SlideShare a Scribd company logo
1 of 11
Download to read offline
aovalle@epri.com
21, rue d’Artois, F-75008 PARIS CIGRE US National Committee
http://www.cigre.org 2019 Grid of the Future Symposium
A Test Case for GIC Harmonics Analysis
A. OVALLE, R. DUGAN, R. ARRITT
Electric Power Research Institute (EPRI)
USA
SUMMARY
Geomagnetically-Induced Currents (GIC) are very low-frequency currents due to the electromagnetic
field induced in the earth caused by solar Geomagnetic Disturbances (GMD) such as coronal mass
ejections.
For analysis purposes, the frequencies are so low that the currents may be represented as direct currents
(dc) on the bulk power system. The induced currents flow through the transmission system and complete
the circuit through the neutral paths in grounded-wye transformers. This quasi-dc current causes part-
cycle saturation of the magnetic circuit of the transformer, yielding highly-distorted exciting currents
containing both even and odd harmonics. This results in high harmonic currents in transformers,
generators, and capacitor banks in the bulk power system that can damage these power delivery
elements.
The capability to estimate the GIC has been incorporated into common power flow tools used in
transmission system planning. However, this has not been combined with frequency-domain harmonics
analysis tools. The main alternative has been to use electromagnetic transients program with lengthy run
times and complicated model setups that are unfamiliar to many planning engineers.
EPRI has been researching this problem since before 2014 and has developed system analysis tool
requirements needed to conduct GIC related harmonic analysis [1]. This has resulted in the development
of the GICharm tool that takes GIC data from a variety of sources and computes estimates of the
harmonic distortion throughout the power transmission system. The current waveforms from saturated
transformers are computed in the time domain using a Python module and are used to populate the
harmonic flow model of the transmission network. The network is modelled in the frequency domain
using EPRI’s open-source OpenDSS tool. OpenDSS is a general nodal admittance multi-phase circuit
solver that uses methods derived from harmonics solvers. GICharm iterates between the time-domain
and frequency-domain solvers to achieve the final result.
Because GICharm is the first tool of its kind, this paper presents a small benchmark case to provide
other researchers with a reference for other similar tools they might develop.
KEYWORDS
Geomagnetic Disturbances, GMD, Geomagnetically-Induced Currents, GIC, Magnetizing Current
Harmonics, Harmonic System Analysis
2
DESCRIPTION OF GICharm
The overall GIC harmonics approach implemented in the EPRI GICharm program is illustrated in the
flow chart in Figure 1. The software is based on the EPRI OpenDSS program with Python-language
auxiliary programs for time-domain solution and for importing data from other sources. The main
network model is first constructed in the OpenDSS program. The GIC values are either computed using
the OpenDSS model or imported from other computer tools in the industry capable of computing the
GIC values given the GMD electric field values. A basic power flow calculation at fundamental
frequency is then made. This may also be imported from another computer program’s power flow
results. This initializes the process.
Figure 1. GICharm Software Overall Algorithm
Non-Linear Saturation Analysis
After initializing the algorithm with a Load Flow analysis, the next step is to run the Non-linear
Saturation Analysis routine mentioned in Figure 1. This routine is used to obtain the spectra of excitation
currents drawn by transformers exposed to GIC. This routine solves magnetic circuits and finds DC flux
linkages over a power-cycle, to characterize the response of different transformer core topologies, i.e.,
3-leg core, 5-leg core, shell-form and single-phase cores. These core topologies are represented by the
magnetic circuits shown in Figure 2 [3][4]. GICharm defines the flux linkage sources in these models
in discrete time steps by reconstructing time-domain voltages across transformer windings from their
spectra. These spectra are given by the initial power flow (only fundamental frequency at the first
GICharm iteration) or by the harmonics solution (at subsequent GICharm iterations). Numerically
integrating these voltage waveforms over time results in the flux linkages in discrete time steps.
As shown in Figure 2, a core topology is represented by a set of flux linkage sources, linear reluctances,
and non-linear reluctances forming a magnetic circuit. In an ideal scenario with only linear reluctances,
the magnetic circuit could be described by a linear expression in nodal “permeance” form (analog to the
familiar nodal admittance form). However, since the flux paths in a core topology saturate, the nodal
admittance representation of the magnetic circuit needs to be adapted to represent the non-linear
saturation behavior. GICharm models saturable reluctances as piece-wise linear reluctances, and
3
iteratively adapt the nodal “permeance” form expression for each time step and flux linkage source. The
routine iteratively solves for DC-flux linkages and excitation currents, given GIC currents and flux
linkage values over time.
Figure 2. Core-Topologies and Magnetic Circuit Models in GICharm
Figure 3 shows the excitation current characteristic waveforms per phase of transformers with 5-leg and
shell-form core topologies exposed to of 0.02 p.u. GIC. These are obtained with the transformer level
modelling capability of GICharm with only fundamental frequency voltage. The interactions of injected
harmonic currents with impedances in the system may result in voltages with nonzero harmonic content,
which in turn may result in excitation current responses different than that of Figure 3.
(a) (b)
Figure 3. Excitation current waveforms (phases A to C from top to bottom) for transformers exposed to
0.02p.u. GIC. (a) 5-leg core; (b) Shell-form
In the OpenDSS model, the computed excitation current spectra per phase are then attached to a Load
object in each phase connected to a fictitious extra wye-connected winding in the transformer object.
The fundamental frequency active and reactive power properties of these load objects are given by the
fundamental components of the excitation currents and the voltages used to compute the discrete time
flux linkage sources. This is the approach used by GICharm to represent the magnetizing branch of each
transformer in the OpenDSS model. More details on the load model of OpenDSS are described in the
following section of the paper.
The non-linear saturation analysis routine computes the excitation current spectra of all the transformers
across the system.
4
Power Flow and Harmonic Power Flow Analysis
Once the magnetizing branch parameters of each transformer across the system are defined, the next
step is to run a harmonic power flow analysis as shown in Figure 1. The basic equation solved by
OpenDSS is the familiar nodal admittance formulation,
𝐢inj = 𝐘SYS 𝐯, (1)
where 𝐯 is the vector of node voltages, 𝐢inj is the vector of injection currents at each node from non-
linear elements, harmonic sources, etc., and 𝐘SYS is the Nodal admittance matrix representing linear
element admittances.
Figure 4. OpenDSS Circuit Model
Nonlinear elements such as loads, generators, and the transformer magnetizing impedances are modeled
as Norton equivalents as shown in Figure 4. The linear admittances of the Norton equivalents are
included in the 𝐘SYS matrix while the current sources make up the components of the 𝐢inj vector.
All Load-class elements in OpenDSS have a harmonic spectrum associated with them as shown in
Figure 5. As mentioned previously, this Load model is used to represent the transformer magnetizing
currents in the GICharm analysis procedure. In the Harmonic Load-Flow analysis the magnetizing
element of each transformer in the model is represented by an OpenDSS load element with its
fundamental frequency active and reactive power values set to the values determined from the non-linear
saturation analysis step.
Injection (Compensation) Currents from Loads, Generators, etc.
(Power Conversion Elements)
VSOURCE
(Norton Equiv.)
Linear Part of Loads Included in YSYSTEM
YSYSTEM
5
Figure 5. Detail on Load Model for Harmonics Solution [2]
For power flow analysis in OpenDSS, the injection currents typically represent the nonlinear voltage
dependence of the loads and (1) is solved iteratively at fundamental frequency. For harmonics power
flow analysis, the injection currents represent the harmonic currents from the various nodes with
distorted currents. After a fundamental frequency solution, OpenDSS executes a linear, non-iterative
solution at each frequency present in the various harmonic sources in the problem.
After the harmonic load flow analysis in complete, the spectra of voltages across transformer windings
in used again to reconstruct the time domain voltage waveforms and the flux linkage waveforms as well.
This is then used to run the non-linear saturation analysis routine once again. This process is repeated
until a suitable convergence for the harmonic current components is reached.
SIMPLE TEST CASE CIRCUIT
