By
By:
:
Prof
Prof.
. Saad Abdel-Hamid Abdel-Hamid Metawa
Saad Abdel-Hamid Abdel-Hamid Metawa
(
(Full Professor of Investment & Finance
Full Professor of Investment & Finance)
)
(
(Faculty of Commerce
Faculty of Commerce -
- Mansoura University)
Mansoura University))
)
2021
2021
Chapter 11
Chapter 11
Cash Flow Estimation and Risk Analysis
Cash Flow Estimation and Risk Analysis
• Estimating cash flows:
Estimating cash flows:
• Relevant cash flows
Relevant cash flows
• Working capital treatment
Working capital treatment
• Inflation
Inflation
• Risk Analysis: Sensitivity Analysis, Scenario
Risk Analysis: Sensitivity Analysis, Scenario
Analysis, and Simulation Analysis
Analysis, and Simulation Analysis
• Cost: $200,000 + $10,000 shipping +
Cost: $200,000 + $10,000 shipping +
$30,000 installation.
$30,000 installation.
• Depreciable cost $240,000.
Depreciable cost $240,000.
• Economic life = 4 years.
Economic life = 4 years.
• Salvage value = $25,000.
Salvage value = $25,000.
• MACRS 3-year class.
MACRS 3-year class.
Proposed Project
• Annual unit sales = 1,250.
Annual unit sales = 1,250.
• Unit sales price = $200.
Unit sales price = $200.
• Unit costs = $100.
Unit costs = $100.
• Net operating working capital (NOWC) =
Net operating working capital (NOWC) =
12% of sales.
12% of sales.
• Tax rate = 40%.
Tax rate = 40%.
• Project cost of capital = 10%.
Project cost of capital = 10%.
Incremental Cash Flow for a
Incremental Cash Flow for a
Project
Project
• Project’s incremental cash flow is:
Project’s incremental cash flow is:
• Corporate cash flow
Corporate cash flow with
with the project
the project
• Minus
Minus
• Corporate cash flow
Corporate cash flow without
without the project.
the project.
• NO
NO.
. We discount project cash flows with a
We discount project cash flows with a
cost of capital that is the rate of return required by
cost of capital that is the rate of return required by
all investors (not just debtholders or
all investors (not just debtholders or
stockholders), and so we should discount the total
stockholders), and so we should discount the total
amount of cash flow available to all investors.
amount of cash flow available to all investors.
• They are part of the costs of capital. If we
They are part of the costs of capital. If we
subtracted them from cash flows, we would be
subtracted them from cash flows, we would be
double counting capital costs.
double counting capital costs.
Should you subtract interest expense or
dividends when calculating CF?
• NO
NO. This is a
. This is a sunk cost
sunk cost. Focus on
. Focus on
incremental investment and operating cash
incremental investment and operating cash
flows.
flows.
Suppose $100,000 had been spent last year
to improve the production line site. Should
this cost be included in the analysis?
• Yes
Yes. Accepting the project means we will not
. Accepting the project means we will not
receive the $25,000. This is an
receive the $25,000. This is an opportunity cost
opportunity cost
and it should be charged to the project.
and it should be charged to the project.
• A.T. opportunity cost = $25,000 (1 - T) = $15,000
A.T. opportunity cost = $25,000 (1 - T) = $15,000
annual cost.
annual cost.
Suppose the plant space could be leased out for
$25,000 a year. Would this affect the analysis?
• Yes
Yes. The effects on the other projects’ CFs
. The effects on the other projects’ CFs
are
are “externalities
“externalities”.
”.
• Net CF loss per year on other lines would be
Net CF loss per year on other lines would be
a cost to this project.
a cost to this project.
• Externalities will be
Externalities will be positive
positive if new projects
if new projects
are complements to existing assets,
are complements to existing assets, negative
negative
if substitutes.
if substitutes.
If the new product line would decrease
sales of the firm’s other products by
$50,000 per year, would this affect the
analysis?
Basis = Cost
+ Shipping
+ Installation
$240,000
What is the depreciation basis?
Year
1
2
3
4
%
0.33
0.45
0.15
0.07
Depr.
$ 79.2
108.0
36.0
16.8
x Basis =
Annual Depreciation Expense (000s)
$240
Annual Sales and Costs
Annual Sales and Costs
Year 1
Year 1 Year 2
Year 2 Year 3
Year 3 Year 4
Year 4
Units
Units 1250
1250 1250
1250 1250
1250 1250
1250
Unit price
Unit price $200
$200 $206
$206 $212.18
$212.18 $218.55
$218.55
Unit cost
Unit cost $100
$100 $103
$103 $106.09
$106.09 $109.27
$109.27
Sales
Sales $250,000
$250,000 $257,500
$257,500 $265,225
$265,225 $273,188
$273,188
Costs
Costs $125,000
$125,000 $128,750
$128,750 $132,613
$132,613 $136,588
$136,588
Why is it important to include
Why is it important to include
inflation when estimating cash
inflation when estimating cash
flows
flows
?
?
• Nominal r > real r. The cost of capital, r,
Nominal r > real r. The cost of capital, r,
includes a premium for inflation.
includes a premium for inflation.
• Nominal CF > real CF. This is because
Nominal CF > real CF. This is because
nominal cash flows incorporate inflation.
nominal cash flows incorporate inflation.
• If you discount real CF with the higher
If you discount real CF with the higher
nominal r, then your NPV estimate is too low.
nominal r, then your NPV estimate is too low.
Inflation (Continued)
Inflation (Continued)
• Nominal CF should be discounted with
Nominal CF should be discounted with
nominal r, and real CF should be discounted
nominal r, and real CF should be discounted
with real r.
with real r.
• It is more realistic to find the nominal CF (i.e.,
It is more realistic to find the nominal CF (i.e.,
increase cash flow estimates with inflation)
increase cash flow estimates with inflation)
than it is to reduce the nominal r to a real r.
than it is to reduce the nominal r to a real r.
