politics social economic political
 
Item # 10 -- Historical Presv. Districts
Item # 10 -- Historical Presv. DistrictsItem # 10 -- Historical Presv. Districts
Item # 10 -- Historical Presv. Districts
 
2024: The FAR - Federal Acquisition Regulations, Part 39
2024: The FAR - Federal Acquisition Regulations, Part 392024: The FAR - Federal Acquisition Regulations, Part 39
2024: The FAR - Federal Acquisition Regulations, Part 39
 
原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样
原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样
原版制作(DPU毕业证书)德保罗大学毕业证Offer一模一样
 
Abiy Berehe - Texas Commission on Environmental Quality Updates
Abiy Berehe - Texas Commission on Environmental Quality UpdatesAbiy Berehe - Texas Commission on Environmental Quality Updates
Abiy Berehe - Texas Commission on Environmental Quality Updates
 
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC Charlotte
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC CharlotteA Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC Charlotte
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC Charlotte
 
Practical guide for the celebration of World Environment Day on june 5th.
Practical guide for the  celebration of World Environment Day on  june 5th.Practical guide for the  celebration of World Environment Day on  june 5th.
Practical guide for the celebration of World Environment Day on june 5th.
 

Common Mistakes: Plan Review & Inspection

  • 1. Common Mistakes: Plan Review & Inspection March 8, 2022 Providing effective energy strategies for buildings and communities ICC Preferred Provider # 2396 ICC Course # 31439
  • 2. 1. Understand the important details to look for during plan review 2. Understand what needs to be included in inspections 3. Learn good practice for communicating critical details to verify during inspection 4. Understand commonly observed mistakes during inspections Learning Objectives
  • 4. The Smart Energy Design Assistance Center (SEDAC) is an applied research program at University of Illinois. Our mission: Reduce the energy footprint of Illinois and beyond. Who We Are
  • 5. SEDAC is the Illinois Energy Conservation Code Training Provider This training program is sponsored by Illinois State Energy Office
  • 6. Energy Code Training Program Technical support energycode@illinois.edu 800.214.7954 Online resources at smartenergy.illinois.edu/energy-code
  • 8. Access to 2018 IECC, Illinois Amendments & Chicago Energy Conservation Code https://www2.illinois.gov/cdb/business/cod es/IllinoisAccessibilityCode/Documents/20 18%20Illinois%20Specific%20Amendment s%20with%20Modifications%20Shown.pdf https://codes.iccsafe.org/content/ CHIEC2019P2 https://codes.iccsafe.org/content/IECC2018P4 https://codes.iccsafe.org/content/IECC2021P2
  • 11. Section Summary 1. Energy Code Required Documentation 2. Key Items for Plan Review 1. Envelope checks 2. Lighting/Electrical checks 3. HVAC checks 4. Service hot water checks
  • 12. Identify compliance path used: • Prescriptive • UA Tradeoff (Also Prescriptive) • Energy Cost Budget/Simulated Performance • ASHRAE 90.1 (Commercial Only) • Energy Rating Index (Residential Only) • Passive House (Coming summer 2022) 1. Compliance Path Changes Documentation
  • 13. • Insulation materials and R-value • Fenestration U-factor and SHGC (Area weighted factors if used) • Mechanical design criteria • Mechanical and hot water system details • Economizer description(s) • Controls narrative • Fan power and controls • Duct and pipe details including sealing, insulation, and location • Lighting fixture schedule with wattage and controls • Daylight zone depictions • Air sealing details 1. C103 Construction Documents
  • 14. 1. R103.2 Construction Documents • Insulation materials and their R-values • Fenestration U-factors and SHGC • Area-weighted U-factors and SHGC calculations • Mechanical System design criteria • Mechanical and service water-heating systems and equipment types, sizes and efficiencies • Equipment and system controls • Duct sealing, duct and pipe insulation and location • Air sealing details
  • 15. 1. Referencing Between Drawings and Specifications Best to have in a single source (prints or specifications) to avoid missing or conflicting data. If in both, include cross references to aid in speed of review. Also good to have a summary table of locations