The circuit shown in Figure 6 is a simple 3-bus system proposed for researchers as a reference for similar
tools they might develop. The system is composed of three 500 kV buses, three transmission lines, two
two-winding generator step-up transformers, one three-winding transformer with a delta tertiary, two
generators, one load, and two capacitors.
6
Figure 6. Simple 3-Bus Test Case
As previously described, the magnetizing branch of each transformer is represented by a fictitious extra
grounded-wye winding with a current source attached. The current source is modeled using an OpenDSS
Load element that ultimately is represented as a Norton equivalent current source. The transformer
parameters are listed in Table 1.
The coordinates of the main buses B1, B2, B3 are listed in Table 2, as well as other buses sharing the
same location. The system is randomly located in the northeastern region of the state of Georgia in the
United States. It is important to mention that the location of these buses is fictitious and doesn’t reveal
any critical infrastructure information.
Two capacitor banks are located at Buses B1 and B2 respectively. Their parameters are described in
Table 3.
Table 1 Transformer parameter names and values
Parameters
Transformer Name
TR1 TR2 TR3
Number of windings
(+1 for magnetizing
branch)
2 (+1) 2 (+1) 3 (+1)
Reactance winding 1 to 2 12% 12% 12%
Reactance winding 1 to 3 7% 7% 35%
Reactance winding 1 to 4 - - 9.5%
Reactance winding 2 to 3 7% 7% 30%
7
Reactance winding 2 to 4 - - 4.5%
Reactance winding 3 to 4 - - 27.5%
Resistance winding 1 0.5% 0.5% 0.5%
Resistance winding 2 0.5% 0.5% 0.5%
Resistance winding 3 0.1% 0.1% 0.5%
Resistance winding 4 0.1%
MVA ratings of all
windings
1000 MVA 500 MVA 100 MVA
Winding voltage bases
115 kV
500 kV
24.9 kV
500 kV
20 kV
24.9 kV
500 kV
13.8 kV
115 kV
24.9 kV
Winding connections
Delta
Wye
Wye
Wye
Delta
Wye
Wye
Delta
Wye
Wye
Core 3 single-phase 5-leg 3-leg
Table 2 Bus parameters and values
Parameters
Main Bus Name
B1 B2 B3
Latitude 33.813358° 33.523973° 33.642800°
Longitude -82.797760° -82.797760° -82.319137°
Buses with same coordinates
BSrc1
Isat_TR1
BSrc2
Isat_TR2
BSrc1
Isat_TR1
BTert
BLoad
Table 3 Capacitor parameters and values
Parameters
Capacitor Name
C1 C2
Bus B1 B2
Total reactive power 10 Mvar 10 Mvar
As described previously, three lines connect the main three buses and their parameters are listed in Table
4.
The following section tests the proposed system under different GMD event characteristics. An analysis
of the response of the system is provided as well.
Table 4 Line parameters and values
Parameters
Line Name
TL1 TL2 TL3
Length 19.88 mi 29.92 mi 28.58 mi
Resistance phase 1 0.087405303 Ω/mile
Resistance phase 2 0.088371212 Ω/mile
Resistance phase 3 0.086666667 Ω/mile
Resistance phase 1 to 2 0.029924242 Ω/mile
Resistance phase 1 to 3 0.029071970 Ω/mile
8
Resistance phase 2 to 3 0.029545455 Ω/mile
Reactance phase 1 0.201723485 Ω/mile @60 Hz
Reactance phase 2 0.198522727 Ω/mile @60 Hz
Reactance phase 3 0.204166667 Ω/mile @60 Hz
Reactance phase 1 to 2 0.198522727 Ω/mile @60 Hz
Reactance phase 1 to 3 0.072897727 Ω/mile @60 Hz
Reactance phase 2 to 3 0.095018939 Ω/mile @60 Hz
Nodal Capacitance phase 1 2.711347560 nF/mile
Nodal Capacitance phase 2 3.004631862 nF/mile
Nodal Capacitance phase 3 2.851710072 nF/mile
Nodal Capacitance phase 1 to 2 0.585011253 nF/mile
Nodal Capacitance phase 1 to 3 -0.350755566 nF/mile
Nodal Capacitance phase 2 to 3 -0.920293787 nF/mile
Bus 1 B1 B1 B2
Bus 2 B2 B3 B3
TEST CASE RESULTS
An initial power flow shows voltage magnitudes at buses B1, B3 at 1.044 p.u. and 1.045 p.u. at bus B2.
For this test, let us consider a GMD event with 2 V/km electric field magnitude pointing to the northeast
at 45° inclination (eastward and northward field components equally valued to √2 V/km). Figure 7(a)
shows a geographic view of the circuit with labels showing the location of buses B1, B2, and GIC
currents beside each line. For line TL1, the figure shows the direction of GIC, flowing from bus B1 to
bus B2. Figure 7(b) shows the geographic view of the circuit including the GIC flow direction and value
for each line. As it may be expected the disposition of line TL2 with respect to the direction of the
electric field makes it less susceptible to current induction, as opposed to TL1 and TL3.
(a) (b)
Figure 7 (a) Circuit geographical view; (b) GIC flow directions and values
The GIC flows into each transformer per phase are 22.576 A, -35.5 A and 12.924 A for TR1, TR2 and
TR3 respectively. These values can be verified with the currents flowing through each line into and out
of each bus in Figure 7(b). Figure 8 shows the magnetizing current waveforms per phase of transformer
TR2 (5-leg core) for this scenario after the 1st
and 10th
iterations under the considered GMD event. The
GIC base is assumed to be the peak rated current (1633 A for TR2). Although changes can be noticed,
especially in phase B, a look at the spectrum per phase could be more useful.
9
(b) (e)
Figure 8 Excitation current waveforms per phase (transformer TR2) after the 1st
iteration (left side) and
the 10th
iteration (right side) of the harmonics loop. From top to bottom, waveforms for phases A, B, C.
(a)
(b)
Figure 9 Excitation current spectrum per phase for transformer TR2 after the 1st iteration (a) and the
10th
iteration (b)
Figure 9 shows the spectra corresponding to these waveforms. A close look at these spectra reveals an
accentuation of the 7th
harmonic across the three phases, as well as an increase in the 3rd
and 9th
harmonics on phase B. However, the differences are rather small because the source at bus BSrc1 is
relatively stiff, not allowing high voltage distortions at the 500-kV level.
10
After the 10th
iteration, the reactive power losses per phase for each transformer during this GMD event
are listed in Table 5. Since T3 has a 3-leg core topology, its losses in TR3 are relatively low compared
to those of TR1 and TR2.
Table 5 GIC and reactive power losses per phase during the GMD event of the example
Parameter
Transformer Name
TR1 TR2 TR3
GIC/phase 22.576 A -35.5 A 12.924 A
Reactive power loss – Phase A 9.29 Mvar 11.74 Mvar 0.3 Mvar
Reactive power loss – Phase B 9.32 Mvar 9.67 Mvar 0.3 Mvar
Reactive power loss – Phase C 9.14 Mvar 11.99 Mvar 0.3 Mvar
These reactive power losses impact the voltage profile across the network. The evolution of the voltage
magnitude at the fundamental frequency at bus B2 is shown in Figure 10. For this GMD event,
fundamental voltage magnitudes settle around 1.0385 p.u. for buses B1 and B2, and 1.037 p.u. for bus
B3.
Figure 10 (Left) Evolution of the fundamental voltage magnitude at bus B2. (Right) Absolute magnitude
change between iterations. Iteration 0 corresponds to the initial magnitude before the GMD event.
Figure 11 Spectrum per phase of the voltage at bus B2 after the 10th iteration
The voltage spectrum at bus B2 is shown in Figure 11. The 6th
harmonic has the highest magnitude,
especially in phases B and C. This is mostly due to the unbalanced harmonic injection caused by
saturation characteristic of 5-leg cores. The 9th
harmonic and harmonics below the 6th
are also present
but their magnitudes are smaller than the 6th
. To understand the effect of the harmonics injected to the
system during a GMD event, a frequency scan at a given bus may reveal relevant information. For this
test case, frequency scans at the three main buses reveal a frequency resonance around the 9th
harmonic
order. Figure 12 shows the results of this frequency scan at bus B1. This frequency scan is obtained by
injecting 1.0 A at each frequency between 60 Hz and 600 Hz (10th
harmonic order). The scan also reveals
11
resonances at frequencies around the 6th
harmonic order. The resonance around the 9th
harmonic is the
cause of its presence in the voltage spectrum. However, it is not as high as that of the 6th
and lower
orders because the amount of 9th
harmonic of current injected to the system is comparatively small.
Figure 12 Frequency sweep of 1A current injected at bus B1
Table 6 THD values at transmission level buses
Parameter
Bus Name
B1 B2 B3
Voltage THD - Phase A 2.76% 2.83% 2.81%
Voltage THD – Phase B 8.90% 9.09% 9.03%
Voltage THD – Phase C 10.70% 10.95% 10.85%
A summary of the Voltage THD values is provided in Table 6. The higher THD are observed in phases
B and C, this reflects on the result shown in the voltage spectrum at bus B2.
CONCLUSIONS
The study of harmonic impact of saturated transformers due to GIC is a relatively new field for which
few computer tools exist. This paper provides a relatively simple, yet challenging, test case for students,
researchers, and developers to learn the field and advance it so that practical networks may be studied.
BIBLIOGRAPHY
[1] Analysis of Geomagnetic Disturbance (GMD) Related Harmonics. EPRI, Palo Alto, CA:
2014. 3002002985.
[2] D. Montenegro, R. Dugan, Gustavo Ramos, “Harmonics Analysis using Sequential-Time
Simulation for Addressing Smart Grid Challenges, CIRED 2015, Lyon, Paper 0946.
[3] Electromagnetic transient-type transformer models for Geomagnetically-Induced Current (GIC)
studies. EPRI, Palo Alto, CA: 2013. 3002000832.
[4] R. A. Walling and A. N. Khan, "Characteristics of transformer exciting-current during
geomagnetic disturbances," in IEEE Transactions on Power Delivery, vol. 6, no. 4, pp. 1707-
1714, Oct. 1991. doi: 10.1109/61.97710

