SlideShare a Scribd company logo
Session 3:
Economic assessment of PV
and wind for energy planning
IRENA Global Atlas
Spatial planning techniques
2-day seminar
Central questions we want to answer
1. Once we know how much electricity can be produced in our country with given resources
(technical potential), we will be able to estimate their generation costs
2. As all available data comes with uncertainties, we should know
a. how sensitive results react on changing input parameters, and,
b. what socio-economic effect highly uncertain input data could have.
2
3
©
RENAC
2014
Irradiation on tilted plane (Wh/m²/a)
Energy generation costs at specific site (€/Wh)
Conversion horizontal solar radiation to optimally
tilted plane
Optimal tilt angle
Energy output calculation
Pre-conversion
losses
Conversion losses
System losses (%)
CAPEX
OPEX
WACC
Life time
Economic
parameters (PV
plant and grid
connection)
Annual energy prod. (Wh/km2/a)
PV capacity per area (W/km2)
Areas potentially suitable for PV systems (km2)
Site assessment (solar atlas data, solar radiation
(kWh/m²/a); open-land and settlements (roofs)
Exclusion of non-suitable areas
Nature conservation areas
Exclusion of non-suitable built-up areas
(i.e. non-suitable roofs)
Transport, supply and communication
infrastructure; very remote areas
Areas technically not suitable (high
slope and above certain altitude, etc.)
Landscape, historic area, other non-
usable land (glaciers, rivers, roads etc.)
Areas potentially suitable for PV systems (km2)
Priority areas for PV (km2),
potentially installed capacity (W), potentially
generated energy (Wh/a) and costs
Energy policy
analysis
Economic
assessment
Performance
Ratio
done
done
CAPEX
=
Capital
expenditure,
OPEX
=
Operation
expenditure,
WACC
=
Weighted
average
cost
of
capital
(debt,
equity)
Contents
1. Levelized cost of electricity (LCOE)
2. Worked example: LCOE sensitivity of PV projects
3. Worked example: LCOE sensitivity of wind projects
4. Worked example: Effects of data uncertainty on the LCOE of PV
4
1. LEVELIZED COST OF
ELECTRICITY (LCOE)
5
Levelized Cost of Electricity (LCOE)
• Calculates the average cost per unit electricity. LCOE takes into account the time value
of money (i.e. capital costs).
Where:
• LCOE: Average Cost of Electricity generation in $/unit electricity
• I0: Investment costs in $
• At: Annual total costs in $ in each year t
• Qel: Amount of electricity generated
• i: Discount interest rate in %
• n: useful economic life
• t: year during the useful life (1, 2, …n)
6
2. LCOE SENSITIVITY OF
PV PROJECTS
Worked example:
7
Worked example – Grid-tied PV in Egypt
• Project type: Grid-tied
• Location at latitude: 20° North
• Reference irradiation (GHI): 2,500 kWh/m²/a
• Reference specific yield (P50): 1,880 MWh/MWp
• System size: 10 MWp
• Specific project CAPEX: 2.000.000 USD/MWp
• Project annual OPEX: 1.5% of project CAPEX
• Discount rate (WACC): 8%
• Project duration: 30 years
• Inverter replacements: 2
• Solar panel degradation: 0,7% p.a. (linear)
8
LCOE sensitivity (absolute)
9
Baseline LCOE: 123 USD/MWh
LCOE sensitivity (relative)
10
Baseline LCOE: 123 USD/MWh
3. LCOE SENSITIVITY OF
WIND PROJECTS
Worked example:
11
Worked example – Grid-tied wind project Egypt
(variation A)
• Project type: Grid-tied wind
• Location: Egypt / south-west of Cairo
• Average wind speed @ 80m: 7.3 m/s
• Wind distribution, shape parameter: 3.5
• Wind distr., scale parameter: 8.11
• Technical availability: 97%
• Reference specific yield (P50): 3,202 MWh/MW (techn. Availability considered)
• Capacity factor: 36.6%
• System size: 8 MW (4 turbines)
• Specific project CAPEX: 4.000.000 USD per turbine
• Project annual OPEX: 3.0% of project CAPEX
• Discount rate (WACC): 8%
• Project duration: 20 years
12
LCOE sensitivity (absolute) – Wind speed only
13
Baseline LCOE: 87.6 USD/MWh
LCOE sensitivity (absolute) – other parameters
14
Baseline LCOE: 87.6 USD/MWh
Worked example – variation B:
lower wind speed & lower shape parameter
• Project type: Grid-tied wind
• Location: Egypt / south-west of Cairo
• Average wind speed @ 80m: 7.3 m/s 5.5 m/s
• Wind distribution, shape parameter: 3.5 m/s 1.5 m/s
• Wind distr., scale parameter: 6.11
• Technical availability: 97%
• Reference specific yield (P50): 2,054 MWh/MW (techn. Availability considered)
• Capacity factor: 23.5%
• System size: 8 MWp (4 turbines)
• Specific project CAPEX: 4.000.000 USD per turbine
• Project annual OPEX: 3.0% of project CAPEX
• Discount rate (WACC): 8%
• Project duration: 20 years
15
LCOE sensitivity (absolute) – Wind speed only
16
Baseline LCOE: 136.6 USD/MWh
LCOE sensitivity (absolute) – other parameters
17
Baseline LCOE: 136.6 USD/MWh
