SlideShare a Scribd company logo
50 MW METRO WIND POWER PROJECT
Project Detail
 Project Location = Jhimpir Sindh Pakistan
 Client Name = Metro Power Company Limited.
 EPC Contractor = Nordex Pakistan Pvt Ltd.
Descon Engineering Ltd.
50 MW METRO WIND POWER PROJECT
Project Brief Introduction
 Award of Contract = Sep 8, 2011.
 First Amendment to Contract = July 1, 2013.
 Second Amendment to Contract = May 15, 2014.
 PNTC (Preliminary Notice to Commence) = July 8, 2013
 PCD (Project Commencement date) establishment = October 9, 2013
 PNTC-II (Preliminary Notice to Commence-II) = May 16, 2014
 NTC (Notice to Commence) = October 22, 2014
 CD (Commencement Date) establishment = Expected March 20, 2015
 Project Completion Date (TOC) = Expected June 20, 2016(15 Month from
CD)
50 MW METRO WIND POWER PROJECT
Preliminary Works-I (Off Shore & On Shore)
 Micrositting
 Topography Survey for Access Road
 Design of Causeway for Naulla crossing
 Geological Survey for WTG
 Topography Survey for Metro Internal Road
 Design Initiation for E-BOP
 Project Management preparation
50 MW METRO WIND POWER PROJECT
Preliminary Works-I
 Micrositing
50 MW METRO WIND POWER PROJECT
Preliminary Works-I
 Geological Survey
50 MW METRO WIND POWER PROJECT
Preliminary Works-I
 Topographical Survey
50 MW METRO WIND POWER PROJECT
Preliminary Works-II (Off Shore)
 Order Confirmation and Advance payment of E-BOP Equipment
 Order Confirmation and Advance payment of Tower Plates
 Order Confirmation and Advance payment of Anchor cage (10 nos)Tower Plates
 Beside Above, PO has been issued for following and ready for shipment upon
CD
1. Tower Flanges
11. Earthing conductor and accessories for WTG.
111. Tower internals (Weld shocked and oil proof plate farms)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II (On Shore)
 Construction of Causeways and Access Road
 Temporary Site Facility (office and residence)
 Lay down Area and Work shop
 Civil works for Batch plat (60 & 30 Cu meter)
 Batch Plant Installation and Calibration
Apart from above, civil works for Metro Internal roads has almost been
completed
50 MW METRO WIND POWER PROJECT
Project Progress
 Overall Project Progress
Overall Project Progress = 31.93 %
50 MW METRO WIND POWER PROJECT
Project Progress
 Project Management Progress
Overall Project Progress = 0.25 %
Main Highlights
Submission of project procedures (HSE, QA/QC, Progress monitoring, Project
Security, Document management Plans etc)
Geotech Survey
Topography Survey
50 MW METRO WIND POWER PROJECT
Project Progress
 Engineering works
Overall Engineering Works Progress = 62.40 (Discipline wise), 3.43 %
(Overall)
Civil Engineering works = 53.87 %
E & I Engineering works = 8.808 %
50 MW METRO WIND POWER PROJECT
Project Progress
 Procurement works
Overall Procurement Works Progress = 50.8 % (Discipline wise), 23.65 %
(Overalll)
Main Procurement Works Highlights
PO issuance of complete E-BOP Equipment
PO issuance of Tower Plates
PO issuance of Tower Flanges
PO issuance of 10 nos Anchor cages
PO issuance of WTG earthing conductor and accessories
PO issuance of Tower internal (weld socket and oil proof plate farms)
50 MW METRO WIND POWER PROJECT
Project Progress
 Construction works
Overall Construction Works Progress = 8.07 % (Discipline wise), 3.68 %
(Overall)
Main Civil Works Highlights
Completion of Access Road
Completion of Causeways
Internal Road in progress
50 MW METRO WIND POWER PROJECT
Project Progress
 Fabrication works
Overall Fabrication Works Progress = 2.58 % (Discipline wise), 1.17 % (overall)
Main Fabrication Highlights
Marking, Cutting, beveling & Rolling = 10 Bottom , 10 Mid 1 , 3 Mid II Sections
Marking, Cutting, beveling = 13 Mid II Sections
Tacking & Welding completed = 4 Bottom, 6 Mid I Sections
Tacking & Welding in progress = 6 Bottom, 4 Mid I, 3 Mid II Sections
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Construction of Cause Way-I
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Construction of Cause Way-II
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Construction of Cause Way-III
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Access Road
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Access Road
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Access Road
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Temporary Site Facilities
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Temporary Site Facilities
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Temporary Site Facilities
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Temporary Site Facilities
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Temporary Site Facilities
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Temporary Site Facilities
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Batch Plant Installation
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Tower Fabrication
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Tower Fabrication
50 MW METRO WIND POWER PROJECT
Preliminary Works-II
 Tower Fabrication
50 MW METRO WIND POWER PROJECT
THANK YOU

