PRESENTATION
         ON
PRODUCTION SCHEDULING




      PRESENTED BY:-
                 POOJA
                 HEMANGI
                 KIRAN
                 ANURADHA
ROADMAP
What is scheduling
Examples
Objectives
Elements
Priority Planning
Master Production scheduling (MPS)
Objectives of MPS
Functions of MPS
Problems of sequencing in scheduling
SCHEDULING
 Scheduling is one of the most important elements in
  production planning.

 Scheduling calls for through understanding of all aspects of
  the production process and is an outcome of the integration
  of the efforts of planners in the planning group and the
  people in the shop-floor.

 Scheduling integrates the people, machine, materials,
  customer demands, and quality requirements in finalizing the
  priorities. Scheduling makes it possible by determining
  starting and completion data each of the operations.
EXAMPLES OF SCHEDULING

Timetabling Scheduling of the Computer :A number
 of different courses (tasks) have to be given using the
 PC room(resource)
Workforce scheduling : Assign shifts for nurses and
 doctors in a Hospital
Sports Scheduling
Drug Scheduling
CONT……….

  Scheduling effects from 2 environmental factors that are
 internal and external to the organization.
Internal environment
External environment
OBJECTIVES OF SCHEDULING

Maximize throughput
Be predictable:
Minimize overhead
Balance resource use
Achieve a balance between response and utilization
Avoid indefinite postponement
Enforce Priorities
Give preference to process holding
Degrade gracefully under heavy loads
ELEMENTS OF SCHEDULING


The processors
The tasks
The processing timings
The precedence relations
PRIORITY PLANNING

 Planning is the process by which the elements
 required to perform a task are determined in advance
 of the job start. The process is as follows :
Operations soft constraints
Management policy constraints
Engineering hard constraints
MASTER PRODUCTION SCHEDULING
     Master scheduling is a part of scheduling.

 A Master Production Schedule is a Schedule of the
    completions of the end items and these completions are
    very much planned in nature.

 A MPS is also in management language referred to as the
    master of all the schedules as this schedule provides the
    production, planning, purchasing & top management, the
    most needed information required for planning and
    control of the whole manufacturing process or the
    operation.
OBJECTIVES OF MASTER SCHEDULING



Keeping the inventories
Setting up the due dates for the availability of items
Maintaining the customer service
Setting proper schedules
FUNCTIONS OF MASTER
             SCHEDULING

Specifies planning periods as daily, weekly, or monthly.
Group work order processing
Tracks accuracy of order forecasting as percentage.
Classifies supply into types such as materials, purchased,
 flow, work order, and transfer.
Schedule can be edited, changed, or consolidated.
PROBLEMS OF SEQUENCING IN
        SCHEDULING



SHORTEST PROCESSING TIME (SPT)
WEIGHTED SHORTEST PROCESSING TIME (WSPT)
EXAMPLE:-
 The data about a set of single operation jobs that is to be processed in
  a CNC lathe and the processing times of the jobs in the given set of jobs
  are as given in table.
 Find the optimal sequence which will minimize the mean flow time and
  also obtain the corresponding minimum mean flow time.

                     Job, j                Processing time, tj
                       1                             7
                       2                            18
                       3                             6
                       4                             8
                       5                            12
SOLUTION:-
 For the given problem, the number of jobs is equal to
 5. The jobs are arranged as per the SPT ordering.

