SlideShare a Scribd company logo
Quarantine Mistakenly
We thankfully acknowledge the receipt of your inquiry. Our offer shall be submitted
shortly.
Mechanical (Maintenance & Project) & Process Work Progress
Report as on 06-04-2021 (Miti: 2077/12/24).
Dear Sir,
Please find the attached copy of the Mechanical Work Progress (Maintenance and
Project) report and Process Work Progress report as on date 06-04-2021 (Miti: 2077/12/24).
Please also find the Daily Manpower report as supplied by NICE ENGG & Prabhat Employers
as on 6th-April & 7th-April-2021 (Miti: 2077/12/24 & 2077/12/25).
This is for your kind notice.
With Thanks & Regards
Vinod Kumar Verma
HOD-Mechanical Department
Balaji Cement Industries (P) Limited,
Chandrauta, Nepal.
Need of Technical Support for mill optimization.
Dear Sir,
We are in an urgent need of your technical support regarding the grinding of OPC &
PPC cement for our Loesche Mill LM35.2 + 2CS. As, we are now suffering from the mill
performance from past week. In this regard you are kindly requested to please provide
required technical support in this matter. We are hereby sending all the screen shot taken
during the mill run from 3rd April-2021 to 6th April-2021, for your reference.
We would also like to offer your technical expert to visit our plant Balaji Cement
Industries (P) Limited, Chandrauta, Nepal to troubleshoot the existing issue and
simultaneously to proceed for the 2nd PG test for continuous run of the mill for 72 Hrs.
although we had already accepted & satisfy with your previously carried out PG; but due to
some issue from our side the PG had not carried out for 72 Hrs.
So, you are kindly requested to please either provide us technical online support or
arrange to visit a technical expert to our plant site.
We immensely expect for your technical support in this regard.
With Thanks & Regards
Alok Verma
Director
WELMECH ENGINEERING SERVICES
Kathmandu, Nepal.
Since very long we are regret to inform that there are many out of which
some are very important items of VNR which had already been generated by M/s.
LOESCHE & still not updated their current status and its scheduled delivery to our plant
site BCIPL-Chandrauta-Clinker-LM 35.2+2CS. Now we are finally suffering due to the
lack of these items pertaining to mechanical as well as E&I Departments, for our
smooth & continuous operation of the plant.
In this regard we would like to inform you that many items of VNR that are
still pending to full fill our needs & support us to run the plant smoothly. Also no any
step had been taken from your side to update the actual status of these pending items.
So you are kindly requested to please arrange to provide us the detailed
copy of all the VNR generated by you for our side BCIPL-Chandrauta-Clinker-LM
35.2+2CS with the current status and its scheduled delivery or its transition state if
delivered so far.
We hopefully expect an immediate response in this regard.
We would like to inform you that there are some pending VNR which had
already been generated by M/s. LOESCHE & still not updated their current status and
its scheduled delivery to our plant site Balaji Cement Industries (P) Limited, Shivraj-6,
Chandrauta, Nepal. That's why we are sporadically suffering due to the lack of these
items for our smooth & continuous operation of the plant.
In this reference, you are kindly requested to please arrange to provide us
the detailed copy of all the VNR generated by you for our plant site BCIPL-Chandrauta-
Clinker-LM 35.2+2CS. Please also take trouble to provide the current status and its
scheduled delivery or its transition state if delivered so far.
We hopefully expect a prompt reply in this regard and it will highly be
appreciable.
With Thanks & Regards
Vinod Kumar Verma
HOD-Mechanical Department
Balaji Cement Industries (P) Limited,
Chandrauta, Nepal.
Meanwhile, we are discussing with welding teams for hard facing job of grinding tyres. pl. let us know
the followings regarding tyre hard facing job:-
1. Is the hard facing wire received at plant site?
2. What are Covid 19 guidelines in Nepal nowadays for vistors from India Via Barni Border ? Is
there any quarantine policy if any welding team visit is planned to Nepal from India?
3. Is Barni Border is operative nowadays or we have to come via Bhairwa?
4. When you are planning for shut down as we need to plan mobilise the tool and tackles first
and then movement of manpower
Respected Sir,
Good day, Sir.
Please find the attached copy of our quotation for manpower supply for plant
operation and maintenance purpose to your line-II clinkerization and grinding unit. We have
well maintained man-power to suit with all maintenance activities as per your need.
So you are kindly requested to please give us an opportunity to work with your
esteemed organization and our long term mutual relationship for our mutual groth.
With Thanks & Regards
Alok Verma
Director
WELMECH ENGINEERING SERVICES
Kathmandu, Nepal.
There are some important clinical guidelines as per recommendations of NMC,
(Nepal Medical Council) which are mentioned hereunder for a general awareness.
1. Hard facing wire is yet not received at our site. Please send the details of it; so as to
inquire for the same.
2. As nowadays COVID-19 pandemic, the viral disease is affecting our lives most tragically
& India is badly suffering from it. Also, its grave impacts on the visitors of Nepal. There
are some important clinical guidelines as per recommendations of NMC, (Nepal Medical
Council); these points are mentioned hereunder for a general application & awareness
purpose.
i)
Quarantine Information:
(i) Nepal announced that all arrivals into Nepal will be self-quarantined for fourteen
(14) days.
(ii) Suspected cases will be quarantined for 14 days.
(iii) Private and non-government sectors are encouraged to postpone their international
programs scheduled to be held in Nepal.
Although, the public vehicles are prohibited at both the borders (Barhni &
Sonauli/Bhairhawa); but its open for general public movement by on foot to cross the borders.
Also there is no special check at the border for a common public until the person is suspected