Operating Cash Flows (Years 1 and 2)
Operating Cash Flows (Years 1 and 2)
Year 1
Year 1 Year 2
Year 2
Sales
Sales $250,000
$250,000 $257,500
$257,500
Costs
Costs $125,000
$125,000 $128,750
$128,750
Depr.
Depr. $79,200
$79,200 $108,000
$108,000
EBIT
EBIT $45,800
$45,800 $20,750
$20,750
Taxes (40%)
Taxes (40%) $18,320
$18,320 $8,300
$8,300
NOPAT
NOPAT $27,480
$27,480 $12,450
$12,450
+ Depr.
+ Depr. $79,200
$79,200 $108,000
$108,000
Net Op. CF
Net Op. CF $106,680
$106,680 $120,450
$120,450
Operating Cash Flows (Years 3 and 4)
Operating Cash Flows (Years 3 and 4)
Year 3
Year 3 Year 4
Year 4
Sales
Sales $265,225
$265,225 $273,188
$273,188
Costs
Costs $132,613
$132,613 $136,588
$136,588
Depr.
Depr. $36,000
$36,000 $16,800
$16,800
EBIT
EBIT $96,612
$96,612 $119,800
$119,800
Taxes (40%)
Taxes (40%) $38,645
$38,645 $47,920
$47,920
NOPAT
NOPAT $57,967
$57,967 $71,880
$71,880
+ Depr.
+ Depr. $36,000
$36,000 $16,800
$16,800
Net Op. CF
Net Op. CF $93,967
$93,967 $88,680
$88,680
Cash Flows due to Investments in
Cash Flows due to Investments in
Net Operating Working Capital
Net Operating Working Capital
(NOWC)
(NOWC)
NOWC
NOWC
Sales
Sales (% of sales)
(% of sales) CF
CF
Year 0
Year 0 $30,000
$30,000-$30,000
-$30,000
Year 1
Year 1 $250,000
$250,000$30,900
$30,900 -$900
-$900
Year 2
Year 2 $257,500
$257,500$31,827
$31,827 -$927
-$927
Year 3
Year 3 $265,225
$265,225$32,783
$32,783 -$956
-$956
Year 4
Year 4 $273,188
$273,188$32,783
$32,783
Salvage Cash Flow at t = 4 (000s)
Salvage Cash Flow at t = 4 (000s)
Salvage value
Tax on SV
Net terminal CF
$25
(10)
$15
What if you terminate a
What if you terminate a
project before the asset is fully
project before the asset is fully
depreciated
depreciated
?
?
Cash flow from sale = Sale proceeds
- taxes paid.
Taxes are based on difference between sales price and tax basis, where:
Basis = Original basis - Accum. deprec.
• Original basis
Original basis = $240.
= $240.
• After 3 years
After 3 years = $16.8 remaining.
= $16.8 remaining.
• Sales price
Sales price = $25.
= $25.
• Tax on sale
Tax on sale = 0.4($25-$16.8)
= 0.4($25-$16.8)
= $3.28.
= $3.28.
• Cash flow
Cash flow = $25-$3.28=$21.72.
= $25-$3.28=$21.72.
Example: If Sold After 3 Years (000s)
Net Cash Flows for Years 1-3
Net Cash Flows for Years 1-3
Year 0
Year 0 Year 1
Year 1 Year 2
Year 2
Init. Cost
Init. Cost -$240,000
-$240,000 0
0 0
0
Op. CF
Op. CF 0
0 $106,680
$106,680 $120,450
$120,450
NOWC CF
NOWC CF -$30,000
-$30,000 -$900
-$900 -$927
-$927
Salvage CF
Salvage CF 0
0 0
0 0
0
Net CF
Net CF -$270,000
-$270,000 $105,780
$105,780 $119,523
$119,523
Net Cash Flows for Years 4
Net Cash Flows for Years 4-5
-5
Year 3
Year 3 Year 4
Year 4
Init. Cost
Init. Cost 0
0 0
0
Op CF
Op CF $93,967
$93,967 $88,680
$88,680
NOWC CF
NOWC CF -$956
-$956 $32,783
$32,783
Salvage CF
Salvage CF 0
0 $15,000
$15,000
Net CF
Net CF $93,011
$93,011 $136,463
$136,463
Project Net CFs on a Time Line
Project Net CFs on a Time Line
Enter CFs in CFLO register and I = 10.
NPV = $88,030.
IRR = 23.9%.
0 1 2 3 4
(270,000) 105,780 119,523 93,011 136,463
What is the project’s MIRR? (000s)
What is the project’s MIRR? (000s)
(270,000)
MIRR = ?
0 1 2 3 4
(270,000) 105,780 119,523 93,011
136,463
102,312
144,623
140,793
524,191
1. Enter positive CFs in CFLO:
I = 10; Solve for NPV = $358,029.581.
2. Use TVM keys: PV = -358,029.581, N =
4, I = 10; PMT = 0; Solve for FV = 524,191.
(TV of inflows)
3. Use TVM keys: N = 4; FV = 524,191;
PV = -270,000; PMT= 0; Solve for I =
18.0.
MIRR = 18.0%.
Calculator Solution
Calculator Solution
What is the project’s payback? (000s)
What is the project’s payback? (000s)
Cumulative:
Payback = 2 + 44/93 = 2.5 years.
0 1 2 3 4
(270)*
(270)
106
(164)
120
(44)
93
49
136
185
What does “risk” mean in
What does “risk” mean in
capital budgeting
capital budgeting
?
?
• Uncertainty about a project’s
Uncertainty about a project’s
future profitability.
future profitability.
• Measured by
Measured by 
NPV
NPV,
, 
IRR
IRR, beta.
, beta.
• Will taking on the project increase
Will taking on the project increase
the firm’s and stockholders’ risk?
the firm’s and stockholders’ risk?