             Job, j          Processing time, tj
               3                       6
               1                       7
               4                       8
               5                      12
               2                      18


Therefore, the job sequence which will minimize the
 mean flow time is 3-1-4-5-2.
CONT
The computation of flow time for the optimal sequence
 (3-1-4-5-2).
               COMPUTATION FLOW TIME
            Job, j     Processing time, tj   Completion time, cj(fj)

                3              6                       6

                1              7                       13

                4              8                       21

                5              12                      33

                2              18                      51
CONT
Since the ready time rj is zero for all the values of j, the flow
  time (fj) = cj for all j.
Therefore,
1/5 ∑ Fj = 1/5 (6+13+21+33+51)
              = 1/5 (124)
              = 24.8 hours
Therefore, the optimal mean flow time = 24.8 hours.
WSPT
Example
           Job, j     Processing time, tj   Weight , wj

             1                7                 1
             2                18                2
             3                6                 1
             4                8                 2
             5                12                3

Determine the sequence which will minimize the
 weighted flow time of this problem. Also find the
 corresponding weighted mean flow time.
SOLUTION:-

 The weighted processing times of various jobs are
 summarized by using the formula tj/wj, j = 1,2,3,4, and 5
           Job, j   Processing time,   Weight , wj   Tj/wj
                           tj
             1             7               1          7

             2            18               2          9

             3             6               1          6

             4             8               2          4

             5            12               3          4
CALCULATIONS OF WEIGHTED
        FLOW TIMES
Job, j   Processing time,   Cj (Fj)   Weight , wj   Fjwj
                tj
  4             8             8           2         16
  5            12             20          3         60
  3             6             26          1         26
  1             7             33          1         33
  2            18             51          2         102
scheduling

More Related Content

What's hot

Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
Dr. Prashant Kalaskar
 
Material management
Material managementMaterial management
Material management
Madiha Ahmed
 
TIME STUDY
TIME STUDYTIME STUDY
TIME STUDY
chhavi narayan
 
Mba ii pmom_unit-1.2 production planning & control a
Mba ii pmom_unit-1.2 production planning & control aMba ii pmom_unit-1.2 production planning & control a
Mba ii pmom_unit-1.2 production planning & control a
Rai University
 
Job shop scheduling
Job shop schedulingJob shop scheduling
Job shop scheduling
Sujeet TAMBE
 
Ppc
PpcPpc
production planning and control
production planning and controlproduction planning and control
production planning and control
Paritosh Kasaudhan
 
Critical path method
Critical path methodCritical path method
Critical path method
Dushyant Nasit
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
KunalJagtap5
 
MRP-II
MRP-IIMRP-II
Aggregate Planning
Aggregate  PlanningAggregate  Planning
Aggregate Planning
ahmad bassiouny
 
Capacity Requirement Planning
Capacity Requirement PlanningCapacity Requirement Planning
Capacity Requirement Planning
senthil.G
 
Forecasting in Management- Methods,features,advantages,importance and process
Forecasting in Management- Methods,features,advantages,importance and processForecasting in Management- Methods,features,advantages,importance and process
Forecasting in Management- Methods,features,advantages,importance and process
AMALDASKH
 
Production planning & control(ppc)
Production planning & control(ppc)Production planning & control(ppc)
Production planning & control(ppc)
Abu Bashar
 
Production planning & control
Production planning & controlProduction planning & control
Production planning & control
Faizan Akhtar
 
AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING
Aqib ali
 
Work measurement
Work measurementWork measurement
Work measurement
Ratnadeepsinh Jadeja
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
Balaji Naik
 
Scheduling
SchedulingScheduling
MRP I and MRP II
MRP I and MRP IIMRP I and MRP II
MRP I and MRP II
Sugandha Vidge
 

What's hot (20)

Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
 
Material management
Material managementMaterial management
Material management
 
TIME STUDY
TIME STUDYTIME STUDY
TIME STUDY
 
Mba ii pmom_unit-1.2 production planning & control a
Mba ii pmom_unit-1.2 production planning & control aMba ii pmom_unit-1.2 production planning & control a
Mba ii pmom_unit-1.2 production planning & control a
 
Job shop scheduling
Job shop schedulingJob shop scheduling
Job shop scheduling
 
Ppc
PpcPpc
Ppc
 
production planning and control
production planning and controlproduction planning and control
production planning and control
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
 