for Covid-19. If such coincidence occurs, then the suspect may have to pass through the
Quarantine norms as imposed by Nepal government. The desired Quarantine Information is
mentioned hereunder for your notice.
We would like to remind you some Pending highlighted issues and VNR; which are
causing problem for the smooth running of plant. We finally need your technical support or
clarification for below mentioned points.
(a) Commissioning of HAG with rice husk is still pending,
(b) HAG diesel firing pump having no standby,
(c) Mill gearbox lubrication LP pump having no standby,
(d) Bag house all rotary air locks pin bush coupling were to be replaced by another suitable
pin bush coupling. However M/s. BCIPL received 2 Nos. of proposed couplings out of 8
Nos.
(e) Installation of stack monitoring device,
(f) Commissioning of fly ash handling system
(g) Mill Motor Coupling Guard replacement by a suitable modified coupling for adequate
cooling of main motor.
-----Ref: - Mailed to M/s. Loesche dated 24/12/2019 with reminders.
(h) Mill Inlet Draft Transmitter was showing error need your technical support,
-----Ref: - Mailed to M/s. Loesche dated 13/01/2020 with sanps.
(i) Mill Bag House Fan VFD repeated sporadic Problem
-----Ref: - Mailed to M/s. Loesche dated 23/11/2020 & 20/01/2021
(j) Mill Main Motor LRS related Problem as discussed earlier.
-----Ref: - Mailed to M/s. Loesche dated 02/02/2021
Another problem which is observed during the plant operation is that when
NEA power failure occurs, it was found that the fan was moving at the speed of set
point given at DCS until stop with inertia. This may cause regenerative power to flow
in the VFD & may cause component failure in the convertor circuit. It further needs
analysis for the component protection whether to implement DBR or not.
Pl.provide below dimensionsof Accumulatorshell.:
Gas valve OD or shell openingontopside.
We can checkour bladderfitmentafterreceiptof above details.
Due to intermittentslightrainfall sheetfixingworkwasstopped.
Parameters Unit
Max. Operating Pressure Bar
Min. Operating pressure Bar
Operating Temp range degC
Require stored volume/discharge volume Ltrs
System Flow rate LPM
Available pump flow LPM
Cycle time Sec
System fluid details
Application details
Dimensional constraints
Required certification
Tarpaulin
Worng
Gate Valves
Gate Valve Installation & Maintenance Instructions
Gate Valves of all materials and seat types are easy to use and long lasting when they are
installed and maintained correctly. The installation technique varies slightly for different end
connections (eg. flanged vs rolled groove vs victaulic) but the other instructions remain the same.
Storage Conditions
 To protect the seat and seals do not unpack the valves until they are ready for installation.
By doing this you are protecting the valve from dust and debris which may eventually cause
seat leakage.
 Keep in a cool well ventilated space if storing for a longer period of time.
Valve Installation
 Valves can be installed in any orientation however it is best if it can be installed upright
especially in bigger sizes for ease of hand wheel access.
 Verify the material of the gate valve, seat and disc before installation. Ensure that there are
no defects caused by storage or transportation.
 Complete all welding works before valve installation and be sure the flange has cooled to
ambient temperature before installing the gate valve using the appropriate gasket.
 Make sure there is no welding residue, waste, rust, pickle paste or other debris in the pipe
before installation. Wash with water or a mild detergent if needed.
 Make sure there is no warpage of the flange or misalignment of the gate valve in relation to
the flange. This is the most common cause of valve problems where it is not aligned with
the flange/pipe correctly. Support the valve where necessary to reduce load on the piping
assembly.
 Install the spacing bolts taking care not to damage the valve seat and adjust the face to face
of the two flanges so there is space when the piping is spread open (enough space to slip
the valve in or out for service).
 Once the pipes are centered, insert the bolts so that the bottom of the valve can rest upon
them to prevent the valve from falling through.
 Tighten the bolts one at a time doing it in stages so even pressure is applied and a seal is
formed between the valve, gasket and flanges.
 Once the installatiion is complete, operate the valve several times to ensure it has not
moved during installation.
Field Testing
 Rubber seated gate valves are designed to hold rated pressures only. Test pressures
above rated working pressure in the closed position can cause damage to the valve.
 With the valve in the open position the pipeline can be tested up to the valve hydrostatic test
pressure.
 Seat leakage can occur when foreign material is wedged between the seat and the body.
If this occurs, open the valve 10% to 15% to obtain high velocity flushing action. Close and
repeat if necessary.
Operation
 Do not use the valve at pressures above its working pressure.
 If the valve is jammed in a position between open and closed check the valve face and seat.
Remove and check for foreign objects (see maintenance).
 Excessive torque from actuators can damage internal valve parts.
Maintenance
 Cycle the valve at least once a month if not used regularly.
 Relieve the system pressure before performing any maintenance.
 To remove from pipework reverse the installation sequence (above).
 Replace valve gate by removing the top body (bonnet) and stem. Screw out the gate and
replace with new part. Install top of body and refit into line.
 See video link under each gate valve model for further instructions.
Design Guidance and Product Advantages
 When sizing the valve always consider available space for handwheel operation.
 Consider valve supports to carry excess weight.
 Extensions shafts in 316 Stainless Steel are available upon request. This will allow for the
valve to be mounted in a pit with above ground operation.
 These valves have Ductile Iron bodies for added strength. High finish moulded seats give
low torque operation for long maintenance free working life.

