1. Ashraf M.Yassin
Mobile : 0 02 01222936544
E-mail : aboyassin65@yahoo.com
Personal Data
Name : Ashraf Mohamed Yassin
Date of Birth : Feb.1965
Experience : painting & coating Engineer
+2 01222936544
Nationality : Egyptian
Military Status : Completed
Languages : Arabic (Mother Tongue), English (Written & Spoken: Fluent)
Education : B.Sc. Mechanical-Power Dep.1987 Suez canal University.
BGAS-CSWIP Painting Inspector Gr2
Qualification
I have been responsible for the application painting procedures, ITP, specification
and international codes relevant to gas, oil industry and petrochemicals.
For the past (20) years ago from (1993 – 2014) working as a painting & coating inspector
Last six years in United Arab Emirates
Follow all quality activities (Q.C) done in site such as blasting by(sand, garnet, grit &aluminum
silicate) painting systems applied onshore such tanks (internal / external paint), pipes, steel
structure and vessels. Estimated the cost & consumption of project required (paint material).
Offshore platforms applied many painting system such (Top side, decks, Splash zone, under
splash zone, offshore pipe lines & Risers).
Also working as a coating inspector applied many wrapping system such concrete, polyethylene,
F.B.E coating & shrink sleeves, polypropylene and under ground paint.
Follow all required tests during and after application
J
JOB Experience
June 2012.Up to date.
Company name: - Aegean oil Terminal, UAE, New Fuel Oil Tank Farm
Consultant: - Germanischer Lloyd Offshore and Industrial Services
Project name: Independent Third Party Certification & Inspection Services.
Title: - Coating &painting Engineer
Place of Inspection Fujairah, UAE
Duties : - Witness and Review all painting and coating activity done in plant
- Onshore pipe line 6, 8, 12&16" diameter follow coating activity in filed weld and
applied all required inspection tests according to project spec. such as pull-off test & holiday test
- Witness surface preparation and painting application done in internal & external tanks, above &
underground pipes carbon steel, stainless steel & duplex and steel structure.
Follow project specification, ITP, International codes and standards.
Sep.2011– June 2012.
Company name: - Leighton Offshore Ltd (LO)
Consultant: - Germanischer Lloyd Offshore and Industrial Services
Project name: Third Party Certification & Inspection Services - (SEALINE Project)
1
2. Title: - Coating &painting Engineer
Manufacturer PSL contractor
Place of Inspection PSL work shop, Hamriyah Free Zone, Sharjah, UAE
Duties : -
Follow coating activity in pipe line 12&16″ applied all required inspection tests
• Witness of the Production of 3 layer polyethylene coating
• Witness the Production of the Concrete coating
• Inspection / Witness of the painting for the onshore piping
• Review and Endorsing the Test Reports
• Issuing the Inspection Report
Aug.2010 – Sep.2011.
Company name: - Abu Dhabi Marine Operating Company (ADMA-OPCO)
Consultant: - Germanischer Lloyd Offshore and Industrial Services
Project name: - Integrated Gas Development Project- Offshore Facilities (IGD-HAP)
46” diameter from HAP platform to Das island approximately39KM
Title: - Coating &painting Engineer
Contractor: - (NPCC) National petroleum construction company DLB-750 barge
Duties : - Follow coating activity in field weld and applied all required inspection tests
according to project spec. such as salts test, pull-off test &holiday test…
Training course in (HUET) helicopter under water escape training &sea survival
Aug.2009 –Sep. 2010
Owner: - international petroleum investment company (IPIC)
Client: - china petroleum engineering construction& corporation (CPECC)
Consultant: - Germanischer Lloyd Offshore and Industrial Services
Project name: - Abu Dhabi crude oil pipe line project habshan-fujairah
Title: - Coating &painting Engineer
Contractor: Belleli energy - Global Suhami
-Follow coating activity in field weld of pipe line (42) inch 3 layers poly propylene and applied all
required inspection tests according to project spec. such as pull-off test & holiday test.
-Follow all painting & coating activities done in plant (8 nos.) Crude Oil Storage Tank Double Deck
Floating Roof 110 M Diameter x 21.7M Height in ADCOP Project, Fujairah, U.A.E.
Applied many Paint system on tanks such as Internal & external and GER.LINING (Fiber Glass)
Follow Project specification, ITP, International codes and standards
Sep.2008 –Aug.2009.
Company name: - Abu Dhabi Marine Operating Company (ADMA-OPCO)
Consultant: - Germanischer Lloyd Offshore and Industrial Services
Project name: - Replacement of 24 nos. water injection offshore pipe lines
In Zakum & Umm Shaif fields (pipe lines& risers).
Title: - Coating Engineer
Contractor: - (NPCC) National petroleum construction company DLB-750&SEP-150 barges
Duties : - Follow coating activity in field weld and applied all required inspection tests
according to project spec. such as pull-off test & holiday test
Painting system (extension decks, Splash zone, above splash zone, Off shore pipe lines & Risers).
Nov.2006 –Aug.2008
Company name: - GUPCO. Joints venture with Bp Company.
Consultant: - E.M.C (Egyptian Maintenance Company)
Title: - Senior painting inspector
2
3. Contractor: - PMS (BARGE 12) &Petrojet.
Project name: - Saqqara Project
Training courses in Arabic academy for science and technology.
(HUET) helicopter under water escape training, sea survival and fire fighting courses.
Duties:
Coating field joints offshore pipe line 12km.length 16"diameter from Saqqara platform to Ras
Shuker by canusa GTS-PP shrink sleeve (120C°) and add infill flowmax fj-3000(concrete) PU +
aggregate.
- Installed Saqqara jacket and paint repair for splash zone, atmospheric zone.
