SchedulingScheduling
Chapter 16Chapter 16
© 2007 Pearson Education
How Scheduling
fits the Operations Management
Philosophy
Operations As a Competitive
Weapon
Operations Strategy
Project Management Process Strategy
Process Analysis
Process Performance and Quality
Constraint Management
Process Layout
Lean Systems
Supply Chain Strategy
Location
Inventory Management
Forecasting
Sales and Operations Planning
Resource Planning
Scheduling
© 2007 Pearson Education
Air New Zealand
 Flight and crew scheduling is a complex process.
 Scheduling begins with a five-year market plan.
 This general plan is further refined to a three-year
plan, and put into an annual budget in which flight
segments have specific departure and arrival times.
 Crew availability must be matched to the flight
schedule. Two types of crews–pilots and
attendants–each comes with its own set of
constraints.
 Sophisticated optimization models are used to
design generic minimum-cost schedules.
© 2007 Pearson Education
Scheduling
 Scheduling: The allocation of resources over time
to accomplish specific tasks.
 Demand scheduling: A type of scheduling
whereby customers are assigned to a definite time
for order fulfillment.
 Workforce scheduling: A type of scheduling that
determines when employees work.
 Operations scheduling: A type of scheduling in
which jobs are assigned to workstations or
employees are assigned to jobs for specified time
periods.
© 2007 Pearson Education
Performance Measures
 Job flow time: The amount of time a job spends in the
service or manufacturing system. Also referred to as
throughput time or time spent in the system, including service.
 Makespan: The total amount of time required to complete a
group of jobs.
 Past due (Tardiness): The amount of time by which a job
missed its due date or the percentage of total jobs processed
over some period of time that missed their due dates.
 Work-in-process (WIP) inventory: Any job that is waiting
in line, moving from one operation to the next, being delayed,
being processed, or residing in a semi-finished state.
 Total inventory: The sum of scheduled receipts and on-
hand inventories.
 Utilization: The percentage of work time that is
productively spent by an employee or machine.
© 2007 Pearson Education
Gantt Charts
 Gantt chart: Used as a tool to monitor the
progress of work and to view the load on
workstations.
 The chart takes two basic forms: (1) the job or activity
progress chart, and (2) the workstation chart.
 The Gantt progress chart graphically displays the
current status of each job or activity relative to its
scheduled completion date.
 The Gantt workstation chart shows the load on
the workstations and the nonproductive time.
© 2007 Pearson Education
Gantt Progress ChartGantt Progress Chart
Plymouth
Ford
Pontiac
Job 4/20 4/22 4/23 4/24 4/25 4/264/214/17 4/18 4/19
CurrentCurrent
datedate
Scheduled activity time
Actual progress
Start activity
Finish activity
Nonproductive time
Gantt Progress Chart for an Auto Parts Company
© 2007 Pearson Education
Gantt Workstation ChartGantt Workstation Chart
Gantt Workstation Chart for Hospital Operating Rooms
© 2007 Pearson Education
Scheduling
Customer Demand
 Three methods are commonly used to schedule
customer demand:
(1) Appointments assign specific times for service
to customers.
(2) Reservations are used when the customer
actually occupies or uses facilities associated
with the service.
(3) Backlogs:
• The customer is given a due date for the
fulfillment a product order, or
• Allow a backlog to develop as customers arrive
at the system. Customers may never know
exactly when their orders will be fulfilled
© 2007 Pearson Education
Scheduling Employees
 Rotating schedule: A schedule that rotates
employees through a series of workdays or hours.
 Fixed schedule: A schedule that calls for each
employee to work the same days and hours each
week.
 Constraints: The technical constraints imposed on
the workforce schedule are the resources provided
by the staffing plan and the requirements placed on
the operating system.
 Other constraints, including legal and behavioral
considerations, also can be imposed.
© 2007 Pearson Education
DayDay MM TT WW ThTh FF SS SuSu
Number of employeesNumber of employees 66 44 88 99 1010 33 22
Required employeesRequired employees
The Amalgamated Parcel Service is open 7 days
a week. The schedule of requirements is:
The manager needs a workforce schedule that provides two
consecutive days off and minimizes the amount of total slack capacity.
To break ties in the selection of off days, the scheduler gives
preference to Saturday and Sunday if it is one of the tied pairs. If not,
she selects one of the tied pairs arbitrarily.
Workforce Scheduling
Example 16.1
© 2007 Pearson Education
Required employeesRequired employees
DayDay MM TT WW ThTh FF SS SuSu
Number of employeesNumber of employees 66 44 88 99 10*10* 33 22
EmployeeEmployee 11 XX XX XX XX XX
Workforce Scheduling
Example 16.1 Steps 1 & 2
Step 1. Find all the pairs of consecutive days that exclude the
maximum daily requirements. Select the unique pair that has the lowest
total requirements for the 2 days.
Friday contains the maximum requirements (10), and the pair S–Su has
the lowest total requirements. Therefore, Employee 1 is scheduled to
work Monday through Friday.
Step 2. If a tie occurs, choose one of the tied pairs or ask the employee
to make a choice.
© 2007 Pearson Education
Required employeesRequired employees
Step 3. Subtract the requirements satisfied by the Employee 1 from the
net requirements for each day the employee is to work and repeat step
one.
Again the pair S–Su has the lowest total requirements. Therefore,
Employee 2 is scheduled to work Monday through Friday.
DayDay MM TT WW ThTh FF SS SuSu
Number of employeesNumber of employees 66 44 88 99 10*10* 33 22
EmployeeEmployee 11 XX XX XX XX XX
RequirementsRequirements 55 33 77 88 9*9* 33 22
EmployeeEmployee 22 XX XX XX XX XX
Workforce Scheduling
Example 16.1 Step 3
© 2007 Pearson Education
Required employeesRequired employees
DayDay MM TT WW ThTh FF SS SuSu
Number of employeesNumber of employees 66 44 88 99 10*10* 33 22
EmployeeEmployee 11 XX XX XX XX XX
RequirementRequirement 55 33 77 88 9*9* 33 22
EmployeeEmployee 22 XX XX XX XX XX
RequirementRequirement 44 22 66 77 8*8* 33 22
EmployeeEmployee 33 XX XX XX XX XX
RequirementRequirement 33 11 55 66 7*7* 33 22
Workforce Scheduling
Example 16.1 Step 4
Step 4. Repeat steps 1 through 3 until all the requirements have been
satisfied. After Employees 1, 2, and 3 have reduced the requirements,
the pair with the lowest requirements changes, and Employee 4 will be
scheduled for Wednesday through Sunday.
© 2007 Pearson Education
DayDay MM TT WW ThTh FF SS SuSu
Number of employeesNumber of employees 66 44 88 99 10*10* 33 22
EmployeeEmployee 11 XX XX XX XX XX
RequirementRequirement 55 33 77 88 9*9* 33 22
EmployeeEmployee 22 XX XX XX XX XX
RequirementRequirement 44 22 66 77 8*8* 33 22
EmployeeEmployee 33 XX XX XX XX XX
RequirementRequirement 33 11 55 66 7*7* 33 22
EmployeeEmployee 44 XX XX XX XX XX
RequirementRequirement 33 11 44 55 6*6* 22 11
EmployeeEmployee 55 XX XX XX XX XX
Required employeesRequired employees
Workforce Scheduling
Example 16.1 Step 4 continued
© 2007 Pearson Education
DayDay MM TT WW ThTh FF SS SuSu
RequirementRequirement 22 00 33 44 5*5* 22 11
EmployeeEmployee 66 XX XX XX XX XX
RequirementRequirement 22 00 22 33 4*4* 11 00
EmployeeEmployee 77 XX XX XX XX XX
RequirementRequirement 11 00 11 22 3*3* 11 00
EmployeeEmployee 88 XX XX XX XX XX
RequirementRequirement 00 00 00 11 2*2* 11 00
EmployeeEmployee 99 XX XX XX XX XX
RequirementRequirement 00 00 00 00 1*1* 00 00
EmployeeEmployee 1010 XX XX XX XX XX
Required employeesRequired employees
Workforce Scheduling
Example 16.1 Step 4 continued
© 2007 Pearson Education
DayDay MM TT WW ThTh FF SS SuSu
EmployeeEmployee 11 XX XX XX XX XX offoff offoff
EmployeeEmployee 22 XX XX XX XX XX offoff offoff
EmployeeEmployee 33 XX XX XX XX XX offoff offoff
EmployeeEmployee 44 offoff offoff XX XX XX XX XX
EmployeeEmployee 55 XX XX XX XX XX offoff offoff
EmployeeEmployee 66 offoff offoff XX XX XX XX XX
EmployeeEmployee 77 XX XX XX XX XX offoff offoff
EmployeeEmployee 88 XX XX XX XX XX offoff offoff
EmployeeEmployee 99 offoff XX XX XX XX XX offoff
EmployeeEmployee 1010 XX XX XX XX XX offoff offoff
Final ScheduleFinal Schedule
Workforce Scheduling
Example 16.1
© 2007 Pearson Education
MM TT WW ThTh FF SS SuSu
EmployeeEmployee 11 XX XX XX XX XX offoff offoff