More Related Content

What's hot

Andrew Dennis Cooper CV 1 (4)
Andrew Dennis Cooper CV 1 (4)Andrew Dennis Cooper CV 1 (4)
Andrew Dennis Cooper CV 1 (4)
Andy Cooper
 
Brickenden Cv
Brickenden CvBrickenden Cv
Brickenden Cv
JimmyRigging
 
Resume2
Resume2Resume2
Resume2
Deverek Wade
 
NEWTON
NEWTONNEWTON
SCS_Company Capabilities Statement
SCS_Company Capabilities StatementSCS_Company Capabilities Statement
SCS_Company Capabilities Statement
Peter White
 
Jacson R Res u
Jacson R Res uJacson R Res u
Jacson R Res u
Jacson Rasmussen
 
bruce_s_new_resume_copy
bruce_s_new_resume_copybruce_s_new_resume_copy
bruce_s_new_resume_copy
Bruce Cyganoski
 
SBGHS towable welfare brochure 2019
SBGHS towable welfare brochure 2019SBGHS towable welfare brochure 2019
SBGHS towable welfare brochure 2019
S & B GROUP HIRE SERVICES LIMITED
 
Bruce_s_new_resume_copy
Bruce_s_new_resume_copyBruce_s_new_resume_copy
Bruce_s_new_resume_copy
Bruce Cyganoski
 
Sbghs towable wefare brochure 2020
Sbghs towable wefare brochure 2020Sbghs towable wefare brochure 2020
Sbghs towable wefare brochure 2020
S & B GROUP HIRE SERVICES LIMITED
 
NOV PP_Service_Flyer
NOV PP_Service_FlyerNOV PP_Service_Flyer
NOV PP_Service_Flyer
Ian Boxall
 
My Updated CV Aug 2016
My Updated CV Aug 2016My Updated CV Aug 2016
My Updated CV Aug 2016
David Scott
 
KontroQuarterly2Q2016 FINAL
KontroQuarterly2Q2016 FINALKontroQuarterly2Q2016 FINAL
KontroQuarterly2Q2016 FINAL
Brent Keeter
 
Petrustech Brochure 2015
Petrustech Brochure 2015Petrustech Brochure 2015
Petrustech Brochure 2015
Alberto Pena
 
Adeel Hammad, Cv
Adeel Hammad, CvAdeel Hammad, Cv
Adeel Hammad, Cv
adeelhammad
 
UPDATED CV
UPDATED CVUPDATED CV
Jwilliams - Brochure 1
Jwilliams - Brochure 1Jwilliams - Brochure 1
Jwilliams - Brochure 1
Jennifer Williams
 

What's hot (17)

Andrew Dennis Cooper CV 1 (4)
Andrew Dennis Cooper CV 1 (4)Andrew Dennis Cooper CV 1 (4)
Andrew Dennis Cooper CV 1 (4)
 
Brickenden Cv
Brickenden CvBrickenden Cv
Brickenden Cv
 
Resume2
Resume2Resume2
Resume2
 
NEWTON
NEWTONNEWTON
NEWTON
 
SCS_Company Capabilities Statement
SCS_Company Capabilities StatementSCS_Company Capabilities Statement
SCS_Company Capabilities Statement
 
Jacson R Res u
Jacson R Res uJacson R Res u
Jacson R Res u
 
bruce_s_new_resume_copy
bruce_s_new_resume_copybruce_s_new_resume_copy
bruce_s_new_resume_copy
 
SBGHS towable welfare brochure 2019
SBGHS towable welfare brochure 2019SBGHS towable welfare brochure 2019
SBGHS towable welfare brochure 2019
 
Bruce_s_new_resume_copy
Bruce_s_new_resume_copyBruce_s_new_resume_copy
Bruce_s_new_resume_copy
 
