SlideShare a Scribd company logo
1 of 19
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
Personnel Lifting Platforms
WAC 296-882-100
Scope
This rule applies to the lifting, lowering, and transporting of personnel
using personnel platforms connected to cranes or derricks.
Personnel platforms can be either suspended from the crane or derrick by
wire rope or chain, or attached to the boom of the crane or derrick. Using
articulating boom cranes with suspended platforms is not allowed
Important!
 Do not use cranes or derricks for personnel lifting when there is a
less hazardous way to accomplish the work.
Cranes and derricks are designed and intended for material
handling, and are not required to meet the same design
standards as manlifts, aerial lifts, bucket trucks, and other
conventional personnel-lifting equipment.
The lifting or lowering of personnel using material handling cranes
and derricks is prohibited unless all of the applicable
requirements of WACs 296-882-100 through 296-882-60030 are
met.
ASME B23-0.1
Within the general scope defined in Section I, ASME B30.23 may apply
to hoisting equipment covered within certain volumes of the ASME
B30 standard, that is used to lift, lower, or transport personnel in a
platform, by wire rope or chain, from hoist equipment, or by a
platform that is mounted on a boom of the hoist equipment. The
lifting of personnel is not allowed using some ASME B30 Standard
equipment. The ASME B30 volume addressing the hoisting
equipment to be used shall be consulted for the applicability of the
ASME B30.23 volume.
Section 23-0.2: Intent of ASME B30.23
The intent of this volume is to establish minimum design criteria,
equipment features, and operational procedures for using material
hoisting equipment to lift personnel. Use of this volume will not raise the
level of safety of the material hoisting equipment to that obtained by
using equipment specifically designed and manufactured for lifting
personnel. The ASME B30 standard hoisting equipment is designed
and intended for material handling and is not required to meet the same
design standards required of conventional personnel lifting equipment
(ANSI/SIA A 92 Aerial Platforms). Lifting and lowering of personnel
using ASME B30 Standard hoisting equipment shall be undertaken only
in circumstances when it is not possible to accomplish the task by less
hazardous means. Unless all of the applicable requirements of this
volume are met, the lifting or lowering of personnel using ASME B30
Standard equipment is prohibited.
WAC 296-882-200
Design and Construction Requirements for Personnel Lifting
Equipment
Summary
Your responsibility:
To make sure personnel lifting equipment is safe for operation.
1
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
WAC 296-882-20005
Design of platforms and suspension systems
You must
• Make sure personnel platforms and suspension systems
manufactured under your direction are designed, constructed and
tested according to ASME B30.23-1998, Personnel Lifting
Systems.
WAC 296-882-20010
Personnel platforms identification plate
You must
• Make sure an identification plate is located inside the platform
and is easy to read from outside the platform while the platform is
on the ground.
- The plate must display the following information:
▪ Manufacturer’s name and address
▪ Platform rating in terms of weight and personnel
▪ Platform identification number
▪ Suspension system description for suspended platforms, or
the intended hoisting equipment manufacturer identification
for boom attached platforms
▪ Weight of the empty platform and its suspension system
▪ Date the platform was manufactured
▪ Certification of compliance to the design, construction, and
testing requirements of this volume
▪ Listing of any unique operational environments for which the
platform has been designed
1.1.1(b)(7)
An identification plate located on the interior of the platform and legible
from outside of the platform, while the platform is on the ground, that
displays, as a minimum, the following information:
a) manufacturer name and address
b) platform rating in terms of weight and personnel
c) platform identification number
d) suspension system description for suspended platforms, or the
intended hoisting equipment manufacturer identification for
boom attached platforms
e) weight of the empty platform and its suspension system
f) date of the platform manufacture
g) certification of compliance to the design, construction, and
testing requirements of this volume
h) listing of any unique operational environments for which the
platform has been designed
2
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
WAC 296-882-300
Hoisting Equipment
Summary
Your responsibility: To make sure hoisting equipment for personnel
lifting is used correctly
WAC 296-831-30005
Use the correct hoisting crane or derrick
You must:
• Make sure the following equipment is
not used to lift personnel:
- Articulating boom cranes
- Pendant supported, jib type boom extensions without positive
stops
(excerpt from B30.23 Scope)
The lifting of personnel is not allowed using some ASME B30 Standard
equipment. The ASME B30 volume addressing the hoisting equipment
to be used shall be consulted for the applicability of the ASME B30.23
volume.
(excerpt from B30.22 Scope)
Exemptions from this volume include:
(c) all units equipped with or designed primarily for personnel baskets,
ladders, platforms, etc.
The second bullet is from (a) on the next page
WAC 296-882-30010
Crane or derrick requirements
Important!
Cranes and derricks must meet the requirements in the WACs that apply
to them, and the applicable hoisting equipment ASME B30 volume, in
addition to these requirements.
You must:
• Make sure the crane or derrick you are using to hoist the
personnel platform meets the following requirements:
- Live boom or live load capabilities allowing free fall are removed
for the period of personnel lifting
- An anti-two-block device is installed on the hoisting systems
- On cranes and derricks with variable angle booms there is a
boom angle indicator that is clearly visible to the operator
- Has a device that clearly shows the operator the boom’s
extended length, unless the boom length does not affect the load
rating, on cranes with telescoping booms
1.2.2 Hoisting Equipment
(a) Features
(1)
Hoist equipment live boom or live load capabilities shall be removed for
the period of personnel lifting.
(2) Rope or chain hoisting systems, that are used for personnel lifting,
shall have an anti-two-block device installed.
(3) Hoisting equipment with a variable angle boom shall have a boom
angle indicator readily visible to the operator
(4) Hoisting equipment with telescoping booms shall have a boom length
indicator, readable from the operator’s station, unless the load rating is
independent of the boom length.
(5) Hooks used for attachment of a personnel lifting platform shall be of
a type that canbe positively locked closed and that will prevent the
platform lifting bridle from being dislodged.
(6) Hoisting equipment shall have automatic brakes such that when the
equipment operating controls are released the motions are brought to
rest.
(7) A holding device (such as a load hold check valve) shall be provided
in hydraulic or pneumatic systems to prevent uncontrolled movement of
.
3
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
- Has hooks, when used to attach a platform, that
 Can be positively locked closed
 Will prevent the lifting bridle from being dislodged
- Has automatic brakes on the equipment, so motions stop when
the operating controls are released
- Has a holding device, such as a load hold check valve, that will
prevent uncontrolled movement of the hoisting equipment if a
system fails, on hydraulic or pneumatic systems
- Has a way to prevent hydraulic or pneumatic outriggers or
stabilizers, if these are a part of the hoisting equipment, from
retracting if the hydraulic or pneumatic line fails
the hoisting equipment in the event of a system failure (e.g. supply
hose).
(8) A means to prevent the retraction of any hydraulically or
pneumatically activated outriggers or stabilizers in the event a hydraulic
or pneumatic line fails, when such devices are a component of the
hoisting equipment.
(9) Pendant supported, jib type, boom extensions without positive stops
shall not be used to lift personnel.
• Make sure the crane is level within 1% of level grade and located
on firm footing
- Make sure outriggers or stabilizers are extended, blocked and
locked according to manufacturer’s recommendations, if the
crane is equipped with them
3.2.2(a)(4)(the operator shall)
verify that the hoisting equipment is set up and maintained within one
percent of level during a personnel lift
3.2.2(a)(3)
operate hoisting equipment with outriggers with outriggers or stabilizers
extended, blocked and locked in accordance with manufacturer’s
specifications.
• Make sure the total weight of the loaded personnel platform and
related rigging does not exceed fifty percent of the crane’s rated load
capacity
3.2.2(a)(7)
Not allow the total weight of the lifted load including rigging, platform,
personnel, tools, and material to exceed 50 percent of the hoisting
equipment’s rated load, under the planned conditions of operation
(except during testing as outlined in Chapter 23-2)
WAC 296-882-400
Inspections, Maintenance and Testing
Summary
Your responsibility: To keep personnel lifting equipment in safe
operating condition by performing regular inspections, maintenance, and
testing.
4
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
WAC 296-882-40005
Initial inspections on personnel platforms
You must
• Have a qualified person inspect personnel platforms before initial
use and at each new job site to make sure the requirements of WAC
296-882-100 through WAC 296-882-60030 are met
2.1.1 Personnel Lifting Platform (Inspection)
(b) Frequency
(1) Initial Inspection. Prior to initial use and at each new job site all
platforms shall be inspected by a qualified person to verify
compliance with the provisions of this volume.
(a) is manufacturer’s requirement:
(1) The platform manufacturer shall furnish
complete inspection criteria for platform users.
The criteria shall address all inspection
frequency classifications listed in this volume
and shall cover:
(a) the platform
(b) rigging components
(c) fasteners
(d) all safety features and attachments.
WAC 296-882-40010
Frequent inspections on personnel platforms
You must
• Make sure an appointed person inspects all items in Table 1 at
least once each day, before use.
• Correct any hazardous condition before using the platform.
• Keep the most recent, dated inspection records available for the
duration of the lift operation.
2.1.1(b)(2) Regular Inspection
(a) Frequent. The platform, suspension system, attachment points, and
any platform motion controls shall be inspected at least once each day,
before use, by a designated person. The inspection is to identify
conditions that have been specifically indicated by the platform
manufacturer, or a qualified person, as potentially creating a hazardous
operating condition. The inspection shall address at least those items
listed in Appendix III. Any conditions found that constitute a hazard shall
be corrected prior to lifting personnel.
2.1.1(b)(2)
(c) Records
(1) For frequent inspections, dated records for the hoisting equipment
and personnel platform shall be made and kept by the platform user for
the duration of the personnel lift operation
(Table 1, Frequent inspection checklist for personnel lifting platforms)
WAC 296-882-40015
Periodic inspections on personnel platforms
You must:
• Make sure a qualified person performs a periodic inspection of
personnel platforms at least once a year, according to manufacturer’s
instructions
• Correct any hazardous condition before using the platform
• Keep the most recent, dated inspection records with the platform
and available for review
Note: Platforms that have been out of service for more than a year don’t
2.1.1(b)(2)
(b) Periodic. At least once every 12 months, or as required by the
platform manufacturer, a periodic inspection of the platform shall be
performed by a qualified person in accordance with the instructions
provided by the manufacturer. Platforms which have been out of service
for 12 or more consecutive months shall receive a periodic inspection
before use.
2.3.1 (b)
(1) Any hazardous condition disclosed by any inspection shall be
corrected before use of the platform is resumed. Adjustments and
repairs shall be accomplished by designated personnel.
2.1.1(b)(2)(c)
(2) For periodic inspections, dated records for the platform shall be
5
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
need to have a periodic inspection until they are put back into use. made by the platform owner. The last periodic inspection shall be kept
with the platform and available for review.
WAC 296-882-40020
Adjustments and repairs on personnel platforms
You must:
• Make sure any adjustments or repairs to the platform is done by
a designated person
− Adjustments or repairs to the suspension system must be done
by a qualified person.
• Make sure replacement parts and repairs are equal to or exceed
the original equipment specifications.
• Make sure the manufacturer or a qualified person has approved
any modifications, in writing, before they are made.
• Keep records of any repairs to the structural components of the
platform
• Make sure all welding repairs are done by a certified welder.
2.3.1(b)(5) Any adjustment or repair to the platform suspension system
shall be done by a qualified person
2.3.1 (b)
(1) Any hazardous condition disclosed by any inspection shall be
corrected before use of the platform is resumed. Adjustments and
repairs shall be accomplished by designated personnel.
2.3.1(a) preventative maintenance
(1) A preventative maintenance program based on the platform
manufacturer’s recommendations should be established
(2) Replacement parts used shall be equal to or exceed the original
equipment specification
2.3.1(b)(3) Replacement parts used or repairs made shall be equal to or
exceed the original equipment specification.
2.3.1(c) Modifications. Only modifications approved in writing by the
manufacturer or a qualified person shall be accomplished.
2.3.1(d) Records. The platform owner shall maintain records on any
repairs to, or replacements of, the structural components of the platform.
2.3.1(b)(4) All welding repairs shall be done by a certified welder
Not used: 2.3.1(b)(2) Adjustments shall
provide for correct functioning of components.
(1) is a “should”.
WAC 296-882-40025
Proof test platforms and rigging
You must
1. Make sure the platform and rigging is proof tested at each new
job site before lifting personnel.
• Test as follows:
- Test to 125% of the platform’s rated capacity
- Hold the platform suspended for 5 minutes with the test
load evenly distributed on the platform
Note: This may be done at the same time as the trial lift
2.2.1(b)Proof Testing
(1) At each new job site, prior to hoisting people in the personnel
platform, the platform and rigging shall be proof tested to 125% of the
platform’s rating. With the proof test load evenly distributed in the
platform, the platform shall be hoisted and held in a suspended position
for not less than five minutes. After the proof testing, the platform shall
be inspected by a qualified person. Any damage revealed by the
inspection shall be corrected and another proof test conducted.
2.2.1(a) is Platform Manufacturer Tests. If
manufacturing their own platforms, they