EmployeeEmployee 22 XX XX XX XX XX offoff offoff
EmployeeEmployee 33 XX XX XX XX XX offoff offoff
EmployeeEmployee 44 offoff offoff XX XX XX XX XX
EmployeeEmployee 55 XX XX XX XX XX offoff offoff
EmployeeEmployee 66 offoff offoff XX XX XX XX XX
EmployeeEmployee 77 XX XX XX XX XX offoff offoff
EmployeeEmployee 88 XX XX XX XX XX offoff offoff
EmployeeEmployee 99 offoff XX XX XX XX XX offoff
EmployeeEmployee 1010 XX XX XX XX XX offoff offoff
Workforce Scheduling
Example 16.1 Final Schedule
Capacity, C 7 8 10 10 10 3 2 50
Requirements, R 6 4 8 9 10 3 2 42
Slack, C – R 1 4 2 1 0 0 0 8
Total
Final ScheduleFinal Schedule
© 2007 Pearson Education
Operations Scheduling
 Operations schedules are short-term plans
designed to implement the master production
schedule.
 Operations scheduling focuses on how best to use
existing capacity.
 Often, several jobs must be processed at one or more
workstations. Typically, a variety of tasks can be
performed at each workstation.
 Job shop: A firm that specializes in low- to
medium-volume production and utilizes job or batch
processes.
 Flow shop: A firm that specializes in medium- to
high-volume production and utilizes line or
continuous processes.
© 2007 Pearson Education
ShippingDepartmentShippingDepartment
Manufacturing ProcessManufacturing Process
RawMaterialsRawMaterials
Legend:Legend:
Batch of partsBatch of parts
WorkstationWorkstation
© 2007 Pearson Education
Job Shop Dispatching
 Dispatching: A method of generating schedules in job
shops whereby the decision about which job to process next
is made using simple priority rules whenever the workstation
becomes available for further processing.
 Priority sequencing rules: The rules that specify the
job processing sequence when several jobs are waiting in line
at a workstation.
 Critical ratio (CR): A ratio that is calculated by dividing
the time remaining until a job’s due date by the total shop time
remaining for the job.
CR = (Due date – Today’s date)/Total shop time remaining(Due date – Today’s date)/Total shop time remaining
 Total Shop Time = Setup, processing, move, and expected
waiting times of all remaining operations, including the operation
being scheduled.
© 2007 Pearson Education
 Earliest due date (EDD): A priority sequencing
rule that specifies that the job with the earliest due
date is the next job to be processed.
 First-come, first-served (FCFS): A priority
sequencing rule that specifies that the job arriving
at the workstation first has the highest priority.
 Shortest processing time (SPT): A priority
sequencing rule that specifies that the job requiring
the shortest processing time is the next job to be
processed.
Job Shop Dispatching
© 2007 Pearson Education
 Slack per remaining operations (S/RO): A
priority sequencing rule that determines
priority by dividing the slack by the number
of operations that remain, including the one
being scheduled.
Job Shop Dispatching
S/RO = ((Due dateS/RO = ((Due date –– Today’s date) – Total shop time remaining)Today’s date) – Total shop time remaining)
Number of operations remainingNumber of operations remaining
© 2007 Pearson Education
 Single-dimension rules: A set of rules such as
FCFS, EDD, and SPT, that bases the priority of a
job on a single aspect of the job, such as arrival
time at the workstation, the due date, or the
processing time.
 Priority rules, such as CR and S/RO, incorporate
information about the remaining workstations at
which the job must be processed. We call these
rules multiple-dimension rules.
 Multiple-dimension rules: A set of rules that apply
to more than one aspect of a job.
Scheduling Jobs for
One Workstation
© 2007 Pearson Education
Five engine blocks are waiting for processing. The processing times
have been estimated. Expected completion times have been agreed.
The table shows the situation as of Monday morning. Customer
pickup times are measured in business hours from Monday morning.
Determine the schedule by using the EDD rule and then the SPT rule.
Calculate the average hours early, hours past due, WIP inventory, and
total inventory for each method.
If low job flow times and WIP inventories are critical, which rule should
be chosen?
Example 16.2Example 16.2
Single-Dimension Rule SequencingSingle-Dimension Rule Sequencing
© 2007 Pearson Education
8 + 14 + 17 + 32 + 448 + 14 + 17 + 32 + 44
4444
Average hours early = 0.6 hourAverage hours early = 0.6 hour
JobJob ScheduledScheduled ActualActual
EngineEngine ProcessingProcessing FlowFlow CustomerCustomer CustomerCustomer HoursHours
BlockBlock BeginBegin TimeTime TimeTime PickupPickup PickupPickup HoursHours PastPast
SequenceSequence WorkWork (hr)(hr) (hr)(hr) TimeTime TimeTime EarlyEarly DueDue
RangerRanger 88 1010
ExplorerExplorer 66 1212
Econoline 150Econoline 150 33 1818
BroncoBronco 1515 2020
ThunderbirdThunderbird 1212 2222
00 ++ == 88 1010 22
1717 ++ == 3232 3232 1212
88 ++ == 1414 1414 22
1414 ++ == 1717 1818 11
3232 ++ == 4444 4444 2222
Example 16.2Example 16.2
Single-Dimension RuleSingle-Dimension Rule –– EDDEDD
Average job flow time = 23 hoursAverage job flow time = 23 hours
Average hours past due = 7.2 hoursAverage hours past due = 7.2 hours Average WIP = 2.61 blocksAverage WIP = 2.61 blocks
Average total inventory = 2.68 engine blocksAverage total inventory = 2.68 engine blocksAverage total inventory =Average total inventory =
10 + 14 + 18 + 32 + 4410 + 14 + 18 + 32 + 44
4444
© 2007 Pearson Education
3 + 9 + 17 + 29 + 443 + 9 + 17 + 29 + 44
4444
Average hours early = 3.6 hourAverage hours early = 3.6 hour
JobJob ScheduledScheduled ActualActual
EngineEngine ProcessingProcessing FlowFlow CustomerCustomer CustomerCustomer HoursHours
BlockBlock BeginBegin TimeTime TimeTime PickupPickup PickupPickup HoursHours PastPast
SequenceSequence WorkWork (hr)(hr) (hr)(hr) TimeTime TimeTime EarlyEarly DueDue
RangerRanger 88 1010
ExplorerExplorer 66 1212
Econoline 150Econoline 150 33 1818
BroncoBronco 1515 2020
ThunderbirdThunderbird 1212 2222
00 ++ == 33 1818 1515
1717 ++ == 2929 2929 77
88 ++ == 99 1212
1414 ++ == 1717 1717 33 77
2929 ++ == 4444 4444 2424
Example 16.2Example 16.2
Single-Dimension RuleSingle-Dimension Rule –– SPTSPT
Average job flow time =Average job flow time = 20.4 hours20.4 hours
Average hours past due = 7.6 hoursAverage hours past due = 7.6 hours Average WIP = 2.32 blocksAverage WIP = 2.32 blocks
Average total inventory = 2.73 engine blocksAverage total inventory = 2.73 engine blocksAverage total inventory =Average total inventory =
18 + 12 + 17 + 20 + 4418 + 12 + 17 + 20 + 44
4444
Econoline 150
Explorer
Ranger
Thunderbird
Bronco
0
3
9
17
29
3
6
8
12
15
18
12
10
22
20
© 2007 Pearson Education
Comparing the
EDD and SPT Rules
EDD SPT
Average job flow time 23.00 20.40
Average hours early 0.60 3.60
Average hours past due 7.20 7.60
Average WIP 2.61 2.32
Average total inventory 2.68 2.73
Using the previous example, a comparison of the EDD and
SPT sequencing is shown below.
• The SPT schedule has a lower average job flow time and lower WIP inventory.
• The EDD schedule has better customer service, (average hours past due) and
lower maximum hours past due.
• EDD also has a lower total inventory because fewer hours were spent waiting
for customers to pick up their engine blocks after they had been completed.
© 2007 Pearson Education
Example 16.3Example 16.3
Multiple-Dimension Rule –Multiple-Dimension Rule – CRCR
11 2.32.3 1515 1010 6.16.1 2.462.46
22 10.510.5 1010 22 7.87.8 1.281.28
33 6.26.2 2020 1212 14.514.5 1.381.38
44 15.615.6 88 55 10.210.2 .78.78
OperationOperation TimeTime
Time atTime at RemainingRemaining Number ofNumber of
EngineEngine to Due Dateto Due Date OperationsOperations Shop TimeShop Time
JobJob Lathe (hr)Lathe (hr) (Days)(Days) RemainingRemaining RemainingRemaining CRCR S/ROS/RO
CRCR ==
Time remaining to due dateTime remaining to due date
Shop time remainingShop time remaining
© 2007 Pearson Education
11 2.32.3 1515 1010 6.16.1 2.462.46 0.890.89
22 10.510.5 1010 22 7.87.8 1.281.28 1.101.10
33 6.26.2 2020 1212 14.514.5 1.381.38 0.460.46
44 15.615.6 88 55 10.210.2 .78.78 – 0.44– 0.44
OperationOperation TimeTime
Time atTime at RemainingRemaining Number ofNumber of
EngineEngine to Due Dateto Due Date OperationsOperations Shop TimeShop Time
JobJob Lathe (hr)Lathe (hr) (Days)(Days) RemainingRemaining RemainingRemaining CRCR S/ROS/RO
S/ROS/RO ==
Time remaining to due dateTime remaining to due date –– Shop time remainingShop time remaining
Number of operations remainingNumber of operations remaining