More Related Content

What's hot

LOAD FLOW ANALYSIS FOR A 220KV LINE – CASE STUDY
LOAD FLOW ANALYSIS FOR A 220KV LINE – CASE STUDYLOAD FLOW ANALYSIS FOR A 220KV LINE – CASE STUDY
LOAD FLOW ANALYSIS FOR A 220KV LINE – CASE STUDYijiert bestjournal
 
International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)ijceronline
 
Comparison of Three leg and Four Leg VSC DSTATCOM for Power Quality Assessment
Comparison of Three leg and Four Leg VSC DSTATCOM for Power Quality AssessmentComparison of Three leg and Four Leg VSC DSTATCOM for Power Quality Assessment
Comparison of Three leg and Four Leg VSC DSTATCOM for Power Quality AssessmentIOSR Journals
 
Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
Research Inventy : International Journal of Engineering and Science
Research Inventy : International Journal of Engineering and ScienceResearch Inventy : International Journal of Engineering and Science
Research Inventy : International Journal of Engineering and Scienceresearchinventy
 
Load Flow Analysis of Jamshoro Thermal Power Station (JTPS) Pakistan Using MA...
Load Flow Analysis of Jamshoro Thermal Power Station (JTPS) Pakistan Using MA...Load Flow Analysis of Jamshoro Thermal Power Station (JTPS) Pakistan Using MA...
Load Flow Analysis of Jamshoro Thermal Power Station (JTPS) Pakistan Using MA...sunny katyara
 