were already told to test in accordance
with the ANSI.
6
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
You must:
• Do the following after proof testing:
- Have an appointed person inspect the platform and
rigging
- Correct any deficiencies
- Perform another test after any deficiencies are corrected
• Keep the most recent proof testing records available at the jobsite
2. Make sure the platform and rigging is proof tested after any structural
repair or modification, before lifting personnel
2.2.1(b)(3) After any structural repair or modification, a platform shall be
proof tested…
2.2.1(b)(2) is a should:
When feasible, the hoisting equipment to be
used for lifting personnel should be the
equipment used to perform the proof tests at
the job site as defined in para. 23-2.2.1(b).
• Test suspended platforms in the following order:
- Test to 150% of the platform’s rated capacity
- Raise the loaded platform, then lower it at a speed of at
least 100 ft/min.
- Bring the platform to a stop by using the hoisting
equipment brakes
- Let the platform hang for at least 5 minutes.
- Have a qualified person inspect the platform and rigging.
- Correct any deficiencies.
- Perform another test after any deficiencies are corrected
2.2.1(b)(3) After any structural repair or modification, a platform shall be
proof tested to 150% of the platforms rating. Boom attached platforms
shall use the test procedure described in para. 23.2.2.1(b)(1).
Suspended platforms shall be tested by raising the loaded platform to a
height, then lowering it at a speed of not less than 100 ft/min. Once a
lowering speed of 100 ft/mion or more is reached, the platform descent
shall be halted by applying the hoisting equipment brakes and then the
platform allowed to hang for a period of not less than five minutes. After
this test and hanging period, the platform shall be inspected by a
qualified person. Any damage revealed by the inspection shall be
corrected and another proof test conducted.
• Test attached platforms in the following order:
- Test to 150% of the platform’s rated capacity.
- Hold the platform suspended for 5 minutes with the test
load evenly distributed on the platform.
- Have an appointed person inspect the platform and
rigging.
- Correct any deficiencies.
- Perform another test after any deficiencies are corrected.
(3) After any structural repair or modification, a platform shall be proof
tested to 150% of the platforms rating. Boom attached platforms shall
use the test procedure described in para. 23.2.2.1(b)(1).
2.2.1(b)(1)
At each new job site, prior to hoisting people in the personnel platform,
the platform and rigging shall be proof tested to 125% of the platform’s
rating. With the proof test load evenly distributed in the platform, the
platform shall be hoisted and held in a suspended position for not less
than five minutes. After the proof testing, the platform shall be inspected
by a qualified person. Any damage revealed by the inspection shall be
corrected and another proof test conducted.
7
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
• Keep the most recent proof testing records
available at the jobsite
2.2.1(c)
Records. The most recent record of proof testing shall be maintained at
the jobsite.
WAC 296-882-500
Management Responsibilities
Your responsibility:
To make sure all duties are performed by the correctly appointed person.
WAC 296-882-50005
Job site management
You must:
• Make sure job site management performs the duties listed in Table 2.
Table 2
Job site management duties
• Designate a “Personnel Lift Supervisor” for each personnel
lift operation.
• Require that all personnel associated with the lift receive the
briefings and safety indoctrinations specified in this volume.
• Prohibit the lifting of personnel whenever the operator:
- Does not feel physically or mentally fit to perform the
operation.
- Has been working for more than 10 hours prior to
the start of the lift or the lift will not be completed
before the operator has been working for 12 hours.
- Did not have at least eight hours off immediately
prior to the work shift containing the personnel lift
operation.
• Designate the appropriate number of signalpersons, ground
crew, and platform occupants to perform the personnel lift
safely.
- In suspended and boom attached platforms without
boom motion controls, one occupant shall be
appointed as the platform signalperson. This
Section 23-3.1: Personnel
23-3.1.1 Management
(a) Responsibilities
(1) Management shall require that the provisions of this volume are
understood and applied at the operational levels, and that the
appropriate portions of this volume are included in the pre-lift briefing
information.
(2) Management shall designate qualified individuals at each job site to
perform the duties of the “Personnel Lift Authorizer.” As a minimum
these individuals shall be responsible for:
(a) verifying the need for a personnel lift;
(b) verifying the equipment to be used for the personnel lift meets the
requirements of Chapter 23-1;
(c) authorizing the personnel lift operation’
(d) requiring the personnel lift be accomplished in accordance with the
provisions of this volume.
(3) Job site management shall require that the provisions of this volume
are implemented during personnel lifting operations.
(4) Job site management shall designate a “Personnel Lift Supervisor”
ANSI’s requirements aren’t separated cleanly; I
listed the two paragraphs here but we
divided the duties according to who is
responsible for them.
8
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
person shall be responsible for communicating with
the operator and/or other appointed signalpersons.
• Require that the hoisting equipment used to lift personnel shall
be in compliance with the requirements prescribed in this
volume and the applicable hoisting equipment ASME B30
volume.
• Have a Personnel Lifting Management and Approval Program
that requires the criteria of this rule to be met before to lifting
personnel.
• Instruct operators of hoisting equipment, installed on floating
vessels, not to lift personnel when the list or trim of the vessel
exceeds five degrees. If mobile hoisting equipment is placed on
floating vessels, operators shall not lift personnel when the list or
trim of the vessel exceeds one degree.
for each personnel lift operation. As a minimum, the individual shall be
responsible for:
(a) holding the pre-lift meeting;
(b) verifying all required inspections have been accomplished;
(c) verifying qualified persons are assigned to perform the functions of
the operator, signalpersons, and ground crew;
(d) supervising the personnel lift operation;
(e) accomplishing other tasks that may be needed to enhance the safety
of the personnel lift.
(5) Job site management shall require that all personnel associated with
the lift receive the briefings and safety indoctrinations specified in this
volume.
(6) Job site management shall not allow or require any operator to lift
personnel under the following circumstances:
(a) The operator does not feel physically or mentally fit to perform the
operation.
(b) The operator has been working for more than 10 hours prior to the
start of the lift or the lift will not be completed before the operator has
been working for 12 hours.
(c) the operator did not have at least eight hours off immediately prior to
the work shift containing the personnel lift operation.
(7) Job site management shall designate the appropriate number of
signalpersons, ground crew, and platform occupants to perform the
personnel lift safely.
(a) In suspended and boom attached platforms without boom motion
controls, one occupant shall be designated as the platform signalperson.
This person shall be responsible for communicating with the operator
and/or other designated signalpersons.
(8) Job site management shall require that the hoisting equipment used
to lift personnel shall be in compliance with the requirements prescribed
in this volume and the applicable hoisting equipment ASME B30 volume.
WAC 296-882-50010
Personnel Lift Authorizer
9
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
You must:
• Assign qualified individuals at each job site who will be responsible for
the duties listed in Table 3.
Table 3
Personnel lift Authorizer Responsibilities
• Verifying
- The need for a personnel lift
- That there are no less hazardous alternatives to
performing the work, or providing access to the
area. The personnel lift shall not be authorized
when less hazardous means are feasible.
• Verifying the equipment to be used for the personnel lift
meets the requirements of the chapter governing that
equipment
• Authorizing the personnel lift operation
• Reviewing and approving the personnel lift plan. Retain the
plan as part of the job site records.
• Verifying that conditions provide clear visibility. When
conditions such as darkness, fog, or snow prevent clear
visibility, do not authorize personnel lifting.
• Authorize personnel lifting over, under, or in the vicinity of
power lines, in accordance with the requirements Chapter
296-45, Safety standards for electrical work
Section 23-3.2: Practices
23-3.2.1 Management
Job site management shall have a Personnel Lifting Management and
Approval Program that requires the criteria of this volume to be met prior
to lifting personnel. The program shall, as a minimum, require:
(a) The Personnel Lift Supervisor to prepare a personnel lift plan
containing at least the information shown in Appendix II. This plan shall
be presented to the Personnel Lift Authorizer for review/approval. The
plan shall be retained as part of the job site records.
(b) The Personnel Lift Authorizer to verify that there are no less
hazardous alternatives to performing the work, or providing access to
the area. The personnel lift shall not be authorized when less hazardous
means are feasible.
(c) The Personnel Lift Authorizer to verify that conditions provide clear
visibility. When conditions such as darkness, fog, or snow prevent clear
visibility, the Personnel Lift Authorizer shall not authorize personnel
lifting.
(d) The Personnel Lift Authorizer to only authorize personnel lifting over,
under, or in the vicinity of power lines, in accordance with the
requirements of Appendix I;
(e) personnel platforms not to be used in winds in excess of 20 mph
(32.2 km/hr) at the hoisted platform height, electric storms, snow, ice,
sleet, or other adverse weather conditions which could affect the safety
of personnel.
(f) the Personnel Lift Supervisor to verify that each of the requirements in
this Section have been met;
(g) the Personnel Lift Supervisor to hold a pre-lift briefing attended by
the hoisting equipment operator, platform occupants, and ground crew.
If individuals are changed during a series of personnel lifts, each new
person shall be appropriately briefed by the Personnel Lift Supervisor.
Contents of the briefing shall, as a minimum, cover:
(1) the operations section of this volume
(2) the assignment and responsibilities of each person involved in the lift
operation
10
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
(3) the procedures to be followed
(4) guidance on general and specific safety precautions
(5) special signals for the operation
(6) unique considerations of the lift
(7) work to be accomplished during the lift
(8) if applicable, the responsibilities and assignments contained in
Appendix I when lifting personnel near electrical power lines
(h) the Personnel Lift Supervisor to terminate personnel lifting operations
if hazardous conditions develop during the lift
(i) personnel platforms to be only used for personnel, their tools, and
sufficient material to do their work. They shall not be used for solely
transporting bulk materials.
(j) a qualified person to evaluate the safety concerns of the operational
environment and verify the platform and hoisting equipment are suitable
for use. Additionally, special work circumstances may require further
precautions. Precautions such as, but not limited to the following shall
be taken:
(1) When welding is to be accomplished from the personnel platform,
suitable electrode holders shall be provided to protect them from contact
with any conducting components of the platform
(2) Job site management shall instruct operators of hoisting equipment,
installed on floating vessels, not to lift personnel when the list or trim of
the vessel exceeds five degrees. If mobile hoisting equipment is placed
on floating vessels, operators shall not lift personnel when the list or trim
of the vessel exceeds one degree.
(3) When personnel lifts are conducted over water, personnel flotation
devices shall be provided and required to be worn. Personnel fall
protection devices with quick release features shall be provided, and
required to be worn. The fall protection device shall be appropriately
attached while personnel are lifted over land and detached while
personnel are lifted over water.
(4) A boat with appropriate rescue personnel shall be available at all
times during a personnel lift over water
(5) Appropriate personnel protective equipment shall be provided and
required to be used around toxic, flammable, or hazardous substances
or fumes.
(6) Any concentrated loading of the platform shall be reviewed to
preclude the overstressing of any component or impairing the platform
stability.
11
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
WAC 296-882-50015
Personnel Lift Supervisor
You must:
• Assign a Personnel Lift Supervisor, who will be responsible for
the duties outlined in Table 4.
Table 4
Personnel Lift Supervisor duties
• Holding the pre-lift meeting;
• Verifying all required inspections have been accomplished;
• Verifying qualified persons are assigned to perform the functions of
the operator, signalpersons, and ground crew;
• Supervising the personnel lift operation;
• Accomplishing other tasks that may be needed to enhance the
safety of the personnel lift.
• Preparing a personnel lift plan containing at least the information
shown in Appendix II.
• Verifying that each of the requirements in this Section have been
met;
• Holding a pre-lift briefing attended by the hoisting equipment
operator, platform occupants, and ground crew. If individuals are
changed during a series of personnel lifts, each new person shall
be appropriately briefed by the Personnel Lift Supervisor. Contents
of the briefing shall, as a minimum, cover:
- the operations section of this rule
- the assignment and responsibilities of each person
involved in the lift operation
- the procedures to be followed
- guidance on general and specific safety precautions
- special signals for the operation
- unique considerations of the lift
- work to be accomplished during the lift
- if applicable, the responsibilities and assignments
contained in Chapter 296-45, Safety standards for
electrical work, when lifting personnel near electrical
power lines
See the two sections listed above for these
requirements.
12
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
• Terminate personnel lifting operations if hazardous conditions
develop during the lift
WAC 296-882-600
Lifting Personnel
Summary
Your responsibility: To make sure personnel lifting equipment is
operated safely.
WAC 296-882-60005
Lift personnel as a last resort only
You must
• Lift personnel on platforms with cranes or
derricks only if it is the only possible way to accomplish the work that
needs to be done.
13
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
WAC 296-882-60010
Hold a prelift meeting
You must
• Make sure a prelift meeting is held before the trial lift at each new