Is risk analysis based on
Is risk analysis based on
historical data or subjective
historical data or subjective
judgment
judgment
?
?
• Can sometimes use historical data, but
Can sometimes use historical data, but
generally cannot.
generally cannot.
• So risk analysis in capital budgeting is
So risk analysis in capital budgeting is
usually based on subjective judgments.
usually based on subjective judgments.
What three types of risk are
What three types of risk are
relevant in capital budgeting
relevant in capital budgeting
?
?
• Stand-alone risk
Stand-alone risk
• Corporate risk
Corporate risk
• Market (or beta) risk
Market (or beta) risk
How is each type of risk measured, and how
How is each type of risk measured, and how
do they relate to one another
do they relate to one another
?
?
1.
1. Stand-Alone Risk
Stand-Alone Risk:
:
• The project’s risk if it were the firm’s only asset
The project’s risk if it were the firm’s only asset
and there were no shareholders.
and there were no shareholders.
• Ignores both firm and shareholder diversification.
Ignores both firm and shareholder diversification.
• Measured by the
Measured by the  or CV of NPV, IRR, or
or CV of NPV, IRR, or
MIRR.
MIRR.
0 E(NPV)
Probability Density
Flatter distribution,
larger , larger
stand-alone risk.
Such graphics are increasingly used
by corporations.
NPV
2.
2. Corporate Risk
Corporate Risk:
:
• Reflects the project’s effect on
Reflects the project’s effect on
corporate earnings stability.
corporate earnings stability.
• Considers firm’s other assets
Considers firm’s other assets
(diversification within firm).
(diversification within firm).
• Depends on:
Depends on:
• project’s
project’s 
, and
, and
• its correlation,
its correlation, 
, with returns
, with returns
on
on firm’s other assets.
firm’s other assets.
• Measured by the project’s corporate
Measured by the project’s corporate
beta.
beta.
Profitability
0 Years
Project X
Total Firm
Rest of Firm
1. Project X is negatively correlated to
firm’s other assets.
2. If  < 1.0, some diversification benefits.
3. If  = 1.0, no diversification effects.
3.
3. Market Risk
Market Risk:
:
• Reflects the project’s effect on a well-
Reflects the project’s effect on a well-
diversified stock portfolio.
diversified stock portfolio.
• Takes account of stockholders’ other
Takes account of stockholders’ other
assets.
assets.
• Depends on project’s
Depends on project’s 
 and correlation
and correlation
with the stock market.
with the stock market.
• Measured by the project’s market beta.
Measured by the project’s market beta.
How is each type of risk used
How is each type of risk used
?
?
• Market risk is theoretically best in most
Market risk is theoretically best in most
situations.
situations.
• However, creditors, customers, suppliers,
However, creditors, customers, suppliers,
and employees are more affected by
and employees are more affected by
corporate risk.
corporate risk.
• Therefore, corporate risk is also relevant.
Therefore, corporate risk is also relevant.
• Stand-alone risk is easiest to measure,
Stand-alone risk is easiest to measure,
more intuitive.
more intuitive.
• Core projects are highly correlated with
Core projects are highly correlated with
other assets, so stand-alone risk
other assets, so stand-alone risk
generally reflects corporate risk.
generally reflects corporate risk.
• If the project is highly correlated with
If the project is highly correlated with
the economy, stand-alone risk also
the economy, stand-alone risk also
reflects market risk.
reflects market risk.
What is sensitivity analysis
What is sensitivity analysis
?
?
• Shows how changes in a variable such
Shows how changes in a variable such
as unit sales affect NPV or IRR.
as unit sales affect NPV or IRR.
• Each variable is fixed except one.
Each variable is fixed except one.
Change this one variable to see the
Change this one variable to see the
effect on NPV or IRR.
effect on NPV or IRR.
• Answers “what if” questions, e.g. “What
Answers “what if” questions, e.g. “What
if sales decline by 30%?”
if sales decline by 30%?”
Sensitivity Analysis
Sensitivity Analysis
-
-
30%
30%
$113
$113
$17
$17
$85
$85
-
-
15%
15%
$100
$100
$52
$52
$86
$86
0%
0%
$88
$88
$88
$88
$88
$88
15%
15%
$76
$76
$124
$124
$90
$90
30%
30%
$65
$65
$159
$159
$91
$91
Change from Resulting NPV (000s)
Base Level r Unit Sales Salvage
-30 -20 -10 Base 10 20 30
Value (%)
88
NPV
(000s)
Unit Sales
Salvage
r
Results of Sensitivity Analysis
Results of Sensitivity Analysis
• Steeper sensitivity lines show greater risk.
Steeper sensitivity lines show greater risk.
Small changes result in large declines in NPV.
Small changes result in large declines in NPV.
• Unit sales line is steeper than salvage value or
Unit sales line is steeper than salvage value or
r, so for this project, should worry most about
r, so for this project, should worry most about
accuracy of sales forecast.
accuracy of sales forecast.
What are the weaknesses of
What are the weaknesses of
sensitivity analysis
sensitivity analysis
?
?
• Does not reflect diversification.
Does not reflect diversification.
• Says nothing about the likelihood of
Says nothing about the likelihood of
change in a variable, i.e. a steep sales
change in a variable, i.e. a steep sales
line is not a problem if sales won’t fall.
line is not a problem if sales won’t fall.
• Ignores relationships among variables.
Ignores relationships among variables.
Why is sensitivity analysis
Why is sensitivity analysis
useful
useful
?
?
• Gives some idea of stand-alone risk.
Gives some idea of stand-alone risk.
• Identifies dangerous variables.
Identifies dangerous variables.
• Gives some breakeven information.
Gives some breakeven information.
What is scenario analysis
What is scenario analysis
?
?
• Examines several possible situations,
Examines several possible situations,
usually worst case, most likely case, and
usually worst case, most likely case, and
best case.
best case.
