SlideShare a Scribd company logo
1 of 58
TRISHULI HYDROPOWER VISIT
Presented by:
Surendra purbey(070/BEL/346)
Kamal singh tharu(070/BEL/314)
Sanjit kumar singh(070/BEL/337)
Sadanand kumar yadav(070/BEL/330)
Binay aale (070/BEL/3 )
Mukesh bhatt(070/BEL/3 )
Aashis karki (070/BEL/243 )
INTRODUCTION
TRISHULI NUWAKOT
GENERAL 0VERVIEW
Located at 70 km north-west of Kathmandu at Trishuli, Nuwakot
Constructed on Trishuli river
Installed capacity 21 MW in 1967 AD consisting of 7 units each of 3 MW
Upgraded to 24 MW in 1995 AD with 6 units each of 3.5 MW and
one unit of 3 MW
Developed By Government of India and Government of Nepal at a
Cost of INR 140 million
Head of station Baburaja Maharjan
SAILENT FEATURES
Maximum net head 51.4 m
Average annual flow 45.66 m^3/s
Length of Dam 139.6 m
Length of Waterway 4,792 m
Penstock 71.66 m & 2.3 m , 3Nos., steel
(length &dia.) 89 m & 1.5 m, 1Nos., steel
No. of Bridge 4
Catchment area 2600 sq km
Design generation 163 GWh annually
GENERATOR
Rated Output 3889 KVA
Rated Voltage 6.6 KV
Rated Frequency 50 Hz
Power factor 0.9
Power Transformer 5 MVA , 6.6/66 KV Single phase,6 Nos
Transmission Line 66 KV 27.6 km , Double circuit
66 KV 5 km ,Single circuit
TURBINE
Number and type 7, Francis
Rated Discharge 7.8 m^3/s
Rated Output 3620 kw
Rated Speed 500 rpm
CIVIL PART
WATER RETAINING STRUCTURE WITH SIDE
CHANNEL SPILLWAY
SIDE INTAKE
LIFT GATE WITH GEAR ROPE ELECTRIC DRIVE
TRAPEZOIDAL OPEN CHANNEL SYSTEM
OVERHEAD FLOW OVER RIVER
o Flow is diverse through residential area with two bridge type canal.
SETTLING BASIN (DECENDER)
oIt removes sediment load up to 0.2mm diameter.
oThe greater basin area & lower the through velocity the smaller the particles can settle down.
oOne traits for this case is being used as picnic spot area.
RESERVOIR
o We can notice problem of high silt.
FOREBAY
oEntry point for three penstock pipes
oStructure being lies on highway of headquarter
PENSTOCK PIPES
o Each 3 pipes serves for two units while last pipe feed single unit
MECHANICAL PART
TURBINE GENERATOR SETS
o Number of blades = 13 Inlet diameter = 1080 mm Throat diameter = 1100 mm
RUNNER
WICKET GATE
GOVERNER
SPIRAL CASING
INLET VALVE BY-PASS VALVE
DRAFT TUBE
TAILRACE
Here centered pipe is used to discharge leakage water (dewatering)
Initially tailrace discharge is mixed to trisuli itself
Now it is used for devighat power plant
ELECTRICAL PART
GENERATORS
parameter Unit 1-3 Unit 4-7
Original designer Rade koncar Fuji electric
Rated output 3500kw(+10% overload) 3500kw(+10% overload)
Rated capacity 3889 KVA 3889 KVA
Rated voltage 6.6KV 6.6KV
Stator connection 2Y 1Y
Rated current 340A 340A
Runaway speed 925 r.p.m 925 r.p.m
Stator winding resistance (per
phase)
0.10064 ohm @ 77°C 0.10064 ohm @ 77°C
Rotor winding resistance (per
phase)
0.1272 0.1159
Full load efficiency 96.79% 96.79%
SYNCHRONIZING PROCESS
Manual operation
Unit is connected to grid when its voltage and real power match system parameters
respectively
POWER FREQUENCY CONTROL
The regulator must designed to be insensitive to fast random
changes, otherwise the system will prone to hunting resulting in
excessive wear & tear of rotating machines & control
equipment.
EXCITATION SYSTEM
PLC or Human machine interface(HMI) is used to control excitation automatically and remotely.
STATIC EXCITATION SYSTEM
Field current:
At no = 157-164.7A @ 77V
At full load = 290-304.2A
At 110% rated load = 306-320A
PLC