location as follows:
- The crane or derrick operator, the signal person, employees who
will be lifted, and the lift supervisor must attend.
- Cover all of the following:
o The requirements of WAC 296-882-200 through WAC
296-882-60030
o Assignments and responsibilities of each person involved
in the operation
o The procedures that will be followed
o Special signals and unique considerations of the lift
o What work will be accomplished during the lift
- Repeat the meeting for any employees new to the operation
3.2.1(g) (The program shall require)
The Personnel Lift Supervisor to hold a pre-lift briefing attended by the
hoisting equipment operator, platform occupants, and ground crew. If
individuals are changed during a series of personnel lifts, each new
person shall be appropriately briefed by the Personnel Lift Supervisor.
Contents of the briefing shall, as a minimum, cover:
(1) the operations section of this volume
(2) assignment and responsibilities of each person involved in the
lift operation
(3) the procedures to be followed
(4) guidance on general and specific safety precautions
(5) special signals for the operation
(6) unique considerations of the lift
(7) work to be accomplished during lift
(8) if applicable, the responsibilities and assignments contained in
Appendix I when lifting personnel near electrical power lines
WAC 296-882-60015
Set up hoisting equipment correctly
You must
• Make sure the operator inspects the area where the hoist equipment
will be set up, and looks for:
- Overhead obstructions and electrical lines
- Hazardous locations
- Inadequate surface area
- Inadequate support to withstand all force imposed
- Wind, weather, and unstable conditions
- Other potentially hazardous conditions
3.2.2(a) the operator shall:
(1) inspect the hoist equipment setup area before the personnel lift and
report his observations to the Personnel Lift Supervisor. The operator
shall inspect the area for potential hazards such as, but not limited to:
(a) excessive load and/or radius
(b) overhead obstructions and electrical transmission lines
(c) hazardous locations
(d) inadequate surface and support to withstand all forces imposed
(e) wind, weather, and unstable conditions
(f) any potentially hazardous conditions
WAC 296-882-60020
Perform a trial lift
You must
• Make sure a trial lift with the personnel platform is performed, on each
shift before lifting personnel, to check the following:
3.2.2(a)(9)
Perform a trial lift prior to lifting personnel with the platform on each shift
and after any change of setup location, hoist equipment configuration, or
operator. These lifts shall be used to ascertain that hoist equipment
setup and configuration is correct, load capacities are adequate, that no
hazardous interferences exist, and to further demonstrate the operator’s
operational competence;
14
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
- Hoist equipment setup and configuration is correct
- Load capacities are adequate
- No hazardous interferences exist
- The operator’s operational competence
• Load the unoccupied platform to at least
the anticipated load weight
(10) verify that during the trial lift, the platform is loaded to at least the
weight expected during the actual lift;
• Repeat the trial lift before lifting personnel whenever
- The crane or derrick is moved and set up in a different location.
- The crane or derrick is reconfigured.
- The operator is changed.
3.2.2(a)(9)
Perform a trial lift prior to lifting personnel with the platform on each shift
and after any change of setup location, hoist equipment configuration, or
operator. These lifts shall be used to ascertain that hoist equipment
setup and configuration is correct, load capacities are adequate, that no
hazardous interferences exist, and to further demonstrate the operator’s
operational competence;
• Make sure any defects that create a safety hazard are corrected
before lifting people.
2.1.1(b)(2)(a)(Frequent inspection)
………Any conditions found that constitute a hazard shall be corrected
prior to lifting personnel
WAC 296-882-60020
Performing the personnel lift
You must
• Safely perform the personnel lift. Make sure:
- The personnel platform is not loaded with more than its rated
load capacity
3.2.2(a)(7)
Not allow the total weight of the lifted load including rigging, platform,
personnel, tools, and material to exceed 50 percent of the hoisting
equipment’s rated load, under the planned conditions of operation
(except during testing as outlined in Chapter 23-2)
- Materials and tools being lifted by a platform are:
 Secured to prevent movement
 Evenly distributed on the platform
3.2.4(a)(5)
(The platform occupants shall)
have materials and equipment evenly distributed and secured while the
platform is lifted
- The personnel platform is hoisted slowly, with no sudden
movements
3.2.2 (a)(14)
Perform all movements of the platform in a slow, controlled manner to
minimize sudden movements of the platform
- Tag lines are used to control the motion of suspended platforms,
unless using them creates a hazard
3.2.3(f)
(The ground crew shall)
use tag lines for motion control of suspended platforms, unless their use
15
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
creates an unsafe condition.
- The platform is secured to the structure where the work will be
performed before employees exit or enter the platform, unless
securing to the structure is unsafe.
3.2.4(a)(8)
(the platform occupants shall)
not enter or exit a suspended platform while it is raised unless the
platform has an installed gate and the platform is physically secured to
the structure to which the occupants are entering or exiting.
- No other load lines on the crane or derrick are used to lift
anything while personnel are on a platform.
3.2.2(a)(22) (The operator shall)
not lift any other loads, on any other load lines, while conducting a
personnel lift. When the hoisting equipment has a boom attached
platform without controls it shall not be used for other lifting service.
- Brakes and locking devices are engaged when the personnel
platform is occupied and in a stationary working position
3.2.2(a)(19) set all brakes and locks on the hoisting equipment after
positioning of the personnel platform and before personnel perform any
work
- The lowering motion is power-controlled only
 Free fall is not allowed
3.2.2(a)(15)
engage the power controlled lowering mechanism at all times the
platform is occupied (no free fall).
• Make sure there are enough signalpersons, ground crew, and
platform occupants to perform the lift safely.
- For platforms without boom motion controls, make sure one
occupant is designated as the platform signalperson, responsible
for communicating with the operator and other signalpersons.
3.1.1(a)(7)
Job site management shall designate the appropriate number of
signalpersons, ground crew, and platform occupants to perform the
personnel lift safely.
(a)In suspended and boom attached platforms without boom motion
controls, one occupant shall be designated as the platform signalperson.
This person shall be responsible for communicating with the operator
and/or other designated signalpersons.
• Make sure an appointed person
- Verifies the platform is securely attached to the crane or derrick 3.1.3(b)(3) verifying the personnel platform is securely attached to the
hoisting equipment
- Verifies the load line is not attached to or wrapped around the
platform
3.1.3(b)(4) verifying the load line is not directly attached to, or wrapped
around, the personnel platform;
- Verifies boom-attached personnel platforms are attached
according to manufacturers specifications or a qualified person
3.1.3(b)(5) verifying boom attached personnel platforms are only
attached using the pins and fittings specified by the hoist equipment
manufacturer or a qualified person;
- Keeps people from passing under the raised platform 3.1.3(b)(6) keeping people from passing under the raised personnel
platform;
• Make sure employees working as part of the ground crew
do not have other duties or engage in any practice that will reduce the
safety of the personnel lift
3.1.3(c) Conduct. The ground crew shall not engage in any practice or
have any other duties which will reduce the safety of the personnel lift
operation.
• Make sure there are no more people on the platform than 3.2.4(a)(4)
16
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
are needed to do the job (The platform occupants shall)
be limited in number, commensurate with the work being performed,
platform design and hoisting equipment limitations.
• Make sure all platform occupants:
- Are qualified to operate the controls on a platform that
has controls
3.1.4(a)(4) Occupants of a platform with controls shall be qualified to
operate the controls.
- Are familiar with the hand signals posted in the platform 3.1.4(b)(5) being familiar with the hand signals posted in the platform.
All occupants shall know the emergency stop signal.
- Know the emergency stop signal 3.1.4(b)(5) being familiar with the hand signals posted in the platform.
All occupants shall know the emergency stop signal.
- Are wearing full body harness attached to specific
anchorage points with a lanyard, unless working over water. See
WAC 296-882-60030 for requirements when working over water.
3.2.4(a)(3) (The platform occupants shall)
wear personnel fall protection devices with lanyards attached to a
specific anchorage point(s), unless special circumstance work
requirements dictate otherwise
This is an increase, but put in per Dan
- Do not stand, sit on, or work from the rails
- Do not use any thing to raise their working height
3.2.4(a)(6) not stand, sit on, or work from the top rail, intermediate rail, to
board, or use any other device to enhance their vertical height working
capability;
- Do not pull the platform out of plumb 3.2.4(a)(7) not pull the platform out of plumb with the hoisting equipment.
- Keep all parts of their body inside the platform during
raising, lowering, and positioning, unless they are the
signalperson
3.1.4(b)(2) platform occupants shall be responsible for keeping all parts
of their body inside the platform during raising, lowering, and positioning,
except when performing duties as a designated signalperson
- Stay in sight of or in direct communication with the
operator
- Stay in continuous sight of the signal person, if used
3.2.4(a)(1)(The platform occupants shall)
remain in continuous sight or in communication with the operator, and in
sight and communication of a signalperson.
• Make sure the operator
- Doesn’t allow the rated load to be exceeded when loads are
transferred to the platform.
3.2.2(a)(8) not allow the platform’s rating or the hoisting equipments
reduced rated load to be exceeded when loads are transferred to the
hoisted platform;
- Positions the platform so it can be tied off to the structure where
occupants are entering or leaving, if the platform can’t be set
down.
 Make sure the operator doesn’t move the platform away from
the structure until it is freely suspended.
3.2.2(a)(11) position the platform so that it may be tied off to the
structure to which the occupants are entering or leaving, if the platform
cannot be landed during the entrance or exit of the occupants. If the
platform has been tied off, the operator shall not move the platform until
it is verified that it is freely suspended.
- Doesn’t move the platform faster than 100 ft/min, except during
testing
3.2.2(a)(16) not lift or lower an occupied platform at a speed in excess of
100 ft/min (except during testing as outlined in 23-2)
- Moves the platform under controlled conditions and under the
direction of a designated signalperson
3.2.2(a)(20) move the platform under controlled conditions and under the
direction of a designated signalperson
17
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
- Doesn’t disable any hoist equipment safety device during a
personnel lift
3.2.2(a)(23) not disable, or allow to be disabled, any hoist equipment
safety device during a personnel lift
- Is at the controls at all times while the engine is running and the
platform is occupied, unless using a boom mounted platform that
has both:
 Boom mounted motion controls
and
 A way of lowering, retracting and rotating if the primary power
source stops working
3.1.2(c)(5)
The hoisting equipment operator shall:
(a) when involved with a suspended platform, boom mounted platform
without controls, or a boom mounted platform with controls but without a
means of lowering, retracting, and rotating in the event the primary
power source becomes inoperative, remain at the hoisting equipment
controls whenever personnel are in the platform
(b) when involved with a boom mounted platform with boom motion
controls and a means of lowering, retracting, and rotating in the event
the primary power source becomes inoperative, be free not to remain at
the hoisting equipment controls
3.2.2(a)(17)(The operator shall:)
in the case of suspended or boom mounted platforms, without controls,
remain at the hoisting equipment controls at all times when the platform
is occupied.
3.2.2(a)(18)
in the case of boom mounted platforms, with controls, be free to not
remain at the hoisting equipment controls.
- Stops hoisting immediately when
 Wind exceeds 20 mph at the hoisted platform height
 Adverse weather, such as electric storms, snow, ice, or sleet
occurs
3.2.1(e)
personnel platforms not to be used in winds in excess of 20 mph at the
hoisted platform height, electric storms, snow, ice, sleet, or other
adverse weather conditions which could affect the saftey of personnel.
• Make sure the crane
does not travel while personnel are being lifted, except when the
equipment runs on fixed rails or runways
3.2.2(a)(13) (The operator shall)
not travel the hoisting equipment with personnel in the personnel
platform except when the equipment runs on fixed rails or runways.
18
Personnel Lifting
March, 2005
Proposed Wording ASME B30.23 Comments
WAC 296-882-60030
Special Work Circumstances
You must
1. Make sure, when lifting personnel over water, that:
- Personal flotation devices are provided and worn
- Personal fall protection devices with quick release features are
provided and worn
- Fall protection devices are attached while personnel are being
lifted over land, and detached while they are lifted over water
3.2.1(j)(3)<for over water>
When personnel lifts are conducted over water, personnel flotation
devices shall be provided and required to be worn. Personnel fall
protection devices with quick release features shall be provided,
and required to be worn. The fall protection device shall be
appropriately attached while personnel are lifted over land and
detached while personnel are lifted over water.
- Make sure a boat with rescue personnel is available at all
times
3.2.1(j)(4)A boat with appropriate rescue personnel shall be available at
all times during a personnel lift over water.
2. Make sure, when hoisting equipment is installed on floating vessels,
that personnel are not lifted when the list or trim of the vessel is more than
5°
3.2.1(j) (2) Job site management shall instruct operators of hoisting
equipment, installed on floating vessels, not to lift personnel when the
list or trim of the vessel exceeds five degrees. If mobile hoisting
equipment is placed on floating vessels, operators shall not lift personnel
when the list or trim of the vessel exceeds one degree.
3. When welding is going to be done from the personnel platform, make
sure suitable electrode holders are provided to protect them from contact
with any conducting parts of the platform.
3.2.1(j)(1)
19