More Related Content

What's hot

السير الذاتية-4
السير الذاتية-4السير الذاتية-4
السير الذاتية-4Nagi Abdalla
 
Ibrahim Nabawy CV 3 .2017
Ibrahim Nabawy CV 3 .2017Ibrahim Nabawy CV 3 .2017
Ibrahim Nabawy CV 3 .2017Ibrahim Nabawy
 
Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017
Crosstown TO
 
2015 MATC Intern Program: Kyle McLaughlin
2015 MATC Intern Program: Kyle McLaughlin2015 MATC Intern Program: Kyle McLaughlin
2015 MATC Intern Program: Kyle McLaughlin
Mid-America Transportation Center
 
Project management plan
Project management planProject management plan
Project management planDonny Olson
 
CV Updated 8-10-16
CV Updated 8-10-16CV Updated 8-10-16
CV Updated 8-10-16SHYAM NIKESH
 

What's hot (9)

السير الذاتية-4
السير الذاتية-4السير الذاتية-4
السير الذاتية-4
 
Ibrahim Nabawy CV 3 .2017
Ibrahim Nabawy CV 3 .2017Ibrahim Nabawy CV 3 .2017
Ibrahim Nabawy CV 3 .2017
 
Moh'd Gaweish_CV
Moh'd Gaweish_CVMoh'd Gaweish_CV
Moh'd Gaweish_CV
 
Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017
 
RS Resume
RS ResumeRS Resume
RS Resume
 
2015 MATC Intern Program: Kyle McLaughlin
2015 MATC Intern Program: Kyle McLaughlin2015 MATC Intern Program: Kyle McLaughlin
2015 MATC Intern Program: Kyle McLaughlin
 
Project management plan
Project management planProject management plan
Project management plan
 
CV Updated 8-10-16
CV Updated 8-10-16CV Updated 8-10-16
CV Updated 8-10-16
 
Peeyush Resume
Peeyush ResumePeeyush Resume
Peeyush Resume
 

Viewers also liked

Wind energy ppp
Wind energy pppWind energy ppp
Wind energy ppp
Fauzia Samreen
 
China Pakistan Economic Corridor (CPEC)
China Pakistan Economic Corridor (CPEC)China Pakistan Economic Corridor (CPEC)
China Pakistan Economic Corridor (CPEC)
shahroze11
 
Tata Power - DDL Company Profile
Tata Power - DDL Company ProfileTata Power - DDL Company Profile
Tata Power - DDL Company Profile
Tata Power Delhi Distribution Limited
 
2009 Wind Technologies Market Report - Powerpoint
2009 Wind Technologies Market Report -  Powerpoint2009 Wind Technologies Market Report -  Powerpoint
2009 Wind Technologies Market Report - PowerpointGlenn Klith Andersen
 
New Green Energy
New Green EnergyNew Green Energy
New Green Energy
yichung hsu
 
WIND FARM PROJECT
WIND FARM PROJECTWIND FARM PROJECT
WIND FARM PROJECTDescon
 
Pakistan wind-power- arif alauddin
Pakistan wind-power- arif alauddinPakistan wind-power- arif alauddin
Pakistan wind-power- arif alauddinIPPAI
 
Gc3 guidance and information for accredited course providers and candida..
Gc3 guidance and information for accredited course providers and candida.. Gc3 guidance and information for accredited course providers and candida..
Gc3 guidance and information for accredited course providers and candida..
kamyjoe214
 
Pakistan Wind Power Indiginisation_Towers
Pakistan Wind Power Indiginisation_TowersPakistan Wind Power Indiginisation_Towers
Pakistan Wind Power Indiginisation_Towersakhtar ali
 