Shape parameter more sensitive!!!
Conclusions on sensitivities and for scenario
development
• Variations of the shape parameter of the Weibull distribution of wind can have very
different effects depending on the chosen scenario
 In variation A (high wind, high shape factor), varying of the shape factor only had a
very little effect on the LCOE.
 In variation B (lower wind, lower shape factor), varying of the shape factor had a
considerable effect on the LCOE.
 Reason: the chosen wind turbine for the scenario has a power curve which operates
better under stronger winds. The Weibull function produces a wind distribution
where relative low wind speeds occur comparably often.
 It is crucial for wind scenario developments, to chose appropriate turbines for sites
with different wind speeds and wind speed distributions.
18
Comparison of Weibull curves for
variations A (left ) + B (right)
19
4. EFFECTS OF DATA
UNCERTAINTY ON THE
LCOE OF PV
Worked example:
20
Why data quality is so important
• All data comes with uncertainties:
 Measurements are always subject to deviations, and ,
 models used for predictions can never simulate what happens in reality.
• It is obvious that the lower uncertainty is the more accurate predictions will be. This, in
turn, will enable us to make better estimates.
• In the following, we will demonstrate how good data (i.e. data with low uncertainties) will
potentially help saving funds for PV Power Purchase Agreements.
21
Uncertainty assumptions
• Low resolution NASA SSE data: +/- 13,7%
• Average Meteonorm 7 data: +/- 7,5%
• Best ground measurement at site: +/- 3,0%
• Important note: Besides uncertainty of irradiation data, there is also uncertainty within
the simulation model and nameplate capacity. However, the latter are comparably small
so that we will, to keep the example simple, only look at resource uncertainty. In real-life,
when it comes to detailed project development, one should always ask the project
developer to provide information about his uncertainty assumptions.
22
Worked example – Grid-tied PV in Egypt
• Project type: Grid-tied
• Location at latitude: 20° North
• Reference irradiation: 2500 kWh/m²/a
• Reference specific yield (P50): 1880 MWh/MWp
• System size: 10 MWp
• Specific project CAPEX: 2.000.000 USD/MWp
• Project annual OPEX: 1.5% of project CAPEX
• Discount rate (WACC): 8%
• Project duration: 30 years
• Inverter replacements: 2
• Solar panel degradation: 0,7% p.a. (linear)
23
Exceedance probability (alternative view)
24
P50: 1880 MWh/MWp
P90
LCOE depends on quality of meteo data
25
LCOE is key factor for PPA tariff calculation
• Assuming a 10% premium on the LCOE as margin for IPP
 Best case: 128 USD/MWh +10% = 141 USD/MWh
 Worst case: 149 USD/MWh +10% = 164 USD/MWh
 Delta: 23 USD/MWh (incl. 10% premium)
26
Country sets a 5% PV goal by 2020
• Sample: Egypt
• Total electricity demand 2012: 109 TWh (Source: indexmundi.com)
• 5% of total: 5.45 TWh
• PPA tariff difference: 23 USD/MWh
• „Unnecessary“ payments in 2020: 5,450,000 MWh * 23 USD/MWh =125.4 Mio USD
• PV power needed: 3,014 MWp (with best P90 value)
27
„Unnecessary“ payments due to inaccurate data
• PV power needed by 2020: 3,014 MWp (with best P90 value)
• Aviodable payments: 376 Mio USD
28
29
©
RENAC
2014
Irradiation on tilted plane (Wh/m²/a)
Energy generation costs at specific site (€/Wh)
Conversion horizontal solar radiation to optimally
tilted plane
Optimal tilt angle
Energy output calculation
Pre-conversion
losses
Conversion losses
System losses (%)
CAPEX
OPEX
WACC
Life time
Economic
parameters (PV
plant and grid
connection)
Annual energy prod. (Wh/km2/a)
PV capacity per area (W/km2)
CAPEX
=
Capital
expenditure,
OPEX
=
Operation
expenditure,
WACC
=
Weighted
average
cost
of
capital
(debt,
equity)
Areas potentially suitable for PV systems (km2)
Site assessment (solar atlas data, solar radiation
(kWh/m²/a); open-land and settlements (roofs)
Exclusion of non-suitable areas
Nature conservation areas
Exclusion of non-suitable built-up areas
(i.e. non-suitable roofs)
Transport, supply and communication
infrastructure; very remote areas
Areas technically not suitable (high
slope and above certain altitude, etc.)
Landscape, historic area, other non-
usable land (glaciers, rivers, roads etc.)
Areas potentially suitable for PV systems (km2)
Priority areas for PV (km2),
potentially installed capacity (W), potentially
generated energy (Wh/a) and costs
Energy policy
analysis
Economic
assessment
Performance
Ratio
done
done done
Thank you very much for your
attention!
Volker Jaensch
Renewables Academy (RENAC)
Phone +49 30 52 689 58-85
jaensch@renac.de
www.renac.de