Programmable Logic Controller is a user friendly, microprocessor specialized computer that
carries out control functions.
oMonitor crucial process parameters and
adjust process operations accordingly.
oCan be programmed, controlled and
operated by a person unskilled in operating
computers.
oPLCs are used in the substation to manage
transformers, voltage regulation, automatic
transfer schemes, custom/automatic reclosing
schemes, automatic service restoration,
remote control, system diagnostics
maintenance
SWITCHING PANELS
o Double for double bus bar system.
INDOOR HV VCB
CONTROL SYSTEM
CONTROL ROOM
oEach unit have its own control set.
oAt least one technical must be here to monitor whether generation and other operation is
within limit.
TRANSFORMER CONTROL & RELAY PANEL
GENERATOR PROTECTION PANEL
DATE U1 U2 U3 U4 U5 U6 U7 TOTAL(
MW)
8/21 3 2.5 3 1 3 3 3 18.5
8/22 3 3 3 1 3 3 3 19
8/23 2 3 3 1 3 3 3 18
8/24 3 2 3 1 3 3 3 18
8/25 3 2 3 1 3 3 3 18
GENERATION DATA OF 8/21 TO 8/25
STATION ANNUNCIATOR PANEL
o It indicates which of several electric circuits has been activated.
RECORDER PANELS
TRANSDUCER PANELS
BATTERY ROOM
oThe control panels and relays require DC supply of 220V.
oNi-Cd batteries are used due to their advantages like low maintenance , longer life
(15-25 years).
oEach cell is of 2V and 6Ah capacity.
o55 cell is connected to 110V charging system.
oNormally charging panel delivers load & give trickle charging to Battery bank
oworks on Auto and Manual mode.
FIRE PROTECTION
o A new fire detection and protection system was installed with complete Halogen gas fire,
portable fire extinguishers and fire hose reels and fire hydrants for total protection of power
house.
SWITCHYARD
oJunction of four areas network
oBalaju-1 and balaju-2 by double circuit transmission line (27.6Km)
oChilime and devighat (5Km) by single circuit
oAlso distribute power to local area
SUBSTATION
SINGLE LINE DIAGRAM
TRANSFORMERS
oSix single phase power transformers of rating 5 MVA 6.6/66 kv
oOne 3 phase distribution transformer of rating 10 MVA 6.6/11 kv for local distribution
COOLING AND FIRE EXTINGUSHER
oCooling pipe are run along all transformers
oOperate when transformer are overloaded or any abnormal conditions
INSTRUMENTATION TRANSFORMERS
66 kv CT 66 kv PT
SF6 CIRCUIT BREAKER
BUS COUPLER
o Coupling is done when one bus bar fails which removes interruption to feeder.
SURGE PROTECTION
LIGHTNING PROTECTOR ROD GAP ARRESTER
CONCLUSION
SPECIAL FEATURES
• One of the oldest HPP but still operating well
• Lies on headquarter of Nuwakot
• More number of units making it more efficient
• 3 single phase transformers combine to make three phase has its
own advantage
• Tailrace utilize for another HPP
PROBLEMS
• Small area of the settling basin so the sand does not settle properly in the basin.
• Problem in diversion system and intake construction.
• There is no SCADA system in use.
• The amount of silt accumulated in the reservoir is excess.
• Weir and tear on the runner due to silt.
• Manual synchronizing and Governing system.
• The settling basin should be upgraded.
• The direction of the flow of water should be managed at diversion weir.
• The SCADA system should be maintained as soon as possible.
• The number of instrument to clean silt should be increased.
• Governing and overall system should be upgraded to digital.
RECOMMENDATIONS
• www.nea.org.np
• www.google.com
• Handbook of
Trishuli hydropower
Project
• Trishuli Upgrading
File
REFERENCES

