Ofgem is introducing competitive tendering for new, high-value onshore electricity transmission projects starting in 2017. Competitively Appointed Transmission Owners (CATOs) will construct, own, and operate transmission assets under 25-year fixed revenue agreements. Eligible projects must be new, separable from existing networks, and over £100 million in capital expenditure. CATO revenue will include incentives for timely completion and availability. Conflicts of interest for incumbent transmission owners bidding on projects will be mitigated by separation, conduct restrictions, and oversight. The first CATO tenders are expected in 2017 for strategic wider works projects not covered by existing price controls.
Meridian 3: autonomous highway, rural and parking test facilities: Competitio...KTN
The Centre for Connected and Autonomous Vehicles (CCAV) will invest up to £25 million in partnership with Meridian Mobility and Innovate UK, part of UK Research and Innovation. This is to develop CAV testing infrastructure for autonomous parking and autonomous driving on rural roads and highways.
View the webcast here: https://www.youtube.com/watch?v=u_4FC5mQ374
Or find out more: https://ktn-uk.co.uk/funding/meridian-3-autonomous-highway-rural-and-parking-test-facilities
The document discusses the UK government's plans to replace Renewable Obligation Certificates (ROCs) with Contracts for Difference (CfDs) as the main policy mechanism for supporting renewable energy projects. CfDs are 15-year contracts that pay generators the difference between the market price of electricity and a guaranteed strike price. The document outlines eligibility requirements for CfDs and the allocation process, including indicative budgets, application deadlines, and obligations for projects before commissioning. CfDs are intended to provide long-term price stability for renewable projects while allowing generators flexibility in their power purchase agreements.
Applying for contracts for difference when the application window commences on 14 October. Details on Allocation Framework and draft allocation regulations from the UK Government and as published on DECC's website.
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Harish Sharma
This document provides guidelines for the implementation of 2000 MW of grid-connected solar PV power projects under Phase II, Batch III of India's Jawaharlal Nehru National Solar Mission (JNNSM). The key points are:
1) SECI will be the implementing agency and will issue Requests for Selection to develop these projects through a competitive bidding process in various states.
2) Projects will be set up either in solar parks being developed by state agencies or on land arranged by developers, and must be a minimum of 10 MW in size.
3) Developers will be provided viability gap funding of up to Rs. 1 crore/MW based on the funding amount they bid for their project.
Developers have several potential next steps in response to the UK government's proposal to introduce contracts for difference (CfDs) for solar plants over 5MW starting April 1, 2015. These include: 1) Setting up framework agreements with main equipment suppliers; 2) Mechanizing the CfD application process for project pipelines of 50-200MW; and 3) Organizing "shovel ready" development packs with all rights and approvals in place. Developers may also look to aggregate resources with funders, manufacturers, and O&M providers to form larger solar companies that can more easily obtain CfDs and financing. The government aims to limit spending on solar and may take time to approve very large CfD applications
STEP on the Bus - Session 4.2 - OLEV Low Emission Bus Scheme_Gloria EspositoSTEP_scotland
The document summarizes the new Low Emission Bus (LEB) Scheme introduced by the Office of Low Emission Vehicles (OLEV) to increase the uptake of low and ultra-low emission buses in England and Wales from 2015 to 2020. The LEB Scheme will provide £30 million in grants to support the purchase of accredited low emission buses and associated infrastructure. Bids for funding will be assessed based on their ambition, deliverability, impact on air quality, and value for money. To qualify for grants, bus manufacturers must certify that vehicles meet emissions reduction targets through testing and certification.
Burness NHS Procurement Seminar - 30 March 2010Elaine Creamer
How does the NHS ensure that it obtains best value when procuring its construction needs? No doubt this will be a question that will increasingly concern the NHS should they be called upon to bear a share of the widely anticipated cuts in public spending.
Over the last 18 months, the NHS has sought to achieve best value through the application of Frameworks Scotland. HFS Frameworks Scotland operates on a design and build basis along with a target cost payment mechanism. Will HFS Frameworks Scotland always be the most appropriate way to procure the construction needs of the
NHS? Can local frameworks be used to procure projects for which Frameworks Scotland is not suitable? Burness, with the assistance of procurement specialists within the NHS and the private sector, will be offering answers to these questions.
Frameworks are no longer the only option for the NHS and a new era of the hub is now dawning. How will hub operate and how will it interact with national and local frameworks? Burness, as legal advisors to the hub South East Territory, is ideally placed to offer views of these important issues.
Does the permitting process in France need a further overhaul?BVG Associates
Presentation given by Mike Blanch and Clare Davis at MRE Manche in October 2015 on the permitting process in France and comparing it with other countries
Meridian 3: autonomous highway, rural and parking test facilities: Competitio...KTN
The Centre for Connected and Autonomous Vehicles (CCAV) will invest up to £25 million in partnership with Meridian Mobility and Innovate UK, part of UK Research and Innovation. This is to develop CAV testing infrastructure for autonomous parking and autonomous driving on rural roads and highways.
View the webcast here: https://www.youtube.com/watch?v=u_4FC5mQ374
Or find out more: https://ktn-uk.co.uk/funding/meridian-3-autonomous-highway-rural-and-parking-test-facilities
The document discusses the UK government's plans to replace Renewable Obligation Certificates (ROCs) with Contracts for Difference (CfDs) as the main policy mechanism for supporting renewable energy projects. CfDs are 15-year contracts that pay generators the difference between the market price of electricity and a guaranteed strike price. The document outlines eligibility requirements for CfDs and the allocation process, including indicative budgets, application deadlines, and obligations for projects before commissioning. CfDs are intended to provide long-term price stability for renewable projects while allowing generators flexibility in their power purchase agreements.
Applying for contracts for difference when the application window commences on 14 October. Details on Allocation Framework and draft allocation regulations from the UK Government and as published on DECC's website.
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Harish Sharma
This document provides guidelines for the implementation of 2000 MW of grid-connected solar PV power projects under Phase II, Batch III of India's Jawaharlal Nehru National Solar Mission (JNNSM). The key points are:
1) SECI will be the implementing agency and will issue Requests for Selection to develop these projects through a competitive bidding process in various states.
2) Projects will be set up either in solar parks being developed by state agencies or on land arranged by developers, and must be a minimum of 10 MW in size.
3) Developers will be provided viability gap funding of up to Rs. 1 crore/MW based on the funding amount they bid for their project.