• Provides a range of possible outcomes.
Provides a range of possible outcomes.
Best scenario: 1,600 units @ $240
Best scenario: 1,600 units @ $240
Worst scenario: 900 units @ $
Worst scenario: 900 units @ $160
160
Scenario
Scenario
Probability
Probability
NPV(000)
NPV(000)
Best 0.25 $ 279
Base 0.50 88
Worst 0.25 -49
E(NPV) = $101.5
(NPV) = 116.6
CV(NPV) = (NPV)/E(NPV) = 1.15
Are there any problems with scenario
analysis?
• Only considers a few possible out-comes.
• Assumes that inputs are perfectly correlated--
all “bad” values occur together and all “good”
values occur together.
• Focuses on stand-alone risk, although
subjective adjustments can be made.
What is a simulation analysis
What is a simulation analysis
?
?
• A computerized version of scenario analysis
A computerized version of scenario analysis
which uses continuous probability
which uses continuous probability
distributions.
distributions.
• Computer selects values for each variable
Computer selects values for each variable
based on given probability distributions.
based on given probability distributions.
• NPV and IRR are calculated.
NPV and IRR are calculated.
• Process is repeated many times (1,000
Process is repeated many times (1,000
or more).
or more).
• End result: Probability distribution of
End result: Probability distribution of
NPV and IRR based on sample of
NPV and IRR based on sample of
simulated values.
simulated values.
• Generally shown graphically.
Generally shown graphically.
Simulation Example
Simulation Example
• Assume a:
Assume a:
• Normal distribution for unit sales:
Normal distribution for unit sales:
• Mean = 1,250
Mean = 1,250
• Standard deviation = 200
Standard deviation = 200
• Triangular distribution for unit price:
Triangular distribution for unit price:
• Lower bound
Lower bound = $160
= $160
• Most likely
Most likely = $200
= $200
• Upper bound
Upper bound = $250
= $250
Simulation Process
Simulation Process
• Pick a random variable for unit sales and sale
Pick a random variable for unit sales and sale
price.
price.
• Substitute these values in the spreadsheet and
Substitute these values in the spreadsheet and
calculate NPV.
calculate NPV.
• Repeat the process many times, saving the
Repeat the process many times, saving the
input variables (units and price) and the output
input variables (units and price) and the output
(NPV).
(NPV).
Simulation Results (1000 trials)
Simulation Results (1000 trials)
(See Ch 11 Mini Case Simulation.xls)
(See Ch 11 Mini Case Simulation.xls)
Units PriceNPV
Mean 1260$202 $95,914
St. Dev. 201$18 $59,875
CV 0.62
Max 1883 $248 $353,238
Min 685$163 ($45,713)
Prob NPV>0 97%
Interpreting the Results
Interpreting the Results
• Inputs are consistent with specificied
Inputs are consistent with specificied
distributions.
distributions.
• Units: Mean = 1260, St. Dev. = 201.
Units: Mean = 1260, St. Dev. = 201.
• Price: Min = $163, Mean = $202, Max = $248.
Price: Min = $163, Mean = $202, Max = $248.
• Mean NPV = $95,914. Low probability of
Mean NPV = $95,914. Low probability of
negative NPV (100% - 97% = 3%).
negative NPV (100% - 97% = 3%).
Histogram of Results
Histogram of Results
-$60,000 $45,000 $150,000 $255,000 $360,000
NPV ($)
Probability
What are the advantages of
What are the advantages of
simulation analysis
simulation analysis
?
?
• Reflects the probability
Reflects the probability
distributions of each input.
distributions of each input.
• Shows range of NPVs, the
Shows range of NPVs, the
expected NPV,
expected NPV, 
NPV
NPV, and CV
, and CVNPV
NPV.
.
• Gives an intuitive graph of the
Gives an intuitive graph of the
risk situation.
risk situation.
What are the disadvantages of
What are the disadvantages of
simulation
simulation
?
?
 Difficult to specify probability distributions
Difficult to specify probability distributions
and correlations.
and correlations.
 If inputs are bad, output will be bad:
If inputs are bad, output will be bad:
“Garbage in, garbage out.”
“Garbage in, garbage out.”
• Sensitivity, scenario, and simulation analyses do
Sensitivity, scenario, and simulation analyses do
not provide a decision rule. They do not indicate
not provide a decision rule. They do not indicate
whether a project’s expected return is sufficient to
whether a project’s expected return is sufficient to
compensate for its risk.
compensate for its risk.
• Sensitivity, scenario, and simulation analyses all
Sensitivity, scenario, and simulation analyses all
ignore diversification. Thus they measure only
ignore diversification. Thus they measure only
stand-alone risk, which may not be the most
stand-alone risk, which may not be the most
relevant risk in capital budgeting.
relevant risk in capital budgeting.
If the firm’s average project has a CV
If the firm’s average project has a CV
of 0.2 to 0.4, is this a high-risk project?
of 0.2 to 0.4, is this a high-risk project?
What type of risk is being measured
What type of risk is being measured
?
?
• CV from scenarios = 0.74, CV from
CV from scenarios = 0.74, CV from
simulation = 0.62. Both are > 0.4, this project
simulation = 0.62. Both are > 0.4, this project
has high risk.
has high risk.
• CV measures a project’s stand-alone risk.
CV measures a project’s stand-alone risk.
• High stand-alone risk usually indicates high
High stand-alone risk usually indicates high
corporate and market risks.
corporate and market risks.
With a 3% risk adjustment, should
With a 3% risk adjustment, should
our project be accepted
our project be accepted
?
?
• Project r = 10% + 3% = 13%.
Project r = 10% + 3% = 13%.
• That’s 30% above base r.
That’s 30% above base r.
• NPV = $65,371.
NPV = $65,371.
• Project remains acceptable after accounting for
Project remains acceptable after accounting for
differential (higher) risk.
differential (higher) risk.