More Related Content

Similar to 16_Economic_assessment_of_PV_and_wind_for_energy_planning_Cairo_Egypt.pdf

19346954 Photovoltaics
19346954  Photovoltaics19346954  Photovoltaics
19346954 PhotovoltaicsNida Amber
 
5.5 off main-grid technologies for power generation in rural contexts
5.5 off main-grid technologies for power generation in rural contexts5.5 off main-grid technologies for power generation in rural contexts
5.5 off main-grid technologies for power generation in rural contextsLeNS_slide
 
DG SYSTEM SELECTION IN URBAN AREA
DG SYSTEM SELECTION IN URBAN AREADG SYSTEM SELECTION IN URBAN AREA
DG SYSTEM SELECTION IN URBAN AREA
Haryo Agung Wibowo
 
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
Ashish Verma
 
Cost development of renewable energy technologies
Cost development of renewable energy technologiesCost development of renewable energy technologies
Cost development of renewable energy technologies
Leonardo ENERGY
 
Session 6 - Presentation by Georgian Industrial Group
Session 6 - Presentation by Georgian Industrial GroupSession 6 - Presentation by Georgian Industrial Group
Session 6 - Presentation by Georgian Industrial Group
OECD Environment
 
March9 2009-workshop-slides
March9 2009-workshop-slidesMarch9 2009-workshop-slides
March9 2009-workshop-slidesSWITCHOntario
 
Wind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity EconomicsWind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity Economics
vijcons
 
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...IPPAI
 
COSTMODEL_IDETC_2010_Jie
COSTMODEL_IDETC_2010_JieCOSTMODEL_IDETC_2010_Jie
COSTMODEL_IDETC_2010_Jie
MDO_Lab
 
Energy Efficiency and Sustainability: Safaricom Perspective
Energy Efficiency and Sustainability: Safaricom PerspectiveEnergy Efficiency and Sustainability: Safaricom Perspective
Energy Efficiency and Sustainability: Safaricom Perspective
ACX
 
performance optimization of Solar pv plant through Micro inverter
performance optimization of Solar pv plant through Micro inverterperformance optimization of Solar pv plant through Micro inverter
performance optimization of Solar pv plant through Micro inverterAshish Verma
 
Utilizing solar+storage to obviate natural gas peaker plants
Utilizing solar+storage to obviate natural gas peaker plants  Utilizing solar+storage to obviate natural gas peaker plants
Utilizing solar+storage to obviate natural gas peaker plants
Clean Coalition
 
Energetic payback time of PV: In Germany and Tunisia
Energetic payback time of PV: In Germany and TunisiaEnergetic payback time of PV: In Germany and Tunisia
Energetic payback time of PV: In Germany and Tunisia
Insulin Angel
 
