SlideShare a Scribd company logo
Keynote #2
The Business of Project Development; Risk, Returns,
and Integrated Project Delivery (IPD)
Bob Springer, P.E., MBA
Sr. Principal
Concurrent Technologies Corporation
springer@ctc.com
814-269-2508
1
Why does this Matter?
The industry is moving;
Technology is leading/enabling;
Competition is relentless;
Leaders will adapt, improve, profit.
2
Outline/Agenda
• IPD Fundamentals
• Project Development Fundamentals
• Making the choice: To IPD or not to IPD
• Implications on choosing IPD or IPD-”like”
3
IPD
4
1
2
34
The fundamentals of the MacLearny curve
are right; but this shift impacts cash flows and
risks in a development environment.
IPD
• Shifting of effort is a rational response to the
environment, as shown.
• This value proposition is an important one; but it is not
complete; there are financial implications and when
placed in a risk environment this can influence things a
great deal.
5
Project Development Environment
6
Project Development Risk Capital
Construction
Finance
Asset Finance
Risk
$
Time
Entitlements Financial Close Substantial
Completion
Site
Control
Rising risk curve
a result of
increasing
“funds at risk”
A
B
C
Project Development
• Developer/Owner is managing exposure to to “Project
Development Risk”
– Risk that a project’s value cannot be realized from delay or
inability to fund project and/or start construction, resulting in a full
or partial loss of invested development resources.
• Risk Curve shown rising from Point A to Point B because
the cumulative value invested is often very illiquid and
100% at risk until financial close at Point B.
• completion.
• This illustrates the point; investments in development
differ from rest of lifecycle; Owner can lose development
investment if disaster strikes two days before point B….
7
Project Development
8
Project Development Risk Capital
Construction
Finance
Asset Finance$
Time
Entitlements Financial Close Substantial
Completion
Site
Control
Site
Acquisition
A
B
CThis environment drives preference to invest later in
development, after key milestones achieved, which
is counter to the design-driven shift driven by the
cost/impact dynamics shown by MacLearny curve.
Cost of Capital & Timing
Investopedia: “The required return necessary to make a capital budgeting project, such as
building a new factory, worthwhile. Cost of capital includes the cost of debt and the cost of equity.”
• Value: does the investment produce value after paying
for the cost of capital?
• Timing: preference is to invest at lower cost of capital,
later in the lifecycle.
• Uncertainty: source of risk, also declining in later stages
of development, which is intuitive.
9
Putting it Together
10
Project Development Risk Capital
Construction
Finance
Asset Finance$
Time
Entitlements Financial Close Substantial
Completion
Site
Control
Arguments…
• Institutional/government/corporate owners not
“developers” ….no development risk.
Really? Risk may be there even if not “core business”.
• Cost of capital “constant” for projects which are balance-
sheet financed…timing doesn’t matter.
Really? “Cheap” money that doesn’t value the risks may lead to bad
investment decisions; hurdle is artificially low.
Truth is there is a sliding scale; things are more or less
amplified under different project business models, owners,
objectives, and funding.
11
Value Propositions for the Owner
12
Strategic Site?
Opportunistic?
First Mover in
Market?
Low Overall Cost?
Accelerated
Schedule?
Financing Requirements??
Delayed Investment?
“GUARANTEE”
Delivery Date?
Net Operating
Income?
Lifecycle Cost?
Revenue?
Market
Requirements?
Business Models
A commercial developer with 3rd party investors utilizing
project-specific debt for construction financing…
Will likely prefer more traditional models.
An institutional user embarking capital construction
program using balance sheet financing...
Will likely prefer more integrated models.
13
Makes sense, but why?
• All projects have competing forces, what drives decision
on IPD?
• What are the levers that affect the balance of choosing a
delivery model?
• Consider the integrated IPD model and MacLearny
Curve cast in a development context…
14
IPD & Cost of Capital
15
1
2
34
The slope of the cost of capital curve
(green) is a key determinate in choosing a
delivery system. Steeper slopes tends to
dampen affect of Cost/Impact relationship,
driving preference for more traditional
delivery models.
Makes sense, but why?
• Remember, investing in earliest stages must consider the risk that
value created in increased predesign MAY NEVER be realized.
• This drives the risk of early stage expenditures way up and also
drives return requirements – making the cost of capital line
“steeper”.
• Early design decisions might create value, but this is only “on
paper”; value has to be monetized, and that path may not be certain
because of other factors driving development risk; market risks,
entitlement risks, financing risks, etc.
16
IPD & Cost of Capital
17
1
2
34
Flatter slope in cost of capital line
(green) drives preference for an
integrated model to leverage the
value of design cost/impact curves.
What determines cost of capital “slope”?
• Drivers of value; what is driving fundamental project
value?
• Components of development risk;
Market? Entitlement? Permits? Financing? Environmental?
• When are returns realized? Through long term asset, or
through short term conditions?
18
Implications
• From a development risk management perspective, MacLearny
curve is compelling, but incomplete;
• Because of the uncertainty of outcomes, the cost of capital in a
development environment is high;
• This cost of money drives up the true cost of a dollar (from a
risk/return perspective) in early stages;
• MacLearny may be comparing dollars to dollars without regard to
risk/return multipliers; every dollar is not the same in a project, and
front-loading costs that may not be recoverable because of
entitlement or market risks can heavily influence decisions.
19
Closing
• Industry needs numbers to make the business case, and make
informed decisions!
• IPD may be written off as aspirational; or taken as directional – this
is a trend and we should embrace that trend vs. take it as
prescriptive.
• The attitude of collaboration and teamwork that underwrites IPD-
that alone may be worth it!
20
Bibliography
• IPD graphic, original concept by Patrick MacLearny, FAIA, CEO, HOK Group, © HOK Group, Inc.,
2009 all rights reserved.
• Project development concepts are adapted from SROPTTC
TM
, which is a trademark of the
Alliance for Sustainable Energy, LLC, the operator of the National Renewable Energy Laboratory.
• http://www.nrel.gov/docs/fy13osti/57963.pdf
• www.Investopedia.com, accessed June 21, 2013.
21
Questions?
Bob Springer
Springer@ctc.com
22

