TRISHULI HYDROPOWER VISIT
Presented by:
Surendra purbey(070/BEL/346)
Kamal singh tharu(070/BEL/314)
Sanjit kumar singh(070/BEL/337)
Sadanand kumar yadav(070/BEL/330)
Binay aale (070/BEL/3 )
Mukesh bhatt(070/BEL/3 )
Aashis karki (070/BEL/243 )
INTRODUCTION
TRISHULI NUWAKOT
GENERAL 0VERVIEW
Located at 70 km north-west of Kathmandu at Trishuli, Nuwakot
Constructed on Trishuli river
Installed capacity 21 MW in 1967 AD consisting of 7 units each of 3 MW
Upgraded to 24 MW in 1995 AD with 6 units each of 3.5 MW and
one unit of 3 MW
Developed By Government of India and Government of Nepal at a
Cost of INR 140 million
Head of station Baburaja Maharjan
SAILENT FEATURES
Maximum net head 51.4 m
Average annual flow 45.66 m^3/s
Length of Dam 139.6 m
Length of Waterway 4,792 m
Penstock 71.66 m & 2.3 m , 3Nos., steel
(length &dia.) 89 m & 1.5 m, 1Nos., steel
No. of Bridge 4
Catchment area 2600 sq km
Design generation 163 GWh annually
GENERATOR
Rated Output 3889 KVA
Rated Voltage 6.6 KV
Rated Frequency 50 Hz
Power factor 0.9
Power Transformer 5 MVA , 6.6/66 KV Single phase,6 Nos
Transmission Line 66 KV 27.6 km , Double circuit
66 KV 5 km ,Single circuit
TURBINE
Number and type 7, Francis
Rated Discharge 7.8 m^3/s
Rated Output 3620 kw
Rated Speed 500 rpm
CIVIL PART
WATER RETAINING STRUCTURE WITH SIDE
CHANNEL SPILLWAY
SIDE INTAKE
LIFT GATE WITH GEAR ROPE ELECTRIC DRIVE
TRAPEZOIDAL OPEN CHANNEL SYSTEM
OVERHEAD FLOW OVER RIVER
o Flow is diverse through residential area with two bridge type canal.
SETTLING BASIN (DECENDER)
oIt removes sediment load up to 0.2mm diameter.
oThe greater basin area & lower the through velocity the smaller the particles can settle down.
oOne traits for this case is being used as picnic spot area.
RESERVOIR
o We can notice problem of high silt.
FOREBAY
oEntry point for three penstock pipes
oStructure being lies on highway of headquarter
PENSTOCK PIPES
o Each 3 pipes serves for two units while last pipe feed single unit
MECHANICAL PART
TURBINE GENERATOR SETS
o Number of blades = 13 Inlet diameter = 1080 mm Throat diameter = 1100 mm
RUNNER
WICKET GATE
GOVERNER
SPIRAL CASING
INLET VALVE BY-PASS VALVE
DRAFT TUBE
TAILRACE
Here centered pipe is used to discharge leakage water (dewatering)
Initially tailrace discharge is mixed to trisuli itself
Now it is used for devighat power plant
ELECTRICAL PART
GENERATORS
parameter Unit 1-3 Unit 4-7
Original designer Rade koncar Fuji electric
Rated output 3500kw(+10% overload) 3500kw(+10% overload)
Rated capacity 3889 KVA 3889 KVA
Rated voltage 6.6KV 6.6KV
Stator connection 2Y 1Y
Rated current 340A 340A
Runaway speed 925 r.p.m 925 r.p.m
Stator winding resistance (per
phase)
0.10064 ohm @ 77°C 0.10064 ohm @ 77°C
Rotor winding resistance (per
phase)
0.1272 0.1159
Full load efficiency 96.79% 96.79%
SYNCHRONIZING PROCESS
Manual operation
Unit is connected to grid when its voltage and real power match system parameters
respectively
POWER FREQUENCY CONTROL
The regulator must designed to be insensitive to fast random
changes, otherwise the system will prone to hunting resulting in
excessive wear & tear of rotating machines & control
equipment.