Sbghs towable wefare brochure 2020
Sbghs towable wefare brochure 2020Sbghs towable wefare brochure 2020
Sbghs towable wefare brochure 2020
 
NOV PP_Service_Flyer
NOV PP_Service_FlyerNOV PP_Service_Flyer
NOV PP_Service_Flyer
 
My Updated CV Aug 2016
My Updated CV Aug 2016My Updated CV Aug 2016
My Updated CV Aug 2016
 
KontroQuarterly2Q2016 FINAL
KontroQuarterly2Q2016 FINALKontroQuarterly2Q2016 FINAL
KontroQuarterly2Q2016 FINAL
 
Petrustech Brochure 2015
Petrustech Brochure 2015Petrustech Brochure 2015
Petrustech Brochure 2015
 
Adeel Hammad, Cv
Adeel Hammad, CvAdeel Hammad, Cv
Adeel Hammad, Cv
 
UPDATED CV
UPDATED CVUPDATED CV
UPDATED CV
 
Jwilliams - Brochure 1
Jwilliams - Brochure 1Jwilliams - Brochure 1
Jwilliams - Brochure 1
 

Similar to April 2021

C.V.-Mohamed Alsharkawy-2016
C.V.-Mohamed Alsharkawy-2016 C.V.-Mohamed Alsharkawy-2016
C.V.-Mohamed Alsharkawy-2016
Mohammed Salah El-Sharkawy
 
Yaqoob Resume.docx 15-4-2015
Yaqoob Resume.docx 15-4-2015Yaqoob Resume.docx 15-4-2015
Yaqoob Resume.docx 15-4-2015
abu khalid almohammadi
 
DWSI (FMD) profile and project details 20140528
DWSI (FMD) profile and project details 20140528DWSI (FMD) profile and project details 20140528
DWSI (FMD) profile and project details 20140528
Sasi K
 
Summer Training Report, DLW Varanasi
Summer Training Report, DLW VaranasiSummer Training Report, DLW Varanasi
Summer Training Report, DLW Varanasi
SHAILESH SHUKLA
 
walid salah.CV
walid salah.CVwalid salah.CV
walid salah.CV
Waleed Salah
 
Anish report
Anish reportAnish report
Anish report
rboy001
 
Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...
Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...
Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...
ABHINAV KUMAR
 
QC INSPECTOR E&I
QC INSPECTOR E&IQC INSPECTOR E&I
QC INSPECTOR E&I
NASIM NEZAM
 
HPCL Shapoorji Environment Impact AssessmentA.pptx
HPCL Shapoorji Environment Impact AssessmentA.pptxHPCL Shapoorji Environment Impact AssessmentA.pptx
HPCL Shapoorji Environment Impact AssessmentA.pptx
sohamsohamalways
 
SABER CV
SABER CVSABER CV
SABER CV
Saber Muallem
 
KQ 1Q 2015 FINALFinal
KQ 1Q 2015 FINALFinalKQ 1Q 2015 FINALFinal
KQ 1Q 2015 FINALFinal
Brent Keeter
 
cv_overview 2016
cv_overview 2016cv_overview 2016
cv_overview 2016
Damon Hughes
 
MS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdfMS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdf
NajiRaheem2
 
DLW training report
DLW  training reportDLW  training report
DLW training report
Ishant Gautam.
 
V.GUHAN-CV 01 link
V.GUHAN-CV 01 linkV.GUHAN-CV 01 link
V.GUHAN-CV 01 link
Guhan Visagan
 
updated Kessouar's Resume
updated Kessouar's Resumeupdated Kessouar's Resume
updated Kessouar's Resume
Mehdi Kessouar
 
Mohamed Hamed'cv
Mohamed Hamed'cvMohamed Hamed'cv
Mohamed Hamed'cv
Mohamed Hamed
 
PROFILE
PROFILEPROFILE
MOHAMMAD Updated CV
MOHAMMAD Updated CV MOHAMMAD Updated CV
MOHAMMAD Updated CV
Mohammad Naushad
 
Cv resume jimmy c. bernal
Cv resume jimmy c. bernalCv resume jimmy c. bernal
Cv resume jimmy c. bernal
Jimmy Bernal
 

Similar to April 2021 (20)

C.V.-Mohamed Alsharkawy-2016
C.V.-Mohamed Alsharkawy-2016 C.V.-Mohamed Alsharkawy-2016
C.V.-Mohamed Alsharkawy-2016
 
Yaqoob Resume.docx 15-4-2015
Yaqoob Resume.docx 15-4-2015Yaqoob Resume.docx 15-4-2015
Yaqoob Resume.docx 15-4-2015
 
DWSI (FMD) profile and project details 20140528
DWSI (FMD) profile and project details 20140528DWSI (FMD) profile and project details 20140528
DWSI (FMD) profile and project details 20140528
 
Summer Training Report, DLW Varanasi
Summer Training Report, DLW VaranasiSummer Training Report, DLW Varanasi
Summer Training Report, DLW Varanasi
 
walid salah.CV
walid salah.CVwalid salah.CV
walid salah.CV
 
Anish report
Anish reportAnish report
Anish report
 
Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...
Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...
Abhinav Kumar Mechanical Engineering Vocational Training Diesel Locomotive Wo...
 
