The warehouse has experienced 330 late shipments in the past 30 days, with over 142 late shipments coming from large orders consisting mostly of item A. These large orders cannot be picked within the allotted time as it currently takes 30 minutes to pick a large order. The goals of this project are to reduce order pick time for large orders from 30 minutes to 15 minutes by the end of the year, decrease shipping time from 4 days to 2 days in the warehouse by the end of the year, and improve on-time delivery to customers by 25% by the end of the year. Key stakeholders include the warehouse supervisor Jimmy Lois, the company president Shauna Walter, the director of warehousing Kemp Miller, and the VP of