- Saqqara project (Ras Shuker onshore plant)
- Onshore pipe line 16" diameter follow coating activity in filed weld and applied all required
inspection tests according to project spec. such as pull-off test & holiday test
- Follow all painting & coating activities done in plant such as internal & external tanks, above &
underground pipes carbon steel, stainless steel & duplex and steel structure.
Follow KBR specification, International codes and standards.
Mar. 2004 – Oct.2006
Company Name: - Khalda petroleum co. (K.P.C.) Joint venture with Apache.
Project Name: - Qasr gas development project
Title: - Senior painting inspector
Follow all coating activities done in
- First line (18 inch from shams to Obayied 42km) 3 layer poly propylene.
- Second line (18 inch from shams to Tarek gas plant 62 km) 3 layer poly propylene.
- Third line (24 inch from shams to Qasr 40 km) 3 layer poly propylene.
Using polypropylene coating for main lines and CanUsa wrapped KLNN for weld joints.
- Follow lowering activity and checked the under ground pipes before laying such as pull-off
test, holiday test, impact and elongation test.
- Also follow all painting activities done on Obayied, Qasr & Tarek areas according to JP Kenny
& Apache specification steel structure, above ground pipes and tanks.
- Estimated the project required quantities of coating & paint material.
-Follow wrapping of weld joints in Umbarka/Meleha flow line (8 inches) nearly 60 km by
KLNN shrink sleeve, applied all required test pull-off, holiday, impact and elongation tests.
- Inspection blasting & painting activity done in Salam new work shop building
Sep. 2003 –Feb. 2004
Company name: - GUPCO. Joints venture with Bp Company.
Project location: -Ras Shuker (offshore fields)
Akhen platform (port-said offshore fields).
Title: - Senior painting inspector
Duties:- Follow re-sandblast & re-paint many offshore petroleum platforms such
(October filed, Morgan field…) heli decks & boat landings, re-coated many of riser pipes (6, 8)
inches by interzone coating according to Gupco Spec’s.
Abu El-Garadek & EL-Razak plants follow sandblast & paint some pipes, steel pipe racks,
vessels as maintenance.
Mar. 2001 – Aug. 2003
3
4. Company name: - Dabetco. (El-Tunisia)
Title: - senior painting inspector
Project name: - Second & third stages
Duties: - Follow all painting activities done on site 6 no. of oil tanks (capacity 20,000),
Two oil tanks (capacity 12,000) & two water tanks (internal / external paint).
Wrapping many flow lines have different size (6, 8, 12, and 16) inches from wells to the plant
using many types of coating (Recham, Canusa, U.B.E,) also follow all inspection tests.
Oct.2000 – Jun. 2001
Company name: - Geisum oil co.
Project location: - PETROJET coating plant
Title: - Coating inspector
Duties:- Inspection & supervision the (F.B.E.) coating for the 8” flow line 26 km follow
all quality activity (QC) such as:-
-Surface preparation according to I so 8501 – 1, surface profile, atmospheric condition, pipe
temp., pre-heating, applied rough primer, thickness of primer, cut back, cooling tower & internal
blast and painting.
Conductivity (Holiday Test) peel off Test, etc…..
Follow the approved procedures, specification & international codes.
August 1998 – May 2000
Company name: - Badr Petroleum Company joint venture with shell
Project name: - (El–Obayied project)
Consultant: - Brown & Root limited Co.
Title: - painting &coating inspector
Shot & grit blast applied in steel structure & piping before paint Internal & external blasting and
painting done in potable water, oil, chemical & condensate tanks
- 8 applicant subcontractor to (PTJ) working on project.
- 4 paint supplier (Hemple, Sigma and Jotun & International).
- Fire proofing (concrete) applied on pipe races beams and columns.
- New flow lines from 9-well heads to plant follow wrapping and tested before lying.
Dec 1997 – Agues 1998
Company name: - Badr Petroleum Company joint venture with shell
Project location: - (BED-1, 2&3).
Title: - painting & coating inspector
- Maintenance job re-sandblast & re-paint pipelines, tanks, vessels & steel structure
- Bed 2/3 pre-compression project (Extension to bed -3 plant) piping, pipe racks & vessels.
- Wrapping new flow line from bed-2 to bed-3 and checked before lying.
- Fire proofing for steel structure (concrete)
- Hot & cold insulation applied on pipes and vessels.
Company name: - Petrobel co. joint venture with AGIP.
Feb. 1987 – Mar. 1994
Company name: - port-said engineering workers (P.S.E.W)
Title: - painting supervisor
During this period through port-said engineering workers
As a painting supervisor follow the activity done in:-
4
5. - Sodium salpht from Qarun lake project in Fayoum city through Mannesmann co.
- El-yamen project with can-oxy (USA Company)
- PORTSAID marine yard follow sandblasting & painting for cargo vessels maintenance
- Many bridges in Egypt as first stage from el- Kabbary Bridge & el- Marg Bridge.
- PORTSAID coating plant follow sand blasting &wrapping activities many types of coating
such as polypropylene, polyethylene, concrete, F.B. E.
Thanks & Best Regards
Ashraf Yassin
5
6. - Sodium salpht from Qarun lake project in Fayoum city through Mannesmann co.
- El-yamen project with can-oxy (USA Company)
- PORTSAID marine yard follow sandblasting & painting for cargo vessels maintenance
- Many bridges in Egypt as first stage from el- Kabbary Bridge & el- Marg Bridge.
- PORTSAID coating plant follow sand blasting &wrapping activities many types of coating
such as polypropylene, polyethylene, concrete, F.B. E.
Thanks & Best Regards
Ashraf Yassin
5