More Related Content

What's hot

Bim Enabled Ipd
Bim Enabled IpdBim Enabled Ipd
Bim Enabled Ipd
marybk
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
marcus evans Network
 
Project Delivery Methods
Project Delivery MethodsProject Delivery Methods
Project Delivery Methods
Stacy Abernathy
 
Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014
SHKLaw
 
Lean construction & BIM
Lean construction & BIMLean construction & BIM
Lean construction & BIM
Stephen Au
 
Digital construction for Integrated Project Delivery
Digital construction for Integrated Project DeliveryDigital construction for Integrated Project Delivery
Digital construction for Integrated Project Delivery
Stephen Au
 
On IP
On IPOn IP
On IP
samnyc123
 
Construction project delivery methods
Construction project delivery methodsConstruction project delivery methods
Construction project delivery methods
Nitin Kumar
 
Consensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in ConstructionConsensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in Construction
DBL Law
 
July 2015 Construct15_Richard Morwood_V4 (2)
July 2015 Construct15_Richard Morwood_V4 (2)July 2015 Construct15_Richard Morwood_V4 (2)
July 2015 Construct15_Richard Morwood_V4 (2)
Richard Morwood
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startup
Bob Prieto
 
BIM: The Promise of an Integrated Approach to Project Delivery
BIM: The Promise of an Integrated Approach to Project DeliveryBIM: The Promise of an Integrated Approach to Project Delivery
BIM: The Promise of an Integrated Approach to Project Delivery
AWC|WEST
 
15-MOR-101_IPDWhitepaper
15-MOR-101_IPDWhitepaper15-MOR-101_IPDWhitepaper
15-MOR-101_IPDWhitepaper
Todd Sullivan
 
BIM – Just another buzzword or a real change in the Industry? - Professor Art...
BIM – Just another buzzword or a real change in the Industry? - Professor Art...BIM – Just another buzzword or a real change in the Industry? - Professor Art...
BIM – Just another buzzword or a real change in the Industry? - Professor Art...
School of the Built Environment - University of Salford
 
BIM and IPD
BIM and IPDBIM and IPD
Human resource management for const management
Human resource management for const managementHuman resource management for const management
Human resource management for const management
Md Manzoor Akhtar
 
integrated-project-delivery-constru
integrated-project-delivery-construintegrated-project-delivery-constru
integrated-project-delivery-constru
Ed LeBard, AIA, RIBA, NCARB, PMP, LEED AP+
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction Projects
Bob Prieto
 
bim and project controls
 bim and project controls bim and project controls
bim and project controls
Omar Selim
 
ACH 121 Lecture 02 (Arch. Basic Services )
ACH 121 Lecture 02 (Arch. Basic Services )ACH 121 Lecture 02 (Arch. Basic Services )
ACH 121 Lecture 02 (Arch. Basic Services )
Anne Arundel Community College
 

What's hot (20)

Bim Enabled Ipd
Bim Enabled IpdBim Enabled Ipd
Bim Enabled Ipd
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
 