More Related Content

What's hot

Overhead railway traction
Overhead railway tractionOverhead railway traction
Overhead railway tractionProbodh Mallick
 
Distributed Control System (DCS) Notes
Distributed Control System (DCS) NotesDistributed Control System (DCS) Notes
Distributed Control System (DCS) NotesRaj Nayak
 
Scada systems automating electrical distribution
Scada systems automating electrical distributionScada systems automating electrical distribution
Scada systems automating electrical distributionSHUBHAM SAINI
 
Basic elements in control systems
Basic elements in control systemsBasic elements in control systems
Basic elements in control systemsSatheeshCS2
 
Introduction to SCADA
Introduction to SCADAIntroduction to SCADA
Introduction to SCADAPraveen Kumar
 
Analysis of Active Power Flow Control with Phase Shifting Transformer in AC T...
Analysis of Active Power Flow Control with Phase Shifting Transformer in AC T...Analysis of Active Power Flow Control with Phase Shifting Transformer in AC T...
Analysis of Active Power Flow Control with Phase Shifting Transformer in AC T...ijtsrd
 
Automation and Robotics Week 02 Theory Notes 20ME51I.pdf
Automation and Robotics Week 02 Theory Notes 20ME51I.pdfAutomation and Robotics Week 02 Theory Notes 20ME51I.pdf
Automation and Robotics Week 02 Theory Notes 20ME51I.pdfTHANMAY JS
 
Gas turbine Power Station Internship Report
Gas turbine Power Station Internship ReportGas turbine Power Station Internship Report
Gas turbine Power Station Internship ReportAsad Hussain
 
Timer in PLC and its Types.pdf
Timer in PLC and its Types.pdfTimer in PLC and its Types.pdf
Timer in PLC and its Types.pdfSAGE Automation
 
Computer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityComputer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityAdama Science and Technology University
 
SCADA PPT-21.08.2016 (Revised)
SCADA PPT-21.08.2016 (Revised)SCADA PPT-21.08.2016 (Revised)
SCADA PPT-21.08.2016 (Revised)Virendra Bharadwaj
 
Types of industrial automation (pdf)
Types of industrial automation (pdf)Types of industrial automation (pdf)
Types of industrial automation (pdf)SAGE Automation
 
Power System Stabilizer (PSS) for generator
Power System Stabilizer (PSS) for generatorPower System Stabilizer (PSS) for generator
Power System Stabilizer (PSS) for generatorKARAN TRIPATHI
 
Available transfer capability (atc) sbw ppt
Available transfer capability (atc) sbw pptAvailable transfer capability (atc) sbw ppt
Available transfer capability (atc) sbw pptRavi Sekpure
 
Hydro turbines(datas)
Hydro turbines(datas)Hydro turbines(datas)
Hydro turbines(datas)abhidude25
 
Modeling and Testing of Induction Motors
Modeling and Testing of Induction MotorsModeling and Testing of Induction Motors
Modeling and Testing of Induction MotorsBirju Besra
 

What's hot (20)

Distributed Control System
Distributed Control SystemDistributed Control System
Distributed Control System
 
Overhead railway traction
Overhead railway tractionOverhead railway traction
Overhead railway traction
 
Distributed Control System (DCS) Notes
Distributed Control System (DCS) NotesDistributed Control System (DCS) Notes
Distributed Control System (DCS) Notes
 
Scada systems automating electrical distribution
Scada systems automating electrical distributionScada systems automating electrical distribution
Scada systems automating electrical distribution
 
Basic elements in control systems
Basic elements in control systemsBasic elements in control systems
Basic elements in control systems
 
Introduction to SCADA
Introduction to SCADAIntroduction to SCADA
Introduction to SCADA
 
Analysis of Active Power Flow Control with Phase Shifting Transformer in AC T...
Analysis of Active Power Flow Control with Phase Shifting Transformer in AC T...Analysis of Active Power Flow Control with Phase Shifting Transformer in AC T...
Analysis of Active Power Flow Control with Phase Shifting Transformer in AC T...
 