Ph d thesis_seminar_on the design of energy efficient wireless access_sibelto...
Ph d thesis_seminar_on the design of energy efficient wireless access_sibelto...Ph d thesis_seminar_on the design of energy efficient wireless access_sibelto...
Ph d thesis_seminar_on the design of energy efficient wireless access_sibelto...
Sibel Tombaz
 
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEMISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
Siksha 'O' Anusandhan (Deemed to be University )
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
Roshdy Abdelrassoul
 

Similar to 16_Economic_assessment_of_PV_and_wind_for_energy_planning_Cairo_Egypt.pdf (20)

19346954 Photovoltaics
19346954  Photovoltaics19346954  Photovoltaics
19346954 Photovoltaics
 
5.5 off main-grid technologies for power generation in rural contexts
5.5 off main-grid technologies for power generation in rural contexts5.5 off main-grid technologies for power generation in rural contexts
5.5 off main-grid technologies for power generation in rural contexts
 
DG SYSTEM SELECTION IN URBAN AREA
DG SYSTEM SELECTION IN URBAN AREADG SYSTEM SELECTION IN URBAN AREA
DG SYSTEM SELECTION IN URBAN AREA
 
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
 
Cost development of renewable energy technologies
Cost development of renewable energy technologiesCost development of renewable energy technologies
Cost development of renewable energy technologies
 
Session 6 - Presentation by Georgian Industrial Group
Session 6 - Presentation by Georgian Industrial GroupSession 6 - Presentation by Georgian Industrial Group
Session 6 - Presentation by Georgian Industrial Group
 
March9 2009-workshop-slides
March9 2009-workshop-slidesMarch9 2009-workshop-slides
March9 2009-workshop-slides
 
Wind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity EconomicsWind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity Economics
 
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...
 
COSTMODEL_IDETC_2010_Jie
COSTMODEL_IDETC_2010_JieCOSTMODEL_IDETC_2010_Jie
COSTMODEL_IDETC_2010_Jie
 
Energy Efficiency and Sustainability: Safaricom Perspective
Energy Efficiency and Sustainability: Safaricom PerspectiveEnergy Efficiency and Sustainability: Safaricom Perspective
Energy Efficiency and Sustainability: Safaricom Perspective
 
Major_Proj_Ramya
Major_Proj_RamyaMajor_Proj_Ramya
Major_Proj_Ramya
 
performance optimization of Solar pv plant through Micro inverter
performance optimization of Solar pv plant through Micro inverterperformance optimization of Solar pv plant through Micro inverter
performance optimization of Solar pv plant through Micro inverter
 
SHAMS Dubai
SHAMS DubaiSHAMS Dubai
SHAMS Dubai
 
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
 
Utilizing solar+storage to obviate natural gas peaker plants
Utilizing solar+storage to obviate natural gas peaker plants  Utilizing solar+storage to obviate natural gas peaker plants
Utilizing solar+storage to obviate natural gas peaker plants
 
Energetic payback time of PV: In Germany and Tunisia
Energetic payback time of PV: In Germany and TunisiaEnergetic payback time of PV: In Germany and Tunisia
Energetic payback time of PV: In Germany and Tunisia
 
Ph d thesis_seminar_on the design of energy efficient wireless access_sibelto...
Ph d thesis_seminar_on the design of energy efficient wireless access_sibelto...Ph d thesis_seminar_on the design of energy efficient wireless access_sibelto...
Ph d thesis_seminar_on the design of energy efficient wireless access_sibelto...
 
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEMISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
 

More from Mohamed Salah

Namburete.Apresentacao de Oslo Fevereiro12022007ministroFinal.ppt
Namburete.Apresentacao de Oslo Fevereiro12022007ministroFinal.pptNamburete.Apresentacao de Oslo Fevereiro12022007ministroFinal.ppt
Namburete.Apresentacao de Oslo Fevereiro12022007ministroFinal.ppt
Mohamed Salah
 
economic-development-guide.pdf
economic-development-guide.pdfeconomic-development-guide.pdf
economic-development-guide.pdf
Mohamed Salah
 
Wind_resource_assessment_using_the_WAsP_software_DTU_Wind_Energy_E_0174_.pdf
Wind_resource_assessment_using_the_WAsP_software_DTU_Wind_Energy_E_0174_.pdfWind_resource_assessment_using_the_WAsP_software_DTU_Wind_Energy_E_0174_.pdf
Wind_resource_assessment_using_the_WAsP_software_DTU_Wind_Energy_E_0174_.pdf
Mohamed Salah
 