Project Delivery Methods
Project Delivery MethodsProject Delivery Methods
Project Delivery Methods
 
Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014
 
Lean construction & BIM
Lean construction & BIMLean construction & BIM
Lean construction & BIM
 
Digital construction for Integrated Project Delivery
Digital construction for Integrated Project DeliveryDigital construction for Integrated Project Delivery
Digital construction for Integrated Project Delivery
 
On IP
On IPOn IP
On IP
 
Construction project delivery methods
Construction project delivery methodsConstruction project delivery methods
Construction project delivery methods
 
Consensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in ConstructionConsensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in Construction
 
July 2015 Construct15_Richard Morwood_V4 (2)
July 2015 Construct15_Richard Morwood_V4 (2)July 2015 Construct15_Richard Morwood_V4 (2)
July 2015 Construct15_Richard Morwood_V4 (2)
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startup
 
BIM: The Promise of an Integrated Approach to Project Delivery
BIM: The Promise of an Integrated Approach to Project DeliveryBIM: The Promise of an Integrated Approach to Project Delivery
BIM: The Promise of an Integrated Approach to Project Delivery
 
15-MOR-101_IPDWhitepaper
15-MOR-101_IPDWhitepaper15-MOR-101_IPDWhitepaper
15-MOR-101_IPDWhitepaper
 
BIM – Just another buzzword or a real change in the Industry? - Professor Art...
BIM – Just another buzzword or a real change in the Industry? - Professor Art...BIM – Just another buzzword or a real change in the Industry? - Professor Art...
BIM – Just another buzzword or a real change in the Industry? - Professor Art...
 
BIM and IPD
BIM and IPDBIM and IPD
BIM and IPD
 
Human resource management for const management
Human resource management for const managementHuman resource management for const management
Human resource management for const management
 
integrated-project-delivery-constru
integrated-project-delivery-construintegrated-project-delivery-constru
integrated-project-delivery-constru
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction Projects
 
bim and project controls
 bim and project controls bim and project controls
bim and project controls
 
ACH 121 Lecture 02 (Arch. Basic Services )
ACH 121 Lecture 02 (Arch. Basic Services )ACH 121 Lecture 02 (Arch. Basic Services )
ACH 121 Lecture 02 (Arch. Basic Services )
 

Similar to Ashrae denver business project development and ipd_ springer

Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
cgautam
 
Project selection
Project selection Project selection
Project selection
SamiuR RahmaN
 
Fundamental Skills for Real Estate Development Professionals I. Site Selecti...
Fundamental Skills for Real Estate Development Professionals I.  Site Selecti...Fundamental Skills for Real Estate Development Professionals I.  Site Selecti...
Fundamental Skills for Real Estate Development Professionals I. Site Selecti...
Virtual ULI
 
10 Capital Investment DecisionsVladTeodoriStockThinkstoc.docx
10 Capital Investment DecisionsVladTeodoriStockThinkstoc.docx10 Capital Investment DecisionsVladTeodoriStockThinkstoc.docx
10 Capital Investment DecisionsVladTeodoriStockThinkstoc.docx
paynetawnya
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
Ahmad Tariq Bhatti
 
2010-Tokyo-EBIG-Schrager-Semagin
2010-Tokyo-EBIG-Schrager-Semagin2010-Tokyo-EBIG-Schrager-Semagin
2010-Tokyo-EBIG-Schrager-Semagin
Denys Semagin
 
Whose project is it anyway?
Whose project is it anyway?Whose project is it anyway?
Whose project is it anyway?
3gamma
 
Project finance
Project financeProject finance
Project finance
Vishnu Rajendran C R
 
Chapter 10:Risk and Refinements In Capital Budgeting
Chapter 10:Risk and Refinements In Capital BudgetingChapter 10:Risk and Refinements In Capital Budgeting
Chapter 10:Risk and Refinements In Capital Budgeting
Inocentshuja Ahmad
 
Chapter 10: Risk and Refinements In Capital Budgeting
Chapter 10: Risk and Refinements In Capital BudgetingChapter 10: Risk and Refinements In Capital Budgeting
Chapter 10: Risk and Refinements In Capital Budgeting
Fiaz Ahmad
 
Fundamental Skill for Real Estate Development Professional I (Charles Long) -...
Fundamental Skill for Real Estate Development Professional I (Charles Long) -...Fundamental Skill for Real Estate Development Professional I (Charles Long) -...
Fundamental Skill for Real Estate Development Professional I (Charles Long) -...
Virtual ULI
 
Fundamental Skills for Real Estate Development Professionals I – Site Selecti...
Fundamental Skills for Real Estate Development Professionals I – Site Selecti...Fundamental Skills for Real Estate Development Professionals I – Site Selecti...
Fundamental Skills for Real Estate Development Professionals I – Site Selecti...
Virtual ULI
 
219088522 new-heritage-doll-solution
219088522 new-heritage-doll-solution219088522 new-heritage-doll-solution
219088522 new-heritage-doll-solution
Faheem Mukhtar
 
What goes wrong on complex projects
What goes wrong on complex projectsWhat goes wrong on complex projects
What goes wrong on complex projects
Walter Akers
 
5
55
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Loay Ghazaleh MBA, BSc Civil Eng.
 