More Related Content

What's hot

Panorama attività UNI, CEN e ISO nel campo degli apparecchi di sollevamento
Panorama attività UNI, CEN e ISO nel campo degli apparecchi di sollevamentoPanorama attività UNI, CEN e ISO nel campo degli apparecchi di sollevamento
Panorama attività UNI, CEN e ISO nel campo degli apparecchi di sollevamentoUNI - Ente Italiano di Normazione
 
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANESB30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANESANA ISABEL R.R.
 
"Rig Inspection Workshop - accredited by OCS Training Institute”
"Rig Inspection Workshop - accredited by OCS Training Institute”"Rig Inspection Workshop - accredited by OCS Training Institute”
"Rig Inspection Workshop - accredited by OCS Training Institute”Muanisa Waras
 
OCS - Rig Inspection Workshop - accredited by IADC
OCS - Rig Inspection Workshop - accredited by IADCOCS - Rig Inspection Workshop - accredited by IADC
OCS - Rig Inspection Workshop - accredited by IADCMuanisa Waras
 
Pamphlet on rake testing procedure for freight stock
Pamphlet on rake testing procedure for freight stockPamphlet on rake testing procedure for freight stock
Pamphlet on rake testing procedure for freight stockSrinivasaRao Guduru
 
Safety in Erection of Steel Structures
Safety in Erection of Steel StructuresSafety in Erection of Steel Structures
Safety in Erection of Steel StructuresAkash Tilokani
 
"IADC Accredited Rig Inspection Workshop"
"IADC Accredited Rig Inspection Workshop""IADC Accredited Rig Inspection Workshop"
"IADC Accredited Rig Inspection Workshop"Muanisa Nisa
 
Airbus safetylib -flt_ops-toff_dep_seq07
Airbus safetylib -flt_ops-toff_dep_seq07Airbus safetylib -flt_ops-toff_dep_seq07
Airbus safetylib -flt_ops-toff_dep_seq07Alberto Garcia Romera
 
Maintenace of passenger emergency alarm system of coaching stock
Maintenace of passenger emergency alarm system of coaching stockMaintenace of passenger emergency alarm system of coaching stock
Maintenace of passenger emergency alarm system of coaching stockSrinivasaRao Guduru
 
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLift Events
 
Safe use of Mobile Cranes
Safe use of Mobile CranesSafe use of Mobile Cranes
Safe use of Mobile CranesMihajlo Stupar
 
"Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche...
"Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche..."Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche...
"Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche...Muanisa Waras
 
Mobile crane safety rules
Mobile crane safety rulesMobile crane safety rules
Mobile crane safety rulesytcrane
 
Mercury mercruiser marine engines #24 gm v 8 305 cid (5.0 l) 350 cid (5.7l) ...
Mercury mercruiser marine engines #24 gm v 8 305 cid (5.0 l)  350 cid (5.7l) ...Mercury mercruiser marine engines #24 gm v 8 305 cid (5.0 l)  350 cid (5.7l) ...
Mercury mercruiser marine engines #24 gm v 8 305 cid (5.0 l) 350 cid (5.7l) ...fjsekkdmme
 
HITACHI EX550-5 EXCAVATOR Service Repair Manual
HITACHI EX550-5 EXCAVATOR Service Repair ManualHITACHI EX550-5 EXCAVATOR Service Repair Manual
HITACHI EX550-5 EXCAVATOR Service Repair Manualhjdksmemd
 

What's hot (19)

Operating practices
Operating practicesOperating practices
Operating practices
 
Panorama attività UNI, CEN e ISO nel campo degli apparecchi di sollevamento
Panorama attività UNI, CEN e ISO nel campo degli apparecchi di sollevamentoPanorama attività UNI, CEN e ISO nel campo degli apparecchi di sollevamento
Panorama attività UNI, CEN e ISO nel campo degli apparecchi di sollevamento
 
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANESB30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
 
Scaffold safe work method statement
Scaffold safe work method statementScaffold safe work method statement
Scaffold safe work method statement
 
"Rig Inspection Workshop - accredited by OCS Training Institute”
"Rig Inspection Workshop - accredited by OCS Training Institute”"Rig Inspection Workshop - accredited by OCS Training Institute”
"Rig Inspection Workshop - accredited by OCS Training Institute”
 
OCS - Rig Inspection Workshop - accredited by IADC
OCS - Rig Inspection Workshop - accredited by IADCOCS - Rig Inspection Workshop - accredited by IADC
OCS - Rig Inspection Workshop - accredited by IADC
 
Pamphlet on rake testing procedure for freight stock
Pamphlet on rake testing procedure for freight stockPamphlet on rake testing procedure for freight stock
Pamphlet on rake testing procedure for freight stock
 
Safety in Erection of Steel Structures
Safety in Erection of Steel StructuresSafety in Erection of Steel Structures
Safety in Erection of Steel Structures
 
"IADC Accredited Rig Inspection Workshop"
"IADC Accredited Rig Inspection Workshop""IADC Accredited Rig Inspection Workshop"
"IADC Accredited Rig Inspection Workshop"
 
Derrick manual
Derrick manualDerrick manual
Derrick manual
 
Rigging
RiggingRigging
Rigging
 
Airbus safetylib -flt_ops-toff_dep_seq07
Airbus safetylib -flt_ops-toff_dep_seq07Airbus safetylib -flt_ops-toff_dep_seq07
Airbus safetylib -flt_ops-toff_dep_seq07
 
Maintenace of passenger emergency alarm system of coaching stock
Maintenace of passenger emergency alarm system of coaching stockMaintenace of passenger emergency alarm system of coaching stock
Maintenace of passenger emergency alarm system of coaching stock
 
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
 
Safe use of Mobile Cranes
Safe use of Mobile CranesSafe use of Mobile Cranes
Safe use of Mobile Cranes
 
"Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche...
"Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche..."Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche...
"Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche...
 
Mobile crane safety rules
Mobile crane safety rulesMobile crane safety rules
Mobile crane safety rules
 
Mercury mercruiser marine engines #24 gm v 8 305 cid (5.0 l) 350 cid (5.7l) ...
Mercury mercruiser marine engines #24 gm v 8 305 cid (5.0 l)  350 cid (5.7l) ...Mercury mercruiser marine engines #24 gm v 8 305 cid (5.0 l)  350 cid (5.7l) ...
Mercury mercruiser marine engines #24 gm v 8 305 cid (5.0 l) 350 cid (5.7l) ...
 