Automation and Robotics Week 02 Theory Notes 20ME51I.pdf
Automation and Robotics Week 02 Theory Notes 20ME51I.pdfAutomation and Robotics Week 02 Theory Notes 20ME51I.pdf
Automation and Robotics Week 02 Theory Notes 20ME51I.pdf
 
Gas turbine Power Station Internship Report
Gas turbine Power Station Internship ReportGas turbine Power Station Internship Report
Gas turbine Power Station Internship Report
 
Timer in PLC and its Types.pdf
Timer in PLC and its Types.pdfTimer in PLC and its Types.pdf
Timer in PLC and its Types.pdf
 
Report on PLCC
Report on PLCCReport on PLCC
Report on PLCC
 
Computer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityComputer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and security
 
SCADA PPT-21.08.2016 (Revised)
SCADA PPT-21.08.2016 (Revised)SCADA PPT-21.08.2016 (Revised)
SCADA PPT-21.08.2016 (Revised)
 
SCADA PPT.pdf
SCADA PPT.pdfSCADA PPT.pdf
SCADA PPT.pdf
 
Lyapunov stability
Lyapunov stability Lyapunov stability
Lyapunov stability
 
Types of industrial automation (pdf)
Types of industrial automation (pdf)Types of industrial automation (pdf)
Types of industrial automation (pdf)
 
Power System Stabilizer (PSS) for generator
Power System Stabilizer (PSS) for generatorPower System Stabilizer (PSS) for generator
Power System Stabilizer (PSS) for generator
 
Available transfer capability (atc) sbw ppt
Available transfer capability (atc) sbw pptAvailable transfer capability (atc) sbw ppt
Available transfer capability (atc) sbw ppt
 
Hydro turbines(datas)
Hydro turbines(datas)Hydro turbines(datas)
Hydro turbines(datas)
 
Modeling and Testing of Induction Motors
Modeling and Testing of Induction MotorsModeling and Testing of Induction Motors
Modeling and Testing of Induction Motors
 

Similar to trisuli hydropower nepal

220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptxssuser1b3e431
 
Kulekhani 2nd hydropower station
Kulekhani 2nd hydropower station Kulekhani 2nd hydropower station
Kulekhani 2nd hydropower station Bikash Gyawali
 
400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.ppt400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.pptMarcWorld
 
Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentationRamendra Dhiman
 
the substation components study
the substation components study the substation components study
the substation components study Krishnaveni Reddy
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxAkshaiSai2
 
Vocational training report NHPC TANAKPUR Uttarakhand
Vocational training report NHPC TANAKPUR UttarakhandVocational training report NHPC TANAKPUR Uttarakhand
Vocational training report NHPC TANAKPUR UttarakhandShadab Khan
 
Ajay binay institute of technology,/ondvc
Ajay binay institute                                  of technology,/ondvcAjay binay institute                                  of technology,/ondvc
Ajay binay institute of technology,/ondvcMukesh Kumar
 
Durgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationDurgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationSaumyadip Moitra
 
SUMMER TRAINING @CHIBRO BY AAKASH
SUMMER TRAINING @CHIBRO BY AAKASH SUMMER TRAINING @CHIBRO BY AAKASH
SUMMER TRAINING @CHIBRO BY AAKASH THDC IHET
 
400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPURsahid raja khan
 
A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYRohitashav Goyal
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)saurabhVEC
 

Similar to trisuli hydropower nepal (20)

220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx
 
Kulekhani 2nd hydropower station
Kulekhani 2nd hydropower station Kulekhani 2nd hydropower station
Kulekhani 2nd hydropower station
 
Kotmale power station
Kotmale power stationKotmale power station
Kotmale power station
 
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan) 2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
 
Ashwani
AshwaniAshwani
Ashwani
 
400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.ppt400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.ppt
 
Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentation
 
the substation components study
the substation components study the substation components study
the substation components study
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
 
Vocational training report NHPC TANAKPUR Uttarakhand
Vocational training report NHPC TANAKPUR UttarakhandVocational training report NHPC TANAKPUR Uttarakhand
Vocational training report NHPC TANAKPUR Uttarakhand
 
Ajay binay institute of technology,/ondvc
Ajay binay institute                                  of technology,/ondvcAjay binay institute                                  of technology,/ondvc
Ajay binay institute of technology,/ondvc
 
Durgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationDurgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentation
 
POWER CAR.pptx
POWER CAR.pptxPOWER CAR.pptx
POWER CAR.pptx
 
SUMMER TRAINING @CHIBRO BY AAKASH
SUMMER TRAINING @CHIBRO BY AAKASH SUMMER TRAINING @CHIBRO BY AAKASH
SUMMER TRAINING @CHIBRO BY AAKASH
 
rough.pptx
rough.pptxrough.pptx
rough.pptx
 
400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR
 
A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
 
Ashish.pptx
Ashish.pptxAshish.pptx
Ashish.pptx
 

Recently uploaded

Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community PartnershipsSpring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community Partnershipsexpandedwebsite
 
Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...EduSkills OECD
 
Đề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinhĐề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinhleson0603
 
Improved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio AppImproved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio AppCeline George
 
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjjStl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjjMohammed Sikander
 
e-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopale-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi RajagopalEADTU
 
The Story of Village Palampur Class 9 Free Study Material PDF
The Story of Village Palampur Class 9 Free Study Material PDFThe Story of Village Palampur Class 9 Free Study Material PDF
The Story of Village Palampur Class 9 Free Study Material PDFVivekanand Anglo Vedic Academy
 
How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxCeline George
 
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...Nguyen Thanh Tu Collection
 
Book Review of Run For Your Life Powerpoint
Book Review of Run For Your Life PowerpointBook Review of Run For Your Life Powerpoint
Book Review of Run For Your Life Powerpoint23600690
 
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...Nguyen Thanh Tu Collection
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxAdelaideRefugio
 
Climbers and Creepers used in landscaping
Climbers and Creepers used in landscapingClimbers and Creepers used in landscaping
Climbers and Creepers used in landscapingDr. M. Kumaresan Hort.
 
SURVEY I created for uni project research
SURVEY I created for uni project researchSURVEY I created for uni project research
SURVEY I created for uni project researchCaitlinCummins3
 
DEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUM
DEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUMDEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUM
DEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUMELOISARIVERA8
 
PSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptxPSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptxMarlene Maheu
 
ANTI PARKISON DRUGS.pptx
ANTI         PARKISON          DRUGS.pptxANTI         PARKISON          DRUGS.pptx
ANTI PARKISON DRUGS.pptxPoojaSen20
 
Graduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptxGraduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptxneillewis46
 

Recently uploaded (20)

Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community PartnershipsSpring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
 
Mattingly "AI and Prompt Design: LLMs with NER"
Mattingly "AI and Prompt Design: LLMs with NER"Mattingly "AI and Prompt Design: LLMs with NER"
Mattingly "AI and Prompt Design: LLMs with NER"
 
Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...
 
Đề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinhĐề tieng anh thpt 2024 danh cho cac ban hoc sinh
Đề tieng anh thpt 2024 danh cho cac ban hoc sinh
 
Improved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio AppImproved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio App
 
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjjStl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
 
e-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopale-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopal
 
The Story of Village Palampur Class 9 Free Study Material PDF
The Story of Village Palampur Class 9 Free Study Material PDFThe Story of Village Palampur Class 9 Free Study Material PDF
The Story of Village Palampur Class 9 Free Study Material PDF
 
How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptx
 
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
 
Book Review of Run For Your Life Powerpoint
Book Review of Run For Your Life PowerpointBook Review of Run For Your Life Powerpoint
Book Review of Run For Your Life Powerpoint
 
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptx
 
Climbers and Creepers used in landscaping
Climbers and Creepers used in landscapingClimbers and Creepers used in landscaping
Climbers and Creepers used in landscaping
 
SURVEY I created for uni project research
SURVEY I created for uni project researchSURVEY I created for uni project research
SURVEY I created for uni project research
 
DEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUM
DEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUMDEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUM
DEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUM
 
OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...
 
PSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptxPSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptx
 
ANTI PARKISON DRUGS.pptx
ANTI         PARKISON          DRUGS.pptxANTI         PARKISON          DRUGS.pptx
ANTI PARKISON DRUGS.pptx
 
Graduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptxGraduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptx
 

trisuli hydropower nepal

  • 1. TRISHULI HYDROPOWER VISIT Presented by: Surendra purbey(070/BEL/346) Kamal singh tharu(070/BEL/314) Sanjit kumar singh(070/BEL/337) Sadanand kumar yadav(070/BEL/330) Binay aale (070/BEL/3 ) Mukesh bhatt(070/BEL/3 ) Aashis karki (070/BEL/243 )
  • 4. GENERAL 0VERVIEW Located at 70 km north-west of Kathmandu at Trishuli, Nuwakot Constructed on Trishuli river Installed capacity 21 MW in 1967 AD consisting of 7 units each of 3 MW Upgraded to 24 MW in 1995 AD with 6 units each of 3.5 MW and one unit of 3 MW Developed By Government of India and Government of Nepal at a Cost of INR 140 million Head of station Baburaja Maharjan
  • 5. SAILENT FEATURES Maximum net head 51.4 m Average annual flow 45.66 m^3/s Length of Dam 139.6 m Length of Waterway 4,792 m Penstock 71.66 m & 2.3 m , 3Nos., steel (length &dia.) 89 m & 1.5 m, 1Nos., steel No. of Bridge 4 Catchment area 2600 sq km Design generation 163 GWh annually
  • 6. GENERATOR Rated Output 3889 KVA Rated Voltage 6.6 KV Rated Frequency 50 Hz Power factor 0.9 Power Transformer 5 MVA , 6.6/66 KV Single phase,6 Nos Transmission Line 66 KV 27.6 km , Double circuit 66 KV 5 km ,Single circuit TURBINE Number and type 7, Francis Rated Discharge 7.8 m^3/s Rated Output 3620 kw Rated Speed 500 rpm
  • 8. WATER RETAINING STRUCTURE WITH SIDE CHANNEL SPILLWAY
  • 10. LIFT GATE WITH GEAR ROPE ELECTRIC DRIVE
  • 12. OVERHEAD FLOW OVER RIVER o Flow is diverse through residential area with two bridge type canal.
  • 13. SETTLING BASIN (DECENDER) oIt removes sediment load up to 0.2mm diameter. oThe greater basin area & lower the through velocity the smaller the particles can settle down. oOne traits for this case is being used as picnic spot area.
  • 14. RESERVOIR o We can notice problem of high silt.
  • 15. FOREBAY oEntry point for three penstock pipes oStructure being lies on highway of headquarter
  • 16. PENSTOCK PIPES o Each 3 pipes serves for two units while last pipe feed single unit
  • 19. o Number of blades = 13 Inlet diameter = 1080 mm Throat diameter = 1100 mm RUNNER
  • 25. TAILRACE Here centered pipe is used to discharge leakage water (dewatering) Initially tailrace discharge is mixed to trisuli itself Now it is used for devighat power plant
  • 27. GENERATORS parameter Unit 1-3 Unit 4-7 Original designer Rade koncar Fuji electric Rated output 3500kw(+10% overload) 3500kw(+10% overload) Rated capacity 3889 KVA 3889 KVA Rated voltage 6.6KV 6.6KV Stator connection 2Y 1Y Rated current 340A 340A Runaway speed 925 r.p.m 925 r.p.m Stator winding resistance (per phase) 0.10064 ohm @ 77°C 0.10064 ohm @ 77°C Rotor winding resistance (per phase) 0.1272 0.1159 Full load efficiency 96.79% 96.79%
  • 28. SYNCHRONIZING PROCESS Manual operation Unit is connected to grid when its voltage and real power match system parameters respectively
  • 29. POWER FREQUENCY CONTROL The regulator must designed to be insensitive to fast random changes, otherwise the system will prone to hunting resulting in excessive wear & tear of rotating machines & control equipment.
  • 30. EXCITATION SYSTEM PLC or Human machine interface(HMI) is used to control excitation automatically and remotely.
