SlideShare a Scribd company logo
Best Bidding Practices for
Project Owners
You can bring
a project in
on-time and
on-budget
The City of DeWitt, Iowa,
brought its 6th Avenue
project in under budget at a
final cost of $1.3 million.
Scope it Out
Never assume
Projects may be similar, but each has
a unique set of circumstances
Define uniqueness
The owner should actively work with the
engineering firm to determine:
◍ Project scope
◍ Preliminary design: emphasizes
drawings and cost estimate
◍ Final design: plans, specifications &
updated cost estimate
◍ Owner’s plans for specific area
◍ How does the project fit into the overall
Capital Improvement Plan?
Clinton, Iowa,
Lincolnway
project
Clinton’s air and rail park
called for a flexible lead rail
track design as funding
sources’ requirements
unfolded.
Options explored for
mitigation to the surrounding
wetlands brought the track in
10% under budget at $1.39
million
Ensure design & changes
are within budget
Estimate 3 times:
◍ Before design
◍ As initial design phase is complete
◍ Prior to bidding
Is your design team current with:
• Construction trends
• Potential bidders
• The bidding environment
• The vendors
• Unique aspects of the project
Research can influence
estimates
Create a Plan
Detailed
plans &
specs are
important
Build in quality metrics
Construction schedule options
affect pricing
Calendar days:
◍ Late start date
◍ Weather days allowed &
count as working days
◍ Can contractor fit “this”
into existing
commitments?
Working days:
◍ Late start date
◍ Charge a working day
only if weather is nice
◍ Completion date is more
variable
Bid letting (opening) schedule
affects pricing
◍ Roadway, utility & grading
contractors schedule their work
differently than building contractors
◍ Time of year makes a difference
◍ Outdoor projects are ideally let in
January & February when
contractors are eager to schedule
work for the entire year
Bid with schedule options to compare
cost of each schedule
Schedule & budget
both important?
Get a Quality Bid
Take the time to clearly
communicate so that:
◍ Contractors have the
same understanding of
the work
◍ Change orders will be
minimized
◍ You save money
Clear plans & specs
encourage more bidders
Designs should be specific, but not dictate
the solution.
◍ Allow the contractor to choose
approach to construction of the project
5 to 10% bid variance is optimal
Bids with low variance
indicates contractors
have the same
understanding of the
project
Research the outlier’s bid
Why is the bid so different?
◍ Different market pricing structure?
◍ Market is busy/not busy?
◍ Experience with owner?
◍ Experience with engineering firm?
Place your screenshot here
I’m happy to share ideas
Geoffry Blandin
563-823-0192
g.blandin@iiwengr.com
© 2015 IIW, P.C. All Rigts Reserved.

More Related Content

What's hot

Project manager responsibility overview
Project manager   responsibility overviewProject manager   responsibility overview
Project manager responsibility overview
Stephen Bryce Liebert, AIA
 
2016 2018 project manager - responsibility overview
2016 2018 project manager - responsibility overview2016 2018 project manager - responsibility overview
2016 2018 project manager - responsibility overview
Stephen Bryce Liebert, AIA
 
Michal Dimayuga1
Michal Dimayuga1Michal Dimayuga1
Michal Dimayuga1
Michal Dimayuga
 
Renovations ccf day 3
Renovations ccf day 3Renovations ccf day 3
Renovations ccf day 3
Adrian Drysdale
 
BBA 3310 Unit VII Assignment./
BBA 3310 Unit VII Assignment./BBA 3310 Unit VII Assignment./
BBA 3310 Unit VII Assignment./
BarryaCaa
 
Banking Proposal Bidding and response to RFP Presentation
Banking Proposal Bidding and response to RFP PresentationBanking Proposal Bidding and response to RFP Presentation
Banking Proposal Bidding and response to RFP Presentation
Harnoor Singh
 
Predicting HDB resale price in Singapore
Predicting HDB resale price in SingaporePredicting HDB resale price in Singapore
Predicting HDB resale price in Singapore
Valerie Lim
 
C.v_Ahmed Sobhy
C.v_Ahmed SobhyC.v_Ahmed Sobhy
C.v_Ahmed Sobhy
Ahmed sobhy
 
QS -MEP cv of S.Dutta 1-11-15 (1) (1)
QS -MEP cv of S.Dutta  1-11-15 (1) (1)QS -MEP cv of S.Dutta  1-11-15 (1) (1)
QS -MEP cv of S.Dutta 1-11-15 (1) (1)
Subhankar Dutta
 