Wind Energy 101.pdf
Wind Energy 101.pdfWind Energy 101.pdf
Wind Energy 101.pdf
Mohamed Salah
 
Eqm addendum egypt directory_2017_a5-ar (1)
Eqm addendum egypt directory_2017_a5-ar (1)Eqm addendum egypt directory_2017_a5-ar (1)
Eqm addendum egypt directory_2017_a5-ar (1)
Mohamed Salah
 

More from Mohamed Salah (8)

Namburete.Apresentacao de Oslo Fevereiro12022007ministroFinal.ppt
Namburete.Apresentacao de Oslo Fevereiro12022007ministroFinal.pptNamburete.Apresentacao de Oslo Fevereiro12022007ministroFinal.ppt
Namburete.Apresentacao de Oslo Fevereiro12022007ministroFinal.ppt
 
economic-development-guide.pdf
economic-development-guide.pdfeconomic-development-guide.pdf
economic-development-guide.pdf
 
Wind_resource_assessment_using_the_WAsP_software_DTU_Wind_Energy_E_0174_.pdf
Wind_resource_assessment_using_the_WAsP_software_DTU_Wind_Energy_E_0174_.pdfWind_resource_assessment_using_the_WAsP_software_DTU_Wind_Energy_E_0174_.pdf
Wind_resource_assessment_using_the_WAsP_software_DTU_Wind_Energy_E_0174_.pdf
 
Wind Energy 101.pdf
Wind Energy 101.pdfWind Energy 101.pdf
Wind Energy 101.pdf
 
22223.pdf
22223.pdf22223.pdf
22223.pdf
 
40462.pdf
40462.pdf40462.pdf
40462.pdf
 
45834.pdf
45834.pdf45834.pdf
45834.pdf
 
Eqm addendum egypt directory_2017_a5-ar (1)
Eqm addendum egypt directory_2017_a5-ar (1)Eqm addendum egypt directory_2017_a5-ar (1)
Eqm addendum egypt directory_2017_a5-ar (1)
 

Recently uploaded

一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
ambekarshweta25
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 

Recently uploaded (20)