Example 16.3Example 16.3
Multiple-Dimension Rule –Multiple-Dimension Rule – S/ROS/RO
© 2007 Pearson Education
11 2.32.3 1515 1010 6.16.1 2.462.46 0.890.89
22 10.510.5 1010 22 7.87.8 1.281.28 1.101.10
33 6.26.2 2020 1212 14.514.5 1.381.38 0.460.46
44 15.615.6 88 55 10.210.2 .78.78 – 0.44– 0.44
OperationOperation TimeTime
Time atTime at RemainingRemaining Number ofNumber of
EngineEngine to Due Dateto Due Date OperationsOperations Shop TimeShop Time
JobJob Lathe (hr)Lathe (hr) (Days)(Days) RemainingRemaining RemainingRemaining CRCR S/ROS/RO
CR SequenceCR Sequence = 4= 4 – 2 – 3 – 1– 2 – 3 – 1
S/RO SequenceS/RO Sequence = 4= 4 – 3 – 1 – 2– 3 – 1 – 2
CR SequenceCR Sequence ==
Comparing theComparing the
CRCR andand S/ROS/RO RulesRules
© 2007 Pearson Education
© 2007 Pearson Education
Priority Rule Summary
FCFS = 1 – 2 – 3 – 4
SPT = 1 – 3 – 2 – 4
EDD = 4 – 2 – 1 – 3
CR = 4 – 2 – 3 – 1
S/RO = 4 – 3 – 1 – 2
Avg Flow Time 17.175 16.100 26.175 27.150 24.025
Avg Early Time 3.425 6.050 0 0 0
Avg Past Due 7.350 8.900 12.925 13.900 10.775
Avg WIP 1.986 1.861 3.026 3.129 2.777
Avg Total Inv 2.382 2.561 3.026 3.129 2.777
Shortest Slack per
Processing Earliest Critical Remaining
FCFS Time Due Date Ratio Operation
• The S/RO rule is better than the EDD rule
and the CR rule but it is much worse than
the SPT rule and the FCFS rule for this
example.
• S/RO has the advantage of allowing
schedule changes when due dates
change. These results cannot be
generalized to other situations because
only four jobs are being processed.
© 2007 Pearson Education
Scheduling Jobs for
Multiple Workstations
 Priority sequencing rules can be used to schedule more than
one operation. Each operation is treated independently.
 Identifying the best priority rule to use at a particular operation
in a process is a complex problem because the output from one
process becomes the input for another.
 Computer simulation models are effective tools to determine
which priority rules work best in a given situation.
 When a workstation becomes idle, the priority rule is applied to
the jobs waiting for that operation, and the job with the highest
priority is selected.
 When that operation is finished, the job is moved to the next
operation in its routing, where it waits until it again has the
highest priority.
© 2007 Pearson Education
Johnson’s Rule
 Johnson’s rule: A procedure that minimizes makespan
when scheduling a group of jobs on two workstations.
 Step 1. Find the shortest processing time among the jobs not
yet scheduled. If two or more jobs are tied, choose one job
arbitrarily.
 Step 2. If the shortest processing time is on workstation 1,
schedule the corresponding job as early as possible. If the
shortest processing time is on workstation 2, schedule the
corresponding job as late as possible.
 Step 3. Eliminate the last job scheduled from further
consideration. Repeat steps 1 and 2 until all jobs have been
scheduled.
© 2007 Pearson Education
Eliminate M3 from consideration. The next shortest time
is M2 at Workstation 1, so schedule M2 first.
Eliminate M5 from consideration. The next shortest time is
M1 at workstation #1, so schedule M1 next.
Eliminate M1 and the only job remaining to be
scheduled is M4.
Example 16.5
Johnson’s RuleJohnson’s Rule at theat the Morris Machine Co.Morris Machine Co.
Time (hr)Time (hr)
MotorMotor Workstation 1Workstation 1 Workstation 2Workstation 2
M1M1 1212 2222
M2M2 44 55
M3M3 55 33
M4M4 1515 1616
M5M5 1010 88
Sequence =Sequence = M1M1M2M2 M3M3M4M4 M5M5
Shortest time is 3 hours at workstation 2, so
schedule job M3 last.
Eliminate M2 from consideration. The next shortest time is
M5 at workstation #2, so schedule M5 next to last.
© 2007 Pearson Education
Workstation
M2
(4)
M1
(12)
M4
(15)
M5
(10)
M3
(5)
Idle—available
for further work
0 5 10 15 20 25 30
Day
35 40 45 50 55 60 65
Idle2 M2
(5)
M1
(22)
M4
(16)
M5
(8)
M3
(3)Idle
1
Gantt Chart for the Morris Machine Company Repair Schedule
The schedule minimizes the idle time of workstation 2
and gives the fastest repair time for all five motors.
No other sequence will produce a lower makespan.
Example 16.5
Johnson’s RuleJohnson’s Rule at theat the Morris Machine Co.Morris Machine Co.
© 2007 Pearson Education
Labor-limited Environments
 The limiting resource thus far has been the number of
machines or workstations available. A more typical constraint
is the amount of labor available.
 Labor-limited environment: An environment in which
the resource constraint is the amount of labor available, not
the number of machines or workstations.
1. Assign personnel to the workstation with the job that has
been in the system longest.
2. Assign personnel to the workstation with the most jobs
waiting for processing.
3. Assign personnel to the workstation with the largest
standard work content.
4. Assign personnel to the workstation with the job that has
the earliest due date.
© 2007 Pearson Education
Linking Operations
Scheduling to the Supply Chain
 Advanced planning and scheduling (APS)
systems: Systems that seek to optimize resources across
the supply chain and align daily operations with strategic
goals. Four characteristics of these systems are:
1. Demand Planning. This capability enables companies in a
supply chain to share demand forecasts.
2. Supply Network Planning. Optimization models based on
linear programming can be used to make long-term decisions.
3. Available-to-Promise. Firms can use this capability to promise
delivery to customers by checking the availability of
components and materials at its suppliers.
4. Manufacturing Scheduling. This module attempts to
determine an optimal grouping and sequencing of
manufacturing orders based on detailed product attributes,
production line capacities, and material flows.
© 2007 Pearson Education
 The Food Bin grocery store operates 24 hours per day, 7
days per week. At the end of the month, they calculated the
average number of checkout registers that should be open
during the first shift each day. Results showed peak needs on
Saturdays and Sundays.
1. Develop a schedule that covers all requirements while giving two
consecutive days off to each clerk. How many clerks are needed?
2. Plans can be made to use the clerks for other duties if slack or idle
time resulting from this schedule can be determined. How much idle
time will result from this schedule, and on what days?
Solved Problem 1Solved Problem 1
© 2007 Pearson Education
© 2007 Pearson Education
Solved Problem 1Solved Problem 1
© 2007 Pearson Education
© 2007 Pearson Education
Solved Problem 1Solved Problem 1
© 2007 Pearson Education
 The Neptune’s Den Machine Shop specializes in overhauling outboard
marine engines. Currently, five engines with varying problems are
awaiting service. The best estimates for the labor times involved and
the promise dates (in number of days from today) are shown in the
following table. Customers usually do not pick up their engines early.
Solved Problem 2Solved Problem 2
Develop separate schedules using SPT and then EDD rules. Compare them
using average job flow time, % of past due jobs, and maximum past due days.
Calculate average WIP inventory (in engines) and average total inventory.
© 2007 Pearson Education
© 2007 Pearson Education
Solved Problem 2
SPT
EDD
© 2007 Pearson Education
© 2007 Pearson Education
SPT EDD
Average job flow time 9.80 15.20
% of past due jobs 40% 60%
Maximum past due days 11 7
Average WIP inventory 2.13 3.30
Average total inventory 3.52 3.52
Solved Problem 2
© 2007 Pearson Education
Cleanup of chemical waste storage basins involves two
operations. Operation 1: Drain and dredge basin. Operation 2:
Incinerate materials. Management estimates that each
operation will require the following amounts of time (in days):
Find a schedule that minimizes the makespan. Calculate the
average job flow time of a storage basin through the two operations.
What is the total elapsed time for cleaning all 10 basins?
Solved Problem 4Solved Problem 4
© 2007 Pearson Education
Dredge Incinerate
A 3 1
B 4 4
C 3 2
D 6 1
E 1 2
F 3 6
G 2 4
H 1 1
I 8 2
J 4 8
Solved Problem 4Solved Problem 4
Four jobs are tied for the shortest process time: A, D, E, and H. (E and H
are tied for first place, while A and D are tied for last place.) We arbitrarily
choose to start with basin E
E H G F B J I C D A
© 2007 Pearson Education
Dredge E H G F B J I C D A
Incinerate E H G F B J I C D A
Storage basin
E H G F B J I C D A
Solved Problem 4Solved Problem 4
The Gantt machine chart for this schedule