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
UNSW Canberra
 
Be aers-fara-modellinginsolvency-nov2010
Be aers-fara-modellinginsolvency-nov2010Be aers-fara-modellinginsolvency-nov2010
Be aers-fara-modellinginsolvency-nov2010
Dodi Mulyadi
 
Capital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasCapital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_Gas
Mircea Tomescu
 
Scope creep - cylfe campain
Scope creep - cylfe campainScope creep - cylfe campain
Scope creep - cylfe campain
M Maged Hegazy, LLM, MBA, CCP, P3O
 

Similar to Ashrae denver business project development and ipd_ springer (20)

Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project selection
Project selection Project selection
Project selection
 
Fundamental Skills for Real Estate Development Professionals I. Site Selecti...
Fundamental Skills for Real Estate Development Professionals I.  Site Selecti...Fundamental Skills for Real Estate Development Professionals I.  Site Selecti...
Fundamental Skills for Real Estate Development Professionals I. Site Selecti...
 
10 Capital Investment DecisionsVladTeodoriStockThinkstoc.docx
10 Capital Investment DecisionsVladTeodoriStockThinkstoc.docx10 Capital Investment DecisionsVladTeodoriStockThinkstoc.docx
10 Capital Investment DecisionsVladTeodoriStockThinkstoc.docx
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
2010-Tokyo-EBIG-Schrager-Semagin
2010-Tokyo-EBIG-Schrager-Semagin2010-Tokyo-EBIG-Schrager-Semagin
2010-Tokyo-EBIG-Schrager-Semagin
 
Whose project is it anyway?
Whose project is it anyway?Whose project is it anyway?
Whose project is it anyway?
 
Project finance
Project financeProject finance
Project finance
 
Chapter 10:Risk and Refinements In Capital Budgeting
Chapter 10:Risk and Refinements In Capital BudgetingChapter 10:Risk and Refinements In Capital Budgeting
Chapter 10:Risk and Refinements In Capital Budgeting
 
Chapter 10: Risk and Refinements In Capital Budgeting
Chapter 10: Risk and Refinements In Capital BudgetingChapter 10: Risk and Refinements In Capital Budgeting
Chapter 10: Risk and Refinements In Capital Budgeting
 
Fundamental Skill for Real Estate Development Professional I (Charles Long) -...
Fundamental Skill for Real Estate Development Professional I (Charles Long) -...Fundamental Skill for Real Estate Development Professional I (Charles Long) -...
Fundamental Skill for Real Estate Development Professional I (Charles Long) -...
 
Fundamental Skills for Real Estate Development Professionals I – Site Selecti...
Fundamental Skills for Real Estate Development Professionals I – Site Selecti...Fundamental Skills for Real Estate Development Professionals I – Site Selecti...
Fundamental Skills for Real Estate Development Professionals I – Site Selecti...
 
219088522 new-heritage-doll-solution
219088522 new-heritage-doll-solution219088522 new-heritage-doll-solution
219088522 new-heritage-doll-solution
 
What goes wrong on complex projects
What goes wrong on complex projectsWhat goes wrong on complex projects
What goes wrong on complex projects
 
5
55
5
 
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
 
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
Chartered Secretaries Risk & Compliance Module 8 - Project Governance - May 2010
 
Be aers-fara-modellinginsolvency-nov2010
Be aers-fara-modellinginsolvency-nov2010Be aers-fara-modellinginsolvency-nov2010
Be aers-fara-modellinginsolvency-nov2010
 
Capital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasCapital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_Gas
 
Scope creep - cylfe campain
Scope creep - cylfe campainScope creep - cylfe campain
Scope creep - cylfe campain
 

More from Roland_Nikles

Ipd analysis summary metrics asce article_julia_2013_12_17
Ipd analysis summary metrics asce article_julia_2013_12_17Ipd analysis summary metrics asce article_julia_2013_12_17
Ipd analysis summary metrics asce article_julia_2013_12_17
Roland_Nikles
 