Ur Home. Ur Choices
Ur Home. Ur ChoicesUr Home. Ur Choices
Ur Home. Ur Choices
Vel Foundation
 
BBA 3310 Unit VI Assignment
BBA 3310 Unit VI AssignmentBBA 3310 Unit VI Assignment
BBA 3310 Unit VI Assignment
BarryaCaa
 
Cs value 2
Cs value 2Cs value 2
Cs value 2
Matthew Voll
 
Construction Spotlight Value
Construction Spotlight ValueConstruction Spotlight Value
Construction Spotlight Value
Matthew Voll
 
Austyn Holderfield Resume 1
Austyn Holderfield Resume 1Austyn Holderfield Resume 1
Austyn Holderfield Resume 1
Austyn Holderfield
 
Scott M Tidwell Resume word document 030415
Scott M Tidwell Resume word document 030415Scott M Tidwell Resume word document 030415
Scott M Tidwell Resume word document 030415
Scott M. Tidwell, Sr.
 
السي في
السي فيالسي في
السي في
Hazem salah
 
Shawn resume in word 2
Shawn resume in word 2Shawn resume in word 2
Shawn resume in word 2
Shawn Gallant
 

What's hot (17)

Project manager responsibility overview
Project manager   responsibility overviewProject manager   responsibility overview
Project manager responsibility overview
 
2016 2018 project manager - responsibility overview
2016 2018 project manager - responsibility overview2016 2018 project manager - responsibility overview
2016 2018 project manager - responsibility overview
 
Michal Dimayuga1
Michal Dimayuga1Michal Dimayuga1
Michal Dimayuga1
 
Renovations ccf day 3
Renovations ccf day 3Renovations ccf day 3
Renovations ccf day 3
 
BBA 3310 Unit VII Assignment./
BBA 3310 Unit VII Assignment./BBA 3310 Unit VII Assignment./
BBA 3310 Unit VII Assignment./
 
Banking Proposal Bidding and response to RFP Presentation
Banking Proposal Bidding and response to RFP PresentationBanking Proposal Bidding and response to RFP Presentation
Banking Proposal Bidding and response to RFP Presentation
 
Predicting HDB resale price in Singapore
Predicting HDB resale price in SingaporePredicting HDB resale price in Singapore
Predicting HDB resale price in Singapore
 
C.v_Ahmed Sobhy
C.v_Ahmed SobhyC.v_Ahmed Sobhy
C.v_Ahmed Sobhy
 
QS -MEP cv of S.Dutta 1-11-15 (1) (1)
QS -MEP cv of S.Dutta  1-11-15 (1) (1)QS -MEP cv of S.Dutta  1-11-15 (1) (1)
QS -MEP cv of S.Dutta 1-11-15 (1) (1)
 
Ur Home. Ur Choices
Ur Home. Ur ChoicesUr Home. Ur Choices
Ur Home. Ur Choices
 
BBA 3310 Unit VI Assignment
BBA 3310 Unit VI AssignmentBBA 3310 Unit VI Assignment
BBA 3310 Unit VI Assignment
 
Cs value 2
Cs value 2Cs value 2
Cs value 2
 
Construction Spotlight Value
Construction Spotlight ValueConstruction Spotlight Value
Construction Spotlight Value
 
Austyn Holderfield Resume 1
Austyn Holderfield Resume 1Austyn Holderfield Resume 1
Austyn Holderfield Resume 1
 
Scott M Tidwell Resume word document 030415
Scott M Tidwell Resume word document 030415Scott M Tidwell Resume word document 030415
Scott M Tidwell Resume word document 030415
 
السي في
السي فيالسي في
السي في
 
Shawn resume in word 2
Shawn resume in word 2Shawn resume in word 2
Shawn resume in word 2
 

Viewers also liked

Infrastructure Finance – Building for Growth - Funding of Infrastructure Proj...
Infrastructure Finance – Building for Growth - Funding of Infrastructure Proj...Infrastructure Finance – Building for Growth - Funding of Infrastructure Proj...
Infrastructure Finance – Building for Growth - Funding of Infrastructure Proj...
Resurgent India
 
Get Commercial Building Construction Company Auburn by TopRung LLC
Get Commercial Building Construction Company Auburn by TopRung LLC  Get Commercial Building Construction Company Auburn by TopRung LLC
Get Commercial Building Construction Company Auburn by TopRung LLC
Top Rung - Building Contractors & Building Construction
 
Road construction, building construction company in noida
Road construction, building construction company in noidaRoad construction, building construction company in noida
Road construction, building construction company in noida
Sai Towers P Ltd.
 