QC INSPECTOR E&I
QC INSPECTOR E&IQC INSPECTOR E&I
QC INSPECTOR E&I
 
HPCL Shapoorji Environment Impact AssessmentA.pptx
HPCL Shapoorji Environment Impact AssessmentA.pptxHPCL Shapoorji Environment Impact AssessmentA.pptx
HPCL Shapoorji Environment Impact AssessmentA.pptx
 
SABER CV
SABER CVSABER CV
SABER CV
 
KQ 1Q 2015 FINALFinal
KQ 1Q 2015 FINALFinalKQ 1Q 2015 FINALFinal
KQ 1Q 2015 FINALFinal
 
cv_overview 2016
cv_overview 2016cv_overview 2016
cv_overview 2016
 
MS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdfMS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdf
 
DLW training report
DLW  training reportDLW  training report
DLW training report
 
V.GUHAN-CV 01 link
V.GUHAN-CV 01 linkV.GUHAN-CV 01 link
V.GUHAN-CV 01 link
 
updated Kessouar's Resume
updated Kessouar's Resumeupdated Kessouar's Resume
updated Kessouar's Resume
 
Mohamed Hamed'cv
Mohamed Hamed'cvMohamed Hamed'cv
Mohamed Hamed'cv
 
PROFILE
PROFILEPROFILE
PROFILE
 
MOHAMMAD Updated CV
MOHAMMAD Updated CV MOHAMMAD Updated CV
MOHAMMAD Updated CV
 
Cv resume jimmy c. bernal
Cv resume jimmy c. bernalCv resume jimmy c. bernal
Cv resume jimmy c. bernal
 

Recently uploaded

一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
yuhofha
 
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
dsnow9802
 
官方认证美国旧金山州立大学毕业证学位证书案例原版一模一样
官方认证美国旧金山州立大学毕业证学位证书案例原版一模一样官方认证美国旧金山州立大学毕业证学位证书案例原版一模一样
官方认证美国旧金山州立大学毕业证学位证书案例原版一模一样
2zjra9bn
 
5 Common Mistakes to Avoid During the Job Application Process.pdf
5 Common Mistakes to Avoid During the Job Application Process.pdf5 Common Mistakes to Avoid During the Job Application Process.pdf
5 Common Mistakes to Avoid During the Job Application Process.pdf
Alliance Jobs
 
A Guide to a Winning Interview June 2024
A Guide to a Winning Interview June 2024A Guide to a Winning Interview June 2024
A Guide to a Winning Interview June 2024
Bruce Bennett
 
Introducing Gopay Mobile App For Environment.pptx
Introducing Gopay Mobile App For Environment.pptxIntroducing Gopay Mobile App For Environment.pptx
Introducing Gopay Mobile App For Environment.pptx
FauzanHarits1
 
thyroid case presentation.pptx Kamala's Lakshaman palatial
thyroid case presentation.pptx Kamala's Lakshaman palatialthyroid case presentation.pptx Kamala's Lakshaman palatial
thyroid case presentation.pptx Kamala's Lakshaman palatial
Aditya Raghav
 
一比一原版(UVic毕业证)维多利亚大学毕业证如何办理
一比一原版(UVic毕业证)维多利亚大学毕业证如何办理一比一原版(UVic毕业证)维多利亚大学毕业证如何办理
一比一原版(UVic毕业证)维多利亚大学毕业证如何办理
pxyhy
 
Lbs last rank 2023 9988kr47h4744j445.pdf
Lbs last rank 2023 9988kr47h4744j445.pdfLbs last rank 2023 9988kr47h4744j445.pdf
Lbs last rank 2023 9988kr47h4744j445.pdf
ashiquepa3
 
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
2zjra9bn
 
一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理
一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理
一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理
taqyea
 
labb123456789123456789123456789123456789
labb123456789123456789123456789123456789labb123456789123456789123456789123456789
labb123456789123456789123456789123456789
Ghh
 
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdfRECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
AlessandroMartins454470
 
一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理
一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理
一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理
pxyhy
 
Leadership Ambassador club Adventist module
Leadership Ambassador club Adventist moduleLeadership Ambassador club Adventist module
Leadership Ambassador club Adventist module
kakomaeric00
 
0624.speakingengagementsandteaching-01.pdf
0624.speakingengagementsandteaching-01.pdf0624.speakingengagementsandteaching-01.pdf
0624.speakingengagementsandteaching-01.pdf
Thomas GIRARD BDes
 
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
pxyhy
 
Job Finding Apps Everything You Need to Know in 2024
Job Finding Apps Everything You Need to Know in 2024Job Finding Apps Everything You Need to Know in 2024
Job Finding Apps Everything You Need to Know in 2024
SnapJob
 
一比一原版(YU毕业证)约克大学毕业证如何办理
一比一原版(YU毕业证)约克大学毕业证如何办理一比一原版(YU毕业证)约克大学毕业证如何办理
一比一原版(YU毕业证)约克大学毕业证如何办理
yuhofha
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
yuhofha
 

Recently uploaded (20)

一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
一比一原版(TMU毕业证)多伦多都会大学毕业证如何办理
 
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
Jill Pizzola's Tenure as Senior Talent Acquisition Partner at THOMSON REUTERS...
 