HITACHI EX550-5 EXCAVATOR Service Repair Manual
HITACHI EX550-5 EXCAVATOR Service Repair ManualHITACHI EX550-5 EXCAVATOR Service Repair Manual
HITACHI EX550-5 EXCAVATOR Service Repair Manual
 

Viewers also liked

2015 Changes to the Discovery Rules of the Federal Rules of Civil Procedure
2015 Changes to the Discovery Rules of the Federal Rules of Civil Procedure2015 Changes to the Discovery Rules of the Federal Rules of Civil Procedure
2015 Changes to the Discovery Rules of the Federal Rules of Civil ProcedureJeremy Richter
 
INFLUENCE OF WIND ON LIFTING OPERATIONS
INFLUENCE OF WIND ON LIFTING OPERATIONSINFLUENCE OF WIND ON LIFTING OPERATIONS
INFLUENCE OF WIND ON LIFTING OPERATIONSSreenath Pokkadavath
 
Mg041911 Cortland Lifting Slings Presentation
Mg041911 Cortland Lifting Slings PresentationMg041911 Cortland Lifting Slings Presentation
Mg041911 Cortland Lifting Slings Presentationrarends
 
Lifting and handling 2
Lifting and handling 2Lifting and handling 2
Lifting and handling 2twalker2
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at workPaul Smith
 
Safe Lifting Training
Safe Lifting TrainingSafe Lifting Training
Safe Lifting TrainingDan Junkins
 
Lifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sitesLifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sitesSimon Faulkner-Duke
 
Mewp inspection checklist-copy1
Mewp inspection checklist-copy1Mewp inspection checklist-copy1
Mewp inspection checklist-copy1wirethehouse
 

Viewers also liked (18)

2015 Changes to the Discovery Rules of the Federal Rules of Civil Procedure
2015 Changes to the Discovery Rules of the Federal Rules of Civil Procedure2015 Changes to the Discovery Rules of the Federal Rules of Civil Procedure
2015 Changes to the Discovery Rules of the Federal Rules of Civil Procedure
 
Gist Croft, "Self-organization of the in vitro attached human embryo and its ...
Gist Croft, "Self-organization of the in vitro attached human embryo and its ...Gist Croft, "Self-organization of the in vitro attached human embryo and its ...
Gist Croft, "Self-organization of the in vitro attached human embryo and its ...
 
George Church and John Aach, "Stem Cells, Engineered Tissues, and Synthetic E...
George Church and John Aach, "Stem Cells, Engineered Tissues, and Synthetic E...George Church and John Aach, "Stem Cells, Engineered Tissues, and Synthetic E...
George Church and John Aach, "Stem Cells, Engineered Tissues, and Synthetic E...
 
INFLUENCE OF WIND ON LIFTING OPERATIONS
INFLUENCE OF WIND ON LIFTING OPERATIONSINFLUENCE OF WIND ON LIFTING OPERATIONS
INFLUENCE OF WIND ON LIFTING OPERATIONS
 
Mg041911 Cortland Lifting Slings Presentation
Mg041911 Cortland Lifting Slings PresentationMg041911 Cortland Lifting Slings Presentation
Mg041911 Cortland Lifting Slings Presentation
 
Lifting and handling 2
Lifting and handling 2Lifting and handling 2
Lifting and handling 2
 
Weekly first aid room checklist
Weekly first aid room checklistWeekly first aid room checklist
Weekly first aid room checklist
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at work
 
Water cooler monthly
Water cooler monthlyWater cooler monthly
Water cooler monthly
 
Safe Lifting Training
Safe Lifting TrainingSafe Lifting Training
Safe Lifting Training
 
Scissor lift 2 daily inspection log
Scissor lift 2 daily inspection logScissor lift 2 daily inspection log
Scissor lift 2 daily inspection log
 
Lifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sitesLifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sites
 
Mewp inspection checklist-copy1
Mewp inspection checklist-copy1Mewp inspection checklist-copy1
Mewp inspection checklist-copy1
 
Toilet cleaning check list
Toilet cleaning check listToilet cleaning check list
Toilet cleaning check list
 
Vehicle plant daily inspection log
Vehicle plant daily inspection logVehicle plant daily inspection log
Vehicle plant daily inspection log
 
Forklift safety
Forklift safetyForklift safety
Forklift safety
 
Weekly ambulance checklist
Weekly ambulance checklistWeekly ambulance checklist
Weekly ambulance checklist
 
Weekly generator check list
Weekly generator check listWeekly generator check list
Weekly generator check list
 

Similar to Personnel liftingad

FORKLIFT_EXCERPTS_FOR_REGULAR_PRINTING
FORKLIFT_EXCERPTS_FOR_REGULAR_PRINTINGFORKLIFT_EXCERPTS_FOR_REGULAR_PRINTING
FORKLIFT_EXCERPTS_FOR_REGULAR_PRINTINGCraig Ihde
 
Suspended personnel platforms 2017
Suspended personnel platforms 2017Suspended personnel platforms 2017
Suspended personnel platforms 2017John Newquist
 
Escalator replacement specifications rev 2 consolidated comments
Escalator replacement specifications   rev 2 consolidated commentsEscalator replacement specifications   rev 2 consolidated comments
Escalator replacement specifications rev 2 consolidated commentsgulilero
 
Aerial Lifts & Other Elevating Platforms Training by Safety Resource LLC
Aerial Lifts & Other Elevating Platforms Training by Safety Resource LLCAerial Lifts & Other Elevating Platforms Training by Safety Resource LLC
Aerial Lifts & Other Elevating Platforms Training by Safety Resource LLCAtlantic Training, LLC.
 
Crane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxCrane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxVikasMore37
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdfdinesh622857
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfssuseref23d3
 
Master Specifications Vehicle Lifts
Master Specifications Vehicle LiftsMaster Specifications Vehicle Lifts
Master Specifications Vehicle LiftsSlideCommunity
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sitesPrastowo Priyatmoko
 
JAR 23 and FAR 23 Comparison part 2
JAR 23 and FAR 23 Comparison part 2JAR 23 and FAR 23 Comparison part 2
JAR 23 and FAR 23 Comparison part 2Jio Gayon
 
ASME-B30.3- Tower Crane by Shamim Khan - Part 01.pptx
ASME-B30.3- Tower Crane by Shamim Khan - Part 01.pptxASME-B30.3- Tower Crane by Shamim Khan - Part 01.pptx
ASME-B30.3- Tower Crane by Shamim Khan - Part 01.pptxssusera34d87
 
Aerial and scissor lift safety
Aerial and scissor lift safetyAerial and scissor lift safety
Aerial and scissor lift safetyJason Redd
 
450 series rail installation instructions rev
450 series rail installation instructions rev450 series rail installation instructions rev
450 series rail installation instructions revYover Rodriguez
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003Minh Bui Si
 

Similar to Personnel liftingad (20)

FORKLIFT_EXCERPTS_FOR_REGULAR_PRINTING
FORKLIFT_EXCERPTS_FOR_REGULAR_PRINTINGFORKLIFT_EXCERPTS_FOR_REGULAR_PRINTING
FORKLIFT_EXCERPTS_FOR_REGULAR_PRINTING
 
Suspended personnel platforms 2017
Suspended personnel platforms 2017Suspended personnel platforms 2017
Suspended personnel platforms 2017
 
36 elevating employees
36 elevating employees36 elevating employees
36 elevating employees
 
Escalator replacement specifications rev 2 consolidated comments
Escalator replacement specifications   rev 2 consolidated commentsEscalator replacement specifications   rev 2 consolidated comments
Escalator replacement specifications rev 2 consolidated comments
 
Aerial Lifts Platforms by SR LLC
Aerial Lifts Platforms by SR LLCAerial Lifts Platforms by SR LLC
Aerial Lifts Platforms by SR LLC
 
Aerial Lifts & Other Elevating Platforms Training by Safety Resource LLC
Aerial Lifts & Other Elevating Platforms Training by Safety Resource LLCAerial Lifts & Other Elevating Platforms Training by Safety Resource LLC
Aerial Lifts & Other Elevating Platforms Training by Safety Resource LLC
 
Crane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxCrane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptx
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdf
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
 
Master Specifications Vehicle Lifts
Master Specifications Vehicle LiftsMaster Specifications Vehicle Lifts
Master Specifications Vehicle Lifts
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites
 
Aerial and scissor lift safety 2
Aerial and scissor lift safety 2Aerial and scissor lift safety 2
Aerial and scissor lift safety 2
 
JAR 23 and FAR 23 Comparison part 2
JAR 23 and FAR 23 Comparison part 2JAR 23 and FAR 23 Comparison part 2
JAR 23 and FAR 23 Comparison part 2
 
Standards Regulations
Standards RegulationsStandards Regulations
Standards Regulations
 
ASME-B30.3- Tower Crane by Shamim Khan - Part 01.pptx
ASME-B30.3- Tower Crane by Shamim Khan - Part 01.pptxASME-B30.3- Tower Crane by Shamim Khan - Part 01.pptx
ASME-B30.3- Tower Crane by Shamim Khan - Part 01.pptx
 
Aerial and scissor lift safety
Aerial and scissor lift safetyAerial and scissor lift safety
Aerial and scissor lift safety
 
is.3938.1983.pdf
is.3938.1983.pdfis.3938.1983.pdf
is.3938.1983.pdf
 
450 series rail installation instructions rev
450 series rail installation instructions rev450 series rail installation instructions rev
450 series rail installation instructions rev
 
2015 CRW - New Crane Rules = New Compliance Directives
 2015 CRW - New Crane Rules = New Compliance Directives 2015 CRW - New Crane Rules = New Compliance Directives
2015 CRW - New Crane Rules = New Compliance Directives
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003
 

Recently uploaded

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 

Recently uploaded (20)

