The document outlines the consultant's work for various airport projects in Greece between 1992-2013. It lists 26 projects where the consultant provided services including environmental impact studies, demand forecasting, fleet mixing, site selection, master planning and design for clients such as the Hellenic Civil Aviation Authority and the Ministry of Transportation. The projects involved airports across Greece such as in Thessaloniki, Lemnos, Skiathos, Ikaria, Samos, Paros, Astypalaia, Kasos, Kastelorizo, Thessaly, Chios, Heraklion, Larissa, Kastelli-Crete, and Andravida.
Millau Viaduct is a cable-stayed bridge that spans the valley of the River Tarn near Millau in southern France.
It is the Tallest bridge in the world.
The Presentation contains the importance of the Project, technology used and few challenges faced during construction in management terms.
Short & Sweet :)
Millau Viaduct is a cable-stayed bridge that spans the valley of the River Tarn near Millau in southern France.
It is the Tallest bridge in the world.
The Presentation contains the importance of the Project, technology used and few challenges faced during construction in management terms.
Short & Sweet :)
1. Date: 1992
Project: Construction of Passengers’ Terminal Expansion at
Thessaloniki’s Airport
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: Andreadis – Zisiadis ATEVE
Subject: Terminal configuration
Position: Consultant
Date: 1993
Project: Environmental Impact Study of Thessaloniki and Lemnos
Airports
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: DENCO
Subject: Forecasting, fleet mix, airport project development assessment
Position: Consultant
Date: 1995
Project: Environmental Impact Study of Skiathos Airport
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: Transeuropean Consulting Group
Subject: Forecasting, fleet mix, airport project development assessment
Position: Consultant
Date: 1995
Project: Environmental Impact Study of Ikaria Airport
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: Transeuropean Consulting Group
Subject: Design of Noise Contours using INM program
2. Position: Consultant
Date: 1995
Project: Environmental Impact Study of Samos Airport
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: SYSM SA
Subject: Forecasting, fleet mix, airport project development assessment
Position: Consultant
Date: 1996
Project: Site Selection for a New Aiport at Paros Island
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: DENCO
Subject: Traffic forecasting, fleet mix. Site selection, Airside
development, Design of obstacle free surfaces. Preliminary
Master Plan
Position: Consultant
Date: 1998
Project: Environmental Impact Study of Astypalaia Airport
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: GEOMATICS
Subject: Forecasting, fleet mix, airport project development assessment
Position: Consultant
3. Date: 1998
Project: Environmental Impact Study of Kasos Airport
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: GEORGE DONTAS
Subject: Forecasting, fleet mix, airport project development assessment,
Design of Noise Contours with INM program, Design of Flight
Paths,
Position: Coordinator, Consultant
Date: 1998
Project: Environmental Impact Study of Kastelorizo Airport
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: SYVILLA Ltd
Subject: Forecasting, fleet mix, airport project development assessment
Position: Consultant
Date: 1999
Project: Demand Forecasting of Thessaly Periphery and Master Plan
Development of the Skiathos, Skyros and N. Anghialos
(Volos) Airports
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: DENCO
Subject: Forecasting, fleet mix, airside sizing and development,
passenger terminal sizing and development, ground access,
Master Plan Development and assessment
Position: Consultant
4. Date: 2001
Project: Environmental Impact Study of Chios Airport
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: JOHN PANAGOPOULOS
Subject: Forecasting, fleet mix, DESIGN OF Noise Contours with INM
program, Design of flight paths, airport project development
assessment
Position: Consultant
Date: 2003
Project: Site Selection of New Heraklion Airport
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: DENCO
Subject: Forecasting, fleet mix, site selection, design of obstacle free
surfaces, sizing of facilities
Position: Consultant
Date: 2003
Project: Demand Forecasting of Thessaly Periphery and Pieria
Perfecture and Master Plan Development of the Larissa
Airport
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: ALVERTOS YIAMIN
Subject: Forecasting, fleet mix, airside sizing and development,
passenger terminal sizing and development, ground access,
Master Plan Development and assessment
Position: Consultant
5. Date: 2009
Project: New Airport at Kastelli - Crete
Client: Hellenic Civil Aviation Authority (HCAA)
Contractor: DENCO
Subject: Forecasting, fleet mix, site selection, design of obstacle free
surfaces, sizing of airside and landside facilities, Master Plan
development
Position: Consultant
Date: 2013
Project: Feasibility study for Andravida Airport
Client: Ministry of Transportation
Contractor: I. Gavriilidis – G. Giannelis
Subject: Forecasting, fleet mix, analysis of competing transportation
modes, catchment’s area analysis and evaluation, airport
competition in the region of Peloponnese, technical analysis of
the proposed design
Position: Consultant