官方认证美国旧金山州立大学毕业证学位证书案例原版一模一样
官方认证美国旧金山州立大学毕业证学位证书案例原版一模一样官方认证美国旧金山州立大学毕业证学位证书案例原版一模一样
官方认证美国旧金山州立大学毕业证学位证书案例原版一模一样
 
5 Common Mistakes to Avoid During the Job Application Process.pdf
5 Common Mistakes to Avoid During the Job Application Process.pdf5 Common Mistakes to Avoid During the Job Application Process.pdf
5 Common Mistakes to Avoid During the Job Application Process.pdf
 
A Guide to a Winning Interview June 2024
A Guide to a Winning Interview June 2024A Guide to a Winning Interview June 2024
A Guide to a Winning Interview June 2024
 
Introducing Gopay Mobile App For Environment.pptx
Introducing Gopay Mobile App For Environment.pptxIntroducing Gopay Mobile App For Environment.pptx
Introducing Gopay Mobile App For Environment.pptx
 
thyroid case presentation.pptx Kamala's Lakshaman palatial
thyroid case presentation.pptx Kamala's Lakshaman palatialthyroid case presentation.pptx Kamala's Lakshaman palatial
thyroid case presentation.pptx Kamala's Lakshaman palatial
 
一比一原版(UVic毕业证)维多利亚大学毕业证如何办理
一比一原版(UVic毕业证)维多利亚大学毕业证如何办理一比一原版(UVic毕业证)维多利亚大学毕业证如何办理
一比一原版(UVic毕业证)维多利亚大学毕业证如何办理
 
Lbs last rank 2023 9988kr47h4744j445.pdf
Lbs last rank 2023 9988kr47h4744j445.pdfLbs last rank 2023 9988kr47h4744j445.pdf
Lbs last rank 2023 9988kr47h4744j445.pdf
 
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
在线制作加拿大萨省大学毕业证文凭证书实拍图原版一模一样
 
一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理
一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理
一比一原版布拉德福德大学毕业证(bradford毕业证)如何办理
 
labb123456789123456789123456789123456789
labb123456789123456789123456789123456789labb123456789123456789123456789123456789
labb123456789123456789123456789123456789
 
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdfRECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
RECOGNITION AWARD 13 - TO ALESSANDRO MARTINS.pdf
 
一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理
一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理
一比一原版(UBC毕业证)不列颠哥伦比亚大学毕业证如何办理
 
Leadership Ambassador club Adventist module
Leadership Ambassador club Adventist moduleLeadership Ambassador club Adventist module
Leadership Ambassador club Adventist module
 
0624.speakingengagementsandteaching-01.pdf
0624.speakingengagementsandteaching-01.pdf0624.speakingengagementsandteaching-01.pdf
0624.speakingengagementsandteaching-01.pdf
 
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
一比一原版(SFU毕业证)西蒙弗雷泽大学毕业证如何办理
 
Job Finding Apps Everything You Need to Know in 2024
Job Finding Apps Everything You Need to Know in 2024Job Finding Apps Everything You Need to Know in 2024
Job Finding Apps Everything You Need to Know in 2024
 
一比一原版(YU毕业证)约克大学毕业证如何办理
一比一原版(YU毕业证)约克大学毕业证如何办理一比一原版(YU毕业证)约克大学毕业证如何办理
一比一原版(YU毕业证)约克大学毕业证如何办理
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
 