More Related Content

What's hot

Scheduling ppt @ DOMS
Scheduling ppt @ DOMSScheduling ppt @ DOMS
Scheduling ppt @ DOMSBabasab Patil
 
Capacity planning
Capacity planningCapacity planning
Capacity planningAkhil Lal
 
Operations scheduling
Operations schedulingOperations scheduling
Operations schedulingRajThakuri
 
Introduction to Operation Management
Introduction to Operation ManagementIntroduction to Operation Management
Introduction to Operation ManagementJoshua Miranda
 
Chapter 5 Capacity Planning.ppt
Chapter 5 Capacity Planning.pptChapter 5 Capacity Planning.ppt
Chapter 5 Capacity Planning.pptssuser7d3776
 
Chapter 15; Short-Term Scheduling
Chapter 15; Short-Term SchedulingChapter 15; Short-Term Scheduling
Chapter 15; Short-Term SchedulingAlvaro Alvarez
 
Capacity Requirement Planning
Capacity Requirement PlanningCapacity Requirement Planning
Capacity Requirement Planningsenthil.G
 
Production and operations management
Production and operations managementProduction and operations management
Production and operations managementAbdulrahman El-Sayed
 
5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptx5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptxvirshit
 
Operations management forecasting
Operations management   forecastingOperations management   forecasting
Operations management forecastingTwinkle Constantino
 
production planning and control
production planning and controlproduction planning and control
production planning and controlParitosh Kasaudhan
 
Capacity Planning
Capacity PlanningCapacity Planning
Capacity PlanningPam Cudal
 
Lecture note no. 1 introduction to operations management
Lecture note  no. 1 introduction to operations management Lecture note  no. 1 introduction to operations management
Lecture note no. 1 introduction to operations management jackjackjackjack1234
 

What's hot (20)

Scheduling ppt @ DOMS
Scheduling ppt @ DOMSScheduling ppt @ DOMS
Scheduling ppt @ DOMS
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Design of Work Systems
Design of Work SystemsDesign of Work Systems
Design of Work Systems
 
Operations scheduling
Operations schedulingOperations scheduling
Operations scheduling
 
Introduction to Operation Management
Introduction to Operation ManagementIntroduction to Operation Management
Introduction to Operation Management
 
SUPPLY CHAIN STRATEGIES
SUPPLY CHAIN STRATEGIESSUPPLY CHAIN STRATEGIES
SUPPLY CHAIN STRATEGIES
 
Production management
Production managementProduction management
Production management
 
Chapter 5 Capacity Planning.ppt
Chapter 5 Capacity Planning.pptChapter 5 Capacity Planning.ppt
Chapter 5 Capacity Planning.ppt
 
Chapter 15; Short-Term Scheduling
Chapter 15; Short-Term SchedulingChapter 15; Short-Term Scheduling
Chapter 15; Short-Term Scheduling
 
Capacity Requirement Planning
Capacity Requirement PlanningCapacity Requirement Planning
Capacity Requirement Planning
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Production and operations management
Production and operations managementProduction and operations management
Production and operations management
 
5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptx5.Production Scheduling and Sequencing.pptx
5.Production Scheduling and Sequencing.pptx
 
Operations management forecasting
Operations management   forecastingOperations management   forecasting
Operations management forecasting
 
production planning and control
production planning and controlproduction planning and control
production planning and control
 
Ch11
Ch11Ch11
Ch11
 
Resource Planning
Resource PlanningResource Planning
Resource Planning
 
Master planning
Master planningMaster planning
Master planning
 
Capacity Planning
Capacity PlanningCapacity Planning
Capacity Planning
 
Lecture note no. 1 introduction to operations management
Lecture note  no. 1 introduction to operations management Lecture note  no. 1 introduction to operations management
Lecture note no. 1 introduction to operations management
 

Viewers also liked (16)

Scheduling
SchedulingScheduling
Scheduling
 
Scheduling
SchedulingScheduling
Scheduling
 
شهادة ASA
شهادة ASAشهادة ASA
شهادة ASA
 
Chapter 08
Chapter 08Chapter 08
Chapter 08
 
01. competing with operations
01. competing with operations01. competing with operations
01. competing with operations
 
01. competing with operations (1)
01. competing with operations (1)01. competing with operations (1)
01. competing with operations (1)
 
01. competing with operations
01. competing with operations01. competing with operations
01. competing with operations
 
Chapter 02
Chapter 02Chapter 02
Chapter 02
 
3 cash management
3 cash management3 cash management
3 cash management
 
Ch03 total quality management
Ch03 total quality managementCh03 total quality management
Ch03 total quality management
 
Chapter 06
Chapter 06Chapter 06
Chapter 06
 
Chapter 13 (2)
Chapter 13 (2)Chapter 13 (2)
Chapter 13 (2)
 
Chapter 05
Chapter 05Chapter 05
Chapter 05
 
operation management and operation strategy
operation management and operation strategyoperation management and operation strategy
operation management and operation strategy
 
Scheduling and sequencing
Scheduling and sequencingScheduling and sequencing
Scheduling and sequencing
 
scheduling
schedulingscheduling
scheduling
 

Similar to Chapter 14

OPS 571 Effective Communication - tutorialrank.com
OPS 571    Effective Communication - tutorialrank.comOPS 571    Effective Communication - tutorialrank.com
OPS 571 Effective Communication - tutorialrank.comBartholomew54
 
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaaSCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaainfinitepestcontrol
 
Ops 571 Education Organization-snaptutorial.com
Ops 571 Education Organization-snaptutorial.comOps 571 Education Organization-snaptutorial.com
Ops 571 Education Organization-snaptutorial.comrobertlesew28
 
OPS 571 Social Responsibility - snaptutorial.com
OPS 571   Social Responsibility - snaptutorial.comOPS 571   Social Responsibility - snaptutorial.com
OPS 571 Social Responsibility - snaptutorial.comDavisMurphyA94
 