EXCITATION SYSTEM
PLC or Human machine interface(HMI) is used to control excitation automatically and remotely.
STATIC EXCITATION SYSTEM
Field current:
At no = 157-164.7A @ 77V
At full load = 290-304.2A
At 110% rated load = 306-320A
PLC
Programmable Logic Controller is a user friendly, microprocessor specialized computer that
carries out control functions.
oMonitor crucial process parameters and
adjust process operations accordingly.
oCan be programmed, controlled and
operated by a person unskilled in operating
computers.
oPLCs are used in the substation to manage
transformers, voltage regulation, automatic
transfer schemes, custom/automatic reclosing
schemes, automatic service restoration,
remote control, system diagnostics
maintenance
SWITCHING PANELS
o Double for double bus bar system.
INDOOR HV VCB
CONTROL SYSTEM
CONTROL ROOM
oEach unit have its own control set.
oAt least one technical must be here to monitor whether generation and other operation is
within limit.
TRANSFORMER CONTROL & RELAY PANEL
GENERATOR PROTECTION PANEL
DATE U1 U2 U3 U4 U5 U6 U7 TOTAL(
MW)
8/21 3 2.5 3 1 3 3 3 18.5
8/22 3 3 3 1 3 3 3 19
8/23 2 3 3 1 3 3 3 18
8/24 3 2 3 1 3 3 3 18
8/25 3 2 3 1 3 3 3 18
GENERATION DATA OF 8/21 TO 8/25
STATION ANNUNCIATOR PANEL
o It indicates which of several electric circuits has been activated.
RECORDER PANELS
TRANSDUCER PANELS
BATTERY ROOM
oThe control panels and relays require DC supply of 220V.
oNi-Cd batteries are used due to their advantages like low maintenance , longer life
(15-25 years).
oEach cell is of 2V and 6Ah capacity.
o55 cell is connected to 110V charging system.
oNormally charging panel delivers load & give trickle charging to Battery bank
oworks on Auto and Manual mode.
FIRE PROTECTION
o A new fire detection and protection system was installed with complete Halogen gas fire,
portable fire extinguishers and fire hose reels and fire hydrants for total protection of power
house.
SWITCHYARD
oJunction of four areas network
oBalaju-1 and balaju-2 by double circuit transmission line (27.6Km)
oChilime and devighat (5Km) by single circuit
oAlso distribute power to local area
SUBSTATION
SINGLE LINE DIAGRAM
TRANSFORMERS
oSix single phase power transformers of rating 5 MVA 6.6/66 kv
oOne 3 phase distribution transformer of rating 10 MVA 6.6/11 kv for local distribution
COOLING AND FIRE EXTINGUSHER
oCooling pipe are run along all transformers
oOperate when transformer are overloaded or any abnormal conditions
INSTRUMENTATION TRANSFORMERS
66 kv CT 66 kv PT
SF6 CIRCUIT BREAKER
BUS COUPLER
o Coupling is done when one bus bar fails which removes interruption to feeder.
SURGE PROTECTION
LIGHTNING PROTECTOR ROD GAP ARRESTER
CONCLUSION
SPECIAL FEATURES
• One of the oldest HPP but still operating well
• Lies on headquarter of Nuwakot
• More number of units making it more efficient
• 3 single phase transformers combine to make three phase has its
own advantage
• Tailrace utilize for another HPP
PROBLEMS
• Small area of the settling basin so the sand does not settle properly in the basin.
• Problem in diversion system and intake construction.
• There is no SCADA system in use.
• The amount of silt accumulated in the reservoir is excess.
• Weir and tear on the runner due to silt.
• Manual synchronizing and Governing system.
• The settling basin should be upgraded.
• The direction of the flow of water should be managed at diversion weir.
• The SCADA system should be maintained as soon as possible.
• The number of instrument to clean silt should be increased.
• Governing and overall system should be upgraded to digital.