Aba division 4 presentation outside consultants handling of change orders (8 ...
Aba division 4 presentation outside consultants handling of change orders (8 ...Aba division 4 presentation outside consultants handling of change orders (8 ...
Aba division 4 presentation outside consultants handling of change orders (8 ...
Roland_Nikles
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)
Roland_Nikles
 
Aba february 2013_presentation
Aba february 2013_presentationAba february 2013_presentation
Aba february 2013_presentation
Roland_Nikles
 
Division 4 presentation_pumphrey_2013_01_22
Division 4 presentation_pumphrey_2013_01_22Division 4 presentation_pumphrey_2013_01_22
Division 4 presentation_pumphrey_2013_01_22
Roland_Nikles
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Roland_Nikles
 

More from Roland_Nikles (6)

Ipd analysis summary metrics asce article_julia_2013_12_17
Ipd analysis summary metrics asce article_julia_2013_12_17Ipd analysis summary metrics asce article_julia_2013_12_17
Ipd analysis summary metrics asce article_julia_2013_12_17
 
Aba division 4 presentation outside consultants handling of change orders (8 ...
Aba division 4 presentation outside consultants handling of change orders (8 ...Aba division 4 presentation outside consultants handling of change orders (8 ...
Aba division 4 presentation outside consultants handling of change orders (8 ...
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)
 
Aba february 2013_presentation
Aba february 2013_presentationAba february 2013_presentation
Aba february 2013_presentation
 
Division 4 presentation_pumphrey_2013_01_22
Division 4 presentation_pumphrey_2013_01_22Division 4 presentation_pumphrey_2013_01_22
Division 4 presentation_pumphrey_2013_01_22
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
 

Recently uploaded

Bridging the gap: Online job postings, survey data and the assessment of job ...
Bridging the gap: Online job postings, survey data and the assessment of job ...Bridging the gap: Online job postings, survey data and the assessment of job ...
Bridging the gap: Online job postings, survey data and the assessment of job ...
Labour Market Information Council | Conseil de l’information sur le marché du travail
 
Tdasx: In-Depth Analysis of Cryptocurrency Giveaway Scams and Security Strate...
Tdasx: In-Depth Analysis of Cryptocurrency Giveaway Scams and Security Strate...Tdasx: In-Depth Analysis of Cryptocurrency Giveaway Scams and Security Strate...
Tdasx: In-Depth Analysis of Cryptocurrency Giveaway Scams and Security Strate...
bresciafarid233
 
Does teamwork really matter? Looking beyond the job posting to understand lab...
Does teamwork really matter? Looking beyond the job posting to understand lab...Does teamwork really matter? Looking beyond the job posting to understand lab...
Does teamwork really matter? Looking beyond the job posting to understand lab...
Labour Market Information Council | Conseil de l’information sur le marché du travail
 
Ending stagnation: How to boost prosperity across Scotland
Ending stagnation: How to boost prosperity across ScotlandEnding stagnation: How to boost prosperity across Scotland
Ending stagnation: How to boost prosperity across Scotland
ResolutionFoundation
 
Accounting Information Systems (AIS).pptx
Accounting Information Systems (AIS).pptxAccounting Information Systems (AIS).pptx
Accounting Information Systems (AIS).pptx
TIZITAWMASRESHA
 
Monthly Market Risk Update: June 2024 [SlideShare]
Monthly Market Risk Update: June 2024 [SlideShare]Monthly Market Risk Update: June 2024 [SlideShare]
Monthly Market Risk Update: June 2024 [SlideShare]
Commonwealth
 
一比一原版(RMIT毕业证)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证)皇家墨尔本理工大学毕业证如何办理一比一原版(RMIT毕业证)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证)皇家墨尔本理工大学毕业证如何办理
k4ncd0z
 
Principal of Economics by Gmanwik .pptx
Principal of Economics by Gmanwik  .pptxPrincipal of Economics by Gmanwik  .pptx
Principal of Economics by Gmanwik .pptx
PrashantBhargava14
 
Fabular Frames and the Four Ratio Problem
Fabular Frames and the Four Ratio ProblemFabular Frames and the Four Ratio Problem
Fabular Frames and the Four Ratio Problem
Majid Iqbal
 
The Rise and Fall of Ponzi Schemes in America.pptx
The Rise and Fall of Ponzi Schemes in America.pptxThe Rise and Fall of Ponzi Schemes in America.pptx
The Rise and Fall of Ponzi Schemes in America.pptx
Diana Rose
 
