Managing Contract Problems - Information Sheet
Contract problems can arise for a wide variety of reasons. To minimise the chance of
a minor problem escalating into a dispute, the issue needs to be identified, discussed
and resolved quickly and efficiently at the lowest practical level. This can be
achieved through open communication, co-operation, mutual understanding of the
problem and a desire by all parties to achieve the contracted outcomes and avoid
problems escalating into something more serious.
What is a contract problem?
A contract problem could be seen as, or caused by, an issue, conflict, disagreement,
unexpected event, breach, variation, change, miscommunication, misinterpretation,
failure, unrealised expectation, or similar situations relating to a contract.
Minimising the risk of contract problems arising
The following suggestions may assist to minimise the likelihood of contract problems
arising.
At an agency level:
• Allow time for forward planning - sufficient time is required to develop and
execute a well constructed, clear and comprehensive contract.
• Appropriately resource the contract management function – appoint a contract
manager or management team with suitable skills, knowledge, time and
support to undertake the role. Provide ongoing training as necessary.
• Ensure appropriate governance structures are in place to encourage and
support good contract management i.e. policy, procedures, checklists, forms,
systems and standards.
At a contract manager level:
• Establish a solid understanding of the contract and the contract management
role.
• Encourage ongoing and open lines of communications between the parties.
This includes having an initial meeting with the contractor once a contract is
awarded.
• Ensure any agency obligations (under the contract) are met as required.
Department of Finance Government Procurement Page 2 of 4
• Actively manage the contract. Promptly address and follow up on any problem
(no matter how minor) and provide feedback as required.
• Keep comprehensive records of actions, discussions and decisions made
during the contract term. Record keeping is a legislative requirement and it is
useful for many other reasons, including providing evidence should problems
reoccur, informs of changes during the contract term, assists with audit
requirements and/or for planning future contracts as examples.
• Look for opportunities to enhance contract management skills (e.g. training
sessions).
• Always seek advice, assistance and/or clarification when needed.
Working the problem
I have a contract problem, what should I do?
Even with a well-planned, clear and comprehensive contract, problems can still
arise. If a problem is minor, having an informal discussion with the contractor is
usually the most effective way of achieving a resolution.
In many cases, providing the opportunity to give/receive feedback will be sufficient to
overcome a contract problem. It is always important to remember to document what
was discussed and any agreed resolution for future reference.
When dealing with a contract problem, it is best practice to follow a structured
process (as outlined by the flowchart on page 3) to help manage a more efficient and
effective resolution. The process may also help provide evidence should the problem
escalate. Should the problem be considered high risk, time sensitive or significantly
serious then the appropriate course of action would be to seek advice before
proceeding.
Depending on the type of problem this would generally be from your procurement or
legal area.
Working with the contractor
Why is there a problem, why doesn’t the contractor just do what they are
contracted to do?
As previously mentioned, the reasons for contract problems arising are many and
varied and while it may appear that a contractor is not doing what they are
contracted to do, it is often not that simple. A problem could exist for any number of
reasons. These could include situations such as:
• The requirements of the contract are not clear or are open to
misinterpretation. For example, something such as “delivery is to be within 10
days” could mean 10 calendar days, 10 business days or even 9 days. In
Department of Finance Government Procurement Page 3 of 4
these situations assumptions are often made which may lead to a problem
arising.
• The expectations for the contract are not realistic or well defined. This may
result in the specific requirements not being covered under the contract or the
outcomes not being achieved. For example stating that the contract reporting
is “as required” rather than specifying what reporting will be required.
• This can lead to frustration for all parties as the required data may not be
available or additional costs may be incurred.
• Contractor performance is not monitored, discussed or documented. This may
occur for many reasons such as the performance measures are not included
in the contract, the measures are ambiguous or not relevant, and there may
be issues with resourcing or communication. If a contractor is not made aware
that there is a problem with its performance; and given the opportunity to
rectify the situation, the problem will remain unresolved and potentially
escalate.
• Establishing a contract, but not having suitable processes in place to support
the management of the contract. For example, it would be good practice to
put in place a communications book for a cleaning contract to document,
monitor and resolve cleaning issues. Establishing sound processes assists to
minimise the risk of miscommunication, unnecessary or unauthorised contract
variations and budget blowout.
• Communication problems. Having limited, or poor communication, or even a
personality clash between the parties may lead to communication difficulties.
Selecting a suitable contract manager and having an appropriate
communication strategy is an important factor in managing stakeholder
relationships and minimising contract problems.
Having good communication with your contractor and ensuring that the roles,
responsibilities and the requirements are understood by all parties will help to avoid
problems and make for smoother contract management.
Terminating a contract
Why can’t I just terminate the contract if I’m having problems?
Terminating a contract may seem like the quick and easy solution; however, just
because a problem occurs it does not necessarily give you the right to terminate a
contract. Terminating a contract can be a very complex and lengthy process which
needs to be handled carefully, and with legal advice being sought before proceeding.
The situation can be made much worse if the required course of action is not
appropriately executed. Where a contract problem exists, following the process as
outlined in the flowchart should help to resolve it and also assist with providing
evidence should the problem escalate.
Department of Finance Government Procurement Page 4 of 4
Please note, the flowchart on the following page is provided as a guide only. Should
the problem be considered high risk, time sensitive or significantly serious then the
appropriate course of action would be to seek advice before proceeding. Depending
on the type of problem this would generally be from your procurement/legal area.