Should subjective risk factors
Should subjective risk factors
be considered
be considered
?
?
• Yes. A numerical analysis may not capture
Yes. A numerical analysis may not capture
all of the risk factors inherent in the project.
all of the risk factors inherent in the project.
• For example, if the project has the potential
For example, if the project has the potential
for bringing on harmful lawsuits, then it
for bringing on harmful lawsuits, then it
might be riskier than a standard analysis
might be riskier than a standard analysis
would indicate.
would indicate.

Chapter 11 - Cash Flow Estimation and Risk Analysis.ppt

  • 1.
    By By: : Prof Prof. . Saad Abdel-HamidAbdel-Hamid Metawa Saad Abdel-Hamid Abdel-Hamid Metawa ( (Full Professor of Investment & Finance Full Professor of Investment & Finance) ) ( (Faculty of Commerce Faculty of Commerce - - Mansoura University) Mansoura University)) ) 2021 2021 Chapter 11 Chapter 11 Cash Flow Estimation and Risk Analysis Cash Flow Estimation and Risk Analysis
  • 2.
    • Estimating cashflows: Estimating cash flows: • Relevant cash flows Relevant cash flows • Working capital treatment Working capital treatment • Inflation Inflation • Risk Analysis: Sensitivity Analysis, Scenario Risk Analysis: Sensitivity Analysis, Scenario Analysis, and Simulation Analysis Analysis, and Simulation Analysis
  • 3.
    • Cost: $200,000+ $10,000 shipping + Cost: $200,000 + $10,000 shipping + $30,000 installation. $30,000 installation. • Depreciable cost $240,000. Depreciable cost $240,000. • Economic life = 4 years. Economic life = 4 years. • Salvage value = $25,000. Salvage value = $25,000. • MACRS 3-year class. MACRS 3-year class. Proposed Project
  • 4.
    • Annual unitsales = 1,250. Annual unit sales = 1,250. • Unit sales price = $200. Unit sales price = $200. • Unit costs = $100. Unit costs = $100. • Net operating working capital (NOWC) = Net operating working capital (NOWC) = 12% of sales. 12% of sales. • Tax rate = 40%. Tax rate = 40%. • Project cost of capital = 10%. Project cost of capital = 10%.
  • 5.
    Incremental Cash Flowfor a Incremental Cash Flow for a Project Project • Project’s incremental cash flow is: Project’s incremental cash flow is: • Corporate cash flow Corporate cash flow with with the project the project • Minus Minus • Corporate cash flow Corporate cash flow without without the project. the project.
  • 6.
    • NO NO. . Wediscount project cash flows with a We discount project cash flows with a cost of capital that is the rate of return required by cost of capital that is the rate of return required by all investors (not just debtholders or all investors (not just debtholders or stockholders), and so we should discount the total stockholders), and so we should discount the total amount of cash flow available to all investors. amount of cash flow available to all investors. • They are part of the costs of capital. If we They are part of the costs of capital. If we subtracted them from cash flows, we would be subtracted them from cash flows, we would be double counting capital costs. double counting capital costs. Should you subtract interest expense or dividends when calculating CF?
  • 7.
    • NO NO. Thisis a . This is a sunk cost sunk cost. Focus on . Focus on incremental investment and operating cash incremental investment and operating cash flows. flows. Suppose $100,000 had been spent last year to improve the production line site. Should this cost be included in the analysis?
  • 8.
    • Yes Yes. Acceptingthe project means we will not . Accepting the project means we will not receive the $25,000. This is an receive the $25,000. This is an opportunity cost opportunity cost and it should be charged to the project. and it should be charged to the project. • A.T. opportunity cost = $25,000 (1 - T) = $15,000 A.T. opportunity cost = $25,000 (1 - T) = $15,000 annual cost. annual cost. Suppose the plant space could be leased out for $25,000 a year. Would this affect the analysis?
  • 9.
    • Yes Yes. Theeffects on the other projects’ CFs . The effects on the other projects’ CFs are are “externalities “externalities”. ”. • Net CF loss per year on other lines would be Net CF loss per year on other lines would be a cost to this project. a cost to this project. • Externalities will be Externalities will be positive positive if new projects if new projects are complements to existing assets, are complements to existing assets, negative negative if substitutes. if substitutes. If the new product line would decrease sales of the firm’s other products by $50,000 per year, would this affect the analysis?
  • 10.
    Basis = Cost +Shipping + Installation $240,000 What is the depreciation basis?
  • 11.
  • 12.
    Annual Sales andCosts Annual Sales and Costs Year 1 Year 1 Year 2 Year 2 Year 3 Year 3 Year 4 Year 4 Units Units 1250 1250 1250 1250 1250 1250 1250 1250 Unit price Unit price $200 $200 $206 $206 $212.18 $212.18 $218.55 $218.55 Unit cost Unit cost $100 $100 $103 $103 $106.09 $106.09 $109.27 $109.27 Sales Sales $250,000 $250,000 $257,500 $257,500 $265,225 $265,225 $273,188 $273,188 Costs Costs $125,000 $125,000 $128,750 $128,750 $132,613 $132,613 $136,588 $136,588
  • 13.
    Why is itimportant to include Why is it important to include inflation when estimating cash inflation when estimating cash flows flows ? ? • Nominal r > real r. The cost of capital, r, Nominal r > real r. The cost of capital, r, includes a premium for inflation. includes a premium for inflation. • Nominal CF > real CF. This is because Nominal CF > real CF. This is because nominal cash flows incorporate inflation. nominal cash flows incorporate inflation. • If you discount real CF with the higher If you discount real CF with the higher nominal r, then your NPV estimate is too low. nominal r, then your NPV estimate is too low.
  • 14.