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 

Personnel liftingad

  • 1. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments Personnel Lifting Platforms WAC 296-882-100 Scope This rule applies to the lifting, lowering, and transporting of personnel using personnel platforms connected to cranes or derricks. Personnel platforms can be either suspended from the crane or derrick by wire rope or chain, or attached to the boom of the crane or derrick. Using articulating boom cranes with suspended platforms is not allowed Important!  Do not use cranes or derricks for personnel lifting when there is a less hazardous way to accomplish the work. Cranes and derricks are designed and intended for material handling, and are not required to meet the same design standards as manlifts, aerial lifts, bucket trucks, and other conventional personnel-lifting equipment. The lifting or lowering of personnel using material handling cranes and derricks is prohibited unless all of the applicable requirements of WACs 296-882-100 through 296-882-60030 are met. ASME B23-0.1 Within the general scope defined in Section I, ASME B30.23 may apply to hoisting equipment covered within certain volumes of the ASME B30 standard, that is used to lift, lower, or transport personnel in a platform, by wire rope or chain, from hoist equipment, or by a platform that is mounted on a boom of the hoist equipment. The lifting of personnel is not allowed using some ASME B30 Standard equipment. The ASME B30 volume addressing the hoisting equipment to be used shall be consulted for the applicability of the ASME B30.23 volume. Section 23-0.2: Intent of ASME B30.23 The intent of this volume is to establish minimum design criteria, equipment features, and operational procedures for using material hoisting equipment to lift personnel. Use of this volume will not raise the level of safety of the material hoisting equipment to that obtained by using equipment specifically designed and manufactured for lifting personnel. The ASME B30 standard hoisting equipment is designed and intended for material handling and is not required to meet the same design standards required of conventional personnel lifting equipment (ANSI/SIA A 92 Aerial Platforms). Lifting and lowering of personnel using ASME B30 Standard hoisting equipment shall be undertaken only in circumstances when it is not possible to accomplish the task by less hazardous means. Unless all of the applicable requirements of this volume are met, the lifting or lowering of personnel using ASME B30 Standard equipment is prohibited. WAC 296-882-200 Design and Construction Requirements for Personnel Lifting Equipment Summary Your responsibility: To make sure personnel lifting equipment is safe for operation. 1
  • 2. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments WAC 296-882-20005 Design of platforms and suspension systems You must • Make sure personnel platforms and suspension systems manufactured under your direction are designed, constructed and tested according to ASME B30.23-1998, Personnel Lifting Systems. WAC 296-882-20010 Personnel platforms identification plate You must • Make sure an identification plate is located inside the platform and is easy to read from outside the platform while the platform is on the ground. - The plate must display the following information: ▪ Manufacturer’s name and address ▪ Platform rating in terms of weight and personnel ▪ Platform identification number ▪ Suspension system description for suspended platforms, or the intended hoisting equipment manufacturer identification for boom attached platforms ▪ Weight of the empty platform and its suspension system ▪ Date the platform was manufactured ▪ Certification of compliance to the design, construction, and testing requirements of this volume ▪ Listing of any unique operational environments for which the platform has been designed 1.1.1(b)(7) An identification plate located on the interior of the platform and legible from outside of the platform, while the platform is on the ground, that displays, as a minimum, the following information: a) manufacturer name and address b) platform rating in terms of weight and personnel c) platform identification number d) suspension system description for suspended platforms, or the intended hoisting equipment manufacturer identification for boom attached platforms e) weight of the empty platform and its suspension system f) date of the platform manufacture g) certification of compliance to the design, construction, and testing requirements of this volume h) listing of any unique operational environments for which the platform has been designed 2
  • 3. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments WAC 296-882-300 Hoisting Equipment Summary Your responsibility: To make sure hoisting equipment for personnel lifting is used correctly WAC 296-831-30005 Use the correct hoisting crane or derrick You must: • Make sure the following equipment is not used to lift personnel: - Articulating boom cranes - Pendant supported, jib type boom extensions without positive stops (excerpt from B30.23 Scope) The lifting of personnel is not allowed using some ASME B30 Standard equipment. The ASME B30 volume addressing the hoisting equipment to be used shall be consulted for the applicability of the ASME B30.23 volume. (excerpt from B30.22 Scope) Exemptions from this volume include: (c) all units equipped with or designed primarily for personnel baskets, ladders, platforms, etc. The second bullet is from (a) on the next page WAC 296-882-30010 Crane or derrick requirements Important! Cranes and derricks must meet the requirements in the WACs that apply to them, and the applicable hoisting equipment ASME B30 volume, in addition to these requirements. You must: • Make sure the crane or derrick you are using to hoist the personnel platform meets the following requirements: - Live boom or live load capabilities allowing free fall are removed for the period of personnel lifting - An anti-two-block device is installed on the hoisting systems - On cranes and derricks with variable angle booms there is a boom angle indicator that is clearly visible to the operator - Has a device that clearly shows the operator the boom’s extended length, unless the boom length does not affect the load rating, on cranes with telescoping booms 1.2.2 Hoisting Equipment (a) Features (1) Hoist equipment live boom or live load capabilities shall be removed for the period of personnel lifting. (2) Rope or chain hoisting systems, that are used for personnel lifting, shall have an anti-two-block device installed. (3) Hoisting equipment with a variable angle boom shall have a boom angle indicator readily visible to the operator (4) Hoisting equipment with telescoping booms shall have a boom length indicator, readable from the operator’s station, unless the load rating is independent of the boom length. (5) Hooks used for attachment of a personnel lifting platform shall be of a type that canbe positively locked closed and that will prevent the platform lifting bridle from being dislodged. (6) Hoisting equipment shall have automatic brakes such that when the equipment operating controls are released the motions are brought to rest. (7) A holding device (such as a load hold check valve) shall be provided in hydraulic or pneumatic systems to prevent uncontrolled movement of . 3
  • 4. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments - Has hooks, when used to attach a platform, that  Can be positively locked closed  Will prevent the lifting bridle from being dislodged - Has automatic brakes on the equipment, so motions stop when the operating controls are released - Has a holding device, such as a load hold check valve, that will prevent uncontrolled movement of the hoisting equipment if a system fails, on hydraulic or pneumatic systems - Has a way to prevent hydraulic or pneumatic outriggers or stabilizers, if these are a part of the hoisting equipment, from retracting if the hydraulic or pneumatic line fails the hoisting equipment in the event of a system failure (e.g. supply hose). (8) A means to prevent the retraction of any hydraulically or pneumatically activated outriggers or stabilizers in the event a hydraulic or pneumatic line fails, when such devices are a component of the hoisting equipment. (9) Pendant supported, jib type, boom extensions without positive stops shall not be used to lift personnel. • Make sure the crane is level within 1% of level grade and located on firm footing - Make sure outriggers or stabilizers are extended, blocked and locked according to manufacturer’s recommendations, if the crane is equipped with them 3.2.2(a)(4)(the operator shall) verify that the hoisting equipment is set up and maintained within one percent of level during a personnel lift 3.2.2(a)(3) operate hoisting equipment with outriggers with outriggers or stabilizers extended, blocked and locked in accordance with manufacturer’s specifications. • Make sure the total weight of the loaded personnel platform and related rigging does not exceed fifty percent of the crane’s rated load capacity 3.2.2(a)(7) Not allow the total weight of the lifted load including rigging, platform, personnel, tools, and material to exceed 50 percent of the hoisting equipment’s rated load, under the planned conditions of operation (except during testing as outlined in Chapter 23-2) WAC 296-882-400 Inspections, Maintenance and Testing Summary Your responsibility: To keep personnel lifting equipment in safe operating condition by performing regular inspections, maintenance, and testing. 4
  • 5. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments WAC 296-882-40005 Initial inspections on personnel platforms You must • Have a qualified person inspect personnel platforms before initial use and at each new job site to make sure the requirements of WAC 296-882-100 through WAC 296-882-60030 are met 2.1.1 Personnel Lifting Platform (Inspection) (b) Frequency (1) Initial Inspection. Prior to initial use and at each new job site all platforms shall be inspected by a qualified person to verify compliance with the provisions of this volume. (a) is manufacturer’s requirement: (1) The platform manufacturer shall furnish complete inspection criteria for platform users. The criteria shall address all inspection frequency classifications listed in this volume and shall cover: (a) the platform (b) rigging components (c) fasteners (d) all safety features and attachments. WAC 296-882-40010 Frequent inspections on personnel platforms You must • Make sure an appointed person inspects all items in Table 1 at least once each day, before use. • Correct any hazardous condition before using the platform. • Keep the most recent, dated inspection records available for the duration of the lift operation. 2.1.1(b)(2) Regular Inspection (a) Frequent. The platform, suspension system, attachment points, and any platform motion controls shall be inspected at least once each day, before use, by a designated person. The inspection is to identify conditions that have been specifically indicated by the platform manufacturer, or a qualified person, as potentially creating a hazardous operating condition. The inspection shall address at least those items listed in Appendix III. Any conditions found that constitute a hazard shall be corrected prior to lifting personnel. 2.1.1(b)(2) (c) Records (1) For frequent inspections, dated records for the hoisting equipment and personnel platform shall be made and kept by the platform user for the duration of the personnel lift operation (Table 1, Frequent inspection checklist for personnel lifting platforms) WAC 296-882-40015 Periodic inspections on personnel platforms You must: • Make sure a qualified person performs a periodic inspection of personnel platforms at least once a year, according to manufacturer’s instructions • Correct any hazardous condition before using the platform • Keep the most recent, dated inspection records with the platform and available for review Note: Platforms that have been out of service for more than a year don’t 2.1.1(b)(2) (b) Periodic. At least once every 12 months, or as required by the platform manufacturer, a periodic inspection of the platform shall be performed by a qualified person in accordance with the instructions provided by the manufacturer. Platforms which have been out of service for 12 or more consecutive months shall receive a periodic inspection before use. 2.3.1 (b) (1) Any hazardous condition disclosed by any inspection shall be corrected before use of the platform is resumed. Adjustments and repairs shall be accomplished by designated personnel. 2.1.1(b)(2)(c) (2) For periodic inspections, dated records for the platform shall be 5
  • 6. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments need to have a periodic inspection until they are put back into use. made by the platform owner. The last periodic inspection shall be kept with the platform and available for review. WAC 296-882-40020 Adjustments and repairs on personnel platforms You must: • Make sure any adjustments or repairs to the platform is done by a designated person − Adjustments or repairs to the suspension system must be done by a qualified person. • Make sure replacement parts and repairs are equal to or exceed the original equipment specifications. • Make sure the manufacturer or a qualified person has approved any modifications, in writing, before they are made. • Keep records of any repairs to the structural components of the platform • Make sure all welding repairs are done by a certified welder. 2.3.1(b)(5) Any adjustment or repair to the platform suspension system shall be done by a qualified person 2.3.1 (b) (1) Any hazardous condition disclosed by any inspection shall be corrected before use of the platform is resumed. Adjustments and repairs shall be accomplished by designated personnel. 2.3.1(a) preventative maintenance (1) A preventative maintenance program based on the platform manufacturer’s recommendations should be established (2) Replacement parts used shall be equal to or exceed the original equipment specification 2.3.1(b)(3) Replacement parts used or repairs made shall be equal to or exceed the original equipment specification. 2.3.1(c) Modifications. Only modifications approved in writing by the manufacturer or a qualified person shall be accomplished. 2.3.1(d) Records. The platform owner shall maintain records on any repairs to, or replacements of, the structural components of the platform. 2.3.1(b)(4) All welding repairs shall be done by a certified welder Not used: 2.3.1(b)(2) Adjustments shall provide for correct functioning of components. (1) is a “should”. WAC 296-882-40025 Proof test platforms and rigging You must 1. Make sure the platform and rigging is proof tested at each new job site before lifting personnel. • Test as follows: - Test to 125% of the platform’s rated capacity - Hold the platform suspended for 5 minutes with the test load evenly distributed on the platform Note: This may be done at the same time as the trial lift 2.2.1(b)Proof Testing (1) At each new job site, prior to hoisting people in the personnel platform, the platform and rigging shall be proof tested to 125% of the platform’s rating. With the proof test load evenly distributed in the platform, the platform shall be hoisted and held in a suspended position for not less than five minutes. After the proof testing, the platform shall be inspected by a qualified person. Any damage revealed by the inspection shall be corrected and another proof test conducted. 2.2.1(a) is Platform Manufacturer Tests. If manufacturing their own platforms, they were already told to test in accordance with the ANSI. 6