Developers have several potential next steps in response to the UK government's proposal to introduce contracts for difference (CfDs) for solar plants over 5MW starting April 1, 2015. These include: 1) Setting up framework agreements with main equipment suppliers; 2) Mechanizing the CfD application process for project pipelines of 50-200MW; and 3) Organizing "shovel ready" development packs with all rights and approvals in place. Developers may also look to aggregate resources with funders, manufacturers, and O&M providers to form larger solar companies that can more easily obtain CfDs and financing. The government aims to limit spending on solar and may take time to approve very large CfD applications
STEP on the Bus - Session 4.2 - OLEV Low Emission Bus Scheme_Gloria EspositoSTEP_scotland
The document summarizes the new Low Emission Bus (LEB) Scheme introduced by the Office of Low Emission Vehicles (OLEV) to increase the uptake of low and ultra-low emission buses in England and Wales from 2015 to 2020. The LEB Scheme will provide £30 million in grants to support the purchase of accredited low emission buses and associated infrastructure. Bids for funding will be assessed based on their ambition, deliverability, impact on air quality, and value for money. To qualify for grants, bus manufacturers must certify that vehicles meet emissions reduction targets through testing and certification.
Burness NHS Procurement Seminar - 30 March 2010Elaine Creamer
How does the NHS ensure that it obtains best value when procuring its construction needs? No doubt this will be a question that will increasingly concern the NHS should they be called upon to bear a share of the widely anticipated cuts in public spending.
Over the last 18 months, the NHS has sought to achieve best value through the application of Frameworks Scotland. HFS Frameworks Scotland operates on a design and build basis along with a target cost payment mechanism. Will HFS Frameworks Scotland always be the most appropriate way to procure the construction needs of the
NHS? Can local frameworks be used to procure projects for which Frameworks Scotland is not suitable? Burness, with the assistance of procurement specialists within the NHS and the private sector, will be offering answers to these questions.
Frameworks are no longer the only option for the NHS and a new era of the hub is now dawning. How will hub operate and how will it interact with national and local frameworks? Burness, as legal advisors to the hub South East Territory, is ideally placed to offer views of these important issues.
Does the permitting process in France need a further overhaul?BVG Associates
Presentation given by Mike Blanch and Clare Davis at MRE Manche in October 2015 on the permitting process in France and comparing it with other countries
Submarine cables structuring and financing optionsAmy Walls
This document discusses structuring and financing options for submarine cable projects. It begins by outlining typical funding requirements, including capital expenditures for cable building pre- and post-ready for service dates, as well as ongoing operational expenditures. It then examines approaches for selecting and managing stakeholders, including potential partner types and analyzing their power and interests. Different ownership structures like private, consortium and public-private partnerships are overviewed. The document concludes by discussing financing options such as project financing, vendor financing and pre-sales.
FERC Order 1000, issued in 2011, requires transmission providers to participate in regional transmission planning processes, consider public policy requirements, remove rights of first refusal for transmission development, improve coordination between transmission planning regions, establish requirements for merchant transmission developers, and implement new cost allocation methods within 12-18 months. The order aimed to promote more efficient transmission planning, development and cost allocation to address the growing need for transmission infrastructure to integrate renewable energy and address reliability concerns.
This document outlines the steps and recommendations for implementing Localizer Performance with Vertical guidance (LPV) procedures using the European Geostationary Navigation Overlay Service (EGNOS). It describes the process for air navigation service providers and airports, which includes meeting with national authorities, conducting airport assessments and procedure designs, flight validations, safety assessments, approvals, and air traffic controller training. It also provides recommendations for aircraft operators regarding certification, installing updates, and obtaining operational approval. The European Satellite Services Provider (ESSP) offers support through guidance materials, workshops, and technical advice to help stakeholders successfully implement LPV procedures.
This document summarizes capacity allocation in gas transmission auctions in Central and Southeast Europe. It provides an overview of the phased implementation of the Capacity Allocation Mechanisms Network Code (CAM NC) by FGSZ, the major transmission system operator in Hungary, including the creation of the Regional Booking Platform (RBP) covering eight transmission system operators across seven EU member states. It also discusses challenges faced in the region related to incompatible domestic legislation and regulations, and analyzes results from regular annual auctions and within-day auctions on the RBP. Finally, it covers incremental capacity processes and long-term booking challenges in Central and Southeast Europe.
Using ppps on projects that involve significant changes during the term - DLA...John Smith
Overview:
Using PPPs on projects that will involve significant changes during the term
• Many recent rail projects were delivered as PPPs
• In each case extensions were contemplated
• But the PPP model is known to be inflexible
• So, why was the PPP model used?
• What challenges did the PPP model create?
• Solutions
• Questions
Ofcom's review identifies several issues with the current public service broadcasting (PSB) model in the UK and proposes some solutions to prepare PSB for the digital future:
1. The costs of ITV1, ITV Wales, ITV Scotland, and Five will likely exceed the benefits by 2009-2012, making it rational for them to return their licenses.
2. Channel 4 will face a significant financial shortfall of £330-420 million per year by 2012 that requires a new economic model and funding solution.
3. Both institutions like the BBC and competitive funding could play important roles in the future by enhancing reach, values, independence, flexibility, and efficiency.
4. In the short term,
The document summarizes the organization of the TV broadcast industry. It discusses four key aspects:
1. Production includes local production by stations using their own equipment to produce daily newscasts, local sports, interviews, and public affairs shows. Networks also produce content available to affiliates and independent producers create syndicated programs.
2. Distribution involves broadcast networks, satellite networks, and syndication companies leasing or distributing tapes, films, and other programs to local TV stations.
3. Exhibition discusses how content is delivered to viewers through cable systems, independent stations, and the business models of commercial TV stations that earn revenue from advertisers and non-commercial TV stations that earn revenue through other means.
4
Small scale LNG projects and solutions were discussed, specifically the Poseidon Med II case. Key points included:
- The Poseidon Med II project connects Greece, Italy and Cyprus through LNG bunkering operations, involving 3 countries, 6 ports, 26 partners and a budget of €53M.
- Technical studies conducted include hazard identification studies, navigational simulations, and regulatory gap analyses to establish guidelines for bunkering safety.
- Training and developing the regulatory framework is important, working with relevant ministries on national and international legislation regarding transportation and handling of dangerous goods.
- Quality assurance and standards for LNG composition need to be further developed.
Capacity charging mechanism for shared CO2 transportation and storage infrast...Global CCS Institute
This webinar discussed capacity charging mechanisms for shared carbon dioxide (CO2) transportation and storage infrastructure. It covered four key parts:
1) Background on third party access and a hypothetical case study.
2) Statement of connection charges methodology with example calculations.
3) Statement of shared system charging methodology including different cost allocation options between charges.
4) Associated topics like allocating costs to multiple users depending on capacity.