MRP-II
MRP-IIMRP-II
MRP-II
 
Aggregate Planning
Aggregate  PlanningAggregate  Planning
Aggregate Planning
 
Capacity Requirement Planning
Capacity Requirement PlanningCapacity Requirement Planning
Capacity Requirement Planning
 
Forecasting in Management- Methods,features,advantages,importance and process
Forecasting in Management- Methods,features,advantages,importance and processForecasting in Management- Methods,features,advantages,importance and process
Forecasting in Management- Methods,features,advantages,importance and process
 
Production planning & control(ppc)
Production planning & control(ppc)Production planning & control(ppc)
Production planning & control(ppc)
 
Production planning & control
Production planning & controlProduction planning & control
Production planning & control
 
AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING AGGREGATE PRODUCTION PLANNING
AGGREGATE PRODUCTION PLANNING
 
Work measurement
Work measurementWork measurement
Work measurement
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 
Scheduling
SchedulingScheduling
Scheduling
 
MRP I and MRP II
MRP I and MRP IIMRP I and MRP II
MRP I and MRP II
 

Similar to scheduling

Scheduling production
Scheduling   productionScheduling   production
Scheduling production
Aditya Powale
 
Operations Research_18ME735_module 5 sequencing notes.pdf
Operations Research_18ME735_module 5 sequencing notes.pdfOperations Research_18ME735_module 5 sequencing notes.pdf
Operations Research_18ME735_module 5 sequencing notes.pdf
RoopaDNDandally
 
Exam110121
Exam110121Exam110121
Exam110121
Sou Tibon
 
Global seek optimization in real time database
Global seek optimization in real time databaseGlobal seek optimization in real time database
Global seek optimization in real time database
IAEME Publication
 
Flowshop scheduling
Flowshop schedulingFlowshop scheduling
Flowshop scheduling
Kunal Goswami
 
SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)
Chris Cummins
 
Litttle knowledge of lean concept helps
Litttle knowledge of lean  concept helpsLitttle knowledge of lean  concept helps
Litttle knowledge of lean concept helps
SF Lau
 
Optimal three stage flow shop scheduling in which processing time, set up tim...
Optimal three stage flow shop scheduling in which processing time, set up tim...Optimal three stage flow shop scheduling in which processing time, set up tim...
Optimal three stage flow shop scheduling in which processing time, set up tim...
Alexander Decker
 
11.optimal three stage flow shop scheduling in which processing time, set up ...
11.optimal three stage flow shop scheduling in which processing time, set up ...11.optimal three stage flow shop scheduling in which processing time, set up ...
11.optimal three stage flow shop scheduling in which processing time, set up ...
Alexander Decker
 
R0260950100
R0260950100R0260950100
R0260950100
ijceronline
 
11.flow shop scheduling problem, processing time associated with probabilitie...
11.flow shop scheduling problem, processing time associated with probabilitie...11.flow shop scheduling problem, processing time associated with probabilitie...
11.flow shop scheduling problem, processing time associated with probabilitie...
Alexander Decker
 
Flow shop scheduling problem, processing time associated with probabilities i...
Flow shop scheduling problem, processing time associated with probabilities i...Flow shop scheduling problem, processing time associated with probabilities i...
Flow shop scheduling problem, processing time associated with probabilities i...
Alexander Decker
 
A case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristicsA case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristics
IJERA Editor
 
A case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristicsA case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristics
IJERA Editor
 
Job Shop Scheduling.pptx
Job Shop Scheduling.pptxJob Shop Scheduling.pptx
Job Shop Scheduling.pptx
SyedAmirIqbal3
 
Application of branch and bound technique for nx3 flow shop scheduling, in wh...
Application of branch and bound technique for nx3 flow shop scheduling, in wh...Application of branch and bound technique for nx3 flow shop scheduling, in wh...
Application of branch and bound technique for nx3 flow shop scheduling, in wh...
Alexander Decker
 