More Related Content

What's hot

The Benefits of Effective Contract Management
The Benefits of Effective Contract Management The Benefits of Effective Contract Management
The Benefits of Effective Contract Management
Bradford Jacob (Virginia)
 
Importance of Contract Management Training Courses
Importance of Contract Management Training CoursesImportance of Contract Management Training Courses
Importance of Contract Management Training Courses
traningservices
 
Knowing and managing what's been agreed the case for contract management
Knowing and managing what's been agreed   the case for contract managementKnowing and managing what's been agreed   the case for contract management
Knowing and managing what's been agreed the case for contract management
Richard Austin
 
Improve Creative Workflow
Improve Creative WorkflowImprove Creative Workflow
Improve Creative Workflow
Hive
 
Preparing project professionals for the role of project manager
Preparing project professionals for the role of project managerPreparing project professionals for the role of project manager
Preparing project professionals for the role of project managerAxium
 
Contract management
Contract managementContract management
Contract managementNishant Rai
 
ConstructionFlow
ConstructionFlowConstructionFlow
ConstructionFlowJeff Dixon
 
Project Planning
Project Planning Project Planning
Project Planning
William Zuppinger, PMP, RMP
 
Scan_Doc0012- Article in Lex Witness Feb 2015
Scan_Doc0012- Article in Lex Witness Feb 2015Scan_Doc0012- Article in Lex Witness Feb 2015
Scan_Doc0012- Article in Lex Witness Feb 2015Subramaniam Ramaswamy
 
Troubled projects recovery
Troubled projects recoveryTroubled projects recovery
Troubled projects recovery
Malcolm Peart
 

What's hot (11)

The Benefits of Effective Contract Management
The Benefits of Effective Contract Management The Benefits of Effective Contract Management
The Benefits of Effective Contract Management
 
Importance of Contract Management Training Courses
Importance of Contract Management Training CoursesImportance of Contract Management Training Courses
Importance of Contract Management Training Courses
 
Knowing and managing what's been agreed the case for contract management
Knowing and managing what's been agreed   the case for contract managementKnowing and managing what's been agreed   the case for contract management
Knowing and managing what's been agreed the case for contract management
 
Improve Creative Workflow
Improve Creative WorkflowImprove Creative Workflow
Improve Creative Workflow
 
Preparing project professionals for the role of project manager
Preparing project professionals for the role of project managerPreparing project professionals for the role of project manager
Preparing project professionals for the role of project manager
 
Contract management
Contract managementContract management
Contract management
 
Practitioner class 4 Preparing the contract 04 july13
Practitioner class 4 Preparing the contract 04 july13Practitioner class 4 Preparing the contract 04 july13
Practitioner class 4 Preparing the contract 04 july13
 