Wind power in pakistan
Wind power in pakistanWind power in pakistan
Wind power in pakistan
Ch. Ghafoor
 
WIND TURBINES
WIND TURBINESWIND TURBINES
WIND TURBINES
shakil2604
 
Wind power in pakistan by tahir
Wind power in pakistan by tahirWind power in pakistan by tahir
Wind power in pakistan by tahir
fauzia samreen
 
Pak China economic corridor
Pak China economic corridorPak China economic corridor
Pak China economic corridor
Talha Saleem
 
Priyank jain - Wind detailed project report _12 mw
Priyank jain - Wind detailed project report _12 mwPriyank jain - Wind detailed project report _12 mw
Priyank jain - Wind detailed project report _12 mw
PRIYANK JAIN
 
Top 7 safety officer interview questions answers
Top 7 safety officer interview questions answersTop 7 safety officer interview questions answers
Top 7 safety officer interview questions answerstomhandsome70
 
China pakistan economic corridor Project
China pakistan economic corridor ProjectChina pakistan economic corridor Project
China pakistan economic corridor Project
anwaar azad
 
Cpec
CpecCpec
Cpec
Sami Khan
 

Viewers also liked (20)

Wind energy ppp
Wind energy pppWind energy ppp
Wind energy ppp
 
China Pakistan Economic Corridor (CPEC)
China Pakistan Economic Corridor (CPEC)China Pakistan Economic Corridor (CPEC)
China Pakistan Economic Corridor (CPEC)
 
Tata Power - DDL Company Profile
Tata Power - DDL Company ProfileTata Power - DDL Company Profile
Tata Power - DDL Company Profile
 
2009 Wind Technologies Market Report - Powerpoint
2009 Wind Technologies Market Report -  Powerpoint2009 Wind Technologies Market Report -  Powerpoint
2009 Wind Technologies Market Report - Powerpoint
 
New Green Energy
New Green EnergyNew Green Energy
New Green Energy
 
My Resume
My Resume My Resume
My Resume
 
WIND FARM PROJECT
WIND FARM PROJECTWIND FARM PROJECT
WIND FARM PROJECT
 
Pakistan wind-power- arif alauddin
Pakistan wind-power- arif alauddinPakistan wind-power- arif alauddin
Pakistan wind-power- arif alauddin
 
Gc3 guidance and information for accredited course providers and candida..
Gc3 guidance and information for accredited course providers and candida.. Gc3 guidance and information for accredited course providers and candida..
Gc3 guidance and information for accredited course providers and candida..
 
Pakistan Wind Power Indiginisation_Towers
Pakistan Wind Power Indiginisation_TowersPakistan Wind Power Indiginisation_Towers
Pakistan Wind Power Indiginisation_Towers
 
Wind sector brief
Wind sector briefWind sector brief
Wind sector brief
 
Wind power in pakistan
Wind power in pakistanWind power in pakistan
Wind power in pakistan
 
WIND TURBINES
WIND TURBINESWIND TURBINES
WIND TURBINES
 
Wind power in pakistan by tahir
Wind power in pakistan by tahirWind power in pakistan by tahir
Wind power in pakistan by tahir
 
Pak China economic corridor
Pak China economic corridorPak China economic corridor
Pak China economic corridor
 
Priyank jain - Wind detailed project report _12 mw
Priyank jain - Wind detailed project report _12 mwPriyank jain - Wind detailed project report _12 mw
Priyank jain - Wind detailed project report _12 mw
 
Top 7 safety officer interview questions answers
Top 7 safety officer interview questions answersTop 7 safety officer interview questions answers
Top 7 safety officer interview questions answers
 
China pakistan economic corridor Project
China pakistan economic corridor ProjectChina pakistan economic corridor Project
China pakistan economic corridor Project
 
Wind energy(Pakistan)
Wind energy(Pakistan)Wind energy(Pakistan)
Wind energy(Pakistan)
 
Cpec
CpecCpec
Cpec
 

Similar to 50 MW METRO WIND POWER PROJECT

V.BASKAR CV
V.BASKAR CVV.BASKAR CV
V.BASKAR CVBaskar v
 
ICI FINAL REPORT
ICI FINAL REPORTICI FINAL REPORT
ICI FINAL REPORT
Clement Seong
 
A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)Ahmed Youssef
 
Fast track projects experiences and overview by Rajesh Prasad
Fast track projects   experiences and overview by Rajesh PrasadFast track projects   experiences and overview by Rajesh Prasad
Fast track projects experiences and overview by Rajesh Prasad
Rajesh Prasad
 