Extlect02
Extlect02Extlect02
Extlect02
Vin Voro
 
Clock driven scheduling
Clock driven schedulingClock driven scheduling
Clock driven scheduling
Kamal Acharya
 
11.machines constrained flow shop scheduling processing time, setup time each...
11.machines constrained flow shop scheduling processing time, setup time each...11.machines constrained flow shop scheduling processing time, setup time each...
11.machines constrained flow shop scheduling processing time, setup time each...
Alexander Decker
 
11.machines constrained flow shop scheduling processing time, setup time each...
11.machines constrained flow shop scheduling processing time, setup time each...11.machines constrained flow shop scheduling processing time, setup time each...
11.machines constrained flow shop scheduling processing time, setup time each...
Alexander Decker
 

Similar to scheduling (20)

Scheduling production
Scheduling   productionScheduling   production
Scheduling production
 
Operations Research_18ME735_module 5 sequencing notes.pdf
Operations Research_18ME735_module 5 sequencing notes.pdfOperations Research_18ME735_module 5 sequencing notes.pdf
Operations Research_18ME735_module 5 sequencing notes.pdf
 
Exam110121
Exam110121Exam110121
Exam110121
 
Global seek optimization in real time database
Global seek optimization in real time databaseGlobal seek optimization in real time database
Global seek optimization in real time database
 
Flowshop scheduling
Flowshop schedulingFlowshop scheduling
Flowshop scheduling
 
SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)
 
Litttle knowledge of lean concept helps
Litttle knowledge of lean  concept helpsLitttle knowledge of lean  concept helps
Litttle knowledge of lean concept helps
 
Optimal three stage flow shop scheduling in which processing time, set up tim...
Optimal three stage flow shop scheduling in which processing time, set up tim...Optimal three stage flow shop scheduling in which processing time, set up tim...
Optimal three stage flow shop scheduling in which processing time, set up tim...
 
11.optimal three stage flow shop scheduling in which processing time, set up ...
11.optimal three stage flow shop scheduling in which processing time, set up ...11.optimal three stage flow shop scheduling in which processing time, set up ...
11.optimal three stage flow shop scheduling in which processing time, set up ...
 
R0260950100
R0260950100R0260950100
R0260950100
 
11.flow shop scheduling problem, processing time associated with probabilitie...
11.flow shop scheduling problem, processing time associated with probabilitie...11.flow shop scheduling problem, processing time associated with probabilitie...
11.flow shop scheduling problem, processing time associated with probabilitie...
 
Flow shop scheduling problem, processing time associated with probabilities i...
Flow shop scheduling problem, processing time associated with probabilities i...Flow shop scheduling problem, processing time associated with probabilities i...
Flow shop scheduling problem, processing time associated with probabilities i...
 
A case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristicsA case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristics
 
A case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristicsA case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristics
 
Job Shop Scheduling.pptx
Job Shop Scheduling.pptxJob Shop Scheduling.pptx
Job Shop Scheduling.pptx
 
Application of branch and bound technique for nx3 flow shop scheduling, in wh...
Application of branch and bound technique for nx3 flow shop scheduling, in wh...Application of branch and bound technique for nx3 flow shop scheduling, in wh...
Application of branch and bound technique for nx3 flow shop scheduling, in wh...
 
Extlect02
Extlect02Extlect02
Extlect02
 
Clock driven scheduling
Clock driven schedulingClock driven scheduling
Clock driven scheduling
 
11.machines constrained flow shop scheduling processing time, setup time each...
11.machines constrained flow shop scheduling processing time, setup time each...11.machines constrained flow shop scheduling processing time, setup time each...
11.machines constrained flow shop scheduling processing time, setup time each...
 
11.machines constrained flow shop scheduling processing time, setup time each...
11.machines constrained flow shop scheduling processing time, setup time each...11.machines constrained flow shop scheduling processing time, setup time each...
11.machines constrained flow shop scheduling processing time, setup time each...
 