OPS 571 Exceptional Education - snaptutorial.com
OPS 571   Exceptional Education - snaptutorial.comOPS 571   Exceptional Education - snaptutorial.com
OPS 571 Exceptional Education - snaptutorial.comDavisMurphyB17
 
Sales & Operations Planning
Sales & Operations PlanningSales & Operations Planning
Sales & Operations Planningmubarak2009
 
OPS 571 Effective Communication - snaptutorial.com
OPS 571 Effective Communication - snaptutorial.comOPS 571 Effective Communication - snaptutorial.com
OPS 571 Effective Communication - snaptutorial.comdonaldzs34
 
Space Age Furniture Company The Space Age Furniture Company manufa.docx
Space Age Furniture Company The Space Age Furniture Company manufa.docxSpace Age Furniture Company The Space Age Furniture Company manufa.docx
Space Age Furniture Company The Space Age Furniture Company manufa.docxwhitneyleman54422
 
Ch13 - Aggregate Planning
Ch13 - Aggregate PlanningCh13 - Aggregate Planning
Ch13 - Aggregate PlanningPelly Sianova
 
Cmgt 410 week 2 gantt chart diagram
Cmgt 410 week 2 gantt chart diagramCmgt 410 week 2 gantt chart diagram
Cmgt 410 week 2 gantt chart diagramenininvin1980
 
OPS 571 Education Specialist / snaptutorial.com
OPS 571 Education Specialist / snaptutorial.comOPS 571 Education Specialist / snaptutorial.com
OPS 571 Education Specialist / snaptutorial.comMcdonaldRyan104
 
9©iStockphotoThinkstockPlanning for Material and Reso.docx
9©iStockphotoThinkstockPlanning for Material and Reso.docx9©iStockphotoThinkstockPlanning for Material and Reso.docx
9©iStockphotoThinkstockPlanning for Material and Reso.docxblondellchancy
 
9©iStockphotoThinkstockPlanning for Material and Reso.docx
9©iStockphotoThinkstockPlanning for Material and Reso.docx9©iStockphotoThinkstockPlanning for Material and Reso.docx
9©iStockphotoThinkstockPlanning for Material and Reso.docxpriestmanmable
 
Track Software -- Shell presentation
Track Software -- Shell presentationTrack Software -- Shell presentation
Track Software -- Shell presentationtracksoftware
 
Staff Scheduling
Staff SchedulingStaff Scheduling
Staff SchedulingEvren E
 
Aggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
Aggregate Production Planning for a Pump Manufacturing Company: Chase StrategyAggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
Aggregate Production Planning for a Pump Manufacturing Company: Chase StrategyIRJET Journal
 
Capacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of CapacityCapacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of CapacityJoanRachelCalansingi
 

Similar to Chapter 14 (20)

OPS 571 Effective Communication - tutorialrank.com
OPS 571    Effective Communication - tutorialrank.comOPS 571    Effective Communication - tutorialrank.com
OPS 571 Effective Communication - tutorialrank.com
 
Framework for Creating an IT labor Charge Back System
Framework for Creating an IT labor Charge Back SystemFramework for Creating an IT labor Charge Back System
Framework for Creating an IT labor Charge Back System
 
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaaSCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
 
Ops 571 Education Organization-snaptutorial.com
Ops 571 Education Organization-snaptutorial.comOps 571 Education Organization-snaptutorial.com
Ops 571 Education Organization-snaptutorial.com
 
OPS 571 Social Responsibility - snaptutorial.com
OPS 571   Social Responsibility - snaptutorial.comOPS 571   Social Responsibility - snaptutorial.com
OPS 571 Social Responsibility - snaptutorial.com
 
OPS 571 Exceptional Education - snaptutorial.com
OPS 571   Exceptional Education - snaptutorial.comOPS 571   Exceptional Education - snaptutorial.com
OPS 571 Exceptional Education - snaptutorial.com
 
Sales & Operations Planning
Sales & Operations PlanningSales & Operations Planning
Sales & Operations Planning
 
OPS 571 Effective Communication - snaptutorial.com
OPS 571 Effective Communication - snaptutorial.comOPS 571 Effective Communication - snaptutorial.com
OPS 571 Effective Communication - snaptutorial.com
 
Space Age Furniture Company The Space Age Furniture Company manufa.docx
Space Age Furniture Company The Space Age Furniture Company manufa.docxSpace Age Furniture Company The Space Age Furniture Company manufa.docx
Space Age Furniture Company The Space Age Furniture Company manufa.docx
 
Ch13 - Aggregate Planning
Ch13 - Aggregate PlanningCh13 - Aggregate Planning
Ch13 - Aggregate Planning
 
Cmgt 410 week 2 gantt chart diagram
Cmgt 410 week 2 gantt chart diagramCmgt 410 week 2 gantt chart diagram
Cmgt 410 week 2 gantt chart diagram
 
OPS 571 Education Specialist / snaptutorial.com
OPS 571 Education Specialist / snaptutorial.comOPS 571 Education Specialist / snaptutorial.com
OPS 571 Education Specialist / snaptutorial.com
 
9©iStockphotoThinkstockPlanning for Material and Reso.docx
9©iStockphotoThinkstockPlanning for Material and Reso.docx9©iStockphotoThinkstockPlanning for Material and Reso.docx
9©iStockphotoThinkstockPlanning for Material and Reso.docx
 
9©iStockphotoThinkstockPlanning for Material and Reso.docx
9©iStockphotoThinkstockPlanning for Material and Reso.docx9©iStockphotoThinkstockPlanning for Material and Reso.docx
9©iStockphotoThinkstockPlanning for Material and Reso.docx
 
Lean Project Leadership
Lean Project LeadershipLean Project Leadership
Lean Project Leadership
 
Track Software -- Shell presentation
Track Software -- Shell presentationTrack Software -- Shell presentation
Track Software -- Shell presentation
 
Staff Scheduling
Staff SchedulingStaff Scheduling
Staff Scheduling
 
Chap004 (1)
Chap004 (1)Chap004 (1)
Chap004 (1)
 
Aggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
Aggregate Production Planning for a Pump Manufacturing Company: Chase StrategyAggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
Aggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
 
Capacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of CapacityCapacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of Capacity
 

Recently uploaded

7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 

Recently uploaded (20)