一比一原版(cwu毕业证书)美国中央华盛顿大学毕业证如何办理
一比一原版(cwu毕业证书)美国中央华盛顿大学毕业证如何办理一比一原版(cwu毕业证书)美国中央华盛顿大学毕业证如何办理
一比一原版(cwu毕业证书)美国中央华盛顿大学毕业证如何办理
asukqco
 
Tdasx: Interpreting the 2024 Cryptocurrency Market Funding Trends and Technol...
Tdasx: Interpreting the 2024 Cryptocurrency Market Funding Trends and Technol...Tdasx: Interpreting the 2024 Cryptocurrency Market Funding Trends and Technol...
Tdasx: Interpreting the 2024 Cryptocurrency Market Funding Trends and Technol...
nimaruinazawa258
 
International Sustainability Standards Board
International Sustainability Standards BoardInternational Sustainability Standards Board
International Sustainability Standards Board
Kumar Ramaiah
 
Money20/20 and EU Networking Event of 20/24!
Money20/20 and EU Networking Event of 20/24!Money20/20 and EU Networking Event of 20/24!
Money20/20 and EU Networking Event of 20/24!
FinTech Belgium
 
South Dakota State University degree offer diploma Transcript
South Dakota State University degree offer diploma TranscriptSouth Dakota State University degree offer diploma Transcript
South Dakota State University degree offer diploma Transcript
ynfqplhm
 
falcon-invoice-discounting-a-premier-investment-platform-for-superior-returns...
falcon-invoice-discounting-a-premier-investment-platform-for-superior-returns...falcon-invoice-discounting-a-premier-investment-platform-for-superior-returns...
falcon-invoice-discounting-a-premier-investment-platform-for-superior-returns...
Falcon Invoice Discounting
 
The state of welfare Resolution Foundation Event
The state of welfare Resolution Foundation EventThe state of welfare Resolution Foundation Event
The state of welfare Resolution Foundation Event
ResolutionFoundation
 
Mutual Fund Taxation – How Mutual Funds Are Taxed
Mutual Fund Taxation – How Mutual Funds Are TaxedMutual Fund Taxation – How Mutual Funds Are Taxed
Mutual Fund Taxation – How Mutual Funds Are Taxed
dhvikdiva
 
Detailed power point presentation on compound interest and how it is calculated
Detailed power point presentation on compound interest  and how it is calculatedDetailed power point presentation on compound interest  and how it is calculated
Detailed power point presentation on compound interest and how it is calculated
KishanChaudhary23
 
Discover the Future of Dogecoin with Our Comprehensive Guidance
Discover the Future of Dogecoin with Our Comprehensive GuidanceDiscover the Future of Dogecoin with Our Comprehensive Guidance
Discover the Future of Dogecoin with Our Comprehensive Guidance
36 Crypto
 

Recently uploaded (20)

Bridging the gap: Online job postings, survey data and the assessment of job ...
Bridging the gap: Online job postings, survey data and the assessment of job ...Bridging the gap: Online job postings, survey data and the assessment of job ...
Bridging the gap: Online job postings, survey data and the assessment of job ...
 
Tdasx: In-Depth Analysis of Cryptocurrency Giveaway Scams and Security Strate...
Tdasx: In-Depth Analysis of Cryptocurrency Giveaway Scams and Security Strate...Tdasx: In-Depth Analysis of Cryptocurrency Giveaway Scams and Security Strate...
Tdasx: In-Depth Analysis of Cryptocurrency Giveaway Scams and Security Strate...
 
Does teamwork really matter? Looking beyond the job posting to understand lab...
Does teamwork really matter? Looking beyond the job posting to understand lab...Does teamwork really matter? Looking beyond the job posting to understand lab...
Does teamwork really matter? Looking beyond the job posting to understand lab...
 
Ending stagnation: How to boost prosperity across Scotland
Ending stagnation: How to boost prosperity across ScotlandEnding stagnation: How to boost prosperity across Scotland
Ending stagnation: How to boost prosperity across Scotland
 
Accounting Information Systems (AIS).pptx
Accounting Information Systems (AIS).pptxAccounting Information Systems (AIS).pptx
Accounting Information Systems (AIS).pptx
 
Monthly Market Risk Update: June 2024 [SlideShare]
Monthly Market Risk Update: June 2024 [SlideShare]Monthly Market Risk Update: June 2024 [SlideShare]
Monthly Market Risk Update: June 2024 [SlideShare]
 
一比一原版(RMIT毕业证)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证)皇家墨尔本理工大学毕业证如何办理一比一原版(RMIT毕业证)皇家墨尔本理工大学毕业证如何办理
一比一原版(RMIT毕业证)皇家墨尔本理工大学毕业证如何办理
 