M.s. resume 150316
M.s. resume 150316M.s. resume 150316
M.s. resume 150316
Mohamad Safarudin
 
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
IESGATEWiz
 
MOHMED EZZ 2014CV
MOHMED EZZ 2014CVMOHMED EZZ 2014CV
MOHMED EZZ 2014CVmohamed ezz
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)jamsheer p
 

Similar to 50 MW METRO WIND POWER PROJECT (20)

CV_Hazwan Updated
CV_Hazwan UpdatedCV_Hazwan Updated
CV_Hazwan Updated
 
V.BASKAR CV
V.BASKAR CVV.BASKAR CV
V.BASKAR CV
 
aditi
aditiaditi
aditi
 
Salakidis Savvas
Salakidis SavvasSalakidis Savvas
Salakidis Savvas
 
C.V
C.VC.V
C.V
 
CV_Ing_Civil _LEMKEDDEM_Eng
CV_Ing_Civil _LEMKEDDEM_EngCV_Ing_Civil _LEMKEDDEM_Eng
CV_Ing_Civil _LEMKEDDEM_Eng
 
ICI FINAL REPORT
ICI FINAL REPORTICI FINAL REPORT
ICI FINAL REPORT
 
Mr Jassadaporn CV apply for UAE
Mr Jassadaporn  CV  apply for UAEMr Jassadaporn  CV  apply for UAE
Mr Jassadaporn CV apply for UAE
 
A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)
 
Fast track projects experiences and overview by Rajesh Prasad
Fast track projects   experiences and overview by Rajesh PrasadFast track projects   experiences and overview by Rajesh Prasad
Fast track projects experiences and overview by Rajesh Prasad
 
M.s. resume 150316
M.s. resume 150316M.s. resume 150316
M.s. resume 150316
 
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
 
MOHMED EZZ 2014CV
MOHMED EZZ 2014CVMOHMED EZZ 2014CV
MOHMED EZZ 2014CV
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)
 
Saeed Ahmad Infrastucture Engineer Utilities
Saeed Ahmad Infrastucture Engineer UtilitiesSaeed Ahmad Infrastucture Engineer Utilities
Saeed Ahmad Infrastucture Engineer Utilities
 
Curiculum Vittae april 2016
Curiculum Vittae april 2016Curiculum Vittae april 2016
Curiculum Vittae april 2016
 
C V-OSAMA-Revised 2014(PDF)
C V-OSAMA-Revised 2014(PDF)C V-OSAMA-Revised 2014(PDF)
C V-OSAMA-Revised 2014(PDF)
 
Resume Jamilatul Adawiah Rev.6
Resume Jamilatul Adawiah Rev.6Resume Jamilatul Adawiah Rev.6
Resume Jamilatul Adawiah Rev.6
 
Sajeevresume_June-28-2015
Sajeevresume_June-28-2015Sajeevresume_June-28-2015
Sajeevresume_June-28-2015
 