A review on_load_flow_studies_final_2
A review on_load_flow_studies_final_2A review on_load_flow_studies_final_2
A review on_load_flow_studies_final_2yareda6
 
Term question eee 305
Term question eee 305Term question eee 305
Term question eee 305TamimAhmed43
 
Analysis and Improved Operation of PEBB Based 5-Level Voltage Source Convert...
Analysis and Improved Operation of PEBB Based 5-Level  Voltage Source Convert...Analysis and Improved Operation of PEBB Based 5-Level  Voltage Source Convert...
Analysis and Improved Operation of PEBB Based 5-Level Voltage Source Convert...IJMER
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 

What's hot (20)

LOAD FLOW ANALYSIS FOR A 220KV LINE – CASE STUDY
LOAD FLOW ANALYSIS FOR A 220KV LINE – CASE STUDYLOAD FLOW ANALYSIS FOR A 220KV LINE – CASE STUDY
LOAD FLOW ANALYSIS FOR A 220KV LINE – CASE STUDY
 
International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)
 
Dual_inverter_uni
Dual_inverter_uniDual_inverter_uni
Dual_inverter_uni
 
Comparison of Three leg and Four Leg VSC DSTATCOM for Power Quality Assessment
Comparison of Three leg and Four Leg VSC DSTATCOM for Power Quality AssessmentComparison of Three leg and Four Leg VSC DSTATCOM for Power Quality Assessment
Comparison of Three leg and Four Leg VSC DSTATCOM for Power Quality Assessment
 
F0443847
F0443847F0443847
F0443847
 
Load flow studies
Load flow studiesLoad flow studies
Load flow studies
 
C04721623
C04721623C04721623
C04721623
 
Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)
 
Research Inventy : International Journal of Engineering and Science
Research Inventy : International Journal of Engineering and ScienceResearch Inventy : International Journal of Engineering and Science
Research Inventy : International Journal of Engineering and Science
 
A Repetitive Sparce Matrix Converter with Z-Source Network to having less Cur...
A Repetitive Sparce Matrix Converter with Z-Source Network to having less Cur...A Repetitive Sparce Matrix Converter with Z-Source Network to having less Cur...
A Repetitive Sparce Matrix Converter with Z-Source Network to having less Cur...
 
Load flow studies 19
Load flow studies 19Load flow studies 19
Load flow studies 19
 
Load Flow Analysis of Jamshoro Thermal Power Station (JTPS) Pakistan Using MA...
Load Flow Analysis of Jamshoro Thermal Power Station (JTPS) Pakistan Using MA...Load Flow Analysis of Jamshoro Thermal Power Station (JTPS) Pakistan Using MA...
Load Flow Analysis of Jamshoro Thermal Power Station (JTPS) Pakistan Using MA...
 
EE6501 - Power System Analysis
EE6501 - Power System AnalysisEE6501 - Power System Analysis
EE6501 - Power System Analysis
 
load flow 1
 load flow 1 load flow 1
load flow 1
 
C010311320
C010311320C010311320
C010311320
 
A review on_load_flow_studies_final_2
A review on_load_flow_studies_final_2A review on_load_flow_studies_final_2
A review on_load_flow_studies_final_2
 
Icraie 2014-s mishra2
Icraie 2014-s mishra2Icraie 2014-s mishra2
Icraie 2014-s mishra2
 
Term question eee 305
Term question eee 305Term question eee 305
Term question eee 305
 
Analysis and Improved Operation of PEBB Based 5-Level Voltage Source Convert...
Analysis and Improved Operation of PEBB Based 5-Level  Voltage Source Convert...Analysis and Improved Operation of PEBB Based 5-Level  Voltage Source Convert...
Analysis and Improved Operation of PEBB Based 5-Level Voltage Source Convert...
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 

Similar to GIC Harmonics Analysis Tool Calculates Distortion Throughout Power Grid

Predictive-Control-For-Harmonic-And-Unbalance-Compensation-Using-Active-Power...
Predictive-Control-For-Harmonic-And-Unbalance-Compensation-Using-Active-Power...Predictive-Control-For-Harmonic-And-Unbalance-Compensation-Using-Active-Power...
Predictive-Control-For-Harmonic-And-Unbalance-Compensation-Using-Active-Power...Venkata Gowtam Nallamothu
 
Three phase diode.pdf
Three phase diode.pdfThree phase diode.pdf
Three phase diode.pdfRajatRaj47
 
[7] a generalized parameter tuning method of proportional resonant controller...
[7] a generalized parameter tuning method of proportional resonant controller...[7] a generalized parameter tuning method of proportional resonant controller...
[7] a generalized parameter tuning method of proportional resonant controller...Ngoc Dinh
 
Fuzzy Logic Controlled Harmonic Suppressor in Cascaded Multilevel Inverter
Fuzzy Logic Controlled Harmonic Suppressor in Cascaded Multilevel InverterFuzzy Logic Controlled Harmonic Suppressor in Cascaded Multilevel Inverter
Fuzzy Logic Controlled Harmonic Suppressor in Cascaded Multilevel InverterIJPEDS-IAES
 
[9_CV] FCS-Model Predictive Control of Induction Motors feed by MultilLevel C...
[9_CV] FCS-Model Predictive Control of Induction Motors feed by MultilLevel C...[9_CV] FCS-Model Predictive Control of Induction Motors feed by MultilLevel C...
[9_CV] FCS-Model Predictive Control of Induction Motors feed by MultilLevel C...Nam Thanh
 
Improved dynamic response of dstatcom using genetic algorithm
Improved dynamic response of dstatcom using genetic algorithmImproved dynamic response of dstatcom using genetic algorithm
Improved dynamic response of dstatcom using genetic algorithmAlexander Decker
 
07 15jan17 18 dec16 14154 28633-1-sm l benyettou(edit)
07 15jan17 18 dec16 14154 28633-1-sm l benyettou(edit)07 15jan17 18 dec16 14154 28633-1-sm l benyettou(edit)
07 15jan17 18 dec16 14154 28633-1-sm l benyettou(edit)nooriasukmaningtyas
 
A Simulink Model for Damping Power System Oscillations Using Fact Devices
A Simulink Model for Damping Power System Oscillations Using Fact DevicesA Simulink Model for Damping Power System Oscillations Using Fact Devices
A Simulink Model for Damping Power System Oscillations Using Fact DevicesIOSR Journals
 
The Need for Enhanced Power System Modelling Techniques and Simulation Tools
The Need for Enhanced Power System Modelling Techniques and Simulation ToolsThe Need for Enhanced Power System Modelling Techniques and Simulation Tools
The Need for Enhanced Power System Modelling Techniques and Simulation ToolsPower System Operation
 