  • 7. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments You must: • Do the following after proof testing: - Have an appointed person inspect the platform and rigging - Correct any deficiencies - Perform another test after any deficiencies are corrected • Keep the most recent proof testing records available at the jobsite 2. Make sure the platform and rigging is proof tested after any structural repair or modification, before lifting personnel 2.2.1(b)(3) After any structural repair or modification, a platform shall be proof tested… 2.2.1(b)(2) is a should: When feasible, the hoisting equipment to be used for lifting personnel should be the equipment used to perform the proof tests at the job site as defined in para. 23-2.2.1(b). • Test suspended platforms in the following order: - Test to 150% of the platform’s rated capacity - Raise the loaded platform, then lower it at a speed of at least 100 ft/min. - Bring the platform to a stop by using the hoisting equipment brakes - Let the platform hang for at least 5 minutes. - Have a qualified person inspect the platform and rigging. - Correct any deficiencies. - Perform another test after any deficiencies are corrected 2.2.1(b)(3) After any structural repair or modification, a platform shall be proof tested to 150% of the platforms rating. Boom attached platforms shall use the test procedure described in para. 23.2.2.1(b)(1). Suspended platforms shall be tested by raising the loaded platform to a height, then lowering it at a speed of not less than 100 ft/min. Once a lowering speed of 100 ft/mion or more is reached, the platform descent shall be halted by applying the hoisting equipment brakes and then the platform allowed to hang for a period of not less than five minutes. After this test and hanging period, the platform shall be inspected by a qualified person. Any damage revealed by the inspection shall be corrected and another proof test conducted. • Test attached platforms in the following order: - Test to 150% of the platform’s rated capacity. - Hold the platform suspended for 5 minutes with the test load evenly distributed on the platform. - Have an appointed person inspect the platform and rigging. - Correct any deficiencies. - Perform another test after any deficiencies are corrected. (3) After any structural repair or modification, a platform shall be proof tested to 150% of the platforms rating. Boom attached platforms shall use the test procedure described in para. 23.2.2.1(b)(1). 2.2.1(b)(1) At each new job site, prior to hoisting people in the personnel platform, the platform and rigging shall be proof tested to 125% of the platform’s rating. With the proof test load evenly distributed in the platform, the platform shall be hoisted and held in a suspended position for not less than five minutes. After the proof testing, the platform shall be inspected by a qualified person. Any damage revealed by the inspection shall be corrected and another proof test conducted. 7
  • 8. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments • Keep the most recent proof testing records available at the jobsite 2.2.1(c) Records. The most recent record of proof testing shall be maintained at the jobsite. WAC 296-882-500 Management Responsibilities Your responsibility: To make sure all duties are performed by the correctly appointed person. WAC 296-882-50005 Job site management You must: • Make sure job site management performs the duties listed in Table 2. Table 2 Job site management duties • Designate a “Personnel Lift Supervisor” for each personnel lift operation. • Require that all personnel associated with the lift receive the briefings and safety indoctrinations specified in this volume. • Prohibit the lifting of personnel whenever the operator: - Does not feel physically or mentally fit to perform the operation. - Has been working for more than 10 hours prior to the start of the lift or the lift will not be completed before the operator has been working for 12 hours. - Did not have at least eight hours off immediately prior to the work shift containing the personnel lift operation. • Designate the appropriate number of signalpersons, ground crew, and platform occupants to perform the personnel lift safely. - In suspended and boom attached platforms without boom motion controls, one occupant shall be appointed as the platform signalperson. This Section 23-3.1: Personnel 23-3.1.1 Management (a) Responsibilities (1) Management shall require that the provisions of this volume are understood and applied at the operational levels, and that the appropriate portions of this volume are included in the pre-lift briefing information. (2) Management shall designate qualified individuals at each job site to perform the duties of the “Personnel Lift Authorizer.” As a minimum these individuals shall be responsible for: (a) verifying the need for a personnel lift; (b) verifying the equipment to be used for the personnel lift meets the requirements of Chapter 23-1; (c) authorizing the personnel lift operation’ (d) requiring the personnel lift be accomplished in accordance with the provisions of this volume. (3) Job site management shall require that the provisions of this volume are implemented during personnel lifting operations. (4) Job site management shall designate a “Personnel Lift Supervisor” ANSI’s requirements aren’t separated cleanly; I listed the two paragraphs here but we divided the duties according to who is responsible for them. 8
  • 9. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments person shall be responsible for communicating with the operator and/or other appointed signalpersons. • Require that the hoisting equipment used to lift personnel shall be in compliance with the requirements prescribed in this volume and the applicable hoisting equipment ASME B30 volume. • Have a Personnel Lifting Management and Approval Program that requires the criteria of this rule to be met before to lifting personnel. • Instruct operators of hoisting equipment, installed on floating vessels, not to lift personnel when the list or trim of the vessel exceeds five degrees. If mobile hoisting equipment is placed on floating vessels, operators shall not lift personnel when the list or trim of the vessel exceeds one degree. for each personnel lift operation. As a minimum, the individual shall be responsible for: (a) holding the pre-lift meeting; (b) verifying all required inspections have been accomplished; (c) verifying qualified persons are assigned to perform the functions of the operator, signalpersons, and ground crew; (d) supervising the personnel lift operation; (e) accomplishing other tasks that may be needed to enhance the safety of the personnel lift. (5) Job site management shall require that all personnel associated with the lift receive the briefings and safety indoctrinations specified in this volume. (6) Job site management shall not allow or require any operator to lift personnel under the following circumstances: (a) The operator does not feel physically or mentally fit to perform the operation. (b) The operator has been working for more than 10 hours prior to the start of the lift or the lift will not be completed before the operator has been working for 12 hours. (c) the operator did not have at least eight hours off immediately prior to the work shift containing the personnel lift operation. (7) Job site management shall designate the appropriate number of signalpersons, ground crew, and platform occupants to perform the personnel lift safely. (a) In suspended and boom attached platforms without boom motion controls, one occupant shall be designated as the platform signalperson. This person shall be responsible for communicating with the operator and/or other designated signalpersons. (8) Job site management shall require that the hoisting equipment used to lift personnel shall be in compliance with the requirements prescribed in this volume and the applicable hoisting equipment ASME B30 volume. WAC 296-882-50010 Personnel Lift Authorizer 9
  • 10. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments You must: • Assign qualified individuals at each job site who will be responsible for the duties listed in Table 3. Table 3 Personnel lift Authorizer Responsibilities • Verifying - The need for a personnel lift - That there are no less hazardous alternatives to performing the work, or providing access to the area. The personnel lift shall not be authorized when less hazardous means are feasible. • Verifying the equipment to be used for the personnel lift meets the requirements of the chapter governing that equipment • Authorizing the personnel lift operation • Reviewing and approving the personnel lift plan. Retain the plan as part of the job site records. • Verifying that conditions provide clear visibility. When conditions such as darkness, fog, or snow prevent clear visibility, do not authorize personnel lifting. • Authorize personnel lifting over, under, or in the vicinity of power lines, in accordance with the requirements Chapter 296-45, Safety standards for electrical work Section 23-3.2: Practices 23-3.2.1 Management Job site management shall have a Personnel Lifting Management and Approval Program that requires the criteria of this volume to be met prior to lifting personnel. The program shall, as a minimum, require: (a) The Personnel Lift Supervisor to prepare a personnel lift plan containing at least the information shown in Appendix II. This plan shall be presented to the Personnel Lift Authorizer for review/approval. The plan shall be retained as part of the job site records. (b) The Personnel Lift Authorizer to verify that there are no less hazardous alternatives to performing the work, or providing access to the area. The personnel lift shall not be authorized when less hazardous means are feasible. (c) The Personnel Lift Authorizer to verify that conditions provide clear visibility. When conditions such as darkness, fog, or snow prevent clear visibility, the Personnel Lift Authorizer shall not authorize personnel lifting. (d) The Personnel Lift Authorizer to only authorize personnel lifting over, under, or in the vicinity of power lines, in accordance with the requirements of Appendix I; (e) personnel platforms not to be used in winds in excess of 20 mph (32.2 km/hr) at the hoisted platform height, electric storms, snow, ice, sleet, or other adverse weather conditions which could affect the safety of personnel. (f) the Personnel Lift Supervisor to verify that each of the requirements in this Section have been met; (g) the Personnel Lift Supervisor to hold a pre-lift briefing attended by the hoisting equipment operator, platform occupants, and ground crew. If individuals are changed during a series of personnel lifts, each new person shall be appropriately briefed by the Personnel Lift Supervisor. Contents of the briefing shall, as a minimum, cover: (1) the operations section of this volume (2) the assignment and responsibilities of each person involved in the lift operation 10
  • 11. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments (3) the procedures to be followed (4) guidance on general and specific safety precautions (5) special signals for the operation (6) unique considerations of the lift (7) work to be accomplished during the lift (8) if applicable, the responsibilities and assignments contained in Appendix I when lifting personnel near electrical power lines (h) the Personnel Lift Supervisor to terminate personnel lifting operations if hazardous conditions develop during the lift (i) personnel platforms to be only used for personnel, their tools, and sufficient material to do their work. They shall not be used for solely transporting bulk materials. (j) a qualified person to evaluate the safety concerns of the operational environment and verify the platform and hoisting equipment are suitable for use. Additionally, special work circumstances may require further precautions. Precautions such as, but not limited to the following shall be taken: (1) When welding is to be accomplished from the personnel platform, suitable electrode holders shall be provided to protect them from contact with any conducting components of the platform (2) Job site management shall instruct operators of hoisting equipment, installed on floating vessels, not to lift personnel when the list or trim of the vessel exceeds five degrees. If mobile hoisting equipment is placed on floating vessels, operators shall not lift personnel when the list or trim of the vessel exceeds one degree. (3) When personnel lifts are conducted over water, personnel flotation devices shall be provided and required to be worn. Personnel fall protection devices with quick release features shall be provided, and required to be worn. The fall protection device shall be appropriately attached while personnel are lifted over land and detached while personnel are lifted over water. (4) A boat with appropriate rescue personnel shall be available at all times during a personnel lift over water (5) Appropriate personnel protective equipment shall be provided and required to be used around toxic, flammable, or hazardous substances or fumes. (6) Any concentrated loading of the platform shall be reviewed to preclude the overstressing of any component or impairing the platform stability. 11
  • 12. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments WAC 296-882-50015 Personnel Lift Supervisor You must: • Assign a Personnel Lift Supervisor, who will be responsible for the duties outlined in Table 4. Table 4 Personnel Lift Supervisor duties • Holding the pre-lift meeting; • Verifying all required inspections have been accomplished; • Verifying qualified persons are assigned to perform the functions of the operator, signalpersons, and ground crew; • Supervising the personnel lift operation; • Accomplishing other tasks that may be needed to enhance the safety of the personnel lift. • Preparing a personnel lift plan containing at least the information shown in Appendix II. • Verifying that each of the requirements in this Section have been met; • Holding a pre-lift briefing attended by the hoisting equipment operator, platform occupants, and ground crew. If individuals are changed during a series of personnel lifts, each new person shall be appropriately briefed by the Personnel Lift Supervisor. Contents of the briefing shall, as a minimum, cover: - the operations section of this rule - the assignment and responsibilities of each person involved in the lift operation - the procedures to be followed - guidance on general and specific safety precautions - special signals for the operation - unique considerations of the lift - work to be accomplished during the lift - if applicable, the responsibilities and assignments contained in Chapter 296-45, Safety standards for electrical work, when lifting personnel near electrical power lines See the two sections listed above for these requirements. 12
  • 13. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments • Terminate personnel lifting operations if hazardous conditions develop during the lift WAC 296-882-600 Lifting Personnel Summary Your responsibility: To make sure personnel lifting equipment is operated safely. WAC 296-882-60005 Lift personnel as a last resort only You must • Lift personnel on platforms with cranes or derricks only if it is the only possible way to accomplish the work that needs to be done. 13