RECOMMENDATIONS
• www.nea.org.np
• www.google.com
• Handbook of
Trishuli hydropower
Project
• Trishuli Upgrading
File
REFERENCES

trisuli hydropower nepal

  • 1.
    TRISHULI HYDROPOWER VISIT Presentedby: Surendra purbey(070/BEL/346) Kamal singh tharu(070/BEL/314) Sanjit kumar singh(070/BEL/337) Sadanand kumar yadav(070/BEL/330) Binay aale (070/BEL/3 ) Mukesh bhatt(070/BEL/3 ) Aashis karki (070/BEL/243 )
  • 2.
  • 3.
  • 4.
    GENERAL 0VERVIEW Located at70 km north-west of Kathmandu at Trishuli, Nuwakot Constructed on Trishuli river Installed capacity 21 MW in 1967 AD consisting of 7 units each of 3 MW Upgraded to 24 MW in 1995 AD with 6 units each of 3.5 MW and one unit of 3 MW Developed By Government of India and Government of Nepal at a Cost of INR 140 million Head of station Baburaja Maharjan
  • 5.
    SAILENT FEATURES Maximum nethead 51.4 m Average annual flow 45.66 m^3/s Length of Dam 139.6 m Length of Waterway 4,792 m Penstock 71.66 m & 2.3 m , 3Nos., steel (length &dia.) 89 m & 1.5 m, 1Nos., steel No. of Bridge 4 Catchment area 2600 sq km Design generation 163 GWh annually
  • 6.
    GENERATOR Rated Output 3889KVA Rated Voltage 6.6 KV Rated Frequency 50 Hz Power factor 0.9 Power Transformer 5 MVA , 6.6/66 KV Single phase,6 Nos Transmission Line 66 KV 27.6 km , Double circuit 66 KV 5 km ,Single circuit TURBINE Number and type 7, Francis Rated Discharge 7.8 m^3/s Rated Output 3620 kw Rated Speed 500 rpm
  • 7.
  • 8.
    WATER RETAINING STRUCTUREWITH SIDE CHANNEL SPILLWAY
  • 9.
  • 10.
    LIFT GATE WITHGEAR ROPE ELECTRIC DRIVE
  • 11.
  • 12.
    OVERHEAD FLOW OVERRIVER o Flow is diverse through residential area with two bridge type canal.
  • 13.
    SETTLING BASIN (DECENDER) oItremoves sediment load up to 0.2mm diameter. oThe greater basin area & lower the through velocity the smaller the particles can settle down. oOne traits for this case is being used as picnic spot area.
  • 14.
    RESERVOIR o We cannotice problem of high silt.
  • 15.
    FOREBAY oEntry point forthree penstock pipes oStructure being lies on highway of headquarter
  • 16.
    PENSTOCK PIPES o Each3 pipes serves for two units while last pipe feed single unit
  • 17.
  • 18.
  • 19.
    o Number ofblades = 13 Inlet diameter = 1080 mm Throat diameter = 1100 mm RUNNER
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
    TAILRACE Here centered pipeis used to discharge leakage water (dewatering) Initially tailrace discharge is mixed to trisuli itself Now it is used for devighat power plant
  • 26.
  • 27.
    GENERATORS parameter Unit 1-3Unit 4-7 Original designer Rade koncar Fuji electric Rated output 3500kw(+10% overload) 3500kw(+10% overload) Rated capacity 3889 KVA 3889 KVA Rated voltage 6.6KV 6.6KV Stator connection 2Y 1Y Rated current 340A 340A Runaway speed 925 r.p.m 925 r.p.m Stator winding resistance (per phase) 0.10064 ohm @ 77°C 0.10064 ohm @ 77°C Rotor winding resistance (per phase) 0.1272 0.1159 Full load efficiency 96.79% 96.79%
  • 28.
    SYNCHRONIZING PROCESS Manual operation Unitis connected to grid when its voltage and real power match system parameters respectively
  • 29.