Principal of Economics by Gmanwik .pptx
Principal of Economics by Gmanwik  .pptxPrincipal of Economics by Gmanwik  .pptx
Principal of Economics by Gmanwik .pptx
 
Fabular Frames and the Four Ratio Problem
Fabular Frames and the Four Ratio ProblemFabular Frames and the Four Ratio Problem
Fabular Frames and the Four Ratio Problem
 
The Rise and Fall of Ponzi Schemes in America.pptx
The Rise and Fall of Ponzi Schemes in America.pptxThe Rise and Fall of Ponzi Schemes in America.pptx
The Rise and Fall of Ponzi Schemes in America.pptx
 
一比一原版(cwu毕业证书)美国中央华盛顿大学毕业证如何办理
一比一原版(cwu毕业证书)美国中央华盛顿大学毕业证如何办理一比一原版(cwu毕业证书)美国中央华盛顿大学毕业证如何办理
一比一原版(cwu毕业证书)美国中央华盛顿大学毕业证如何办理
 
Tdasx: Interpreting the 2024 Cryptocurrency Market Funding Trends and Technol...
Tdasx: Interpreting the 2024 Cryptocurrency Market Funding Trends and Technol...Tdasx: Interpreting the 2024 Cryptocurrency Market Funding Trends and Technol...
Tdasx: Interpreting the 2024 Cryptocurrency Market Funding Trends and Technol...
 
International Sustainability Standards Board
International Sustainability Standards BoardInternational Sustainability Standards Board
International Sustainability Standards Board
 
Money20/20 and EU Networking Event of 20/24!
Money20/20 and EU Networking Event of 20/24!Money20/20 and EU Networking Event of 20/24!
Money20/20 and EU Networking Event of 20/24!
 
South Dakota State University degree offer diploma Transcript
South Dakota State University degree offer diploma TranscriptSouth Dakota State University degree offer diploma Transcript
South Dakota State University degree offer diploma Transcript
 
falcon-invoice-discounting-a-premier-investment-platform-for-superior-returns...
falcon-invoice-discounting-a-premier-investment-platform-for-superior-returns...falcon-invoice-discounting-a-premier-investment-platform-for-superior-returns...
falcon-invoice-discounting-a-premier-investment-platform-for-superior-returns...
 
The state of welfare Resolution Foundation Event
The state of welfare Resolution Foundation EventThe state of welfare Resolution Foundation Event
The state of welfare Resolution Foundation Event
 
Mutual Fund Taxation – How Mutual Funds Are Taxed
Mutual Fund Taxation – How Mutual Funds Are TaxedMutual Fund Taxation – How Mutual Funds Are Taxed
Mutual Fund Taxation – How Mutual Funds Are Taxed
 
Detailed power point presentation on compound interest and how it is calculated
Detailed power point presentation on compound interest  and how it is calculatedDetailed power point presentation on compound interest  and how it is calculated
Detailed power point presentation on compound interest and how it is calculated
 
Discover the Future of Dogecoin with Our Comprehensive Guidance
Discover the Future of Dogecoin with Our Comprehensive GuidanceDiscover the Future of Dogecoin with Our Comprehensive Guidance
Discover the Future of Dogecoin with Our Comprehensive Guidance
 