7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 

Chapter 14

  • 1. © 2007 Pearson Education SchedulingScheduling Chapter 16Chapter 16
  • 2. © 2007 Pearson Education How Scheduling fits the Operations Management Philosophy Operations As a Competitive Weapon Operations Strategy Project Management Process Strategy Process Analysis Process Performance and Quality Constraint Management Process Layout Lean Systems Supply Chain Strategy Location Inventory Management Forecasting Sales and Operations Planning Resource Planning Scheduling
  • 3. © 2007 Pearson Education Air New Zealand  Flight and crew scheduling is a complex process.  Scheduling begins with a five-year market plan.  This general plan is further refined to a three-year plan, and put into an annual budget in which flight segments have specific departure and arrival times.  Crew availability must be matched to the flight schedule. Two types of crews–pilots and attendants–each comes with its own set of constraints.  Sophisticated optimization models are used to design generic minimum-cost schedules.
  • 4. © 2007 Pearson Education Scheduling  Scheduling: The allocation of resources over time to accomplish specific tasks.  Demand scheduling: A type of scheduling whereby customers are assigned to a definite time for order fulfillment.  Workforce scheduling: A type of scheduling that determines when employees work.  Operations scheduling: A type of scheduling in which jobs are assigned to workstations or employees are assigned to jobs for specified time periods.
  • 5. © 2007 Pearson Education Performance Measures  Job flow time: The amount of time a job spends in the service or manufacturing system. Also referred to as throughput time or time spent in the system, including service.  Makespan: The total amount of time required to complete a group of jobs.  Past due (Tardiness): The amount of time by which a job missed its due date or the percentage of total jobs processed over some period of time that missed their due dates.  Work-in-process (WIP) inventory: Any job that is waiting in line, moving from one operation to the next, being delayed, being processed, or residing in a semi-finished state.  Total inventory: The sum of scheduled receipts and on- hand inventories.  Utilization: The percentage of work time that is productively spent by an employee or machine.
  • 6. © 2007 Pearson Education Gantt Charts  Gantt chart: Used as a tool to monitor the progress of work and to view the load on workstations.  The chart takes two basic forms: (1) the job or activity progress chart, and (2) the workstation chart.  The Gantt progress chart graphically displays the current status of each job or activity relative to its scheduled completion date.  The Gantt workstation chart shows the load on the workstations and the nonproductive time.
  • 7. © 2007 Pearson Education Gantt Progress ChartGantt Progress Chart Plymouth Ford Pontiac Job 4/20 4/22 4/23 4/24 4/25 4/264/214/17 4/18 4/19 CurrentCurrent datedate Scheduled activity time Actual progress Start activity Finish activity Nonproductive time Gantt Progress Chart for an Auto Parts Company
  • 8. © 2007 Pearson Education Gantt Workstation ChartGantt Workstation Chart Gantt Workstation Chart for Hospital Operating Rooms
  • 9. © 2007 Pearson Education Scheduling Customer Demand  Three methods are commonly used to schedule customer demand: (1) Appointments assign specific times for service to customers. (2) Reservations are used when the customer actually occupies or uses facilities associated with the service. (3) Backlogs: • The customer is given a due date for the fulfillment a product order, or • Allow a backlog to develop as customers arrive at the system. Customers may never know exactly when their orders will be fulfilled
  • 10. © 2007 Pearson Education Scheduling Employees  Rotating schedule: A schedule that rotates employees through a series of workdays or hours.  Fixed schedule: A schedule that calls for each employee to work the same days and hours each week.  Constraints: The technical constraints imposed on the workforce schedule are the resources provided by the staffing plan and the requirements placed on the operating system.  Other constraints, including legal and behavioral considerations, also can be imposed.
  • 11. © 2007 Pearson Education DayDay MM TT WW ThTh FF SS SuSu Number of employeesNumber of employees 66 44 88 99 1010 33 22 Required employeesRequired employees The Amalgamated Parcel Service is open 7 days a week. The schedule of requirements is: The manager needs a workforce schedule that provides two consecutive days off and minimizes the amount of total slack capacity. To break ties in the selection of off days, the scheduler gives preference to Saturday and Sunday if it is one of the tied pairs. If not, she selects one of the tied pairs arbitrarily. Workforce Scheduling Example 16.1
  • 12. © 2007 Pearson Education Required employeesRequired employees DayDay MM TT WW ThTh FF SS SuSu Number of employeesNumber of employees 66 44 88 99 10*10* 33 22 EmployeeEmployee 11 XX XX XX XX XX Workforce Scheduling Example 16.1 Steps 1 & 2 Step 1. Find all the pairs of consecutive days that exclude the maximum daily requirements. Select the unique pair that has the lowest total requirements for the 2 days. Friday contains the maximum requirements (10), and the pair S–Su has the lowest total requirements. Therefore, Employee 1 is scheduled to work Monday through Friday. Step 2. If a tie occurs, choose one of the tied pairs or ask the employee to make a choice.
  • 13. © 2007 Pearson Education Required employeesRequired employees Step 3. Subtract the requirements satisfied by the Employee 1 from the net requirements for each day the employee is to work and repeat step one. Again the pair S–Su has the lowest total requirements. Therefore, Employee 2 is scheduled to work Monday through Friday. DayDay MM TT WW ThTh FF SS SuSu Number of employeesNumber of employees 66 44 88 99 10*10* 33 22 EmployeeEmployee 11 XX XX XX XX XX RequirementsRequirements 55 33 77 88 9*9* 33 22 EmployeeEmployee 22 XX XX XX XX XX Workforce Scheduling Example 16.1 Step 3
  • 14. © 2007 Pearson Education Required employeesRequired employees DayDay MM TT WW ThTh FF SS SuSu Number of employeesNumber of employees 66 44 88 99 10*10* 33 22 EmployeeEmployee 11 XX XX XX XX XX RequirementRequirement 55 33 77 88 9*9* 33 22 EmployeeEmployee 22 XX XX XX XX XX RequirementRequirement 44 22 66 77 8*8* 33 22 EmployeeEmployee 33 XX XX XX XX XX RequirementRequirement 33 11 55 66 7*7* 33 22 Workforce Scheduling Example 16.1 Step 4 Step 4. Repeat steps 1 through 3 until all the requirements have been satisfied. After Employees 1, 2, and 3 have reduced the requirements, the pair with the lowest requirements changes, and Employee 4 will be scheduled for Wednesday through Sunday.
  • 15. © 2007 Pearson Education DayDay MM TT WW ThTh FF SS SuSu Number of employeesNumber of employees 66 44 88 99 10*10* 33 22 EmployeeEmployee 11 XX XX XX XX XX RequirementRequirement 55 33 77 88 9*9* 33 22 EmployeeEmployee 22 XX XX XX XX XX RequirementRequirement 44 22 66 77 8*8* 33 22 EmployeeEmployee 33 XX XX XX XX XX RequirementRequirement 33 11 55 66 7*7* 33 22 EmployeeEmployee 44 XX XX XX XX XX RequirementRequirement 33 11 44 55 6*6* 22 11 EmployeeEmployee 55 XX XX XX XX XX Required employeesRequired employees Workforce Scheduling Example 16.1 Step 4 continued
  • 16. © 2007 Pearson Education DayDay MM TT WW ThTh FF SS SuSu RequirementRequirement 22 00 33 44 5*5* 22 11 EmployeeEmployee 66 XX XX XX XX XX RequirementRequirement 22 00 22 33 4*4* 11 00 EmployeeEmployee 77 XX XX XX XX XX RequirementRequirement 11 00 11 22 3*3* 11 00 EmployeeEmployee 88 XX XX XX XX XX RequirementRequirement 00 00 00 11 2*2* 11 00 EmployeeEmployee 99 XX XX XX XX XX RequirementRequirement 00 00 00 00 1*1* 00 00 EmployeeEmployee 1010 XX XX XX XX XX Required employeesRequired employees Workforce Scheduling Example 16.1 Step 4 continued
  • 17. © 2007 Pearson Education DayDay MM TT WW ThTh FF SS SuSu EmployeeEmployee 11 XX XX XX XX XX offoff offoff EmployeeEmployee 22 XX XX XX XX XX offoff offoff EmployeeEmployee 33 XX XX XX XX XX offoff offoff EmployeeEmployee 44 offoff offoff XX XX XX XX XX EmployeeEmployee 55 XX XX XX XX XX offoff offoff EmployeeEmployee 66 offoff offoff XX XX XX XX XX EmployeeEmployee 77 XX XX XX XX XX offoff offoff EmployeeEmployee 88 XX XX XX XX XX offoff offoff EmployeeEmployee 99 offoff XX XX XX XX XX offoff EmployeeEmployee 1010 XX XX XX XX XX offoff offoff Final ScheduleFinal Schedule Workforce Scheduling Example 16.1