April 2021

  • 1. Quarantine Mistakenly We thankfully acknowledge the receipt of your inquiry. Our offer shall be submitted shortly. Mechanical (Maintenance & Project) & Process Work Progress Report as on 06-04-2021 (Miti: 2077/12/24). Dear Sir, Please find the attached copy of the Mechanical Work Progress (Maintenance and Project) report and Process Work Progress report as on date 06-04-2021 (Miti: 2077/12/24). Please also find the Daily Manpower report as supplied by NICE ENGG & Prabhat Employers as on 6th-April & 7th-April-2021 (Miti: 2077/12/24 & 2077/12/25). This is for your kind notice. With Thanks & Regards Vinod Kumar Verma HOD-Mechanical Department Balaji Cement Industries (P) Limited, Chandrauta, Nepal.
  • 2. Need of Technical Support for mill optimization. Dear Sir, We are in an urgent need of your technical support regarding the grinding of OPC & PPC cement for our Loesche Mill LM35.2 + 2CS. As, we are now suffering from the mill performance from past week. In this regard you are kindly requested to please provide required technical support in this matter. We are hereby sending all the screen shot taken during the mill run from 3rd April-2021 to 6th April-2021, for your reference. We would also like to offer your technical expert to visit our plant Balaji Cement Industries (P) Limited, Chandrauta, Nepal to troubleshoot the existing issue and simultaneously to proceed for the 2nd PG test for continuous run of the mill for 72 Hrs. although we had already accepted & satisfy with your previously carried out PG; but due to some issue from our side the PG had not carried out for 72 Hrs. So, you are kindly requested to please either provide us technical online support or arrange to visit a technical expert to our plant site. We immensely expect for your technical support in this regard. With Thanks & Regards Alok Verma Director WELMECH ENGINEERING SERVICES Kathmandu, Nepal. Since very long we are regret to inform that there are many out of which some are very important items of VNR which had already been generated by M/s. LOESCHE & still not updated their current status and its scheduled delivery to our plant
  • 3. site BCIPL-Chandrauta-Clinker-LM 35.2+2CS. Now we are finally suffering due to the lack of these items pertaining to mechanical as well as E&I Departments, for our smooth & continuous operation of the plant. In this regard we would like to inform you that many items of VNR that are still pending to full fill our needs & support us to run the plant smoothly. Also no any step had been taken from your side to update the actual status of these pending items. So you are kindly requested to please arrange to provide us the detailed copy of all the VNR generated by you for our side BCIPL-Chandrauta-Clinker-LM 35.2+2CS with the current status and its scheduled delivery or its transition state if delivered so far. We hopefully expect an immediate response in this regard. We would like to inform you that there are some pending VNR which had already been generated by M/s. LOESCHE & still not updated their current status and its scheduled delivery to our plant site Balaji Cement Industries (P) Limited, Shivraj-6, Chandrauta, Nepal. That's why we are sporadically suffering due to the lack of these items for our smooth & continuous operation of the plant. In this reference, you are kindly requested to please arrange to provide us the detailed copy of all the VNR generated by you for our plant site BCIPL-Chandrauta- Clinker-LM 35.2+2CS. Please also take trouble to provide the current status and its scheduled delivery or its transition state if delivered so far. We hopefully expect a prompt reply in this regard and it will highly be appreciable. With Thanks & Regards Vinod Kumar Verma HOD-Mechanical Department Balaji Cement Industries (P) Limited, Chandrauta, Nepal. Meanwhile, we are discussing with welding teams for hard facing job of grinding tyres. pl. let us know the followings regarding tyre hard facing job:-
  • 4. 1. Is the hard facing wire received at plant site? 2. What are Covid 19 guidelines in Nepal nowadays for vistors from India Via Barni Border ? Is there any quarantine policy if any welding team visit is planned to Nepal from India? 3. Is Barni Border is operative nowadays or we have to come via Bhairwa? 4. When you are planning for shut down as we need to plan mobilise the tool and tackles first and then movement of manpower Respected Sir, Good day, Sir. Please find the attached copy of our quotation for manpower supply for plant operation and maintenance purpose to your line-II clinkerization and grinding unit. We have well maintained man-power to suit with all maintenance activities as per your need. So you are kindly requested to please give us an opportunity to work with your esteemed organization and our long term mutual relationship for our mutual groth. With Thanks & Regards Alok Verma Director WELMECH ENGINEERING SERVICES Kathmandu, Nepal. There are some important clinical guidelines as per recommendations of NMC, (Nepal Medical Council) which are mentioned hereunder for a general awareness.
  • 5. 1. Hard facing wire is yet not received at our site. Please send the details of it; so as to inquire for the same. 2. As nowadays COVID-19 pandemic, the viral disease is affecting our lives most tragically & India is badly suffering from it. Also, its grave impacts on the visitors of Nepal. There are some important clinical guidelines as per recommendations of NMC, (Nepal Medical Council); these points are mentioned hereunder for a general application & awareness purpose. i) Quarantine Information: (i) Nepal announced that all arrivals into Nepal will be self-quarantined for fourteen (14) days. (ii) Suspected cases will be quarantined for 14 days. (iii) Private and non-government sectors are encouraged to postpone their international programs scheduled to be held in Nepal. Although, the public vehicles are prohibited at both the borders (Barhni & Sonauli/Bhairhawa); but its open for general public movement by on foot to cross the borders. Also there is no special check at the border for a common public until the person is suspected for Covid-19. If such coincidence occurs, then the suspect may have to pass through the Quarantine norms as imposed by Nepal government. The desired Quarantine Information is mentioned hereunder for your notice. We would like to remind you some Pending highlighted issues and VNR; which are causing problem for the smooth running of plant. We finally need your technical support or clarification for below mentioned points. (a) Commissioning of HAG with rice husk is still pending, (b) HAG diesel firing pump having no standby, (c) Mill gearbox lubrication LP pump having no standby,