ConstructionFlow
ConstructionFlowConstructionFlow
ConstructionFlow
 
Project Planning
Project Planning Project Planning
Project Planning
 
Scan_Doc0012- Article in Lex Witness Feb 2015
Scan_Doc0012- Article in Lex Witness Feb 2015Scan_Doc0012- Article in Lex Witness Feb 2015
Scan_Doc0012- Article in Lex Witness Feb 2015
 
Troubled projects recovery
Troubled projects recoveryTroubled projects recovery
Troubled projects recovery
 

Similar to Cm managing contract_problems

Chapter 5.1 Contracts Management - Contract Administration-owners perspective...
Chapter 5.1 Contracts Management - Contract Administration-owners perspective...Chapter 5.1 Contracts Management - Contract Administration-owners perspective...
Chapter 5.1 Contracts Management - Contract Administration-owners perspective...
ChandanLawrence
 
Best Practices To Improve Contract Management Process
Best Practices To Improve Contract Management Process Best Practices To Improve Contract Management Process
Best Practices To Improve Contract Management Process
Benny Henson
 
Procuring for agile: thoughts on what good looks like webinar, 23 April 2020
Procuring for agile: thoughts on what good looks like webinar, 23 April 2020Procuring for agile: thoughts on what good looks like webinar, 23 April 2020
Procuring for agile: thoughts on what good looks like webinar, 23 April 2020
Association for Project Management
 
OUTSTANDING OUTSOURCING - Checklist
OUTSTANDING OUTSOURCING - ChecklistOUTSTANDING OUTSOURCING - Checklist
OUTSTANDING OUTSOURCING - Checklist
Joe Orlando
 
Outsourcing checklist1
Outsourcing checklist1Outsourcing checklist1
Outsourcing checklist1
Joe Orlando
 
Dispute-Management-Strategies-in-Contract-Management.pptx
Dispute-Management-Strategies-in-Contract-Management.pptxDispute-Management-Strategies-in-Contract-Management.pptx
Dispute-Management-Strategies-in-Contract-Management.pptx
ALISAGAR4
 
Modernizing Contract Negotiation for Desired Business Outcomes
Modernizing Contract Negotiation for Desired Business Outcomes Modernizing Contract Negotiation for Desired Business Outcomes
Modernizing Contract Negotiation for Desired Business Outcomes
Cogneesol
 
MMA Presentaton Info
MMA Presentaton InfoMMA Presentaton Info
MMA Presentaton Infoamberbeebe
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
Sarah Fox
 
TOPIC8.pdf
TOPIC8.pdfTOPIC8.pdf
TOPIC8.pdf
HASMANIRA
 
Agreement Implementation.pptx
Agreement Implementation.pptxAgreement Implementation.pptx
Agreement Implementation.pptx
AndresVillarreal48
 
Tips to Simplify Contracting Process By SN Panigrahi
Tips to Simplify Contracting Process By SN PanigrahiTips to Simplify Contracting Process By SN Panigrahi
Tips to Simplify Contracting Process By SN Panigrahi
SN Panigrahi, PMP
 
Contracts and Knowledge Base Building
Contracts and Knowledge Base Building Contracts and Knowledge Base Building
Contracts and Knowledge Base Building
Jerry Ting
 
Lessons Learned Document from the Successful Buyout Project .docx
Lessons Learned Document from the Successful Buyout Project .docxLessons Learned Document from the Successful Buyout Project .docx
Lessons Learned Document from the Successful Buyout Project .docx
SHIVA101531
 
Stay_out_of_Litigation[1]-practical tips
Stay_out_of_Litigation[1]-practical tipsStay_out_of_Litigation[1]-practical tips
Stay_out_of_Litigation[1]-practical tipsSubramaniam Ramaswamy
 
Multi year it services contracts-2021
Multi year it services contracts-2021Multi year it services contracts-2021
Multi year it services contracts-2021
Sirq
 
Contract admn ajit philip
Contract admn ajit philipContract admn ajit philip
Contract admn ajit philipFarhan Moosa
 
Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015
SONU61709
 

Similar to Cm managing contract_problems (20)

Chapter 5.1 Contracts Management - Contract Administration-owners perspective...
Chapter 5.1 Contracts Management - Contract Administration-owners perspective...Chapter 5.1 Contracts Management - Contract Administration-owners perspective...
Chapter 5.1 Contracts Management - Contract Administration-owners perspective...
 