The webinar explained how capacity charging mechanisms can influence the development of CCUS by affecting investment and use of shared infrastructure. Legal and regulatory frameworks were also noted as major influences on the design of these mechanisms.
The document outlines Greece's alternative measures for further liberalizing its wholesale electricity generation market, including lignite-fired power plants. Key points include:
1. Greece will make 40% of PPC's lignite generation capacity available to third parties by 2015 through a combination of structural measures transferring ownership of plants and transitory measures granting short-term rights to unused capacity.
2. By 2012, 900MW of capacity will be made available, with 457MW through structural measures like long-term ownership transfers and 443MW through transitory rights to unused plant capacity.
3. A monitoring trustee will oversee the process and report annually to the European Commission on compliance with liberalization targets.
Over-The-Top (OTT) video delivery uses third-party content delivery networks to stream video over the internet. YouTube is a popular free OTT service, and the proliferation of internet-connected devices has increased complex, multi-screen video consumption. As a result, video delivery is shifting from pay TV operators and set-top boxes to content owners and many different devices. For pay TV operators, OTT poses a threat as subscribers may opt for OTT services instead. To remain relevant, pay TV operators should acquire content, ensure high quality of service, expand beyond set-top boxes with OTT apps, and provide a unified subscription for viewing on multiple devices and screens.
PIA is part of Openreach's DPA program that allows communication providers (CPs) to use Openreach's physical infrastructure like ducts and poles to facilitate fiber network rollouts. Using PIA can reduce capital expenditures per premise by 25-60% while allowing for faster and less disruptive deployments with higher yields. PIA is estimated to provide around 70% availability across the UK. While PIA products and pricing are well advanced, some ambiguities remain such as draft caps proposed for enablement work of £4-6k per kilometer. CPs can select contractors to complete enablement work or work directly with Openreach. Openreach reference offers are due by end of 2017 with a complete PIA
This document summarizes the findings of a study on developing innovative financing solutions for the deployment of ERTMS in Europe. Key points:
1) There is a large funding gap (€430 billion) for rail projects in Europe through 2030, far exceeding available funds (€24 billion) from the Connecting Europe Facility.
2) Grants from the CEF are insufficient to fully deploy ERTMS by 2030 as required. Innovative financing is needed to complement grants.
3) The study examined potential business models and financing schemes, including public-private partnerships, to attract private investment in ERTMS deployment across infrastructure and rolling stock.
4) Corridor-level analysis
This document discusses options for international auctions of renewable energy in the EU. It analyzes two options: 1) reciprocally opened auctions where countries open their national auctions to installations in other countries, and 2) common auctions where two or more countries hold an auction together. Common auctions require more coordination but are more scalable. The document also presents a case study of a potential common auction between Portugal and Belgium and provides recommendations for the new RES Directive regarding auction design elements and international cooperation.
This document proposes delivering High Speed 2 for £39 billion by establishing a guaranteed maximum price and using innovative project delivery methods. It involves sharing risks and potential savings between the project team and government. The project team would keep 50% of any savings and the other 50% would go to a third party trust fund. The delivery approach aims to complete routes and trains within 6 years using lean management practices and a capped workforce of 1,000.
Ownership and Economics of SSDAB - SSDAB & Community Radio: Past, Present, & ...CMA_Slides
SSDAB & Community Radio: Past, Present, & Future
University of Bedfordshire, Luton - Saturday 25th March, 11am-4pm
This free event was for community radio stations, commercial radio broadcasters and individuals interested in small-scale digital audio broadcasting (SSDAB) and community media.
Assessment of Offshore Transmission Tender Round 1 benefits (2014)CEPA Ltd
Ofgem has published their conclusions on the consultation relating to the evaluation of Offshore Transmission Owners (OFTO) Tender Round One (TR1). The consultation was based on a report by CEPA and BDO which assessed the benefits that TR1 may have created. Ofgem’s conclusions paper followed a workshop where CEPA presented the report to stakeholders and comments on the report were subsequently fed back to Ofgem.
This document provides Network Rail's CP5 Enhancements Delivery Plan, setting out the projects, funds, and milestones they are committed to delivering between 2014-2019. Key points include:
- The plan was developed based on the Route Utilization Strategies, High Level Output Specifications from DfT and Transport Scotland, and the ORR's Final Determination.
- There are several categories of projects including committed projects specified in the HLOSs, investment funds where Network Rail must deliver authorized schemes, and other electrification, capacity, and airport/port access projects.
- Traction power supply enhancements are also needed to support service changes. Network Rail will take a more strategic approach through National
Submarine cables structuring and financing optionsAmy Walls
This document discusses structuring and financing options for submarine cable projects. It begins by outlining typical funding requirements, including capital expenditures for cable building pre- and post-ready for service dates, as well as ongoing operational expenditures. It then examines approaches for selecting and managing stakeholders, including potential partner types and analyzing their power and interests. Different ownership structures like private, consortium and public-private partnerships are overviewed. The document concludes by discussing financing options such as project financing, vendor financing and pre-sales.
FERC Order 1000, issued in 2011, requires transmission providers to participate in regional transmission planning processes, consider public policy requirements, remove rights of first refusal for transmission development, improve coordination between transmission planning regions, establish requirements for merchant transmission developers, and implement new cost allocation methods within 12-18 months. The order aimed to promote more efficient transmission planning, development and cost allocation to address the growing need for transmission infrastructure to integrate renewable energy and address reliability concerns.
This document outlines the steps and recommendations for implementing Localizer Performance with Vertical guidance (LPV) procedures using the European Geostationary Navigation Overlay Service (EGNOS). It describes the process for air navigation service providers and airports, which includes meeting with national authorities, conducting airport assessments and procedure designs, flight validations, safety assessments, approvals, and air traffic controller training. It also provides recommendations for aircraft operators regarding certification, installing updates, and obtaining operational approval. The European Satellite Services Provider (ESSP) offers support through guidance materials, workshops, and technical advice to help stakeholders successfully implement LPV procedures.
This document summarizes capacity allocation in gas transmission auctions in Central and Southeast Europe. It provides an overview of the phased implementation of the Capacity Allocation Mechanisms Network Code (CAM NC) by FGSZ, the major transmission system operator in Hungary, including the creation of the Regional Booking Platform (RBP) covering eight transmission system operators across seven EU member states. It also discusses challenges faced in the region related to incompatible domestic legislation and regulations, and analyzes results from regular annual auctions and within-day auctions on the RBP. Finally, it covers incremental capacity processes and long-term booking challenges in Central and Southeast Europe.