  • 18. © 2007 Pearson Education MM TT WW ThTh FF SS SuSu EmployeeEmployee 11 XX XX XX XX XX offoff offoff EmployeeEmployee 22 XX XX XX XX XX offoff offoff EmployeeEmployee 33 XX XX XX XX XX offoff offoff EmployeeEmployee 44 offoff offoff XX XX XX XX XX EmployeeEmployee 55 XX XX XX XX XX offoff offoff EmployeeEmployee 66 offoff offoff XX XX XX XX XX EmployeeEmployee 77 XX XX XX XX XX offoff offoff EmployeeEmployee 88 XX XX XX XX XX offoff offoff EmployeeEmployee 99 offoff XX XX XX XX XX offoff EmployeeEmployee 1010 XX XX XX XX XX offoff offoff Workforce Scheduling Example 16.1 Final Schedule Capacity, C 7 8 10 10 10 3 2 50 Requirements, R 6 4 8 9 10 3 2 42 Slack, C – R 1 4 2 1 0 0 0 8 Total Final ScheduleFinal Schedule
  • 19. © 2007 Pearson Education Operations Scheduling  Operations schedules are short-term plans designed to implement the master production schedule.  Operations scheduling focuses on how best to use existing capacity.  Often, several jobs must be processed at one or more workstations. Typically, a variety of tasks can be performed at each workstation.  Job shop: A firm that specializes in low- to medium-volume production and utilizes job or batch processes.  Flow shop: A firm that specializes in medium- to high-volume production and utilizes line or continuous processes.
  • 20. © 2007 Pearson Education ShippingDepartmentShippingDepartment Manufacturing ProcessManufacturing Process RawMaterialsRawMaterials Legend:Legend: Batch of partsBatch of parts WorkstationWorkstation
  • 21. © 2007 Pearson Education Job Shop Dispatching  Dispatching: A method of generating schedules in job shops whereby the decision about which job to process next is made using simple priority rules whenever the workstation becomes available for further processing.  Priority sequencing rules: The rules that specify the job processing sequence when several jobs are waiting in line at a workstation.  Critical ratio (CR): A ratio that is calculated by dividing the time remaining until a job’s due date by the total shop time remaining for the job. CR = (Due date – Today’s date)/Total shop time remaining(Due date – Today’s date)/Total shop time remaining  Total Shop Time = Setup, processing, move, and expected waiting times of all remaining operations, including the operation being scheduled.
  • 22. © 2007 Pearson Education  Earliest due date (EDD): A priority sequencing rule that specifies that the job with the earliest due date is the next job to be processed.  First-come, first-served (FCFS): A priority sequencing rule that specifies that the job arriving at the workstation first has the highest priority.  Shortest processing time (SPT): A priority sequencing rule that specifies that the job requiring the shortest processing time is the next job to be processed. Job Shop Dispatching
  • 23. © 2007 Pearson Education  Slack per remaining operations (S/RO): A priority sequencing rule that determines priority by dividing the slack by the number of operations that remain, including the one being scheduled. Job Shop Dispatching S/RO = ((Due dateS/RO = ((Due date –– Today’s date) – Total shop time remaining)Today’s date) – Total shop time remaining) Number of operations remainingNumber of operations remaining
  • 24. © 2007 Pearson Education  Single-dimension rules: A set of rules such as FCFS, EDD, and SPT, that bases the priority of a job on a single aspect of the job, such as arrival time at the workstation, the due date, or the processing time.  Priority rules, such as CR and S/RO, incorporate information about the remaining workstations at which the job must be processed. We call these rules multiple-dimension rules.  Multiple-dimension rules: A set of rules that apply to more than one aspect of a job. Scheduling Jobs for One Workstation
  • 25. © 2007 Pearson Education Five engine blocks are waiting for processing. The processing times have been estimated. Expected completion times have been agreed. The table shows the situation as of Monday morning. Customer pickup times are measured in business hours from Monday morning. Determine the schedule by using the EDD rule and then the SPT rule. Calculate the average hours early, hours past due, WIP inventory, and total inventory for each method. If low job flow times and WIP inventories are critical, which rule should be chosen? Example 16.2Example 16.2 Single-Dimension Rule SequencingSingle-Dimension Rule Sequencing
  • 26. © 2007 Pearson Education 8 + 14 + 17 + 32 + 448 + 14 + 17 + 32 + 44 4444 Average hours early = 0.6 hourAverage hours early = 0.6 hour JobJob ScheduledScheduled ActualActual EngineEngine ProcessingProcessing FlowFlow CustomerCustomer CustomerCustomer HoursHours BlockBlock BeginBegin TimeTime TimeTime PickupPickup PickupPickup HoursHours PastPast SequenceSequence WorkWork (hr)(hr) (hr)(hr) TimeTime TimeTime EarlyEarly DueDue RangerRanger 88 1010 ExplorerExplorer 66 1212 Econoline 150Econoline 150 33 1818 BroncoBronco 1515 2020 ThunderbirdThunderbird 1212 2222 00 ++ == 88 1010 22 1717 ++ == 3232 3232 1212 88 ++ == 1414 1414 22 1414 ++ == 1717 1818 11 3232 ++ == 4444 4444 2222 Example 16.2Example 16.2 Single-Dimension RuleSingle-Dimension Rule –– EDDEDD Average job flow time = 23 hoursAverage job flow time = 23 hours Average hours past due = 7.2 hoursAverage hours past due = 7.2 hours Average WIP = 2.61 blocksAverage WIP = 2.61 blocks Average total inventory = 2.68 engine blocksAverage total inventory = 2.68 engine blocksAverage total inventory =Average total inventory = 10 + 14 + 18 + 32 + 4410 + 14 + 18 + 32 + 44 4444
  • 27. © 2007 Pearson Education 3 + 9 + 17 + 29 + 443 + 9 + 17 + 29 + 44 4444 Average hours early = 3.6 hourAverage hours early = 3.6 hour JobJob ScheduledScheduled ActualActual EngineEngine ProcessingProcessing FlowFlow CustomerCustomer CustomerCustomer HoursHours BlockBlock BeginBegin TimeTime TimeTime PickupPickup PickupPickup HoursHours PastPast SequenceSequence WorkWork (hr)(hr) (hr)(hr) TimeTime TimeTime EarlyEarly DueDue RangerRanger 88 1010 ExplorerExplorer 66 1212 Econoline 150Econoline 150 33 1818 BroncoBronco 1515 2020 ThunderbirdThunderbird 1212 2222 00 ++ == 33 1818 1515 1717 ++ == 2929 2929 77 88 ++ == 99 1212 1414 ++ == 1717 1717 33 77 2929 ++ == 4444 4444 2424 Example 16.2Example 16.2 Single-Dimension RuleSingle-Dimension Rule –– SPTSPT Average job flow time =Average job flow time = 20.4 hours20.4 hours Average hours past due = 7.6 hoursAverage hours past due = 7.6 hours Average WIP = 2.32 blocksAverage WIP = 2.32 blocks Average total inventory = 2.73 engine blocksAverage total inventory = 2.73 engine blocksAverage total inventory =Average total inventory = 18 + 12 + 17 + 20 + 4418 + 12 + 17 + 20 + 44 4444 Econoline 150 Explorer Ranger Thunderbird Bronco 0 3 9 17 29 3 6 8 12 15 18 12 10 22 20
  • 28. © 2007 Pearson Education Comparing the EDD and SPT Rules EDD SPT Average job flow time 23.00 20.40 Average hours early 0.60 3.60 Average hours past due 7.20 7.60 Average WIP 2.61 2.32 Average total inventory 2.68 2.73 Using the previous example, a comparison of the EDD and SPT sequencing is shown below. • The SPT schedule has a lower average job flow time and lower WIP inventory. • The EDD schedule has better customer service, (average hours past due) and lower maximum hours past due. • EDD also has a lower total inventory because fewer hours were spent waiting for customers to pick up their engine blocks after they had been completed.
  • 29. © 2007 Pearson Education Example 16.3Example 16.3 Multiple-Dimension Rule –Multiple-Dimension Rule – CRCR 11 2.32.3 1515 1010 6.16.1 2.462.46 22 10.510.5 1010 22 7.87.8 1.281.28 33 6.26.2 2020 1212 14.514.5 1.381.38 44 15.615.6 88 55 10.210.2 .78.78 OperationOperation TimeTime Time atTime at RemainingRemaining Number ofNumber of EngineEngine to Due Dateto Due Date OperationsOperations Shop TimeShop Time JobJob Lathe (hr)Lathe (hr) (Days)(Days) RemainingRemaining RemainingRemaining CRCR S/ROS/RO CRCR == Time remaining to due dateTime remaining to due date Shop time remainingShop time remaining
  • 30. © 2007 Pearson Education 11 2.32.3 1515 1010 6.16.1 2.462.46 0.890.89 22 10.510.5 1010 22 7.87.8 1.281.28 1.101.10 33 6.26.2 2020 1212 14.514.5 1.381.38 0.460.46 44 15.615.6 88 55 10.210.2 .78.78 – 0.44– 0.44 OperationOperation TimeTime Time atTime at RemainingRemaining Number ofNumber of EngineEngine to Due Dateto Due Date OperationsOperations Shop TimeShop Time JobJob Lathe (hr)Lathe (hr) (Days)(Days) RemainingRemaining RemainingRemaining CRCR S/ROS/RO S/ROS/RO == Time remaining to due dateTime remaining to due date –– Shop time remainingShop time remaining Number of operations remainingNumber of operations remaining Example 16.3Example 16.3 Multiple-Dimension Rule –Multiple-Dimension Rule – S/ROS/RO