  • 16. 1. Insulation levels 2. Air barrier compliance 3. Skylights (>2,500 SF >15’ tall) 4. Vestibules 5. Lighting power density 6. Daylight responsive controls 7. Occupant lighting controls 8. HVAC load calculations 9. HVAC energy recovery 10.Service water heating controls 2. Top 10 Commercial Plan review items
  • 17. 1. Air barrier (air control layer) location 2. Air infiltration level (default is 4 ACH50) 3. Insulation levels or total UA 4. Fenestration criteria (U-factor, SHGC, air tightness) 5. Table R402.4.1.1 6. High Efficacy lighting 7. Ventilation system 8. Manual J / Manual S / Manual D 9. Hot water circulation controls 10.Duct/pipe insulation for unconditioned spaces 2. Top 10 Residential Plan review items
  • 18. 2.1 Plan Review – Insulation Summary In architectural plan summary page, include table with insulation summary • Code required R-value/U-factor, Design values, and applicable areas • For fenestration, also include code and design SHGC. For UA trade-offs, include minimally compliant UA vs. calculated UA
  • 19. 2.1 Plan Review – Insulation Summary In architectural plan summary page, include table with insulation summary • Code required R-value/U-factor, Design values, and applicable areas • For fenestration, also include code and design SHGC. For UA trade-offs, include minimally compliant UA vs. calculated UA
  • 20. 2.1 Check Alignment of Control Layers Alignment of thermal barrier between wall and above-deck roof insulation often a difficult detail. Again, call out sealing between differing materials and joints between assemblies. Source: https://www.buildingenclosureonline.com/articles/88782‐ceu‐parapetscontinuity‐of‐control‐layers
  • 21. 2.1 Plan Review – Air & Thermal Barrier Details Section views of walls and details of joints between dissimilar materials should show the continuity of the thermal and air barriers clearly. Show sealing compounds between joints/materials, too. Image Source:  https://basc.pnnl.gov/cad‐files Air  Barrier
  • 22. 2.1 R402.4 Air Barrier Review Checklist The sealing methods between dissimilar materials shall allow for differential expansion and contraction. Be sure to include appropriate detailing for building joints and fenestration. (See table R402.4.1.1)
  • 23. 2.2 Plan Drawing Showing Daylit Zones
  • 24. 2.2 Required Documentation for R404 Lighting fixture schedule with lumens, wattage, and quantities. Helpful to include lumens per watt R404.1 calls out 90% or more of fixtures shall contain high-efficacy lamps. • Note it is fixture-based 90% requirement, not bulb-count based. Helpful to have fixture count in summary table as above so reviewer doesn’t have to count fixture types in lighting floor-plan drawings. Fixture Lumens Wattage Lm/W Fixture Quantity % of total A 1100 12 92 50 35% B 840 9 93 72 50% C 635 65 10 12 8% D 450 6 75 8 6% E 536 12 45 2 1%
  • 25. 2.3 Verify Ventilation Strategy Type: Negative Positive Balanced Relies on: Infiltration Exfiltration Neither
  • 26. 2.3 Control Narratives and Sensor Graphics Control Graphic Control Narrative Usually in a controls drawing  section  or sub‐section of  mechanical, satisfies C103.2  information requirements for  controls, economizer  description, etc.
  • 27. 2.3 What about Rules of Thumb? Common old rule-of-thumb for residential HVAC sizing was 1 ton of cooling for every 500sf - 600sf. https://www.energyvanguard.com/blog/air‐conditioner‐sizing‐rules‐of‐thumb‐must‐die Source :
  • 28. 2.3 Mechanical System Design Process ACCA Technical manuals cover design, installation and maintenance for residential and light commercial HVAC systems. HVAC Design Impacts • 1st construction costs • Comfort • Indoor air quality • Building durability • Energy efficiency • Higher customer satisfaction/ lower call backs https://www.acca.org/standards/technical-manuals
  • 29. 2.3 Verify Outdoor Design Conditions https://farm-energy.extension.org/wp-content/uploads/2019/04/7.-Outdoor_Design_Conditions_508.pdf Ranges:  ‐4‐10     88‐93
  • 30.
  • 31. 2.4 Circulation Systems & Demand Recirculation Systems • “Controls…shall start the pump based on the identification of a demand for hot  water within the occupancy. The controls shall automatically turn off the pump  when the water in the circulation loop is at the desired temperature and when  there is not a demand for hot water.” • “The controls shall start the pump upon receiving a signal from the action of a  user of a fixture or appliance…The controls shall limit the temperature of the  water entering the cold‐water piping to ≤ 104 °F.”