Using ppps on projects that involve significant changes during the term - DLA...John Smith
Overview:
Using PPPs on projects that will involve significant changes during the term
• Many recent rail projects were delivered as PPPs
• In each case extensions were contemplated
• But the PPP model is known to be inflexible
• So, why was the PPP model used?
• What challenges did the PPP model create?
• Solutions
• Questions
Ofcom's review identifies several issues with the current public service broadcasting (PSB) model in the UK and proposes some solutions to prepare PSB for the digital future:
1. The costs of ITV1, ITV Wales, ITV Scotland, and Five will likely exceed the benefits by 2009-2012, making it rational for them to return their licenses.
2. Channel 4 will face a significant financial shortfall of £330-420 million per year by 2012 that requires a new economic model and funding solution.
3. Both institutions like the BBC and competitive funding could play important roles in the future by enhancing reach, values, independence, flexibility, and efficiency.
4. In the short term,
The document summarizes the organization of the TV broadcast industry. It discusses four key aspects:
1. Production includes local production by stations using their own equipment to produce daily newscasts, local sports, interviews, and public affairs shows. Networks also produce content available to affiliates and independent producers create syndicated programs.
2. Distribution involves broadcast networks, satellite networks, and syndication companies leasing or distributing tapes, films, and other programs to local TV stations.
3. Exhibition discusses how content is delivered to viewers through cable systems, independent stations, and the business models of commercial TV stations that earn revenue from advertisers and non-commercial TV stations that earn revenue through other means.
4
Small scale LNG projects and solutions were discussed, specifically the Poseidon Med II case. Key points included:
- The Poseidon Med II project connects Greece, Italy and Cyprus through LNG bunkering operations, involving 3 countries, 6 ports, 26 partners and a budget of €53M.
- Technical studies conducted include hazard identification studies, navigational simulations, and regulatory gap analyses to establish guidelines for bunkering safety.
- Training and developing the regulatory framework is important, working with relevant ministries on national and international legislation regarding transportation and handling of dangerous goods.
- Quality assurance and standards for LNG composition need to be further developed.
Capacity charging mechanism for shared CO2 transportation and storage infrast...Global CCS Institute
This webinar discussed capacity charging mechanisms for shared carbon dioxide (CO2) transportation and storage infrastructure. It covered four key parts:
1) Background on third party access and a hypothetical case study.
2) Statement of connection charges methodology with example calculations.
3) Statement of shared system charging methodology including different cost allocation options between charges.
4) Associated topics like allocating costs to multiple users depending on capacity.
The webinar explained how capacity charging mechanisms can influence the development of CCUS by affecting investment and use of shared infrastructure. Legal and regulatory frameworks were also noted as major influences on the design of these mechanisms.
The document outlines Greece's alternative measures for further liberalizing its wholesale electricity generation market, including lignite-fired power plants. Key points include:
1. Greece will make 40% of PPC's lignite generation capacity available to third parties by 2015 through a combination of structural measures transferring ownership of plants and transitory measures granting short-term rights to unused capacity.
2. By 2012, 900MW of capacity will be made available, with 457MW through structural measures like long-term ownership transfers and 443MW through transitory rights to unused plant capacity.
3. A monitoring trustee will oversee the process and report annually to the European Commission on compliance with liberalization targets.
Over-The-Top (OTT) video delivery uses third-party content delivery networks to stream video over the internet. YouTube is a popular free OTT service, and the proliferation of internet-connected devices has increased complex, multi-screen video consumption. As a result, video delivery is shifting from pay TV operators and set-top boxes to content owners and many different devices. For pay TV operators, OTT poses a threat as subscribers may opt for OTT services instead. To remain relevant, pay TV operators should acquire content, ensure high quality of service, expand beyond set-top boxes with OTT apps, and provide a unified subscription for viewing on multiple devices and screens.
PIA is part of Openreach's DPA program that allows communication providers (CPs) to use Openreach's physical infrastructure like ducts and poles to facilitate fiber network rollouts. Using PIA can reduce capital expenditures per premise by 25-60% while allowing for faster and less disruptive deployments with higher yields. PIA is estimated to provide around 70% availability across the UK. While PIA products and pricing are well advanced, some ambiguities remain such as draft caps proposed for enablement work of £4-6k per kilometer. CPs can select contractors to complete enablement work or work directly with Openreach. Openreach reference offers are due by end of 2017 with a complete PIA
This document summarizes the findings of a study on developing innovative financing solutions for the deployment of ERTMS in Europe. Key points:
1) There is a large funding gap (€430 billion) for rail projects in Europe through 2030, far exceeding available funds (€24 billion) from the Connecting Europe Facility.
2) Grants from the CEF are insufficient to fully deploy ERTMS by 2030 as required. Innovative financing is needed to complement grants.
3) The study examined potential business models and financing schemes, including public-private partnerships, to attract private investment in ERTMS deployment across infrastructure and rolling stock.
4) Corridor-level analysis
This document discusses options for international auctions of renewable energy in the EU. It analyzes two options: 1) reciprocally opened auctions where countries open their national auctions to installations in other countries, and 2) common auctions where two or more countries hold an auction together. Common auctions require more coordination but are more scalable. The document also presents a case study of a potential common auction between Portugal and Belgium and provides recommendations for the new RES Directive regarding auction design elements and international cooperation.
This document proposes delivering High Speed 2 for £39 billion by establishing a guaranteed maximum price and using innovative project delivery methods. It involves sharing risks and potential savings between the project team and government. The project team would keep 50% of any savings and the other 50% would go to a third party trust fund. The delivery approach aims to complete routes and trains within 6 years using lean management practices and a capped workforce of 1,000.
Ownership and Economics of SSDAB - SSDAB & Community Radio: Past, Present, & ...CMA_Slides
SSDAB & Community Radio: Past, Present, & Future
University of Bedfordshire, Luton - Saturday 25th March, 11am-4pm
This free event was for community radio stations, commercial radio broadcasters and individuals interested in small-scale digital audio broadcasting (SSDAB) and community media.
Assessment of Offshore Transmission Tender Round 1 benefits (2014)CEPA Ltd
Ofgem has published their conclusions on the consultation relating to the evaluation of Offshore Transmission Owners (OFTO) Tender Round One (TR1). The consultation was based on a report by CEPA and BDO which assessed the benefits that TR1 may have created. Ofgem’s conclusions paper followed a workshop where CEPA presented the report to stakeholders and comments on the report were subsequently fed back to Ofgem.
This document provides Network Rail's CP5 Enhancements Delivery Plan, setting out the projects, funds, and milestones they are committed to delivering between 2014-2019. Key points include:
- The plan was developed based on the Route Utilization Strategies, High Level Output Specifications from DfT and Transport Scotland, and the ORR's Final Determination.