Best Practices To Improve Contract Management Process
Best Practices To Improve Contract Management Process Best Practices To Improve Contract Management Process
Best Practices To Improve Contract Management Process
 
Procuring for agile: thoughts on what good looks like webinar, 23 April 2020
Procuring for agile: thoughts on what good looks like webinar, 23 April 2020Procuring for agile: thoughts on what good looks like webinar, 23 April 2020
Procuring for agile: thoughts on what good looks like webinar, 23 April 2020
 
OUTSTANDING OUTSOURCING - Checklist
OUTSTANDING OUTSOURCING - ChecklistOUTSTANDING OUTSOURCING - Checklist
OUTSTANDING OUTSOURCING - Checklist
 
Outsourcing checklist1
Outsourcing checklist1Outsourcing checklist1
Outsourcing checklist1
 
Dispute-Management-Strategies-in-Contract-Management.pptx
Dispute-Management-Strategies-in-Contract-Management.pptxDispute-Management-Strategies-in-Contract-Management.pptx
Dispute-Management-Strategies-in-Contract-Management.pptx
 
Modernizing Contract Negotiation for Desired Business Outcomes
Modernizing Contract Negotiation for Desired Business Outcomes Modernizing Contract Negotiation for Desired Business Outcomes
Modernizing Contract Negotiation for Desired Business Outcomes
 
MMA Presentaton Info
MMA Presentaton InfoMMA Presentaton Info
MMA Presentaton Info
 
Contract Management
Contract ManagementContract Management
Contract Management
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
TOPIC8.pdf
TOPIC8.pdfTOPIC8.pdf
TOPIC8.pdf
 
Getting past yes
Getting past yesGetting past yes
Getting past yes
 
Agreement Implementation.pptx
Agreement Implementation.pptxAgreement Implementation.pptx
Agreement Implementation.pptx
 
Tips to Simplify Contracting Process By SN Panigrahi
Tips to Simplify Contracting Process By SN PanigrahiTips to Simplify Contracting Process By SN Panigrahi
Tips to Simplify Contracting Process By SN Panigrahi
 
Contracts and Knowledge Base Building
Contracts and Knowledge Base Building Contracts and Knowledge Base Building
Contracts and Knowledge Base Building
 
Lessons Learned Document from the Successful Buyout Project .docx
Lessons Learned Document from the Successful Buyout Project .docxLessons Learned Document from the Successful Buyout Project .docx
Lessons Learned Document from the Successful Buyout Project .docx
 
Stay_out_of_Litigation[1]-practical tips
Stay_out_of_Litigation[1]-practical tipsStay_out_of_Litigation[1]-practical tips
Stay_out_of_Litigation[1]-practical tips
 
Multi year it services contracts-2021
Multi year it services contracts-2021Multi year it services contracts-2021
Multi year it services contracts-2021
 
Contract admn ajit philip
Contract admn ajit philipContract admn ajit philip
Contract admn ajit philip
 
Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015
 

Recently uploaded

Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 

Recently uploaded (20)

Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 

Cm managing contract_problems

  • 1. Managing Contract Problems - Information Sheet Contract problems can arise for a wide variety of reasons. To minimise the chance of a minor problem escalating into a dispute, the issue needs to be identified, discussed and resolved quickly and efficiently at the lowest practical level. This can be achieved through open communication, co-operation, mutual understanding of the problem and a desire by all parties to achieve the contracted outcomes and avoid problems escalating into something more serious. What is a contract problem? A contract problem could be seen as, or caused by, an issue, conflict, disagreement, unexpected event, breach, variation, change, miscommunication, misinterpretation, failure, unrealised expectation, or similar situations relating to a contract. Minimising the risk of contract problems arising The following suggestions may assist to minimise the likelihood of contract problems arising. At an agency level: • Allow time for forward planning - sufficient time is required to develop and execute a well constructed, clear and comprehensive contract. • Appropriately resource the contract management function – appoint a contract manager or management team with suitable skills, knowledge, time and support to undertake the role. Provide ongoing training as necessary. • Ensure appropriate governance structures are in place to encourage and support good contract management i.e. policy, procedures, checklists, forms, systems and standards. At a contract manager level: • Establish a solid understanding of the contract and the contract management role. • Encourage ongoing and open lines of communications between the parties. This includes having an initial meeting with the contractor once a contract is awarded. • Ensure any agency obligations (under the contract) are met as required.
  • 2. Department of Finance Government Procurement Page 2 of 4 • Actively manage the contract. Promptly address and follow up on any problem (no matter how minor) and provide feedback as required. • Keep comprehensive records of actions, discussions and decisions made during the contract term. Record keeping is a legislative requirement and it is useful for many other reasons, including providing evidence should problems reoccur, informs of changes during the contract term, assists with audit requirements and/or for planning future contracts as examples. • Look for opportunities to enhance contract management skills (e.g. training sessions). • Always seek advice, assistance and/or clarification when needed. Working the problem I have a contract problem, what should I do? Even with a well-planned, clear and comprehensive contract, problems can still arise. If a problem is minor, having an informal discussion with the contractor is usually the most effective way of achieving a resolution. In many cases, providing the opportunity to give/receive feedback will be sufficient to overcome a contract problem. It is always important to remember to document what was discussed and any agreed resolution for future reference. When dealing with a contract problem, it is best practice to follow a structured process (as outlined by the flowchart on page 3) to help manage a more efficient and effective resolution. The process may also help provide evidence should the problem escalate. Should the problem be considered high risk, time sensitive or significantly serious then the appropriate course of action would be to seek advice before proceeding. Depending on the type of problem this would generally be from your procurement or legal area. Working with the contractor Why is there a problem, why doesn’t the contractor just do what they are contracted to do? As previously mentioned, the reasons for contract problems arising are many and varied and while it may appear that a contractor is not doing what they are contracted to do, it is often not that simple. A problem could exist for any number of reasons. These could include situations such as: • The requirements of the contract are not clear or are open to misinterpretation. For example, something such as “delivery is to be within 10 days” could mean 10 calendar days, 10 business days or even 9 days. In
  • 3. Department of Finance Government Procurement Page 3 of 4 these situations assumptions are often made which may lead to a problem arising. • The expectations for the contract are not realistic or well defined. This may result in the specific requirements not being covered under the contract or the outcomes not being achieved. For example stating that the contract reporting is “as required” rather than specifying what reporting will be required. • This can lead to frustration for all parties as the required data may not be available or additional costs may be incurred. • Contractor performance is not monitored, discussed or documented. This may occur for many reasons such as the performance measures are not included in the contract, the measures are ambiguous or not relevant, and there may be issues with resourcing or communication. If a contractor is not made aware that there is a problem with its performance; and given the opportunity to rectify the situation, the problem will remain unresolved and potentially escalate. • Establishing a contract, but not having suitable processes in place to support the management of the contract. For example, it would be good practice to put in place a communications book for a cleaning contract to document, monitor and resolve cleaning issues. Establishing sound processes assists to minimise the risk of miscommunication, unnecessary or unauthorised contract variations and budget blowout. • Communication problems. Having limited, or poor communication, or even a personality clash between the parties may lead to communication difficulties. Selecting a suitable contract manager and having an appropriate communication strategy is an important factor in managing stakeholder relationships and minimising contract problems. Having good communication with your contractor and ensuring that the roles, responsibilities and the requirements are understood by all parties will help to avoid problems and make for smoother contract management. Terminating a contract Why can’t I just terminate the contract if I’m having problems? Terminating a contract may seem like the quick and easy solution; however, just because a problem occurs it does not necessarily give you the right to terminate a contract. Terminating a contract can be a very complex and lengthy process which needs to be handled carefully, and with legal advice being sought before proceeding. The situation can be made much worse if the required course of action is not appropriately executed. Where a contract problem exists, following the process as outlined in the flowchart should help to resolve it and also assist with providing evidence should the problem escalate.
  • 4. Department of Finance Government Procurement Page 4 of 4 Please note, the flowchart on the following page is provided as a guide only. Should the problem be considered high risk, time sensitive or significantly serious then the appropriate course of action would be to seek advice before proceeding. Depending on the type of problem this would generally be from your procurement/legal area.