    Inflation (Continued) Inflation (Continued) •Nominal CF should be discounted with Nominal CF should be discounted with nominal r, and real CF should be discounted nominal r, and real CF should be discounted with real r. with real r. • It is more realistic to find the nominal CF (i.e., It is more realistic to find the nominal CF (i.e., increase cash flow estimates with inflation) increase cash flow estimates with inflation) than it is to reduce the nominal r to a real r. than it is to reduce the nominal r to a real r.
  • 15.
    Operating Cash Flows(Years 1 and 2) Operating Cash Flows (Years 1 and 2) Year 1 Year 1 Year 2 Year 2 Sales Sales $250,000 $250,000 $257,500 $257,500 Costs Costs $125,000 $125,000 $128,750 $128,750 Depr. Depr. $79,200 $79,200 $108,000 $108,000 EBIT EBIT $45,800 $45,800 $20,750 $20,750 Taxes (40%) Taxes (40%) $18,320 $18,320 $8,300 $8,300 NOPAT NOPAT $27,480 $27,480 $12,450 $12,450 + Depr. + Depr. $79,200 $79,200 $108,000 $108,000 Net Op. CF Net Op. CF $106,680 $106,680 $120,450 $120,450
  • 16.
    Operating Cash Flows(Years 3 and 4) Operating Cash Flows (Years 3 and 4) Year 3 Year 3 Year 4 Year 4 Sales Sales $265,225 $265,225 $273,188 $273,188 Costs Costs $132,613 $132,613 $136,588 $136,588 Depr. Depr. $36,000 $36,000 $16,800 $16,800 EBIT EBIT $96,612 $96,612 $119,800 $119,800 Taxes (40%) Taxes (40%) $38,645 $38,645 $47,920 $47,920 NOPAT NOPAT $57,967 $57,967 $71,880 $71,880 + Depr. + Depr. $36,000 $36,000 $16,800 $16,800 Net Op. CF Net Op. CF $93,967 $93,967 $88,680 $88,680
  • 17.
    Cash Flows dueto Investments in Cash Flows due to Investments in Net Operating Working Capital Net Operating Working Capital (NOWC) (NOWC) NOWC NOWC Sales Sales (% of sales) (% of sales) CF CF Year 0 Year 0 $30,000 $30,000-$30,000 -$30,000 Year 1 Year 1 $250,000 $250,000$30,900 $30,900 -$900 -$900 Year 2 Year 2 $257,500 $257,500$31,827 $31,827 -$927 -$927 Year 3 Year 3 $265,225 $265,225$32,783 $32,783 -$956 -$956 Year 4 Year 4 $273,188 $273,188$32,783 $32,783
  • 18.
    Salvage Cash Flowat t = 4 (000s) Salvage Cash Flow at t = 4 (000s) Salvage value Tax on SV Net terminal CF $25 (10) $15
  • 19.
    What if youterminate a What if you terminate a project before the asset is fully project before the asset is fully depreciated depreciated ? ? Cash flow from sale = Sale proceeds - taxes paid. Taxes are based on difference between sales price and tax basis, where: Basis = Original basis - Accum. deprec.
  • 20.
    • Original basis Originalbasis = $240. = $240. • After 3 years After 3 years = $16.8 remaining. = $16.8 remaining. • Sales price Sales price = $25. = $25. • Tax on sale Tax on sale = 0.4($25-$16.8) = 0.4($25-$16.8) = $3.28. = $3.28. • Cash flow Cash flow = $25-$3.28=$21.72. = $25-$3.28=$21.72. Example: If Sold After 3 Years (000s)
  • 21.
    Net Cash Flowsfor Years 1-3 Net Cash Flows for Years 1-3 Year 0 Year 0 Year 1 Year 1 Year 2 Year 2 Init. Cost Init. Cost -$240,000 -$240,000 0 0 0 0 Op. CF Op. CF 0 0 $106,680 $106,680 $120,450 $120,450 NOWC CF NOWC CF -$30,000 -$30,000 -$900 -$900 -$927 -$927 Salvage CF Salvage CF 0 0 0 0 0 0 Net CF Net CF -$270,000 -$270,000 $105,780 $105,780 $119,523 $119,523
  • 22.
    Net Cash Flowsfor Years 4 Net Cash Flows for Years 4-5 -5 Year 3 Year 3 Year 4 Year 4 Init. Cost Init. Cost 0 0 0 0 Op CF Op CF $93,967 $93,967 $88,680 $88,680 NOWC CF NOWC CF -$956 -$956 $32,783 $32,783 Salvage CF Salvage CF 0 0 $15,000 $15,000 Net CF Net CF $93,011 $93,011 $136,463 $136,463
  • 23.
    Project Net CFson a Time Line Project Net CFs on a Time Line Enter CFs in CFLO register and I = 10. NPV = $88,030. IRR = 23.9%. 0 1 2 3 4 (270,000) 105,780 119,523 93,011 136,463
  • 24.
    What is theproject’s MIRR? (000s) What is the project’s MIRR? (000s) (270,000) MIRR = ? 0 1 2 3 4 (270,000) 105,780 119,523 93,011 136,463 102,312 144,623 140,793 524,191
  • 25.
    1. Enter positiveCFs in CFLO: I = 10; Solve for NPV = $358,029.581. 2. Use TVM keys: PV = -358,029.581, N = 4, I = 10; PMT = 0; Solve for FV = 524,191. (TV of inflows) 3. Use TVM keys: N = 4; FV = 524,191; PV = -270,000; PMT= 0; Solve for I = 18.0. MIRR = 18.0%. Calculator Solution Calculator Solution
  • 26.
    What is theproject’s payback? (000s) What is the project’s payback? (000s) Cumulative: Payback = 2 + 44/93 = 2.5 years. 0 1 2 3 4 (270)* (270) 106 (164) 120 (44) 93 49 136 185
  • 27.