- There are several categories of projects including committed projects specified in the HLOSs, investment funds where Network Rail must deliver authorized schemes, and other electrification, capacity, and airport/port access projects.
- Traction power supply enhancements are also needed to support service changes. Network Rail will take a more strategic approach through National
Economics of Electricity Transmission Line Rehabilitation Investments Sener Salci
The analytical challenges in evaluating the impacts of transmission line investments have vexed practitioners and electricity market regulators. The purpose of this study is to provide a guideline for improving the accuracy and predictability of the impacts of electricity rehabilitation projects. The subject is too broad to address completely here. The proposed guideline is suitable for evaluations of such project implemented in a broken electricity network. In such case, the demand for electricity is deterred, the supply of the electricity is unreliable, and the system is far away from its least-cost optimum production/consumption level. The guideline does not rebut the catalog of existing evaluation models or approaches. The guideline utilizes them for a reasonable ex-ante assessment to identify “good” projects that satisfy the economic and public objectives of the economy. An integrated cost-benefit analysis (CBA) framework is recommended to appraise such projects along with allocating the impacts to stakeholders in a manner that is commensurate with the net benefits they receive. Such an integrated analysis is much more than a set of procedures for estimating the expected net present values or rates of return of the project.
The document provides information on key agreements and contract structures for solar photovoltaic rooftop projects, including power purchase agreements. It discusses the main components and considerations for engineering, procurement, and construction contracts; power purchase agreements between developers and off-takers; and rooftop lease agreements. The document also presents a case study of agreements for solar projects with Indian Railways and summarizes various contract relationships and components to address in lease and power purchase agreements for solar rooftop projects.
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission ProjectsAmitava Nag
As per Para 5.3 of Tariff Policy 2016, intra-state transmission projects shall be developed by the State Governments through competitive bidding process for projects costing above a threshold limit which shall be decided by the State Commissions. State has been given option either to use VGF based MTA document of Planning Commission or the Standard Bidding Document of Ministry of Power for procurement of intra-state transmission services. For the VGF based bidding, the unitary charges will require to be approved by the State Commissions prior to bidding. The above said guidelines are for procurement of transmission services to select transmission service provider for a new transmission line. A transmission charges for providing transmission service and O&M required for the various transmission elements shall form the basis for bidding. Under the MTA, it has been decided that the prospective bidders would be awarded projects on the basis of lowest grant sought or highest premium offered.
UK is at the forefront of 5G technology and pursue to become a leader in due course. These slides summarize some of the key policies of UK government and its affiliated institutions.
The document discusses models and funding schemes for Mediterranean electricity interconnectors projects. It recommends:
1) Seeking diversified funding from multilateral lenders to trigger further investment and considering Euro Project Bonds.
2) Securing long-term electricity transmission contracts through purchasing groups to obtain necessary financing.
3) Implementing appropriate public-private partnerships between northern and southern project companies to optimize funding.
4) Preparing an international agreement for political commitment and stable regulation to support projects over 50-70 years.
The document introduces the Bulgarian version of the FAC-1 Framework Alliance Contract and discusses its benefits. It summarizes that a framework alliance can link success in meeting agreed targets to rewarding members through incentives like additional work. It provides examples of how alliances in the UK Ministry of Justice and local government achieved savings through improved collaboration between members and with subcontractors/suppliers.
This document summarizes Gaz de France's response to the European Commission's Green Paper on energy policy. Some key points:
- Full implementation of unbundling between grids and energy trading is important, but ownership unbundling should not be mandatory as there is no clear evidence it improves performance.
- More harmonization of rules across Europe would benefit customers and companies operating across borders. A European regulator could help with harmonization and cross-border infrastructure projects.
- Investments in infrastructure need support, including exemptions for large cross-border projects. Long-term gas contracts are important for securing supply and should not be restricted.
- Energy efficiency, renewables and diversification should be encouraged
Submarine cables - Structuring and Financing Options Jan 2015_finalDominique Reverdy
- Submarine cable projects require large upfront capital expenditures for construction that are paid to manufacturers and contractors, as well as ongoing operational costs until revenue from capacity sales is generated.
- Typical construction timeframes are 1-3 years, though ready for service dates are often delayed from initial plans due to non-technical factors.
- Capital expenditures follow an S-curve with most spending occurring in the middle of construction, though actual payments can differ significantly from planned schedules.
The briefing at the following link explores the impact of the proposed changes to the renewable subsidy regime for solar facilities installed in England and Wales that are five (5) megawatts or larger in size ('Large-scale PV Plants') given the 13 May 2014 announcement from DECC ('URN 14D/114').
DECC have put forward that in their view the capacity threshold of gigawatts installed of Large-Scale PV Plants in England and Wales will be achieved by the solar development community (including funders, contractors and developers) by mid-2015 rather than by the earlier predicted threshold-achievement by mid-2017.
Given the predicted threshold-achievement by 2015, the portion of the Levy Control Framework budget for Large-Scale PV Plants accredited for ROCs will have to end in the UK Government's view in April 2015, rather than in April 2017, with the net result that contracts for difference ('CfDs') will have an earlier adoption date that coincides with the targeted curtailment of ROCs for PV Plants on 1.4.15 ('Cut-off-Date').
The non-progression of "grandfathering" of ROCs following the Cut-off-Date for plants already accredited for receipt of ROCs, and the likely impact of the key terms of the current form of CfD are explored in this article, together with brief discussion on the other proposals to tackle the early threshold-achievement that were considered by DECC and reported on in URN 14D/114.
Our team are ready to assist with preparation of responses to the Consultation due by 7.7.14.
The document discusses how regulation in the UK has evolved to incentivize electricity network companies to innovate in order to reduce future costs associated with increasing low carbon technologies. It outlines how Ofgem, the energy regulator, established various time-limited funding mechanisms like the Low Carbon Network Fund and Network Innovation Allowances to allow companies to trial innovative solutions. It also describes how the current regulatory framework, called RIIO, contains incentives for companies to deploy proven innovative solutions. The goal is that innovation funding and trials will provide learning benefits, add to solution toolkits, and inform future regulatory and market changes needed to facilitate wider roll-out of smart grids.
OECD review of the PPP governance framework in the United-Kingdom: preliminar...OECD Governance
The document summarizes the preliminary results of an OECD review of the UK's PPP governance framework. It finds that the UK has a comprehensive institutional framework for PPPs that aligns with OECD principles on transparency, value for money, and budgeting. Key aspects include the National Infrastructure Plan for prioritizing projects, guidance in the Green Book for evaluating delivery options, and transparency tools like the Whole of Government Accounts. The framework has evolved over time, with reforms through the PF2 model, but continues to provide integrity in the procurement process.