  • 31. © 2007 Pearson Education 11 2.32.3 1515 1010 6.16.1 2.462.46 0.890.89 22 10.510.5 1010 22 7.87.8 1.281.28 1.101.10 33 6.26.2 2020 1212 14.514.5 1.381.38 0.460.46 44 15.615.6 88 55 10.210.2 .78.78 – 0.44– 0.44 OperationOperation TimeTime Time atTime at RemainingRemaining Number ofNumber of EngineEngine to Due Dateto Due Date OperationsOperations Shop TimeShop Time JobJob Lathe (hr)Lathe (hr) (Days)(Days) RemainingRemaining RemainingRemaining CRCR S/ROS/RO CR SequenceCR Sequence = 4= 4 – 2 – 3 – 1– 2 – 3 – 1 S/RO SequenceS/RO Sequence = 4= 4 – 3 – 1 – 2– 3 – 1 – 2 CR SequenceCR Sequence == Comparing theComparing the CRCR andand S/ROS/RO RulesRules
  • 32. © 2007 Pearson Education © 2007 Pearson Education Priority Rule Summary FCFS = 1 – 2 – 3 – 4 SPT = 1 – 3 – 2 – 4 EDD = 4 – 2 – 1 – 3 CR = 4 – 2 – 3 – 1 S/RO = 4 – 3 – 1 – 2 Avg Flow Time 17.175 16.100 26.175 27.150 24.025 Avg Early Time 3.425 6.050 0 0 0 Avg Past Due 7.350 8.900 12.925 13.900 10.775 Avg WIP 1.986 1.861 3.026 3.129 2.777 Avg Total Inv 2.382 2.561 3.026 3.129 2.777 Shortest Slack per Processing Earliest Critical Remaining FCFS Time Due Date Ratio Operation • The S/RO rule is better than the EDD rule and the CR rule but it is much worse than the SPT rule and the FCFS rule for this example. • S/RO has the advantage of allowing schedule changes when due dates change. These results cannot be generalized to other situations because only four jobs are being processed.
  • 33. © 2007 Pearson Education Scheduling Jobs for Multiple Workstations  Priority sequencing rules can be used to schedule more than one operation. Each operation is treated independently.  Identifying the best priority rule to use at a particular operation in a process is a complex problem because the output from one process becomes the input for another.  Computer simulation models are effective tools to determine which priority rules work best in a given situation.  When a workstation becomes idle, the priority rule is applied to the jobs waiting for that operation, and the job with the highest priority is selected.  When that operation is finished, the job is moved to the next operation in its routing, where it waits until it again has the highest priority.
  • 34. © 2007 Pearson Education Johnson’s Rule  Johnson’s rule: A procedure that minimizes makespan when scheduling a group of jobs on two workstations.  Step 1. Find the shortest processing time among the jobs not yet scheduled. If two or more jobs are tied, choose one job arbitrarily.  Step 2. If the shortest processing time is on workstation 1, schedule the corresponding job as early as possible. If the shortest processing time is on workstation 2, schedule the corresponding job as late as possible.  Step 3. Eliminate the last job scheduled from further consideration. Repeat steps 1 and 2 until all jobs have been scheduled.
  • 35. © 2007 Pearson Education Eliminate M3 from consideration. The next shortest time is M2 at Workstation 1, so schedule M2 first. Eliminate M5 from consideration. The next shortest time is M1 at workstation #1, so schedule M1 next. Eliminate M1 and the only job remaining to be scheduled is M4. Example 16.5 Johnson’s RuleJohnson’s Rule at theat the Morris Machine Co.Morris Machine Co. Time (hr)Time (hr) MotorMotor Workstation 1Workstation 1 Workstation 2Workstation 2 M1M1 1212 2222 M2M2 44 55 M3M3 55 33 M4M4 1515 1616 M5M5 1010 88 Sequence =Sequence = M1M1M2M2 M3M3M4M4 M5M5 Shortest time is 3 hours at workstation 2, so schedule job M3 last. Eliminate M2 from consideration. The next shortest time is M5 at workstation #2, so schedule M5 next to last.
  • 36. © 2007 Pearson Education Workstation M2 (4) M1 (12) M4 (15) M5 (10) M3 (5) Idle—available for further work 0 5 10 15 20 25 30 Day 35 40 45 50 55 60 65 Idle2 M2 (5) M1 (22) M4 (16) M5 (8) M3 (3)Idle 1 Gantt Chart for the Morris Machine Company Repair Schedule The schedule minimizes the idle time of workstation 2 and gives the fastest repair time for all five motors. No other sequence will produce a lower makespan. Example 16.5 Johnson’s RuleJohnson’s Rule at theat the Morris Machine Co.Morris Machine Co.
  • 37. © 2007 Pearson Education Labor-limited Environments  The limiting resource thus far has been the number of machines or workstations available. A more typical constraint is the amount of labor available.  Labor-limited environment: An environment in which the resource constraint is the amount of labor available, not the number of machines or workstations. 1. Assign personnel to the workstation with the job that has been in the system longest. 2. Assign personnel to the workstation with the most jobs waiting for processing. 3. Assign personnel to the workstation with the largest standard work content. 4. Assign personnel to the workstation with the job that has the earliest due date.
  • 38. © 2007 Pearson Education Linking Operations Scheduling to the Supply Chain  Advanced planning and scheduling (APS) systems: Systems that seek to optimize resources across the supply chain and align daily operations with strategic goals. Four characteristics of these systems are: 1. Demand Planning. This capability enables companies in a supply chain to share demand forecasts. 2. Supply Network Planning. Optimization models based on linear programming can be used to make long-term decisions. 3. Available-to-Promise. Firms can use this capability to promise delivery to customers by checking the availability of components and materials at its suppliers. 4. Manufacturing Scheduling. This module attempts to determine an optimal grouping and sequencing of manufacturing orders based on detailed product attributes, production line capacities, and material flows.
  • 39. © 2007 Pearson Education  The Food Bin grocery store operates 24 hours per day, 7 days per week. At the end of the month, they calculated the average number of checkout registers that should be open during the first shift each day. Results showed peak needs on Saturdays and Sundays. 1. Develop a schedule that covers all requirements while giving two consecutive days off to each clerk. How many clerks are needed? 2. Plans can be made to use the clerks for other duties if slack or idle time resulting from this schedule can be determined. How much idle time will result from this schedule, and on what days? Solved Problem 1Solved Problem 1
  • 40. © 2007 Pearson Education © 2007 Pearson Education Solved Problem 1Solved Problem 1
  • 41. © 2007 Pearson Education © 2007 Pearson Education Solved Problem 1Solved Problem 1
  • 42. © 2007 Pearson Education  The Neptune’s Den Machine Shop specializes in overhauling outboard marine engines. Currently, five engines with varying problems are awaiting service. The best estimates for the labor times involved and the promise dates (in number of days from today) are shown in the following table. Customers usually do not pick up their engines early. Solved Problem 2Solved Problem 2 Develop separate schedules using SPT and then EDD rules. Compare them using average job flow time, % of past due jobs, and maximum past due days. Calculate average WIP inventory (in engines) and average total inventory.
  • 43. © 2007 Pearson Education © 2007 Pearson Education Solved Problem 2 SPT EDD
  • 44. © 2007 Pearson Education © 2007 Pearson Education SPT EDD Average job flow time 9.80 15.20 % of past due jobs 40% 60% Maximum past due days 11 7 Average WIP inventory 2.13 3.30 Average total inventory 3.52 3.52 Solved Problem 2
  • 45. © 2007 Pearson Education Cleanup of chemical waste storage basins involves two operations. Operation 1: Drain and dredge basin. Operation 2: Incinerate materials. Management estimates that each operation will require the following amounts of time (in days): Find a schedule that minimizes the makespan. Calculate the average job flow time of a storage basin through the two operations. What is the total elapsed time for cleaning all 10 basins? Solved Problem 4Solved Problem 4
  • 46. © 2007 Pearson Education Dredge Incinerate A 3 1 B 4 4 C 3 2 D 6 1 E 1 2 F 3 6 G 2 4 H 1 1 I 8 2 J 4 8 Solved Problem 4Solved Problem 4 Four jobs are tied for the shortest process time: A, D, E, and H. (E and H are tied for first place, while A and D are tied for last place.) We arbitrarily choose to start with basin E E H G F B J I C D A
  • 47. © 2007 Pearson Education Dredge E H G F B J I C D A Incinerate E H G F B J I C D A Storage basin E H G F B J I C D A Solved Problem 4Solved Problem 4 The Gantt machine chart for this schedule