Unit -1 Introdcution to PSA.pptx
Unit -1  Introdcution to PSA.pptxUnit -1  Introdcution to PSA.pptx
Unit -1 Introdcution to PSA.pptxSanjeevKumarkumar11
 
High Performance of Matrix Converter Fed Induction Motor for IPF Compensation...
High Performance of Matrix Converter Fed Induction Motor for IPF Compensation...High Performance of Matrix Converter Fed Induction Motor for IPF Compensation...
High Performance of Matrix Converter Fed Induction Motor for IPF Compensation...IOSR Journals
 
Investigation of THD for Cascaded Multi-Level Inverter Using Multicarrier Mod...
Investigation of THD for Cascaded Multi-Level Inverter Using Multicarrier Mod...Investigation of THD for Cascaded Multi-Level Inverter Using Multicarrier Mod...
Investigation of THD for Cascaded Multi-Level Inverter Using Multicarrier Mod...IJERA Editor
 
6.[36 45]seven level modified cascaded inverter for induction motor drive app...
6.[36 45]seven level modified cascaded inverter for induction motor drive app...6.[36 45]seven level modified cascaded inverter for induction motor drive app...
6.[36 45]seven level modified cascaded inverter for induction motor drive app...Alexander Decker
 
Distortion Analysis of Differential Amplifier
Distortion Analysis of Differential AmplifierDistortion Analysis of Differential Amplifier
Distortion Analysis of Differential AmplifierIOSR Journals
 

Similar to GIC Harmonics Analysis Tool Calculates Distortion Throughout Power Grid (20)

Predictive-Control-For-Harmonic-And-Unbalance-Compensation-Using-Active-Power...
Predictive-Control-For-Harmonic-And-Unbalance-Compensation-Using-Active-Power...Predictive-Control-For-Harmonic-And-Unbalance-Compensation-Using-Active-Power...
Predictive-Control-For-Harmonic-And-Unbalance-Compensation-Using-Active-Power...
 
Three phase diode.pdf
Three phase diode.pdfThree phase diode.pdf
Three phase diode.pdf
 
Study of the operation of the output filter of a single-phase series active p...
Study of the operation of the output filter of a single-phase series active p...Study of the operation of the output filter of a single-phase series active p...
Study of the operation of the output filter of a single-phase series active p...
 
[7] a generalized parameter tuning method of proportional resonant controller...
[7] a generalized parameter tuning method of proportional resonant controller...[7] a generalized parameter tuning method of proportional resonant controller...
[7] a generalized parameter tuning method of proportional resonant controller...
 
[IJET V2I2P30] Authors: AnkurGheewala, Jay Chanawala,Nikhil Jadav,Modi Rishit...
[IJET V2I2P30] Authors: AnkurGheewala, Jay Chanawala,Nikhil Jadav,Modi Rishit...[IJET V2I2P30] Authors: AnkurGheewala, Jay Chanawala,Nikhil Jadav,Modi Rishit...
[IJET V2I2P30] Authors: AnkurGheewala, Jay Chanawala,Nikhil Jadav,Modi Rishit...
 
A380114
A380114A380114
A380114
 
A Generalized Parameter Tuning Method of Proportional-Resonant Controllers fo...
A Generalized Parameter Tuning Method of Proportional-Resonant Controllers fo...A Generalized Parameter Tuning Method of Proportional-Resonant Controllers fo...
A Generalized Parameter Tuning Method of Proportional-Resonant Controllers fo...
 
Fuzzy Logic Controlled Harmonic Suppressor in Cascaded Multilevel Inverter
Fuzzy Logic Controlled Harmonic Suppressor in Cascaded Multilevel InverterFuzzy Logic Controlled Harmonic Suppressor in Cascaded Multilevel Inverter
Fuzzy Logic Controlled Harmonic Suppressor in Cascaded Multilevel Inverter
 
[9_CV] FCS-Model Predictive Control of Induction Motors feed by MultilLevel C...
[9_CV] FCS-Model Predictive Control of Induction Motors feed by MultilLevel C...[9_CV] FCS-Model Predictive Control of Induction Motors feed by MultilLevel C...
[9_CV] FCS-Model Predictive Control of Induction Motors feed by MultilLevel C...
 
Improved dynamic response of dstatcom using genetic algorithm
Improved dynamic response of dstatcom using genetic algorithmImproved dynamic response of dstatcom using genetic algorithm
Improved dynamic response of dstatcom using genetic algorithm
 
07 15jan17 18 dec16 14154 28633-1-sm l benyettou(edit)
07 15jan17 18 dec16 14154 28633-1-sm l benyettou(edit)07 15jan17 18 dec16 14154 28633-1-sm l benyettou(edit)
07 15jan17 18 dec16 14154 28633-1-sm l benyettou(edit)
 
A Simulink Model for Damping Power System Oscillations Using Fact Devices
A Simulink Model for Damping Power System Oscillations Using Fact DevicesA Simulink Model for Damping Power System Oscillations Using Fact Devices
A Simulink Model for Damping Power System Oscillations Using Fact Devices
 
The Need for Enhanced Power System Modelling Techniques and Simulation Tools
The Need for Enhanced Power System Modelling Techniques and Simulation ToolsThe Need for Enhanced Power System Modelling Techniques and Simulation Tools
The Need for Enhanced Power System Modelling Techniques and Simulation Tools
 
Unit -1 Introdcution to PSA.pptx
Unit -1  Introdcution to PSA.pptxUnit -1  Introdcution to PSA.pptx
Unit -1 Introdcution to PSA.pptx
 
Ci36507510
Ci36507510Ci36507510
Ci36507510
 
High Performance of Matrix Converter Fed Induction Motor for IPF Compensation...
High Performance of Matrix Converter Fed Induction Motor for IPF Compensation...High Performance of Matrix Converter Fed Induction Motor for IPF Compensation...
High Performance of Matrix Converter Fed Induction Motor for IPF Compensation...
 
Finite-Control-Set Predictive Current Control Based Real and Reactive Power C...
Finite-Control-Set Predictive Current Control Based Real and Reactive Power C...Finite-Control-Set Predictive Current Control Based Real and Reactive Power C...
Finite-Control-Set Predictive Current Control Based Real and Reactive Power C...
 
Investigation of THD for Cascaded Multi-Level Inverter Using Multicarrier Mod...
Investigation of THD for Cascaded Multi-Level Inverter Using Multicarrier Mod...Investigation of THD for Cascaded Multi-Level Inverter Using Multicarrier Mod...
Investigation of THD for Cascaded Multi-Level Inverter Using Multicarrier Mod...
 