OpenMinteD Project - building a TDM infrastructure
OpenMinteD Project - building a TDM infrastructureOpenMinteD Project - building a TDM infrastructure
OpenMinteD Project - building a TDM infrastructure
FutureTDM
 
Centralized monitoring station for it computing and network infrastructure1
Centralized monitoring station for it computing and network infrastructure1Centralized monitoring station for it computing and network infrastructure1
Centralized monitoring station for it computing and network infrastructure1
MOHD ARISH
 
Building Structure Project 2 report
Building Structure Project 2 reportBuilding Structure Project 2 report
Building Structure Project 2 report
Tan Jaden
 
Building construction project 1 report
Building construction project 1 reportBuilding construction project 1 report
Building construction project 1 reportchenliang923
 
Digital research infrastructure on European integration - CVCE Status report ...
Digital research infrastructure on European integration - CVCE Status report ...Digital research infrastructure on European integration - CVCE Status report ...
Digital research infrastructure on European integration - CVCE Status report ...
BackesMarianne
 
Building Construction Project 1 Report
Building Construction Project 1 ReportBuilding Construction Project 1 Report
Building Construction Project 1 Report
Sürayyn Selvan
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
Joshua Lee
 
Final year project on Remote Infrastructure Management
Final year project on Remote Infrastructure ManagementFinal year project on Remote Infrastructure Management
Final year project on Remote Infrastructure Management
jairaman
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
Anshul Shakya
 
An Analytical Analysis on Weighted Average Cost of Capital
An Analytical Analysis on Weighted Average Cost of CapitalAn Analytical Analysis on Weighted Average Cost of Capital
An Analytical Analysis on Weighted Average Cost of Capital
Rahmatullah Pashtoon
 
Global LNG bunkering infrastructure as of January 2014
Global LNG bunkering infrastructure as of January 2014Global LNG bunkering infrastructure as of January 2014
Global LNG bunkering infrastructure as of January 2014
Lars Petter Blikom
 
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORTBUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
Darshiini Vig
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
Sheau Hui Tan
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
L&W BUILDING SOLUTIONS PVT. LMT.
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
Abhishek Singh
 
Spencer's retail ltd. project report (summer internship project)
Spencer's retail ltd. project report (summer internship project)Spencer's retail ltd. project report (summer internship project)
Spencer's retail ltd. project report (summer internship project)
akgicbm
 
WIPRO PROJECT FILE
WIPRO PROJECT FILEWIPRO PROJECT FILE
WIPRO PROJECT FILE
Harsh Yadav
 

Viewers also liked (20)

Infrastructure Finance – Building for Growth - Funding of Infrastructure Proj...
Infrastructure Finance – Building for Growth - Funding of Infrastructure Proj...Infrastructure Finance – Building for Growth - Funding of Infrastructure Proj...
Infrastructure Finance – Building for Growth - Funding of Infrastructure Proj...
 
Get Commercial Building Construction Company Auburn by TopRung LLC
Get Commercial Building Construction Company Auburn by TopRung LLC  Get Commercial Building Construction Company Auburn by TopRung LLC
Get Commercial Building Construction Company Auburn by TopRung LLC
 
Road construction, building construction company in noida
Road construction, building construction company in noidaRoad construction, building construction company in noida
Road construction, building construction company in noida
 
OpenMinteD Project - building a TDM infrastructure
OpenMinteD Project - building a TDM infrastructureOpenMinteD Project - building a TDM infrastructure
OpenMinteD Project - building a TDM infrastructure
 
Centralized monitoring station for it computing and network infrastructure1
Centralized monitoring station for it computing and network infrastructure1Centralized monitoring station for it computing and network infrastructure1
Centralized monitoring station for it computing and network infrastructure1
 
Building Structure Project 2 report
Building Structure Project 2 reportBuilding Structure Project 2 report
Building Structure Project 2 report
 
Building construction project 1 report
Building construction project 1 reportBuilding construction project 1 report
Building construction project 1 report
 
Digital research infrastructure on European integration - CVCE Status report ...
Digital research infrastructure on European integration - CVCE Status report ...Digital research infrastructure on European integration - CVCE Status report ...
Digital research infrastructure on European integration - CVCE Status report ...
 