AVEVA ProCon FPSO Europe Congress 2016AVEVA ProCon
Rock, Paper, Scissors
A Case Study on complementing cost-savings with strong governance and capital discipline
A recent survey* of 9 FPSO projects identified a combined 38% cost overrun totaling $2.5bn in wasted capital. One of the identified causal factors behind this dead-weight additional capital was “a lack of clarity regarding contract responsibilities”.
8over8 presented a case study where efficiency gains were generated in the world’s first FLNG project by implementing a proven system of strong governance and commercial discipline. The result was connected decision making and reduced incidence of conflict and claims amongst stakeholders in the world’s first FLNG project.
*Source: Douglas Westwood“ FPSO Industry at a Crossroads”- An Industry Whitepaper
To request a free audit visit http://info.8over8.com/contact-us/capital-savings-review/
For more information, visit http://www.8over8.com/procon-overview/
FERC Order 1000: Understanding Transmission Planning in a New ParadigmDNVGLEnergy
FERC Order 1000 requires transmission providers to consider public policy and interregional coordination in transmission planning. It also requires removing rights of first refusal and implementing regional and interregional cost allocation methods. The presentation discusses how these principles have been implemented by transmission providers like SPP, MISO, CAISO and PJM through competitive bidding processes and direct sponsorship models for transmission project selection. It also outlines the qualification process for developers to participate and submit detailed project proposals for consideration in regional transmission plans.
Similar to CATOs-Opportunities-for-Onshore-Tranmission-final[1] (20)
2. CATOs
Opportunities in onshore transmission
Contents
The Opportunity 1
Eligibility 2
Paying for the CATO 3
Tender Models 5
Conflict Mitigation 6
Timetable for Implementation 7
Potential CATO Appointment Process 8
CATO Team 9
3. 1
CATOs – opportunities in onshore transmission
The Opportunity
Ofgem has proposed to introduce competitive tendering to new, high
value, separable onshore electricity transmission assets with the first
CATO tender expected to be run by Ofgem in 2017.
Only strategic wider works (large investment projects that are not part of
the price control settlement funding) will be included up to 31 March 2021
("SWW").
Competitively Appointed Transmission Owners ("CATOs") will receive a
25-year fixed revenue stream subject to certain incentives and adjustments
to construct, own and operate and, in the long-term, design transmission
projects.
Ofgem has run a series of consultations on CATOs since October 2015
and is currently consulting on the criteria and process for identifying when
a competitive tender can be run, the pre-tender arrangements, as well as
conflict mitigation measures
1
(the "Consultation"). The Consultation
closes on 22 July 2016.
Ofgem’s informal estimate of the potential size of the competitive
investment in respect of CATOs is one billion pounds (£1,000,000,000) to
one billion five hundred million pounds (£1,500,000,000) of projects per
annum during the period however the opportunity is widely anticipated to
eclipse Offshore Transmission Owner (OFTO) investment currently two
billion nine hundred and forty million pounds (£2,940,000)
2
.
Background
Great Britain’s onshore electricity transmission network is currently
planned, constructed, owned and operated by three monopoly
1
https://www.ofgem.gov.uk/system/files/docs/2016/05/ecit_may_2016_consultation_0.pdf
2
Data includes projects awarded in R1 to R4 OFTO
transmission owners ("TOs"): National Grid Electricity Transmission
("NGET") in England and Wales, SP Transmission in the south of
Scotland, and Scottish Hydro Electric Transmission in the north of
Scotland. NGET is also the system operator ("SO") for the whole of GB's
onshore and offshore transmission network.
These networks are natural monopolies and therefore Ofgem sets price
controls that allow the recovery of a reasonable return on investment in
addition to the companies’ costs, provided the TO's achieve the targets set
by Ofgem. The onshore TOs are currently regulated under the RIIO
(Revenue=Incentives + Innovation + Outputs) - T1 regime.
However, in March 2011 Ofgem introduced competition in the offshore
transmission sector by putting in place the OFTO regime. An independent
report commissioned by Ofgem (in August 2014) found that the OFTOs
had generated savings of two hundred million pounds (£200,000,000) to
four hundred million pounds (£400,000,000) (against one billion one
hundred million pounds (£1,100,000,000) worth of investment) across the
first nine projects against the counterfactual price-control regime (the
alternative policy options which Ofgem may have been expected to
implement in the absence of the adopted OFTO policy)
3
.
Following the success of the OFTO regime in generating savings, Ofgem
conducted its Integrated Transmission Planning and Regulation (ITPR)
project in September 2015, and set out its decision to extend the role of
competitive tendering to new, separable and high value onshore
transmission assets.
3
https://www.ofgem.gov.uk/ofgem-
publications/87717/cepabdotr1benefitsassessmentfinalreport.pdf
4. 2
CATOs – opportunities in onshore transmission
Eligibility
Projects Defined
Onshore transmission projects that are new, separable and high value will
be eligible for competitive tendering. A project is defined by Ofgem in the
Consultation document as an efficient package of works, or multiple
packages of work to be delivered together which have been identified to
meet a common need on the transmission system
4
("Project").
New, Separable and High Value
New- To be eligible, a transmission Project must be new - this would
include installation of brand new overhead lines, cables and sub-stations,
as well as the complete replacement of existing lines, cables and sub-
stations.
Separable- The Project must be separable from the existing transmission
network. Ofgem proposals do not require electrical separability (for
example, the use of a circuit breaker at each interface) in order for a
Project to be eligible to be tendered. The assets also do not need to be
directly and physically connected to each other in order to be tendered,
however they must form part of a coherent package. Interface
management issues are expected to be dealt with by way of commercial
negotiation as they are dealt with under the current system. Nevertheless,
under the proposals, the SO would be able to make a case for additional
electrical separability, if it can show a cost-benefit justification based on
system operability.
High Value- Ofgem intends to define high value as one hundred million
pounds (£100,000,000) or above of capital expenditure ("Capex"). Ofgem
believes that this level of value will ensure that the tendering benefits
outweigh the tender costs and will attract competitive market interest from
potential bidders.
4
Paragraph 2.31 of the Consultation document
During the RIIO-T1 period (2013-21)
Only SWW Projects will be eligible for competitive tendering during the
RIIO-T1 period until 2021. SWW Projects are large projects identified by
the SO for which funding has not been awarded to incumbent TOs as part
of the price control settlement. Projects that are covered by price
settlement funding are procured under EPC frameworks set up by NGET
5
.
The SO will be responsible for identifying SWW Projects (as well as
developing the needs case – i.e. whether there is a technical and
economic need for the SWW Project).