Vinoth2016 - CV
Vinoth2016 - CVVinoth2016 - CV
Vinoth2016 - CV
 

50 MW METRO WIND POWER PROJECT

  • 1.
  • 2. 50 MW METRO WIND POWER PROJECT Project Detail  Project Location = Jhimpir Sindh Pakistan  Client Name = Metro Power Company Limited.  EPC Contractor = Nordex Pakistan Pvt Ltd. Descon Engineering Ltd.
  • 3. 50 MW METRO WIND POWER PROJECT Project Brief Introduction  Award of Contract = Sep 8, 2011.  First Amendment to Contract = July 1, 2013.  Second Amendment to Contract = May 15, 2014.  PNTC (Preliminary Notice to Commence) = July 8, 2013  PCD (Project Commencement date) establishment = October 9, 2013  PNTC-II (Preliminary Notice to Commence-II) = May 16, 2014  NTC (Notice to Commence) = October 22, 2014  CD (Commencement Date) establishment = Expected March 20, 2015  Project Completion Date (TOC) = Expected June 20, 2016(15 Month from CD)
  • 4. 50 MW METRO WIND POWER PROJECT Preliminary Works-I (Off Shore & On Shore)  Micrositting  Topography Survey for Access Road  Design of Causeway for Naulla crossing  Geological Survey for WTG  Topography Survey for Metro Internal Road  Design Initiation for E-BOP  Project Management preparation
  • 5. 50 MW METRO WIND POWER PROJECT Preliminary Works-I  Micrositing
  • 6. 50 MW METRO WIND POWER PROJECT Preliminary Works-I  Geological Survey
  • 7. 50 MW METRO WIND POWER PROJECT Preliminary Works-I  Topographical Survey
  • 8. 50 MW METRO WIND POWER PROJECT Preliminary Works-II (Off Shore)  Order Confirmation and Advance payment of E-BOP Equipment  Order Confirmation and Advance payment of Tower Plates  Order Confirmation and Advance payment of Anchor cage (10 nos)Tower Plates  Beside Above, PO has been issued for following and ready for shipment upon CD 1. Tower Flanges 11. Earthing conductor and accessories for WTG. 111. Tower internals (Weld shocked and oil proof plate farms)
  • 9. 50 MW METRO WIND POWER PROJECT Preliminary Works-II (On Shore)  Construction of Causeways and Access Road  Temporary Site Facility (office and residence)  Lay down Area and Work shop  Civil works for Batch plat (60 & 30 Cu meter)  Batch Plant Installation and Calibration Apart from above, civil works for Metro Internal roads has almost been completed
  • 10. 50 MW METRO WIND POWER PROJECT Project Progress  Overall Project Progress Overall Project Progress = 31.93 %
  • 11. 50 MW METRO WIND POWER PROJECT Project Progress  Project Management Progress Overall Project Progress = 0.25 % Main Highlights Submission of project procedures (HSE, QA/QC, Progress monitoring, Project Security, Document management Plans etc) Geotech Survey Topography Survey
  • 12. 50 MW METRO WIND POWER PROJECT Project Progress  Engineering works Overall Engineering Works Progress = 62.40 (Discipline wise), 3.43 % (Overall) Civil Engineering works = 53.87 % E & I Engineering works = 8.808 %
  • 13. 50 MW METRO WIND POWER PROJECT Project Progress  Procurement works Overall Procurement Works Progress = 50.8 % (Discipline wise), 23.65 % (Overalll) Main Procurement Works Highlights PO issuance of complete E-BOP Equipment PO issuance of Tower Plates PO issuance of Tower Flanges PO issuance of 10 nos Anchor cages PO issuance of WTG earthing conductor and accessories PO issuance of Tower internal (weld socket and oil proof plate farms)
  • 14. 50 MW METRO WIND POWER PROJECT Project Progress  Construction works Overall Construction Works Progress = 8.07 % (Discipline wise), 3.68 % (Overall) Main Civil Works Highlights Completion of Access Road Completion of Causeways Internal Road in progress
  • 15. 50 MW METRO WIND POWER PROJECT Project Progress  Fabrication works Overall Fabrication Works Progress = 2.58 % (Discipline wise), 1.17 % (overall) Main Fabrication Highlights Marking, Cutting, beveling & Rolling = 10 Bottom , 10 Mid 1 , 3 Mid II Sections Marking, Cutting, beveling = 13 Mid II Sections Tacking & Welding completed = 4 Bottom, 6 Mid I Sections Tacking & Welding in progress = 6 Bottom, 4 Mid I, 3 Mid II Sections
  • 16. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Construction of Cause Way-I
  • 17. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Construction of Cause Way-II
  • 18. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Construction of Cause Way-III
  • 19. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Access Road
  • 20. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Access Road
  • 21. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Access Road
  • 22. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Temporary Site Facilities
  • 23. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Temporary Site Facilities
  • 24. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Temporary Site Facilities
  • 25. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Temporary Site Facilities
  • 26. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Temporary Site Facilities
  • 27. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Temporary Site Facilities
  • 28. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Batch Plant Installation
  • 29. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Tower Fabrication
  • 30. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Tower Fabrication
  • 31. 50 MW METRO WIND POWER PROJECT Preliminary Works-II  Tower Fabrication
  • 32. 50 MW METRO WIND POWER PROJECT THANK YOU