Building Construction Project 1 Report
Building Construction Project 1 ReportBuilding Construction Project 1 Report
Building Construction Project 1 Report
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
 
Final year project on Remote Infrastructure Management
Final year project on Remote Infrastructure ManagementFinal year project on Remote Infrastructure Management
Final year project on Remote Infrastructure Management
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
 
An Analytical Analysis on Weighted Average Cost of Capital
An Analytical Analysis on Weighted Average Cost of CapitalAn Analytical Analysis on Weighted Average Cost of Capital
An Analytical Analysis on Weighted Average Cost of Capital
 
Global LNG bunkering infrastructure as of January 2014
Global LNG bunkering infrastructure as of January 2014Global LNG bunkering infrastructure as of January 2014
Global LNG bunkering infrastructure as of January 2014
 
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORTBUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
 
Spencer's retail ltd. project report (summer internship project)
Spencer's retail ltd. project report (summer internship project)Spencer's retail ltd. project report (summer internship project)
Spencer's retail ltd. project report (summer internship project)
 
WIPRO PROJECT FILE
WIPRO PROJECT FILEWIPRO PROJECT FILE
WIPRO PROJECT FILE
 

Similar to Best bidding practices for owners of infrastructure & building projects

Alternative Delivery
Alternative DeliveryAlternative Delivery
COST ANALYSIS OF BRICK AND BOLT CONSTRUCTION IS IT WORTH IT.pptx
COST ANALYSIS OF BRICK AND BOLT CONSTRUCTION IS IT WORTH IT.pptxCOST ANALYSIS OF BRICK AND BOLT CONSTRUCTION IS IT WORTH IT.pptx
COST ANALYSIS OF BRICK AND BOLT CONSTRUCTION IS IT WORTH IT.pptx
BrickAndBolt
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
R.R.G.S Bandara
 
Sanjeewa_CV updated on 23.02.2016
Sanjeewa_CV  updated on 23.02.2016Sanjeewa_CV  updated on 23.02.2016
Sanjeewa_CV updated on 23.02.2016
Sanjeewa Mahawedage
 
Document 1
Document 1Document 1
Document 1
Erik Ong
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
Pang Khai Shuen
 
Aerosol Sealing in New Construction
Aerosol Sealing in New ConstructionAerosol Sealing in New Construction
Aerosol Sealing in New Construction
Center for Energy and Environment
 
Design build risks and rewards for public owner
Design build risks and rewards for public ownerDesign build risks and rewards for public owner
Design build risks and rewards for public owner
Jon Straw
 
AGC Webinar
AGC WebinarAGC Webinar
Eng. Sherif kadry C.V.updating April 2016
Eng. Sherif kadry C.V.updating April 2016Eng. Sherif kadry C.V.updating April 2016
Eng. Sherif kadry C.V.updating April 2016
sherif kadry
 
ARTSCAPE_Introduction
ARTSCAPE_IntroductionARTSCAPE_Introduction
ARTSCAPE_Introduction
Artscape projects
 
CV
CVCV
CV
CVCV
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdfCCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
ChassyTesoro1
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
Abadit Tadesse
 
Mohammed Abdelazeem Resume
Mohammed Abdelazeem ResumeMohammed Abdelazeem Resume
Mohammed Abdelazeem Resume
Mohammed Abdelazeem, PMP ®
 
Pp report
Pp reportPp report
Pp report
Arthur Wilson
 
Session 1 Tendering Concepts in construction
Session 1 Tendering Concepts in constructionSession 1 Tendering Concepts in construction
Session 1 Tendering Concepts in construction
mahendraprajapati54
 
CV Shehzad SQS
CV Shehzad SQSCV Shehzad SQS
CV Shehzad SQS
Muhammad Shehzad Ali
 

Similar to Best bidding practices for owners of infrastructure & building projects (20)

Alternative Delivery
Alternative DeliveryAlternative Delivery
Alternative Delivery
 
COST ANALYSIS OF BRICK AND BOLT CONSTRUCTION IS IT WORTH IT.pptx
COST ANALYSIS OF BRICK AND BOLT CONSTRUCTION IS IT WORTH IT.pptxCOST ANALYSIS OF BRICK AND BOLT CONSTRUCTION IS IT WORTH IT.pptx
COST ANALYSIS OF BRICK AND BOLT CONSTRUCTION IS IT WORTH IT.pptx
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Sanjeewa_CV updated on 23.02.2016
Sanjeewa_CV  updated on 23.02.2016Sanjeewa_CV  updated on 23.02.2016
Sanjeewa_CV updated on 23.02.2016
 