Once an SWW Project is approved, the relevant TOs will be funded to
complete pre-construction works under the Early Build Model, a CATO will
be appointed to undertake most of the Preliminary Works, which shall
include initial solution design, surveys, environmental impact assessments,
DCO and/or section 37 consents, easements, wayleaves, etc
("Preliminary Works").
Applications for construction funding will be submitted following completion
of Preliminary Works - once the need and costs for the SWW Project have
solidified. Ofgem is currently considering the suitability of the SWW
Projects proposed by the TOs.
From the start of RIIO-T2 (post 2021)
Ofgem anticipates that all new assets that meet the eligibility criteria will be
capable of being bid for CATOs from the start of RIIO –T2.
The SO is expected to be responsible for identifying eligible tender projects
based on the needs of the transmission system through a network options
assessment.
Ofgem will ultimately make the final decision, based on the SO’s analysis,
as to whether a tender should be held for a Project.
5
The Onshore Underground Cable Framework and The Overhead Lines Design & Build Framework
5. 3
CATOs – opportunities in onshore transmission
Paying for the CATO
Although Ofgem will determine the final market offering for a particular
CATO nearer the time of the tender based on project specifics and the
prevalent market conditions, the regulated revenue package and
incentives proposed for a CATO are as follows:
Fixed 25-year revenue term
The CATO's annual revenue for the construction and operation of the
assets will be fixed for a period of 25 years without any periodic reviews
subject to limited reopeners for construction and operations risks which
would not be economic and efficient for bidders to price into their bids.
Such risks could potentially include foreign exchange rates, movement in
base interest rates, unexpected ground conditions, extreme weather
events and financing costs beyond the commitment periods.
It is expected that this will allow other costs to be fixed and for bidders to
access a broad range of financing options as well as provide scope for
financial innovation. For very large assets or those with a very long
construction timetable, an exception may be made to allow partial revenue
generation.
Construction risk is an inherent part of the structure as the annual revenue
will only commence upon completion of construction to incentivise timely
asset delivery.
A proportion of revenue (to be proposed by the bidder in percentage
terms) will be index linked to inflation.
Residual Value and Impact of Financing
Consumers will pay for all the CATOs assets over the 45 year period
(consistent with the period for cost recovery under the RIIO price control).
The difference between the period of cost recovery from consumers and
the 25-year fixed revenue term, will mean that the CATO’s asset will be
allowed to partially depreciate over the 25-year fixed revenue term, leaving
a residual asset value ("RV").
Ofgem has proposed that the CATO's asset will have a regulatory RV
equal to the non-depreciated asset value, which is proposed to be set as a
percentage of their bid Capex. This will then be recovered from future
consumers.
This approach may require CATOs to use a bullet (or non-amortising) bond
to finance part of construction, which could limit financing options and
potentially drive up financing costs as a result. Ofgem also expects to
clarify the regulatory treatment of RV in order to allow CATOs to secure
debt finance for this portion of the costs and expects to make it subject to
any deductions (capped at 10 per cent of annual revenue) based on clearly
pre-agreed asset standards judged against clearly defined parameters
contained in potentially the CATO licence.
Upon expiry of the 25-year fixed revenue stream, a CATO’s assets may be
dealt with by Ofgem in accordance with any of the following four options:
Retendering and appointing a new CATO to take over the assets;
Extending the CATO’s revenue term for another fixed period;
Transferring the assets to an incumbent TO or potentially another
CATO at a price determined by Ofgem; or
Decommissioning the assets in the event they are no longer
required.
Ofgem will decide the appropriate option route nearer the time on
account of the fact that the transmission network is likely to
change significantly over the next few decades.
6. 4
CATO – opportunities in onshore transmission
Refinancing gain-share mechanism
The proposed refinancing gain-share mechanism will return a proportion of
any refinancing gain during the 25 year period to consumers.
A loss sharing mechanism is not however envisaged, as Ofgem does not
think that consumers should contribute to any refinancing losses incurred
by a CATO.
Availability based incentive
An incentive based on meeting a percentage availability target may be
offered (potentially with a capped upside and downside of annual revenue
for over- or underperformance) to secure system reliability (similar to the
position under OFTOs).
Ofgem proposes that up to 10 per cent of a CATO's annual revenue
should be at risk through underperformance against the contractual
availability threshold.
Other types of incentives
A mechanism to allow CATOs to make additional investments for upgrades
and extensions during the 25-year term.
Incentives may be also be offered to ensure asset condition at the end of
the revenue term – for example, by way of a performance bond or
retention fund, whereby a certain portion of a CATO’s revenue in the final
year(s) could be made contingent on the assets meeting the required
standard at the end of the revenue term.
7. 5
CATOs – opportunities in onshore transmission
Tender Models
Ofgem has proposed to develop two CATO tender models - the "Early
Build Model" and the "Late Build Model". The difference between the
two is the stage at which the tender process is run.
Under the early Build Model, a CATO will be appointed to undertake most
of the Preliminary Work whereas, under Late Build Model, the SO or TO
would complete all necessary Preliminary Works and Ofgem would run a
tender to appoint a CATO only for the construction and operation of the
Project.
In the short to medium term, Ofgem will adopt the Late Build Model as
RIIO-T1 SWW Projects are likely to be too far advanced for the first CATO
tender to be procured under the early build model. Ofgem also believes
that the Late Build Model is closer to existing public infrastructure
procurement models and therefore would initially be more attractive to
potential bidders.
The Early Build Model is expected to be used where the project design
could benefit from competition.
Ofgem has indicated that a Late Build Model tender will typically start
around four to five years before the assets are needed, whereas the period
would typically be around seven to nine years in the case of an Early Build
Model.
Other main differences between the two models include:
Under the Late Build Model, bidders would bid a fixed price for
construction and operation on the basis that they should have a high level
of certainty over the Project and its output requirements
6
.
6
There may be some limited cost re-openers for risks during construction and operation that would
mean that it would not be economic and efficient for a CATO to manage or for bidders to price into
their bids at the tender stage.
under the Early Build Model, bidders would bid a fixed return on equity, a
fixed gearing and an indicative cost of debt. This reflects the possibility that
the Project scope may change during the Preliminary Works period.
8. 6
CATOs – opportunities in onshore transmission
Conflict Mitigation
Ofgem has proposed that the incumbent TOs be allowed to compete
against third parties in the tender process to ensure a level playing field
between the bidders.
This requires mechanisms to prevent conflicts of interest arising from the
roles of the SO and existing TOs in relation to tendered Projects, or from
other bidders with knowledge of a Project.