Recently uploaded

Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper PresentationKirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip
 
Kanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR ReportKanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR Report
Helen Meek
 
Dpboss Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Satta Matta Matka Kalyan Chart Indian MatkaDpboss Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Discover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling ServiceDiscover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling Service
obriengroupinc04
 
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
concepsionchomo153
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
➑➌➋➑➒➎➑➑➊➍
 
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka ResultsKalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Satta Matka Dpboss Kalyan Matka Results
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...
❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...
❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...
essorprof62
 
PDT 99 - $3.5M - Seed - Feel Therapeutics.pdf
PDT 99 - $3.5M - Seed - Feel Therapeutics.pdfPDT 99 - $3.5M - Seed - Feel Therapeutics.pdf
PDT 99 - $3.5M - Seed - Feel Therapeutics.pdf
HajeJanKamps
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
ZevinAttisha
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
msthrill
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
deft. 2024 pricing guide for onboarding
deft.  2024 pricing guide for onboardingdeft.  2024 pricing guide for onboarding
deft. 2024 pricing guide for onboarding
hello960827
 
Stainless Steel Conveyor Manufacturers Chennai
Stainless Steel Conveyor Manufacturers ChennaiStainless Steel Conveyor Manufacturers Chennai
Stainless Steel Conveyor Manufacturers Chennai
ConveyorSystem
 
Science Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around UsScience Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around Us
PennapaKeavsiri
 
一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理
一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理
一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理
eaqmokn
 
japanese language course in delhi near me
japanese language course in delhi near mejapanese language course in delhi near me
japanese language course in delhi near me
heyfairies7
 

Recently uploaded (20)

Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper PresentationKirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper Presentation
 
Kanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR ReportKanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR Report
 
Dpboss Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Satta Matta Matka Kalyan Chart Indian MatkaDpboss Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Satta Matta Matka Kalyan Chart Indian Matka
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Discover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling ServiceDiscover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling Service
 
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
 
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka ResultsKalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...
❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...
❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...
 
PDT 99 - $3.5M - Seed - Feel Therapeutics.pdf
PDT 99 - $3.5M - Seed - Feel Therapeutics.pdfPDT 99 - $3.5M - Seed - Feel Therapeutics.pdf
PDT 99 - $3.5M - Seed - Feel Therapeutics.pdf
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
deft. 2024 pricing guide for onboarding
deft.  2024 pricing guide for onboardingdeft.  2024 pricing guide for onboarding
deft. 2024 pricing guide for onboarding
 
Stainless Steel Conveyor Manufacturers Chennai
Stainless Steel Conveyor Manufacturers ChennaiStainless Steel Conveyor Manufacturers Chennai
Stainless Steel Conveyor Manufacturers Chennai
 
Science Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around UsScience Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around Us
 
一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理
一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理
一比一原版(lbs毕业证书)英国伦敦商学院毕业证如何办理
 
japanese language course in delhi near me
japanese language course in delhi near mejapanese language course in delhi near me
japanese language course in delhi near me
 