Document 1
Document 1Document 1
Document 1
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
 
Aerosol Sealing in New Construction
Aerosol Sealing in New ConstructionAerosol Sealing in New Construction
Aerosol Sealing in New Construction
 
Design build risks and rewards for public owner
Design build risks and rewards for public ownerDesign build risks and rewards for public owner
Design build risks and rewards for public owner
 
AGC Webinar
AGC WebinarAGC Webinar
AGC Webinar
 
Eng. Sherif kadry C.V.updating April 2016
Eng. Sherif kadry C.V.updating April 2016Eng. Sherif kadry C.V.updating April 2016
Eng. Sherif kadry C.V.updating April 2016
 
ARTSCAPE_Introduction
ARTSCAPE_IntroductionARTSCAPE_Introduction
ARTSCAPE_Introduction
 
CV
CVCV
CV
 
CV
CVCV
CV
 
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdfCCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
 
Mohammed Abdelazeem Resume
Mohammed Abdelazeem ResumeMohammed Abdelazeem Resume
Mohammed Abdelazeem Resume
 
Pp report
Pp reportPp report
Pp report
 
Session 1 Tendering Concepts in construction
Session 1 Tendering Concepts in constructionSession 1 Tendering Concepts in construction
Session 1 Tendering Concepts in construction
 
CV Shehzad SQS
CV Shehzad SQSCV Shehzad SQS
CV Shehzad SQS
 

Recently uploaded

Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
bijceesjournal
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
PKavitha10
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
integral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdfintegral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdf
gaafergoudaay7aga
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
Mahmoud Morsy
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
VANDANAMOHANGOUDA
 

Recently uploaded (20)

Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
integral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdfintegral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdf
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
 

Best bidding practices for owners of infrastructure & building projects

  • 1. Best Bidding Practices for Project Owners
  • 2. You can bring a project in on-time and on-budget The City of DeWitt, Iowa, brought its 6th Avenue project in under budget at a final cost of $1.3 million.
  • 4. Never assume Projects may be similar, but each has a unique set of circumstances
  • 5. Define uniqueness The owner should actively work with the engineering firm to determine: ◍ Project scope ◍ Preliminary design: emphasizes drawings and cost estimate ◍ Final design: plans, specifications & updated cost estimate ◍ Owner’s plans for specific area ◍ How does the project fit into the overall Capital Improvement Plan?
  • 6. Clinton, Iowa, Lincolnway project Clinton’s air and rail park called for a flexible lead rail track design as funding sources’ requirements unfolded. Options explored for mitigation to the surrounding wetlands brought the track in 10% under budget at $1.39 million
  • 7. Ensure design & changes are within budget Estimate 3 times: ◍ Before design ◍ As initial design phase is complete ◍ Prior to bidding
  • 8. Is your design team current with: • Construction trends • Potential bidders • The bidding environment • The vendors • Unique aspects of the project Research can influence estimates
  • 11. Build in quality metrics
  • 12. Construction schedule options affect pricing Calendar days: ◍ Late start date ◍ Weather days allowed & count as working days ◍ Can contractor fit “this” into existing commitments? Working days: ◍ Late start date ◍ Charge a working day only if weather is nice ◍ Completion date is more variable
  • 13. Bid letting (opening) schedule affects pricing ◍ Roadway, utility & grading contractors schedule their work differently than building contractors ◍ Time of year makes a difference ◍ Outdoor projects are ideally let in January & February when contractors are eager to schedule work for the entire year
  • 14. Bid with schedule options to compare cost of each schedule Schedule & budget both important?
  • 16. Take the time to clearly communicate so that: ◍ Contractors have the same understanding of the work ◍ Change orders will be minimized ◍ You save money
  • 17. Clear plans & specs encourage more bidders Designs should be specific, but not dictate the solution. ◍ Allow the contractor to choose approach to construction of the project
  • 18. 5 to 10% bid variance is optimal Bids with low variance indicates contractors have the same understanding of the project
  • 19. Research the outlier’s bid Why is the bid so different? ◍ Different market pricing structure? ◍ Market is busy/not busy? ◍ Experience with owner? ◍ Experience with engineering firm?
  • 20. Place your screenshot here I’m happy to share ideas Geoffry Blandin 563-823-0192 g.blandin@iiwengr.com © 2015 IIW, P.C. All Rigts Reserved.