    What does “risk”mean in What does “risk” mean in capital budgeting capital budgeting ? ? • Uncertainty about a project’s Uncertainty about a project’s future profitability. future profitability. • Measured by Measured by  NPV NPV, ,  IRR IRR, beta. , beta. • Will taking on the project increase Will taking on the project increase the firm’s and stockholders’ risk? the firm’s and stockholders’ risk?
  • 28.
    Is risk analysisbased on Is risk analysis based on historical data or subjective historical data or subjective judgment judgment ? ? • Can sometimes use historical data, but Can sometimes use historical data, but generally cannot. generally cannot. • So risk analysis in capital budgeting is So risk analysis in capital budgeting is usually based on subjective judgments. usually based on subjective judgments.
  • 29.
    What three typesof risk are What three types of risk are relevant in capital budgeting relevant in capital budgeting ? ? • Stand-alone risk Stand-alone risk • Corporate risk Corporate risk • Market (or beta) risk Market (or beta) risk
  • 30.
    How is eachtype of risk measured, and how How is each type of risk measured, and how do they relate to one another do they relate to one another ? ? 1. 1. Stand-Alone Risk Stand-Alone Risk: : • The project’s risk if it were the firm’s only asset The project’s risk if it were the firm’s only asset and there were no shareholders. and there were no shareholders. • Ignores both firm and shareholder diversification. Ignores both firm and shareholder diversification. • Measured by the Measured by the  or CV of NPV, IRR, or or CV of NPV, IRR, or MIRR. MIRR.
  • 31.
    0 E(NPV) Probability Density Flatterdistribution, larger , larger stand-alone risk. Such graphics are increasingly used by corporations. NPV
  • 32.
    2. 2. Corporate Risk CorporateRisk: : • Reflects the project’s effect on Reflects the project’s effect on corporate earnings stability. corporate earnings stability. • Considers firm’s other assets Considers firm’s other assets (diversification within firm). (diversification within firm). • Depends on: Depends on: • project’s project’s  , and , and • its correlation, its correlation,  , with returns , with returns on on firm’s other assets. firm’s other assets. • Measured by the project’s corporate Measured by the project’s corporate beta. beta.
  • 33.
    Profitability 0 Years Project X TotalFirm Rest of Firm 1. Project X is negatively correlated to firm’s other assets. 2. If  < 1.0, some diversification benefits. 3. If  = 1.0, no diversification effects.
  • 34.
    3. 3. Market Risk MarketRisk: : • Reflects the project’s effect on a well- Reflects the project’s effect on a well- diversified stock portfolio. diversified stock portfolio. • Takes account of stockholders’ other Takes account of stockholders’ other assets. assets. • Depends on project’s Depends on project’s   and correlation and correlation with the stock market. with the stock market. • Measured by the project’s market beta. Measured by the project’s market beta.
  • 35.
    How is eachtype of risk used How is each type of risk used ? ? • Market risk is theoretically best in most Market risk is theoretically best in most situations. situations. • However, creditors, customers, suppliers, However, creditors, customers, suppliers, and employees are more affected by and employees are more affected by corporate risk. corporate risk. • Therefore, corporate risk is also relevant. Therefore, corporate risk is also relevant.
  • 36.
    • Stand-alone riskis easiest to measure, Stand-alone risk is easiest to measure, more intuitive. more intuitive. • Core projects are highly correlated with Core projects are highly correlated with other assets, so stand-alone risk other assets, so stand-alone risk generally reflects corporate risk. generally reflects corporate risk. • If the project is highly correlated with If the project is highly correlated with the economy, stand-alone risk also the economy, stand-alone risk also reflects market risk. reflects market risk.
  • 37.
    What is sensitivityanalysis What is sensitivity analysis ? ? • Shows how changes in a variable such Shows how changes in a variable such as unit sales affect NPV or IRR. as unit sales affect NPV or IRR. • Each variable is fixed except one. Each variable is fixed except one. Change this one variable to see the Change this one variable to see the effect on NPV or IRR. effect on NPV or IRR. • Answers “what if” questions, e.g. “What Answers “what if” questions, e.g. “What if sales decline by 30%?” if sales decline by 30%?”
  • 38.
  • 39.
    -30 -20 -10Base 10 20 30 Value (%) 88 NPV (000s) Unit Sales Salvage r
  • 40.
    Results of SensitivityAnalysis Results of Sensitivity Analysis • Steeper sensitivity lines show greater risk. Steeper sensitivity lines show greater risk. Small changes result in large declines in NPV. Small changes result in large declines in NPV. • Unit sales line is steeper than salvage value or Unit sales line is steeper than salvage value or r, so for this project, should worry most about r, so for this project, should worry most about accuracy of sales forecast. accuracy of sales forecast.
  • 41.
    What are theweaknesses of What are the weaknesses of sensitivity analysis sensitivity analysis ? ? • Does not reflect diversification. Does not reflect diversification. • Says nothing about the likelihood of Says nothing about the likelihood of change in a variable, i.e. a steep sales change in a variable, i.e. a steep sales line is not a problem if sales won’t fall. line is not a problem if sales won’t fall. • Ignores relationships among variables. Ignores relationships among variables.
  • 42.
    Why is sensitivityanalysis Why is sensitivity analysis useful useful ? ? • Gives some idea of stand-alone risk. Gives some idea of stand-alone risk. • Identifies dangerous variables. Identifies dangerous variables. • Gives some breakeven information. Gives some breakeven information.
  • 43.
    What is scenarioanalysis What is scenario analysis ? ? • Examines several possible situations, Examines several possible situations, usually worst case, most likely case, and usually worst case, most likely case, and best case. best case. • Provides a range of possible outcomes. Provides a range of possible outcomes.
  • 44.
    Best scenario: 1,600units @ $240 Best scenario: 1,600 units @ $240 Worst scenario: 900 units @ $ Worst scenario: 900 units @ $160 160 Scenario Scenario Probability Probability NPV(000) NPV(000) Best 0.25 $ 279 Base 0.50 88 Worst 0.25 -49 E(NPV) = $101.5 (NPV) = 116.6 CV(NPV) = (NPV)/E(NPV) = 1.15
  • 45.