Ashrae denver business project development and ipd_ springer

  • 1. Keynote #2 The Business of Project Development; Risk, Returns, and Integrated Project Delivery (IPD) Bob Springer, P.E., MBA Sr. Principal Concurrent Technologies Corporation springer@ctc.com 814-269-2508 1
  • 2. Why does this Matter? The industry is moving; Technology is leading/enabling; Competition is relentless; Leaders will adapt, improve, profit. 2
  • 3. Outline/Agenda • IPD Fundamentals • Project Development Fundamentals • Making the choice: To IPD or not to IPD • Implications on choosing IPD or IPD-”like” 3
  • 4. IPD 4 1 2 34 The fundamentals of the MacLearny curve are right; but this shift impacts cash flows and risks in a development environment.
  • 5. IPD • Shifting of effort is a rational response to the environment, as shown. • This value proposition is an important one; but it is not complete; there are financial implications and when placed in a risk environment this can influence things a great deal. 5
  • 6. Project Development Environment 6 Project Development Risk Capital Construction Finance Asset Finance Risk $ Time Entitlements Financial Close Substantial Completion Site Control Rising risk curve a result of increasing “funds at risk” A B C
  • 7. Project Development • Developer/Owner is managing exposure to to “Project Development Risk” – Risk that a project’s value cannot be realized from delay or inability to fund project and/or start construction, resulting in a full or partial loss of invested development resources. • Risk Curve shown rising from Point A to Point B because the cumulative value invested is often very illiquid and 100% at risk until financial close at Point B. • completion. • This illustrates the point; investments in development differ from rest of lifecycle; Owner can lose development investment if disaster strikes two days before point B…. 7
  • 8. Project Development 8 Project Development Risk Capital Construction Finance Asset Finance$ Time Entitlements Financial Close Substantial Completion Site Control Site Acquisition A B CThis environment drives preference to invest later in development, after key milestones achieved, which is counter to the design-driven shift driven by the cost/impact dynamics shown by MacLearny curve.
  • 9. Cost of Capital & Timing Investopedia: “The required return necessary to make a capital budgeting project, such as building a new factory, worthwhile. Cost of capital includes the cost of debt and the cost of equity.” • Value: does the investment produce value after paying for the cost of capital? • Timing: preference is to invest at lower cost of capital, later in the lifecycle. • Uncertainty: source of risk, also declining in later stages of development, which is intuitive. 9
  • 10. Putting it Together 10 Project Development Risk Capital Construction Finance Asset Finance$ Time Entitlements Financial Close Substantial Completion Site Control
  • 11. Arguments… • Institutional/government/corporate owners not “developers” ….no development risk. Really? Risk may be there even if not “core business”. • Cost of capital “constant” for projects which are balance- sheet financed…timing doesn’t matter. Really? “Cheap” money that doesn’t value the risks may lead to bad investment decisions; hurdle is artificially low. Truth is there is a sliding scale; things are more or less amplified under different project business models, owners, objectives, and funding. 11
  • 12. Value Propositions for the Owner 12 Strategic Site? Opportunistic? First Mover in Market? Low Overall Cost? Accelerated Schedule? Financing Requirements?? Delayed Investment? “GUARANTEE” Delivery Date? Net Operating Income? Lifecycle Cost? Revenue? Market Requirements?
  • 13. Business Models A commercial developer with 3rd party investors utilizing project-specific debt for construction financing… Will likely prefer more traditional models. An institutional user embarking capital construction program using balance sheet financing... Will likely prefer more integrated models. 13
  • 14. Makes sense, but why? • All projects have competing forces, what drives decision on IPD? • What are the levers that affect the balance of choosing a delivery model? • Consider the integrated IPD model and MacLearny Curve cast in a development context… 14
  • 15. IPD & Cost of Capital 15 1 2 34 The slope of the cost of capital curve (green) is a key determinate in choosing a delivery system. Steeper slopes tends to dampen affect of Cost/Impact relationship, driving preference for more traditional delivery models.
  • 16. Makes sense, but why? • Remember, investing in earliest stages must consider the risk that value created in increased predesign MAY NEVER be realized. • This drives the risk of early stage expenditures way up and also drives return requirements – making the cost of capital line “steeper”. • Early design decisions might create value, but this is only “on paper”; value has to be monetized, and that path may not be certain because of other factors driving development risk; market risks, entitlement risks, financing risks, etc. 16
  • 17. IPD & Cost of Capital 17 1 2 34 Flatter slope in cost of capital line (green) drives preference for an integrated model to leverage the value of design cost/impact curves.
  • 18. What determines cost of capital “slope”? • Drivers of value; what is driving fundamental project value? • Components of development risk; Market? Entitlement? Permits? Financing? Environmental? • When are returns realized? Through long term asset, or through short term conditions? 18
  • 19. Implications • From a development risk management perspective, MacLearny curve is compelling, but incomplete; • Because of the uncertainty of outcomes, the cost of capital in a development environment is high; • This cost of money drives up the true cost of a dollar (from a risk/return perspective) in early stages; • MacLearny may be comparing dollars to dollars without regard to risk/return multipliers; every dollar is not the same in a project, and front-loading costs that may not be recoverable because of entitlement or market risks can heavily influence decisions. 19
  • 20. Closing • Industry needs numbers to make the business case, and make informed decisions! • IPD may be written off as aspirational; or taken as directional – this is a trend and we should embrace that trend vs. take it as prescriptive. • The attitude of collaboration and teamwork that underwrites IPD- that alone may be worth it! 20
  • 21. Bibliography • IPD graphic, original concept by Patrick MacLearny, FAIA, CEO, HOK Group, © HOK Group, Inc., 2009 all rights reserved. • Project development concepts are adapted from SROPTTC TM , which is a trademark of the Alliance for Sustainable Energy, LLC, the operator of the National Renewable Energy Laboratory. • http://www.nrel.gov/docs/fy13osti/57963.pdf • www.Investopedia.com, accessed June 21, 2013. 21