  • 32. 2.4 R403.8 Systems serving multiple units Service Water Heating or HVAC Systems serving multiple dwelling units shall comply with Sections C403 and C404 of the IECC – Commercial Provisions instead of R403
  • 34. Site Inspections Summary 1. Footing and Foundation Inspection 2. Framing and Rough-in Inspection 1. Insulation Installation Quality 2. Window Details 3. Air Sealing Testing 3. Plumbing Rough-in Inspection 4. Mechanical Rough-in Inspection 5. Final Inspection
  • 35. 1. C105.2.1 / R105.2.1 Footing and foundation Checking R-value, location, thickness, depth of burial and protection of insulation https://foundationhandbook.ornl.gov/handbook/ 
  • 36. 1. R105.2.1 Footing and foundation Checking depth of burial • Does it go down far enough? (2’, 4’, 10’, within 6” of basement slab, etc.) • Part may be horizontal
  • 37. 1.1 C105.2.5 / R105.2.5 Framing and rough-in Can be two parts – Framing structural & air sealing, followed by insulation inspection (insulation makes air sealing harder to inspect) Can also be single inspection, depending on building department
  • 38. 1.1 C105.2.5/R105.2.2 Thermal Envelope Checking other thermal envelope air leakage controls • Are the joints of dis-similar materials sealed? • Are the joints of similar materials sealed?
  • 39. 1.1 C105.2.5 Thermal Envelope Checking proper installation • Fills the cavity • Uncompressed
  • 40. 1.2 R105.2.5 / C105.2.5 Framing and rough-in Checking fenestration properties such as U-factor and SHGC, proper installation, and air leakage controls
  • 41. 1.2 R105.2.5 Framing and rough-in Checking fenestration for proper installation • Adequate space for air sealing around window • Bottom flange not caulked to allow water out
  • 42. 1.3 R402.4.1.2 Blower Door Testing Mandatory for residential construction Residential air leakage rate not to exceed 4 air changes per hour @ 50 pascals Where required by code official, testing shall be conducted by an approved third party. Testing performed after creation of all penetrations of the building thermal envelope
  • 43. 1.3 Bloor Door Testing for Multifamily Housing Low-rise multifamily Air leakage not exceeding 0.25 cubic feet per minute of enclosure area (all six sides) at 50 Pascal. Sampling methodology available for buildings >7 units https://www.mncee.org/blog/may-2019/research-sidesteps-obstacles-measuring-air-tightne/
  • 44. 2. R105.2.3 / C105.2.3 Plumbing system Types of insulation, corresponding R-value, protection, required controls, and heat traps
  • 45. 3. R105.2.4 / C105.2.4 Mechanical system HVAC equipment type, size, required controls, system insulation, and corresponding R-value, system and damper air leakage control, minimum fan efficiency, energy recovery, and economizer
  • 46. 3. Mechanical rough-in HVAC equipment size • Does it match the design? • Larger or smaller is a problem
  • 47. • Commissioning process should start early in building process – design drawings! • Initial commissioning report may be reviewed during rough-in inspections for HVAC systems – check some progress put into functional testing as systems installed and brought online • Verify there is a testing plan in place for controls required in C403 through C405 for HVAC, service hot water, and electrical. 3. C408 Commissioning
  • 48. 3. R105.2.4 / C105.2.4 Mechanical system HVAC system air leakage control • Duct sealing completed (UL tape, mastic, etc)? • Damper air leakage rates or duct testing?
  • 49. 3. R105.2.4 Mechanical rough-in whole-house ventilation system/controls • System present? • Designed controls installed?
  • 50. 4. C105.2.5 Electrical System Lighting system controls, components, and meters *Meters for Group R‐2
  • 51. 4. C105.2.6 Final Installation and proper operation of all required building controls, and documentation verifying activities associated with required building commissioning have been conducted in accordance with Section C408
  • 52. 4. R105.2.5 Final Any required remaining building systems, equipment, and controls and their operation and the required number of high efficacy fixtures