    Are there anyproblems with scenario analysis? • Only considers a few possible out-comes. • Assumes that inputs are perfectly correlated-- all “bad” values occur together and all “good” values occur together. • Focuses on stand-alone risk, although subjective adjustments can be made.
  • 46.
    What is asimulation analysis What is a simulation analysis ? ? • A computerized version of scenario analysis A computerized version of scenario analysis which uses continuous probability which uses continuous probability distributions. distributions. • Computer selects values for each variable Computer selects values for each variable based on given probability distributions. based on given probability distributions.
  • 47.
    • NPV andIRR are calculated. NPV and IRR are calculated. • Process is repeated many times (1,000 Process is repeated many times (1,000 or more). or more). • End result: Probability distribution of End result: Probability distribution of NPV and IRR based on sample of NPV and IRR based on sample of simulated values. simulated values. • Generally shown graphically. Generally shown graphically.
  • 48.
    Simulation Example Simulation Example •Assume a: Assume a: • Normal distribution for unit sales: Normal distribution for unit sales: • Mean = 1,250 Mean = 1,250 • Standard deviation = 200 Standard deviation = 200 • Triangular distribution for unit price: Triangular distribution for unit price: • Lower bound Lower bound = $160 = $160 • Most likely Most likely = $200 = $200 • Upper bound Upper bound = $250 = $250
  • 49.
    Simulation Process Simulation Process •Pick a random variable for unit sales and sale Pick a random variable for unit sales and sale price. price. • Substitute these values in the spreadsheet and Substitute these values in the spreadsheet and calculate NPV. calculate NPV. • Repeat the process many times, saving the Repeat the process many times, saving the input variables (units and price) and the output input variables (units and price) and the output (NPV). (NPV).
  • 50.
    Simulation Results (1000trials) Simulation Results (1000 trials) (See Ch 11 Mini Case Simulation.xls) (See Ch 11 Mini Case Simulation.xls) Units PriceNPV Mean 1260$202 $95,914 St. Dev. 201$18 $59,875 CV 0.62 Max 1883 $248 $353,238 Min 685$163 ($45,713) Prob NPV>0 97%
  • 51.
    Interpreting the Results Interpretingthe Results • Inputs are consistent with specificied Inputs are consistent with specificied distributions. distributions. • Units: Mean = 1260, St. Dev. = 201. Units: Mean = 1260, St. Dev. = 201. • Price: Min = $163, Mean = $202, Max = $248. Price: Min = $163, Mean = $202, Max = $248. • Mean NPV = $95,914. Low probability of Mean NPV = $95,914. Low probability of negative NPV (100% - 97% = 3%). negative NPV (100% - 97% = 3%).
  • 52.
    Histogram of Results Histogramof Results -$60,000 $45,000 $150,000 $255,000 $360,000 NPV ($) Probability
  • 53.
    What are theadvantages of What are the advantages of simulation analysis simulation analysis ? ? • Reflects the probability Reflects the probability distributions of each input. distributions of each input. • Shows range of NPVs, the Shows range of NPVs, the expected NPV, expected NPV,  NPV NPV, and CV , and CVNPV NPV. . • Gives an intuitive graph of the Gives an intuitive graph of the risk situation. risk situation.
  • 54.
    What are thedisadvantages of What are the disadvantages of simulation simulation ? ?  Difficult to specify probability distributions Difficult to specify probability distributions and correlations. and correlations.  If inputs are bad, output will be bad: If inputs are bad, output will be bad: “Garbage in, garbage out.” “Garbage in, garbage out.”
  • 55.
    • Sensitivity, scenario,and simulation analyses do Sensitivity, scenario, and simulation analyses do not provide a decision rule. They do not indicate not provide a decision rule. They do not indicate whether a project’s expected return is sufficient to whether a project’s expected return is sufficient to compensate for its risk. compensate for its risk. • Sensitivity, scenario, and simulation analyses all Sensitivity, scenario, and simulation analyses all ignore diversification. Thus they measure only ignore diversification. Thus they measure only stand-alone risk, which may not be the most stand-alone risk, which may not be the most relevant risk in capital budgeting. relevant risk in capital budgeting.
  • 56.
    If the firm’saverage project has a CV If the firm’s average project has a CV of 0.2 to 0.4, is this a high-risk project? of 0.2 to 0.4, is this a high-risk project? What type of risk is being measured What type of risk is being measured ? ? • CV from scenarios = 0.74, CV from CV from scenarios = 0.74, CV from simulation = 0.62. Both are > 0.4, this project simulation = 0.62. Both are > 0.4, this project has high risk. has high risk. • CV measures a project’s stand-alone risk. CV measures a project’s stand-alone risk. • High stand-alone risk usually indicates high High stand-alone risk usually indicates high corporate and market risks. corporate and market risks.
  • 57.
    With a 3%risk adjustment, should With a 3% risk adjustment, should our project be accepted our project be accepted ? ? • Project r = 10% + 3% = 13%. Project r = 10% + 3% = 13%. • That’s 30% above base r. That’s 30% above base r. • NPV = $65,371. NPV = $65,371. • Project remains acceptable after accounting for Project remains acceptable after accounting for differential (higher) risk. differential (higher) risk.
  • 58.
    Should subjective riskfactors Should subjective risk factors be considered be considered ? ? • Yes. A numerical analysis may not capture Yes. A numerical analysis may not capture all of the risk factors inherent in the project. all of the risk factors inherent in the project. • For example, if the project has the potential For example, if the project has the potential for bringing on harmful lawsuits, then it for bringing on harmful lawsuits, then it might be riskier than a standard analysis might be riskier than a standard analysis would indicate. would indicate.