  • 6. (d) Bag house all rotary air locks pin bush coupling were to be replaced by another suitable pin bush coupling. However M/s. BCIPL received 2 Nos. of proposed couplings out of 8 Nos. (e) Installation of stack monitoring device, (f) Commissioning of fly ash handling system (g) Mill Motor Coupling Guard replacement by a suitable modified coupling for adequate cooling of main motor. -----Ref: - Mailed to M/s. Loesche dated 24/12/2019 with reminders. (h) Mill Inlet Draft Transmitter was showing error need your technical support, -----Ref: - Mailed to M/s. Loesche dated 13/01/2020 with sanps. (i) Mill Bag House Fan VFD repeated sporadic Problem -----Ref: - Mailed to M/s. Loesche dated 23/11/2020 & 20/01/2021 (j) Mill Main Motor LRS related Problem as discussed earlier. -----Ref: - Mailed to M/s. Loesche dated 02/02/2021 Another problem which is observed during the plant operation is that when NEA power failure occurs, it was found that the fan was moving at the speed of set point given at DCS until stop with inertia. This may cause regenerative power to flow in the VFD & may cause component failure in the convertor circuit. It further needs analysis for the component protection whether to implement DBR or not.
  • 7.
  • 8. Pl.provide below dimensionsof Accumulatorshell.: Gas valve OD or shell openingontopside. We can checkour bladderfitmentafterreceiptof above details. Due to intermittentslightrainfall sheetfixingworkwasstopped. Parameters Unit Max. Operating Pressure Bar Min. Operating pressure Bar Operating Temp range degC Require stored volume/discharge volume Ltrs System Flow rate LPM Available pump flow LPM Cycle time Sec System fluid details Application details Dimensional constraints Required certification
  • 10. Worng Gate Valves Gate Valve Installation & Maintenance Instructions Gate Valves of all materials and seat types are easy to use and long lasting when they are installed and maintained correctly. The installation technique varies slightly for different end connections (eg. flanged vs rolled groove vs victaulic) but the other instructions remain the same. Storage Conditions  To protect the seat and seals do not unpack the valves until they are ready for installation. By doing this you are protecting the valve from dust and debris which may eventually cause seat leakage.
  • 11.  Keep in a cool well ventilated space if storing for a longer period of time. Valve Installation  Valves can be installed in any orientation however it is best if it can be installed upright especially in bigger sizes for ease of hand wheel access.  Verify the material of the gate valve, seat and disc before installation. Ensure that there are no defects caused by storage or transportation.  Complete all welding works before valve installation and be sure the flange has cooled to ambient temperature before installing the gate valve using the appropriate gasket.  Make sure there is no welding residue, waste, rust, pickle paste or other debris in the pipe before installation. Wash with water or a mild detergent if needed.  Make sure there is no warpage of the flange or misalignment of the gate valve in relation to the flange. This is the most common cause of valve problems where it is not aligned with the flange/pipe correctly. Support the valve where necessary to reduce load on the piping assembly.  Install the spacing bolts taking care not to damage the valve seat and adjust the face to face of the two flanges so there is space when the piping is spread open (enough space to slip the valve in or out for service).  Once the pipes are centered, insert the bolts so that the bottom of the valve can rest upon them to prevent the valve from falling through.  Tighten the bolts one at a time doing it in stages so even pressure is applied and a seal is formed between the valve, gasket and flanges.  Once the installatiion is complete, operate the valve several times to ensure it has not moved during installation. Field Testing  Rubber seated gate valves are designed to hold rated pressures only. Test pressures above rated working pressure in the closed position can cause damage to the valve.  With the valve in the open position the pipeline can be tested up to the valve hydrostatic test pressure.  Seat leakage can occur when foreign material is wedged between the seat and the body. If this occurs, open the valve 10% to 15% to obtain high velocity flushing action. Close and repeat if necessary. Operation  Do not use the valve at pressures above its working pressure.  If the valve is jammed in a position between open and closed check the valve face and seat. Remove and check for foreign objects (see maintenance).  Excessive torque from actuators can damage internal valve parts. Maintenance
  • 12.  Cycle the valve at least once a month if not used regularly.  Relieve the system pressure before performing any maintenance.  To remove from pipework reverse the installation sequence (above).  Replace valve gate by removing the top body (bonnet) and stem. Screw out the gate and replace with new part. Install top of body and refit into line.  See video link under each gate valve model for further instructions. Design Guidance and Product Advantages  When sizing the valve always consider available space for handwheel operation.  Consider valve supports to carry excess weight.  Extensions shafts in 316 Stainless Steel are available upon request. This will allow for the valve to be mounted in a pit with above ground operation.  These valves have Ductile Iron bodies for added strength. High finish moulded seats give low torque operation for long maintenance free working life.