    POWER FREQUENCY CONTROL Theregulator must designed to be insensitive to fast random changes, otherwise the system will prone to hunting resulting in excessive wear & tear of rotating machines & control equipment.
  • 30.
    EXCITATION SYSTEM PLC orHuman machine interface(HMI) is used to control excitation automatically and remotely.
  • 31.
    STATIC EXCITATION SYSTEM Fieldcurrent: At no = 157-164.7A @ 77V At full load = 290-304.2A At 110% rated load = 306-320A
  • 32.
    PLC Programmable Logic Controlleris a user friendly, microprocessor specialized computer that carries out control functions. oMonitor crucial process parameters and adjust process operations accordingly. oCan be programmed, controlled and operated by a person unskilled in operating computers. oPLCs are used in the substation to manage transformers, voltage regulation, automatic transfer schemes, custom/automatic reclosing schemes, automatic service restoration, remote control, system diagnostics maintenance
  • 33.
    SWITCHING PANELS o Doublefor double bus bar system.
  • 34.
  • 35.
  • 36.
    CONTROL ROOM oEach unithave its own control set. oAt least one technical must be here to monitor whether generation and other operation is within limit.
  • 37.
  • 38.
  • 39.
    DATE U1 U2U3 U4 U5 U6 U7 TOTAL( MW) 8/21 3 2.5 3 1 3 3 3 18.5 8/22 3 3 3 1 3 3 3 19 8/23 2 3 3 1 3 3 3 18 8/24 3 2 3 1 3 3 3 18 8/25 3 2 3 1 3 3 3 18 GENERATION DATA OF 8/21 TO 8/25
  • 40.
    STATION ANNUNCIATOR PANEL oIt indicates which of several electric circuits has been activated.
  • 41.
  • 42.
  • 43.
    BATTERY ROOM oThe controlpanels and relays require DC supply of 220V. oNi-Cd batteries are used due to their advantages like low maintenance , longer life (15-25 years). oEach cell is of 2V and 6Ah capacity. o55 cell is connected to 110V charging system. oNormally charging panel delivers load & give trickle charging to Battery bank oworks on Auto and Manual mode.
  • 44.
    FIRE PROTECTION o Anew fire detection and protection system was installed with complete Halogen gas fire, portable fire extinguishers and fire hose reels and fire hydrants for total protection of power house.
  • 45.
  • 46.
    oJunction of fourareas network oBalaju-1 and balaju-2 by double circuit transmission line (27.6Km) oChilime and devighat (5Km) by single circuit oAlso distribute power to local area SUBSTATION
  • 47.
  • 48.
    TRANSFORMERS oSix single phasepower transformers of rating 5 MVA 6.6/66 kv oOne 3 phase distribution transformer of rating 10 MVA 6.6/11 kv for local distribution
  • 49.
    COOLING AND FIREEXTINGUSHER oCooling pipe are run along all transformers oOperate when transformer are overloaded or any abnormal conditions
  • 50.
  • 51.
  • 52.
    BUS COUPLER o Couplingis done when one bus bar fails which removes interruption to feeder.
  • 53.
  • 54.
  • 55.
    SPECIAL FEATURES • Oneof the oldest HPP but still operating well • Lies on headquarter of Nuwakot • More number of units making it more efficient • 3 single phase transformers combine to make three phase has its own advantage • Tailrace utilize for another HPP
  • 56.
    PROBLEMS • Small areaof the settling basin so the sand does not settle properly in the basin. • Problem in diversion system and intake construction. • There is no SCADA system in use. • The amount of silt accumulated in the reservoir is excess. • Weir and tear on the runner due to silt. • Manual synchronizing and Governing system. • The settling basin should be upgraded. • The direction of the flow of water should be managed at diversion weir. • The SCADA system should be maintained as soon as possible. • The number of instrument to clean silt should be increased. • Governing and overall system should be upgraded to digital. RECOMMENDATIONS
  • 58.
    • www.nea.org.np • www.google.com •Handbook of Trishuli hydropower Project • Trishuli Upgrading File REFERENCES