6.[36 45]seven level modified cascaded inverter for induction motor drive app...
6.[36 45]seven level modified cascaded inverter for induction motor drive app...6.[36 45]seven level modified cascaded inverter for induction motor drive app...
6.[36 45]seven level modified cascaded inverter for induction motor drive app...
 
Distortion Analysis of Differential Amplifier
Distortion Analysis of Differential AmplifierDistortion Analysis of Differential Amplifier
Distortion Analysis of Differential Amplifier
 

More from Power System Operation

Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panelsPower System Operation
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsPower System Operation
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action SchemePower System Operation
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...Power System Operation
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePower System Operation
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)Power System Operation
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & PartsPower System Operation
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools Power System Operation
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy SystemPower System Operation
 

More from Power System Operation (20)

ENERGY TRANSITION OUTLOOK 2021
ENERGY TRANSITION OUTLOOK  2021ENERGY TRANSITION OUTLOOK  2021
ENERGY TRANSITION OUTLOOK 2021
 
Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panels
 
What does peak shaving mean
What does peak shaving meanWhat does peak shaving mean
What does peak shaving mean
 
What's short circuit level
What's short circuit levelWhat's short circuit level
What's short circuit level
 
Power System Restoration Guide
Power System Restoration Guide  Power System Restoration Guide
Power System Restoration Guide
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid Operations
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action Scheme
 
Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground Resistance
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
 
What is load management
What is load managementWhat is load management
What is load management
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
 
What are Balancing Services ?
What are  Balancing Services ?What are  Balancing Services ?
What are Balancing Services ?
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
 
Power Purchase Agreement PPA
Power Purchase Agreement PPA Power Purchase Agreement PPA
Power Purchase Agreement PPA
 
Harmonic study and analysis
Harmonic study and analysisHarmonic study and analysis
Harmonic study and analysis
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
 

Recently uploaded

Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 

Recently uploaded (20)

Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 

GIC Harmonics Analysis Tool Calculates Distortion Throughout Power Grid

  • 1. aovalle@epri.com 21, rue d’Artois, F-75008 PARIS CIGRE US National Committee http://www.cigre.org 2019 Grid of the Future Symposium A Test Case for GIC Harmonics Analysis A. OVALLE, R. DUGAN, R. ARRITT Electric Power Research Institute (EPRI) USA SUMMARY Geomagnetically-Induced Currents (GIC) are very low-frequency currents due to the electromagnetic field induced in the earth caused by solar Geomagnetic Disturbances (GMD) such as coronal mass ejections. For analysis purposes, the frequencies are so low that the currents may be represented as direct currents (dc) on the bulk power system. The induced currents flow through the transmission system and complete the circuit through the neutral paths in grounded-wye transformers. This quasi-dc current causes part- cycle saturation of the magnetic circuit of the transformer, yielding highly-distorted exciting currents containing both even and odd harmonics. This results in high harmonic currents in transformers, generators, and capacitor banks in the bulk power system that can damage these power delivery elements. The capability to estimate the GIC has been incorporated into common power flow tools used in transmission system planning. However, this has not been combined with frequency-domain harmonics analysis tools. The main alternative has been to use electromagnetic transients program with lengthy run times and complicated model setups that are unfamiliar to many planning engineers. EPRI has been researching this problem since before 2014 and has developed system analysis tool requirements needed to conduct GIC related harmonic analysis [1]. This has resulted in the development of the GICharm tool that takes GIC data from a variety of sources and computes estimates of the harmonic distortion throughout the power transmission system. The current waveforms from saturated transformers are computed in the time domain using a Python module and are used to populate the harmonic flow model of the transmission network. The network is modelled in the frequency domain using EPRI’s open-source OpenDSS tool. OpenDSS is a general nodal admittance multi-phase circuit solver that uses methods derived from harmonics solvers. GICharm iterates between the time-domain and frequency-domain solvers to achieve the final result. Because GICharm is the first tool of its kind, this paper presents a small benchmark case to provide other researchers with a reference for other similar tools they might develop. KEYWORDS Geomagnetic Disturbances, GMD, Geomagnetically-Induced Currents, GIC, Magnetizing Current Harmonics, Harmonic System Analysis
  • 2. 2 DESCRIPTION OF GICharm The overall GIC harmonics approach implemented in the EPRI GICharm program is illustrated in the flow chart in Figure 1. The software is based on the EPRI OpenDSS program with Python-language auxiliary programs for time-domain solution and for importing data from other sources. The main network model is first constructed in the OpenDSS program. The GIC values are either computed using the OpenDSS model or imported from other computer tools in the industry capable of computing the GIC values given the GMD electric field values. A basic power flow calculation at fundamental frequency is then made. This may also be imported from another computer program’s power flow results. This initializes the process. Figure 1. GICharm Software Overall Algorithm Non-Linear Saturation Analysis After initializing the algorithm with a Load Flow analysis, the next step is to run the Non-linear Saturation Analysis routine mentioned in Figure 1. This routine is used to obtain the spectra of excitation currents drawn by transformers exposed to GIC. This routine solves magnetic circuits and finds DC flux linkages over a power-cycle, to characterize the response of different transformer core topologies, i.e., 3-leg core, 5-leg core, shell-form and single-phase cores. These core topologies are represented by the magnetic circuits shown in Figure 2 [3][4]. GICharm defines the flux linkage sources in these models in discrete time steps by reconstructing time-domain voltages across transformer windings from their spectra. These spectra are given by the initial power flow (only fundamental frequency at the first GICharm iteration) or by the harmonics solution (at subsequent GICharm iterations). Numerically integrating these voltage waveforms over time results in the flux linkages in discrete time steps. As shown in Figure 2, a core topology is represented by a set of flux linkage sources, linear reluctances, and non-linear reluctances forming a magnetic circuit. In an ideal scenario with only linear reluctances, the magnetic circuit could be described by a linear expression in nodal “permeance” form (analog to the familiar nodal admittance form). However, since the flux paths in a core topology saturate, the nodal admittance representation of the magnetic circuit needs to be adapted to represent the non-linear saturation behavior. GICharm models saturable reluctances as piece-wise linear reluctances, and
  • 3. 3 iteratively adapt the nodal “permeance” form expression for each time step and flux linkage source. The routine iteratively solves for DC-flux linkages and excitation currents, given GIC currents and flux linkage values over time. Figure 2. Core-Topologies and Magnetic Circuit Models in GICharm Figure 3 shows the excitation current characteristic waveforms per phase of transformers with 5-leg and shell-form core topologies exposed to of 0.02 p.u. GIC. These are obtained with the transformer level modelling capability of GICharm with only fundamental frequency voltage. The interactions of injected harmonic currents with impedances in the system may result in voltages with nonzero harmonic content, which in turn may result in excitation current responses different than that of Figure 3. (a) (b) Figure 3. Excitation current waveforms (phases A to C from top to bottom) for transformers exposed to 0.02p.u. GIC. (a) 5-leg core; (b) Shell-form In the OpenDSS model, the computed excitation current spectra per phase are then attached to a Load object in each phase connected to a fictitious extra wye-connected winding in the transformer object. The fundamental frequency active and reactive power properties of these load objects are given by the fundamental components of the excitation currents and the voltages used to compute the discrete time flux linkage sources. This is the approach used by GICharm to represent the magnetizing branch of each transformer in the OpenDSS model. More details on the load model of OpenDSS are described in the following section of the paper. The non-linear saturation analysis routine computes the excitation current spectra of all the transformers across the system.
  • 4. 4 Power Flow and Harmonic Power Flow Analysis Once the magnetizing branch parameters of each transformer across the system are defined, the next step is to run a harmonic power flow analysis as shown in Figure 1. The basic equation solved by OpenDSS is the familiar nodal admittance formulation, 𝐢inj = 𝐘SYS 𝐯, (1) where 𝐯 is the vector of node voltages, 𝐢inj is the vector of injection currents at each node from non- linear elements, harmonic sources, etc., and 𝐘SYS is the Nodal admittance matrix representing linear element admittances. Figure 4. OpenDSS Circuit Model Nonlinear elements such as loads, generators, and the transformer magnetizing impedances are modeled as Norton equivalents as shown in Figure 4. The linear admittances of the Norton equivalents are included in the 𝐘SYS matrix while the current sources make up the components of the 𝐢inj vector. All Load-class elements in OpenDSS have a harmonic spectrum associated with them as shown in Figure 5. As mentioned previously, this Load model is used to represent the transformer magnetizing currents in the GICharm analysis procedure. In the Harmonic Load-Flow analysis the magnetizing element of each transformer in the model is represented by an OpenDSS load element with its fundamental frequency active and reactive power values set to the values determined from the non-linear saturation analysis step. Injection (Compensation) Currents from Loads, Generators, etc. (Power Conversion Elements) VSOURCE (Norton Equiv.) Linear Part of Loads Included in YSYSTEM YSYSTEM
  • 5. 5 Figure 5. Detail on Load Model for Harmonics Solution [2] For power flow analysis in OpenDSS, the injection currents typically represent the nonlinear voltage dependence of the loads and (1) is solved iteratively at fundamental frequency. For harmonics power flow analysis, the injection currents represent the harmonic currents from the various nodes with distorted currents. After a fundamental frequency solution, OpenDSS executes a linear, non-iterative solution at each frequency present in the various harmonic sources in the problem. After the harmonic load flow analysis in complete, the spectra of voltages across transformer windings in used again to reconstruct the time domain voltage waveforms and the flux linkage waveforms as well. This is then used to run the non-linear saturation analysis routine once again. This process is repeated until a suitable convergence for the harmonic current components is reached. SIMPLE TEST CASE CIRCUIT The circuit shown in Figure 6 is a simple 3-bus system proposed for researchers as a reference for similar tools they might develop. The system is composed of three 500 kV buses, three transmission lines, two two-winding generator step-up transformers, one three-winding transformer with a delta tertiary, two generators, one load, and two capacitors.