scheduling

  • 1. PRESENTATION ON PRODUCTION SCHEDULING PRESENTED BY:- POOJA HEMANGI KIRAN ANURADHA
  • 2. ROADMAP What is scheduling Examples Objectives Elements Priority Planning Master Production scheduling (MPS) Objectives of MPS Functions of MPS Problems of sequencing in scheduling
  • 3. SCHEDULING  Scheduling is one of the most important elements in production planning.  Scheduling calls for through understanding of all aspects of the production process and is an outcome of the integration of the efforts of planners in the planning group and the people in the shop-floor.  Scheduling integrates the people, machine, materials, customer demands, and quality requirements in finalizing the priorities. Scheduling makes it possible by determining starting and completion data each of the operations.
  • 4. EXAMPLES OF SCHEDULING Timetabling Scheduling of the Computer :A number of different courses (tasks) have to be given using the PC room(resource) Workforce scheduling : Assign shifts for nurses and doctors in a Hospital Sports Scheduling Drug Scheduling
  • 5.
  • 6. CONT………. Scheduling effects from 2 environmental factors that are internal and external to the organization. Internal environment External environment
  • 7. OBJECTIVES OF SCHEDULING Maximize throughput Be predictable: Minimize overhead Balance resource use Achieve a balance between response and utilization Avoid indefinite postponement Enforce Priorities Give preference to process holding Degrade gracefully under heavy loads
  • 8. ELEMENTS OF SCHEDULING The processors The tasks The processing timings The precedence relations
  • 9. PRIORITY PLANNING Planning is the process by which the elements required to perform a task are determined in advance of the job start. The process is as follows : Operations soft constraints Management policy constraints Engineering hard constraints
  • 10.
  • 11. MASTER PRODUCTION SCHEDULING  Master scheduling is a part of scheduling.  A Master Production Schedule is a Schedule of the completions of the end items and these completions are very much planned in nature.  A MPS is also in management language referred to as the master of all the schedules as this schedule provides the production, planning, purchasing & top management, the most needed information required for planning and control of the whole manufacturing process or the operation.
  • 12.
  • 13. OBJECTIVES OF MASTER SCHEDULING Keeping the inventories Setting up the due dates for the availability of items Maintaining the customer service Setting proper schedules
  • 14. FUNCTIONS OF MASTER SCHEDULING Specifies planning periods as daily, weekly, or monthly. Group work order processing Tracks accuracy of order forecasting as percentage. Classifies supply into types such as materials, purchased, flow, work order, and transfer. Schedule can be edited, changed, or consolidated.
  • 15. PROBLEMS OF SEQUENCING IN SCHEDULING SHORTEST PROCESSING TIME (SPT) WEIGHTED SHORTEST PROCESSING TIME (WSPT)
  • 16. EXAMPLE:-  The data about a set of single operation jobs that is to be processed in a CNC lathe and the processing times of the jobs in the given set of jobs are as given in table.  Find the optimal sequence which will minimize the mean flow time and also obtain the corresponding minimum mean flow time. Job, j Processing time, tj 1 7 2 18 3 6 4 8 5 12
  • 17. SOLUTION:- For the given problem, the number of jobs is equal to 5. The jobs are arranged as per the SPT ordering. Job, j Processing time, tj 3 6 1 7 4 8 5 12 2 18 Therefore, the job sequence which will minimize the mean flow time is 3-1-4-5-2.
  • 18. CONT The computation of flow time for the optimal sequence (3-1-4-5-2).  COMPUTATION FLOW TIME Job, j Processing time, tj Completion time, cj(fj) 3 6 6 1 7 13 4 8 21 5 12 33 2 18 51
  • 19. CONT Since the ready time rj is zero for all the values of j, the flow time (fj) = cj for all j. Therefore, 1/5 ∑ Fj = 1/5 (6+13+21+33+51) = 1/5 (124) = 24.8 hours Therefore, the optimal mean flow time = 24.8 hours.
  • 20. WSPT Example Job, j Processing time, tj Weight , wj 1 7 1 2 18 2 3 6 1 4 8 2 5 12 3 Determine the sequence which will minimize the weighted flow time of this problem. Also find the corresponding weighted mean flow time.
  • 21. SOLUTION:-  The weighted processing times of various jobs are summarized by using the formula tj/wj, j = 1,2,3,4, and 5 Job, j Processing time, Weight , wj Tj/wj tj 1 7 1 7 2 18 2 9 3 6 1 6 4 8 2 4 5 12 3 4
  • 22. CALCULATIONS OF WEIGHTED FLOW TIMES Job, j Processing time, Cj (Fj) Weight , wj Fjwj tj 4 8 8 2 16 5 12 20 3 60 3 6 26 1 26 1 7 33 1 33 2 18 51 2 102