  • 14. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments WAC 296-882-60010 Hold a prelift meeting You must • Make sure a prelift meeting is held before the trial lift at each new location as follows: - The crane or derrick operator, the signal person, employees who will be lifted, and the lift supervisor must attend. - Cover all of the following: o The requirements of WAC 296-882-200 through WAC 296-882-60030 o Assignments and responsibilities of each person involved in the operation o The procedures that will be followed o Special signals and unique considerations of the lift o What work will be accomplished during the lift - Repeat the meeting for any employees new to the operation 3.2.1(g) (The program shall require) The Personnel Lift Supervisor to hold a pre-lift briefing attended by the hoisting equipment operator, platform occupants, and ground crew. If individuals are changed during a series of personnel lifts, each new person shall be appropriately briefed by the Personnel Lift Supervisor. Contents of the briefing shall, as a minimum, cover: (1) the operations section of this volume (2) assignment and responsibilities of each person involved in the lift operation (3) the procedures to be followed (4) guidance on general and specific safety precautions (5) special signals for the operation (6) unique considerations of the lift (7) work to be accomplished during lift (8) if applicable, the responsibilities and assignments contained in Appendix I when lifting personnel near electrical power lines WAC 296-882-60015 Set up hoisting equipment correctly You must • Make sure the operator inspects the area where the hoist equipment will be set up, and looks for: - Overhead obstructions and electrical lines - Hazardous locations - Inadequate surface area - Inadequate support to withstand all force imposed - Wind, weather, and unstable conditions - Other potentially hazardous conditions 3.2.2(a) the operator shall: (1) inspect the hoist equipment setup area before the personnel lift and report his observations to the Personnel Lift Supervisor. The operator shall inspect the area for potential hazards such as, but not limited to: (a) excessive load and/or radius (b) overhead obstructions and electrical transmission lines (c) hazardous locations (d) inadequate surface and support to withstand all forces imposed (e) wind, weather, and unstable conditions (f) any potentially hazardous conditions WAC 296-882-60020 Perform a trial lift You must • Make sure a trial lift with the personnel platform is performed, on each shift before lifting personnel, to check the following: 3.2.2(a)(9) Perform a trial lift prior to lifting personnel with the platform on each shift and after any change of setup location, hoist equipment configuration, or operator. These lifts shall be used to ascertain that hoist equipment setup and configuration is correct, load capacities are adequate, that no hazardous interferences exist, and to further demonstrate the operator’s operational competence; 14
  • 15. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments - Hoist equipment setup and configuration is correct - Load capacities are adequate - No hazardous interferences exist - The operator’s operational competence • Load the unoccupied platform to at least the anticipated load weight (10) verify that during the trial lift, the platform is loaded to at least the weight expected during the actual lift; • Repeat the trial lift before lifting personnel whenever - The crane or derrick is moved and set up in a different location. - The crane or derrick is reconfigured. - The operator is changed. 3.2.2(a)(9) Perform a trial lift prior to lifting personnel with the platform on each shift and after any change of setup location, hoist equipment configuration, or operator. These lifts shall be used to ascertain that hoist equipment setup and configuration is correct, load capacities are adequate, that no hazardous interferences exist, and to further demonstrate the operator’s operational competence; • Make sure any defects that create a safety hazard are corrected before lifting people. 2.1.1(b)(2)(a)(Frequent inspection) ………Any conditions found that constitute a hazard shall be corrected prior to lifting personnel WAC 296-882-60020 Performing the personnel lift You must • Safely perform the personnel lift. Make sure: - The personnel platform is not loaded with more than its rated load capacity 3.2.2(a)(7) Not allow the total weight of the lifted load including rigging, platform, personnel, tools, and material to exceed 50 percent of the hoisting equipment’s rated load, under the planned conditions of operation (except during testing as outlined in Chapter 23-2) - Materials and tools being lifted by a platform are:  Secured to prevent movement  Evenly distributed on the platform 3.2.4(a)(5) (The platform occupants shall) have materials and equipment evenly distributed and secured while the platform is lifted - The personnel platform is hoisted slowly, with no sudden movements 3.2.2 (a)(14) Perform all movements of the platform in a slow, controlled manner to minimize sudden movements of the platform - Tag lines are used to control the motion of suspended platforms, unless using them creates a hazard 3.2.3(f) (The ground crew shall) use tag lines for motion control of suspended platforms, unless their use 15
  • 16. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments creates an unsafe condition. - The platform is secured to the structure where the work will be performed before employees exit or enter the platform, unless securing to the structure is unsafe. 3.2.4(a)(8) (the platform occupants shall) not enter or exit a suspended platform while it is raised unless the platform has an installed gate and the platform is physically secured to the structure to which the occupants are entering or exiting. - No other load lines on the crane or derrick are used to lift anything while personnel are on a platform. 3.2.2(a)(22) (The operator shall) not lift any other loads, on any other load lines, while conducting a personnel lift. When the hoisting equipment has a boom attached platform without controls it shall not be used for other lifting service. - Brakes and locking devices are engaged when the personnel platform is occupied and in a stationary working position 3.2.2(a)(19) set all brakes and locks on the hoisting equipment after positioning of the personnel platform and before personnel perform any work - The lowering motion is power-controlled only  Free fall is not allowed 3.2.2(a)(15) engage the power controlled lowering mechanism at all times the platform is occupied (no free fall). • Make sure there are enough signalpersons, ground crew, and platform occupants to perform the lift safely. - For platforms without boom motion controls, make sure one occupant is designated as the platform signalperson, responsible for communicating with the operator and other signalpersons. 3.1.1(a)(7) Job site management shall designate the appropriate number of signalpersons, ground crew, and platform occupants to perform the personnel lift safely. (a)In suspended and boom attached platforms without boom motion controls, one occupant shall be designated as the platform signalperson. This person shall be responsible for communicating with the operator and/or other designated signalpersons. • Make sure an appointed person - Verifies the platform is securely attached to the crane or derrick 3.1.3(b)(3) verifying the personnel platform is securely attached to the hoisting equipment - Verifies the load line is not attached to or wrapped around the platform 3.1.3(b)(4) verifying the load line is not directly attached to, or wrapped around, the personnel platform; - Verifies boom-attached personnel platforms are attached according to manufacturers specifications or a qualified person 3.1.3(b)(5) verifying boom attached personnel platforms are only attached using the pins and fittings specified by the hoist equipment manufacturer or a qualified person; - Keeps people from passing under the raised platform 3.1.3(b)(6) keeping people from passing under the raised personnel platform; • Make sure employees working as part of the ground crew do not have other duties or engage in any practice that will reduce the safety of the personnel lift 3.1.3(c) Conduct. The ground crew shall not engage in any practice or have any other duties which will reduce the safety of the personnel lift operation. • Make sure there are no more people on the platform than 3.2.4(a)(4) 16
  • 17. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments are needed to do the job (The platform occupants shall) be limited in number, commensurate with the work being performed, platform design and hoisting equipment limitations. • Make sure all platform occupants: - Are qualified to operate the controls on a platform that has controls 3.1.4(a)(4) Occupants of a platform with controls shall be qualified to operate the controls. - Are familiar with the hand signals posted in the platform 3.1.4(b)(5) being familiar with the hand signals posted in the platform. All occupants shall know the emergency stop signal. - Know the emergency stop signal 3.1.4(b)(5) being familiar with the hand signals posted in the platform. All occupants shall know the emergency stop signal. - Are wearing full body harness attached to specific anchorage points with a lanyard, unless working over water. See WAC 296-882-60030 for requirements when working over water. 3.2.4(a)(3) (The platform occupants shall) wear personnel fall protection devices with lanyards attached to a specific anchorage point(s), unless special circumstance work requirements dictate otherwise This is an increase, but put in per Dan - Do not stand, sit on, or work from the rails - Do not use any thing to raise their working height 3.2.4(a)(6) not stand, sit on, or work from the top rail, intermediate rail, to board, or use any other device to enhance their vertical height working capability; - Do not pull the platform out of plumb 3.2.4(a)(7) not pull the platform out of plumb with the hoisting equipment. - Keep all parts of their body inside the platform during raising, lowering, and positioning, unless they are the signalperson 3.1.4(b)(2) platform occupants shall be responsible for keeping all parts of their body inside the platform during raising, lowering, and positioning, except when performing duties as a designated signalperson - Stay in sight of or in direct communication with the operator - Stay in continuous sight of the signal person, if used 3.2.4(a)(1)(The platform occupants shall) remain in continuous sight or in communication with the operator, and in sight and communication of a signalperson. • Make sure the operator - Doesn’t allow the rated load to be exceeded when loads are transferred to the platform. 3.2.2(a)(8) not allow the platform’s rating or the hoisting equipments reduced rated load to be exceeded when loads are transferred to the hoisted platform; - Positions the platform so it can be tied off to the structure where occupants are entering or leaving, if the platform can’t be set down.  Make sure the operator doesn’t move the platform away from the structure until it is freely suspended. 3.2.2(a)(11) position the platform so that it may be tied off to the structure to which the occupants are entering or leaving, if the platform cannot be landed during the entrance or exit of the occupants. If the platform has been tied off, the operator shall not move the platform until it is verified that it is freely suspended. - Doesn’t move the platform faster than 100 ft/min, except during testing 3.2.2(a)(16) not lift or lower an occupied platform at a speed in excess of 100 ft/min (except during testing as outlined in 23-2) - Moves the platform under controlled conditions and under the direction of a designated signalperson 3.2.2(a)(20) move the platform under controlled conditions and under the direction of a designated signalperson 17
  • 18. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments - Doesn’t disable any hoist equipment safety device during a personnel lift 3.2.2(a)(23) not disable, or allow to be disabled, any hoist equipment safety device during a personnel lift - Is at the controls at all times while the engine is running and the platform is occupied, unless using a boom mounted platform that has both:  Boom mounted motion controls and  A way of lowering, retracting and rotating if the primary power source stops working 3.1.2(c)(5) The hoisting equipment operator shall: (a) when involved with a suspended platform, boom mounted platform without controls, or a boom mounted platform with controls but without a means of lowering, retracting, and rotating in the event the primary power source becomes inoperative, remain at the hoisting equipment controls whenever personnel are in the platform (b) when involved with a boom mounted platform with boom motion controls and a means of lowering, retracting, and rotating in the event the primary power source becomes inoperative, be free not to remain at the hoisting equipment controls 3.2.2(a)(17)(The operator shall:) in the case of suspended or boom mounted platforms, without controls, remain at the hoisting equipment controls at all times when the platform is occupied. 3.2.2(a)(18) in the case of boom mounted platforms, with controls, be free to not remain at the hoisting equipment controls. - Stops hoisting immediately when  Wind exceeds 20 mph at the hoisted platform height  Adverse weather, such as electric storms, snow, ice, or sleet occurs 3.2.1(e) personnel platforms not to be used in winds in excess of 20 mph at the hoisted platform height, electric storms, snow, ice, sleet, or other adverse weather conditions which could affect the saftey of personnel. • Make sure the crane does not travel while personnel are being lifted, except when the equipment runs on fixed rails or runways 3.2.2(a)(13) (The operator shall) not travel the hoisting equipment with personnel in the personnel platform except when the equipment runs on fixed rails or runways. 18
  • 19. Personnel Lifting March, 2005 Proposed Wording ASME B30.23 Comments WAC 296-882-60030 Special Work Circumstances You must 1. Make sure, when lifting personnel over water, that: - Personal flotation devices are provided and worn - Personal fall protection devices with quick release features are provided and worn - Fall protection devices are attached while personnel are being lifted over land, and detached while they are lifted over water 3.2.1(j)(3)<for over water> When personnel lifts are conducted over water, personnel flotation devices shall be provided and required to be worn. Personnel fall protection devices with quick release features shall be provided, and required to be worn. The fall protection device shall be appropriately attached while personnel are lifted over land and detached while personnel are lifted over water. - Make sure a boat with rescue personnel is available at all times 3.2.1(j)(4)A boat with appropriate rescue personnel shall be available at all times during a personnel lift over water. 2. Make sure, when hoisting equipment is installed on floating vessels, that personnel are not lifted when the list or trim of the vessel is more than 5° 3.2.1(j) (2) Job site management shall instruct operators of hoisting equipment, installed on floating vessels, not to lift personnel when the list or trim of the vessel exceeds five degrees. If mobile hoisting equipment is placed on floating vessels, operators shall not lift personnel when the list or trim of the vessel exceeds one degree. 3. When welding is going to be done from the personnel platform, make sure suitable electrode holders are provided to protect them from contact with any conducting parts of the platform. 3.2.1(j)(1) 19