  • 6. 6 Figure 6. Simple 3-Bus Test Case As previously described, the magnetizing branch of each transformer is represented by a fictitious extra grounded-wye winding with a current source attached. The current source is modeled using an OpenDSS Load element that ultimately is represented as a Norton equivalent current source. The transformer parameters are listed in Table 1. The coordinates of the main buses B1, B2, B3 are listed in Table 2, as well as other buses sharing the same location. The system is randomly located in the northeastern region of the state of Georgia in the United States. It is important to mention that the location of these buses is fictitious and doesn’t reveal any critical infrastructure information. Two capacitor banks are located at Buses B1 and B2 respectively. Their parameters are described in Table 3. Table 1 Transformer parameter names and values Parameters Transformer Name TR1 TR2 TR3 Number of windings (+1 for magnetizing branch) 2 (+1) 2 (+1) 3 (+1) Reactance winding 1 to 2 12% 12% 12% Reactance winding 1 to 3 7% 7% 35% Reactance winding 1 to 4 - - 9.5% Reactance winding 2 to 3 7% 7% 30%
  • 7. 7 Reactance winding 2 to 4 - - 4.5% Reactance winding 3 to 4 - - 27.5% Resistance winding 1 0.5% 0.5% 0.5% Resistance winding 2 0.5% 0.5% 0.5% Resistance winding 3 0.1% 0.1% 0.5% Resistance winding 4 0.1% MVA ratings of all windings 1000 MVA 500 MVA 100 MVA Winding voltage bases 115 kV 500 kV 24.9 kV 500 kV 20 kV 24.9 kV 500 kV 13.8 kV 115 kV 24.9 kV Winding connections Delta Wye Wye Wye Delta Wye Wye Delta Wye Wye Core 3 single-phase 5-leg 3-leg Table 2 Bus parameters and values Parameters Main Bus Name B1 B2 B3 Latitude 33.813358° 33.523973° 33.642800° Longitude -82.797760° -82.797760° -82.319137° Buses with same coordinates BSrc1 Isat_TR1 BSrc2 Isat_TR2 BSrc1 Isat_TR1 BTert BLoad Table 3 Capacitor parameters and values Parameters Capacitor Name C1 C2 Bus B1 B2 Total reactive power 10 Mvar 10 Mvar As described previously, three lines connect the main three buses and their parameters are listed in Table 4. The following section tests the proposed system under different GMD event characteristics. An analysis of the response of the system is provided as well. Table 4 Line parameters and values Parameters Line Name TL1 TL2 TL3 Length 19.88 mi 29.92 mi 28.58 mi Resistance phase 1 0.087405303 Ω/mile Resistance phase 2 0.088371212 Ω/mile Resistance phase 3 0.086666667 Ω/mile Resistance phase 1 to 2 0.029924242 Ω/mile Resistance phase 1 to 3 0.029071970 Ω/mile
  • 8. 8 Resistance phase 2 to 3 0.029545455 Ω/mile Reactance phase 1 0.201723485 Ω/mile @60 Hz Reactance phase 2 0.198522727 Ω/mile @60 Hz Reactance phase 3 0.204166667 Ω/mile @60 Hz Reactance phase 1 to 2 0.198522727 Ω/mile @60 Hz Reactance phase 1 to 3 0.072897727 Ω/mile @60 Hz Reactance phase 2 to 3 0.095018939 Ω/mile @60 Hz Nodal Capacitance phase 1 2.711347560 nF/mile Nodal Capacitance phase 2 3.004631862 nF/mile Nodal Capacitance phase 3 2.851710072 nF/mile Nodal Capacitance phase 1 to 2 0.585011253 nF/mile Nodal Capacitance phase 1 to 3 -0.350755566 nF/mile Nodal Capacitance phase 2 to 3 -0.920293787 nF/mile Bus 1 B1 B1 B2 Bus 2 B2 B3 B3 TEST CASE RESULTS An initial power flow shows voltage magnitudes at buses B1, B3 at 1.044 p.u. and 1.045 p.u. at bus B2. For this test, let us consider a GMD event with 2 V/km electric field magnitude pointing to the northeast at 45° inclination (eastward and northward field components equally valued to √2 V/km). Figure 7(a) shows a geographic view of the circuit with labels showing the location of buses B1, B2, and GIC currents beside each line. For line TL1, the figure shows the direction of GIC, flowing from bus B1 to bus B2. Figure 7(b) shows the geographic view of the circuit including the GIC flow direction and value for each line. As it may be expected the disposition of line TL2 with respect to the direction of the electric field makes it less susceptible to current induction, as opposed to TL1 and TL3. (a) (b) Figure 7 (a) Circuit geographical view; (b) GIC flow directions and values The GIC flows into each transformer per phase are 22.576 A, -35.5 A and 12.924 A for TR1, TR2 and TR3 respectively. These values can be verified with the currents flowing through each line into and out of each bus in Figure 7(b). Figure 8 shows the magnetizing current waveforms per phase of transformer TR2 (5-leg core) for this scenario after the 1st and 10th iterations under the considered GMD event. The GIC base is assumed to be the peak rated current (1633 A for TR2). Although changes can be noticed, especially in phase B, a look at the spectrum per phase could be more useful.
  • 9. 9 (b) (e) Figure 8 Excitation current waveforms per phase (transformer TR2) after the 1st iteration (left side) and the 10th iteration (right side) of the harmonics loop. From top to bottom, waveforms for phases A, B, C. (a) (b) Figure 9 Excitation current spectrum per phase for transformer TR2 after the 1st iteration (a) and the 10th iteration (b) Figure 9 shows the spectra corresponding to these waveforms. A close look at these spectra reveals an accentuation of the 7th harmonic across the three phases, as well as an increase in the 3rd and 9th harmonics on phase B. However, the differences are rather small because the source at bus BSrc1 is relatively stiff, not allowing high voltage distortions at the 500-kV level.
  • 10. 10 After the 10th iteration, the reactive power losses per phase for each transformer during this GMD event are listed in Table 5. Since T3 has a 3-leg core topology, its losses in TR3 are relatively low compared to those of TR1 and TR2. Table 5 GIC and reactive power losses per phase during the GMD event of the example Parameter Transformer Name TR1 TR2 TR3 GIC/phase 22.576 A -35.5 A 12.924 A Reactive power loss – Phase A 9.29 Mvar 11.74 Mvar 0.3 Mvar Reactive power loss – Phase B 9.32 Mvar 9.67 Mvar 0.3 Mvar Reactive power loss – Phase C 9.14 Mvar 11.99 Mvar 0.3 Mvar These reactive power losses impact the voltage profile across the network. The evolution of the voltage magnitude at the fundamental frequency at bus B2 is shown in Figure 10. For this GMD event, fundamental voltage magnitudes settle around 1.0385 p.u. for buses B1 and B2, and 1.037 p.u. for bus B3. Figure 10 (Left) Evolution of the fundamental voltage magnitude at bus B2. (Right) Absolute magnitude change between iterations. Iteration 0 corresponds to the initial magnitude before the GMD event. Figure 11 Spectrum per phase of the voltage at bus B2 after the 10th iteration The voltage spectrum at bus B2 is shown in Figure 11. The 6th harmonic has the highest magnitude, especially in phases B and C. This is mostly due to the unbalanced harmonic injection caused by saturation characteristic of 5-leg cores. The 9th harmonic and harmonics below the 6th are also present but their magnitudes are smaller than the 6th . To understand the effect of the harmonics injected to the system during a GMD event, a frequency scan at a given bus may reveal relevant information. For this test case, frequency scans at the three main buses reveal a frequency resonance around the 9th harmonic order. Figure 12 shows the results of this frequency scan at bus B1. This frequency scan is obtained by injecting 1.0 A at each frequency between 60 Hz and 600 Hz (10th harmonic order). The scan also reveals
  • 11. 11 resonances at frequencies around the 6th harmonic order. The resonance around the 9th harmonic is the cause of its presence in the voltage spectrum. However, it is not as high as that of the 6th and lower orders because the amount of 9th harmonic of current injected to the system is comparatively small. Figure 12 Frequency sweep of 1A current injected at bus B1 Table 6 THD values at transmission level buses Parameter Bus Name B1 B2 B3 Voltage THD - Phase A 2.76% 2.83% 2.81% Voltage THD – Phase B 8.90% 9.09% 9.03% Voltage THD – Phase C 10.70% 10.95% 10.85% A summary of the Voltage THD values is provided in Table 6. The higher THD are observed in phases B and C, this reflects on the result shown in the voltage spectrum at bus B2. CONCLUSIONS The study of harmonic impact of saturated transformers due to GIC is a relatively new field for which few computer tools exist. This paper provides a relatively simple, yet challenging, test case for students, researchers, and developers to learn the field and advance it so that practical networks may be studied. BIBLIOGRAPHY [1] Analysis of Geomagnetic Disturbance (GMD) Related Harmonics. EPRI, Palo Alto, CA: 2014. 3002002985. [2] D. Montenegro, R. Dugan, Gustavo Ramos, “Harmonics Analysis using Sequential-Time Simulation for Addressing Smart Grid Challenges, CIRED 2015, Lyon, Paper 0946. [3] Electromagnetic transient-type transformer models for Geomagnetically-Induced Current (GIC) studies. EPRI, Palo Alto, CA: 2013. 3002000832. [4] R. A. Walling and A. N. Khan, "Characteristics of transformer exciting-current during geomagnetic disturbances," in IEEE Transactions on Power Delivery, vol. 6, no. 4, pp. 1707- 1714, Oct. 1991. doi: 10.1109/61.97710