  • 31. STATIC EXCITATION SYSTEM Field current: At no = 157-164.7A @ 77V At full load = 290-304.2A At 110% rated load = 306-320A
  • 32. PLC Programmable Logic Controller is a user friendly, microprocessor specialized computer that carries out control functions. oMonitor crucial process parameters and adjust process operations accordingly. oCan be programmed, controlled and operated by a person unskilled in operating computers. oPLCs are used in the substation to manage transformers, voltage regulation, automatic transfer schemes, custom/automatic reclosing schemes, automatic service restoration, remote control, system diagnostics maintenance
  • 33. SWITCHING PANELS o Double for double bus bar system.
  • 36. CONTROL ROOM oEach unit have its own control set. oAt least one technical must be here to monitor whether generation and other operation is within limit.
  • 37. TRANSFORMER CONTROL & RELAY PANEL
  • 39. DATE U1 U2 U3 U4 U5 U6 U7 TOTAL( MW) 8/21 3 2.5 3 1 3 3 3 18.5 8/22 3 3 3 1 3 3 3 19 8/23 2 3 3 1 3 3 3 18 8/24 3 2 3 1 3 3 3 18 8/25 3 2 3 1 3 3 3 18 GENERATION DATA OF 8/21 TO 8/25
  • 40. STATION ANNUNCIATOR PANEL o It indicates which of several electric circuits has been activated.
  • 43. BATTERY ROOM oThe control panels and relays require DC supply of 220V. oNi-Cd batteries are used due to their advantages like low maintenance , longer life (15-25 years). oEach cell is of 2V and 6Ah capacity. o55 cell is connected to 110V charging system. oNormally charging panel delivers load & give trickle charging to Battery bank oworks on Auto and Manual mode.
  • 44. FIRE PROTECTION o A new fire detection and protection system was installed with complete Halogen gas fire, portable fire extinguishers and fire hose reels and fire hydrants for total protection of power house.
  • 46. oJunction of four areas network oBalaju-1 and balaju-2 by double circuit transmission line (27.6Km) oChilime and devighat (5Km) by single circuit oAlso distribute power to local area SUBSTATION
  • 48. TRANSFORMERS oSix single phase power transformers of rating 5 MVA 6.6/66 kv oOne 3 phase distribution transformer of rating 10 MVA 6.6/11 kv for local distribution
  • 49. COOLING AND FIRE EXTINGUSHER oCooling pipe are run along all transformers oOperate when transformer are overloaded or any abnormal conditions
  • 52. BUS COUPLER o Coupling is done when one bus bar fails which removes interruption to feeder.
  • 55. SPECIAL FEATURES • One of the oldest HPP but still operating well • Lies on headquarter of Nuwakot • More number of units making it more efficient • 3 single phase transformers combine to make three phase has its own advantage • Tailrace utilize for another HPP
  • 56. PROBLEMS • Small area of the settling basin so the sand does not settle properly in the basin. • Problem in diversion system and intake construction. • There is no SCADA system in use. • The amount of silt accumulated in the reservoir is excess. • Weir and tear on the runner due to silt. • Manual synchronizing and Governing system. • The settling basin should be upgraded. • The direction of the flow of water should be managed at diversion weir. • The SCADA system should be maintained as soon as possible. • The number of instrument to clean silt should be increased. • Governing and overall system should be upgraded to digital. RECOMMENDATIONS
  • 57.
  • 58. • www.nea.org.np • www.google.com • Handbook of Trishuli hydropower Project • Trishuli Upgrading File REFERENCES