The measures for addressing conflicts of interest in respect of bidders
other than SO and TOs mirror those that apply in case of the OFTO
regime.
Ofgem highlights that there is more risk of conflicts of interest arising in the
case of NGET given its role as SO and TO however conflict mitigation
measures that apply in relation to SOs will be proposed in due course
following Ofgem's wider work on the SO's role in relation to CATOs.
The Consultation document sets out Ofgem's proposals to address
conflicts of interest arising from the following:
the SO’s role in relation to onshore competition;
the TOs’ roles in relation to onshore competition, in particular
where a TO undertakes Preliminary Works for a tendered Project
in RIIO-T1; and
any other bidder with knowledge of a tendered Project.
Ofgem has proposed to address potential conflicts by placing the following
key obligations:
obligations on conduct: to act transparently, efficiently and in a way that
does not give the TO or any other party an undue advantage over other
participants in the CATO tender process;
business separation measures: TO bidding party's access to the
information should be the same as other participants, with clear division in
management responsibility and restrictions on employee involvement, and
physical financial, and legal separation between the TO Preliminary Works
team and the TO bidding party; and
scrutiny: Ofgem has proposed that at a minimum, there should be internal
scrutiny by a person appointed by the TO to oversee its compliance with
the conflict mitigation measures and independent scrutiny should be
considered.
Ofgem has proposed that a compliance methodology for approval should
be submitted by TOs before a tender - which covers the steps the TO has
taken in the three overarching areas of conduct, business separation and
scrutiny and defines the relationship between the TO Preliminary Works
team, the TO bidding party and any other relevant constituents of the TO.
It should also include a compliance statement and an undertaking on
arrangements that will apply during the tender.
9. 7
CATOs – opportunities in onshore transmission
Timetable for Implementation
Identification of CATO Projects
Further information regarding the SWW programme and some of the
Projects which may be taken forward under it can be found in this Ofgem
factsheet.
It is not yet clear which SWW Projects may be taken forward by way of
competitive tendering. Ofgem will decide whether to tender specific SWW
Projects once it has considered submissions by the existing TOs in relation
to the SWW Projects within their areas. In the medium to long term, the
SO will be responsible for identifying Projects for tendering however, the
final decision on tendering would lie with Ofgem.
Legislative Progress
On 21 January 2016, DECC published the draft primary legislation to be
used to implement CATOs in its Draft Legislation on Energy (the "Draft
Legislation").
On 3 May 2016 the House of Lords ("HOL") agreed in principle with the
proposals to introduce competitive tendering for certain onshore
transmission assets.
Draft clause 16 and the schedule to the Draft Legislation relate to
competitive tendering for onshore transmission and distribution licences
7
.
7
The Government has proposed extending the competitive tendering regime to distribution
networks as well, with a view to future proofing the Draft Legislation however this has been criticised
by the Energy Networks Association for not being in consideration of potential implications although
the Government has clarified that distribution assets will only be included in a competitive regime
after due consultation and in any event only post 2023 upon completion of the current distribution
price control period.
The proposed schedule amends the Electricity Act 1989, by inserting new
section 6CA, which changes the provisions for recovering costs after a
tender exercise (currently in section 6D). It broadens the class of potential
contributors to include those who had made a connection request in
relation to a previous tender exercise, and to existing licence holders.
The HOL have made the following recommendations to the Government:
That the differential impact in Scotland compared with England and Wales
be addressed to ensure a level playing field for transmission projects
throughout Great Britain;
That Ofgem should have to publish a Project-specific impact assessment
when it decides whether and how to tender an asset; and
That, the Government should set out how it will ensure the current
planning regime in Scotland does not prevent or delay the development of
competitively tendered Projects there.
Licence amendments
Ofgem intends to implement the revised roles and obligations on the SO
and TOs in respect of CATOs by raising modifications to their licences
following consultation. The modifications will cover the introduction of pre-
tender arrangements and conflict mitigation measures.
Ofgem is expected to progress proposals for TO licence modifications as a
priority following the Consultation (potentially summer 2016).
SO licence modifications to support onshore competition will be linked to
Ofgem's wider work on the future SO role (detailed proposals for
consultation are expected to be initiated next year with a view to
implementation by late 2017 or early 2018).
10. 8
CATOs – opportunities in onshore transmission
Potential CATO Appointment process
1. SO nominates Project and prepares the tender specification
based on system performance requirements and Preliminary
Works, including the parameters of any planning consent (in the
case of an Early Build Model, the SO will prepare a tender
specification setting out the system performance requirements
and bidders will set out their high-level asset design and
Development Consent Order (DCO) application, including
detailed route planning).
2. Ofgem approves Project nominated by SO, and validates the
Project scope and tender specification.
3. In case of a Late Build Model, the SO is funded to carry out
Preliminary Works.
4. Ofgem runs a competitive process with defined tender stages
and requirements which is accessible to range of funding
approaches.
5. Project specific bidding opens based on a 25 year revenue
stream.
6. Ofgem shortlists bidders based on evaluation of bidder's
technical and financial capability and issues ITT to shortlisted
bidders.
7. Ofgem evaluates tender offers against criteria covering
capability/deliverability, costs and robustness of offer.
8. Preferred bidder is granted a licence and acquires a fixed 25
year revenue stream subject to application of incentives and
adjustment s, and complying with licence obligations.
9. Ofgem oversees the finalisation of arrangements
between the preferred bidder and relevant TO to reach
financial close
11. 9
CATOs Team
For a further discussion of this note please contact the team below or your usual Nabarro partner.
CORE TEAM
CORE TEAM
James Snape
Partner
T +44 (0)20 7524 6804
j.snape@nabarro.com
Lucy Plowright
Partner
T +44 (0)20 7524 6779
l.plowright@nabarro.com
Aditi Tulpule
Associate
T +44 (0)20 7524 6364
a.tulpule@nabarro.com
Infrastructure, Construction and Energy Real Estate and Planning
Martin Evans
Partner
T +44 (0)20 7524 6950
m.evans@nabarro.com
Joshua Risso Gill
Partner
T +44 (0)20 7524 6124
j.risso-gill@nabarro.com
Chris Hallam
Partner
T +44 (0)161 393 4757
c.hallam@nabarro.com
Camilla Bolton
Associate
T +44 (0)20 7524 6467
c.bolton@nabarro.com
Ryan Fordham
Senior Associate
T +44 (0)20 7524 6956
r.fordham@nabarro.com
Priya Rawal
Associate
T +44 (0)20 7524 6365
p.rawal@nabarro.com
Christopher Bowes
Associate
T +44 (0)114 279 4006
c.bowes@nabarro.com