一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 

16_Economic_assessment_of_PV_and_wind_for_energy_planning_Cairo_Egypt.pdf

  • 1. Session 3: Economic assessment of PV and wind for energy planning IRENA Global Atlas Spatial planning techniques 2-day seminar
  • 2. Central questions we want to answer 1. Once we know how much electricity can be produced in our country with given resources (technical potential), we will be able to estimate their generation costs 2. As all available data comes with uncertainties, we should know a. how sensitive results react on changing input parameters, and, b. what socio-economic effect highly uncertain input data could have. 2
  • 3. 3 © RENAC 2014 Irradiation on tilted plane (Wh/m²/a) Energy generation costs at specific site (€/Wh) Conversion horizontal solar radiation to optimally tilted plane Optimal tilt angle Energy output calculation Pre-conversion losses Conversion losses System losses (%) CAPEX OPEX WACC Life time Economic parameters (PV plant and grid connection) Annual energy prod. (Wh/km2/a) PV capacity per area (W/km2) Areas potentially suitable for PV systems (km2) Site assessment (solar atlas data, solar radiation (kWh/m²/a); open-land and settlements (roofs) Exclusion of non-suitable areas Nature conservation areas Exclusion of non-suitable built-up areas (i.e. non-suitable roofs) Transport, supply and communication infrastructure; very remote areas Areas technically not suitable (high slope and above certain altitude, etc.) Landscape, historic area, other non- usable land (glaciers, rivers, roads etc.) Areas potentially suitable for PV systems (km2) Priority areas for PV (km2), potentially installed capacity (W), potentially generated energy (Wh/a) and costs Energy policy analysis Economic assessment Performance Ratio done done CAPEX = Capital expenditure, OPEX = Operation expenditure, WACC = Weighted average cost of capital (debt, equity)
  • 4. Contents 1. Levelized cost of electricity (LCOE) 2. Worked example: LCOE sensitivity of PV projects 3. Worked example: LCOE sensitivity of wind projects 4. Worked example: Effects of data uncertainty on the LCOE of PV 4
  • 5. 1. LEVELIZED COST OF ELECTRICITY (LCOE) 5
  • 6. Levelized Cost of Electricity (LCOE) • Calculates the average cost per unit electricity. LCOE takes into account the time value of money (i.e. capital costs). Where: • LCOE: Average Cost of Electricity generation in $/unit electricity • I0: Investment costs in $ • At: Annual total costs in $ in each year t • Qel: Amount of electricity generated • i: Discount interest rate in % • n: useful economic life • t: year during the useful life (1, 2, …n) 6
  • 7. 2. LCOE SENSITIVITY OF PV PROJECTS Worked example: 7
  • 8. Worked example – Grid-tied PV in Egypt • Project type: Grid-tied • Location at latitude: 20° North • Reference irradiation (GHI): 2,500 kWh/m²/a • Reference specific yield (P50): 1,880 MWh/MWp • System size: 10 MWp • Specific project CAPEX: 2.000.000 USD/MWp • Project annual OPEX: 1.5% of project CAPEX • Discount rate (WACC): 8% • Project duration: 30 years • Inverter replacements: 2 • Solar panel degradation: 0,7% p.a. (linear) 8
  • 11. 3. LCOE SENSITIVITY OF WIND PROJECTS Worked example: 11
  • 12. Worked example – Grid-tied wind project Egypt (variation A) • Project type: Grid-tied wind • Location: Egypt / south-west of Cairo • Average wind speed @ 80m: 7.3 m/s • Wind distribution, shape parameter: 3.5 • Wind distr., scale parameter: 8.11 • Technical availability: 97% • Reference specific yield (P50): 3,202 MWh/MW (techn. Availability considered) • Capacity factor: 36.6% • System size: 8 MW (4 turbines) • Specific project CAPEX: 4.000.000 USD per turbine • Project annual OPEX: 3.0% of project CAPEX • Discount rate (WACC): 8% • Project duration: 20 years 12
  • 13. LCOE sensitivity (absolute) – Wind speed only 13 Baseline LCOE: 87.6 USD/MWh
  • 14. LCOE sensitivity (absolute) – other parameters 14 Baseline LCOE: 87.6 USD/MWh
  • 15. Worked example – variation B: lower wind speed & lower shape parameter • Project type: Grid-tied wind • Location: Egypt / south-west of Cairo • Average wind speed @ 80m: 7.3 m/s 5.5 m/s • Wind distribution, shape parameter: 3.5 m/s 1.5 m/s • Wind distr., scale parameter: 6.11 • Technical availability: 97% • Reference specific yield (P50): 2,054 MWh/MW (techn. Availability considered) • Capacity factor: 23.5% • System size: 8 MWp (4 turbines) • Specific project CAPEX: 4.000.000 USD per turbine • Project annual OPEX: 3.0% of project CAPEX • Discount rate (WACC): 8% • Project duration: 20 years 15
  • 16. LCOE sensitivity (absolute) – Wind speed only 16 Baseline LCOE: 136.6 USD/MWh
  • 17. LCOE sensitivity (absolute) – other parameters 17 Baseline LCOE: 136.6 USD/MWh Shape parameter more sensitive!!!
  • 18. Conclusions on sensitivities and for scenario development • Variations of the shape parameter of the Weibull distribution of wind can have very different effects depending on the chosen scenario  In variation A (high wind, high shape factor), varying of the shape factor only had a very little effect on the LCOE.  In variation B (lower wind, lower shape factor), varying of the shape factor had a considerable effect on the LCOE.  Reason: the chosen wind turbine for the scenario has a power curve which operates better under stronger winds. The Weibull function produces a wind distribution where relative low wind speeds occur comparably often.  It is crucial for wind scenario developments, to chose appropriate turbines for sites with different wind speeds and wind speed distributions. 18
  • 19. Comparison of Weibull curves for variations A (left ) + B (right) 19
  • 20. 4. EFFECTS OF DATA UNCERTAINTY ON THE LCOE OF PV Worked example: 20
  • 21. Why data quality is so important • All data comes with uncertainties:  Measurements are always subject to deviations, and ,  models used for predictions can never simulate what happens in reality. • It is obvious that the lower uncertainty is the more accurate predictions will be. This, in turn, will enable us to make better estimates. • In the following, we will demonstrate how good data (i.e. data with low uncertainties) will potentially help saving funds for PV Power Purchase Agreements. 21
  • 22. Uncertainty assumptions • Low resolution NASA SSE data: +/- 13,7% • Average Meteonorm 7 data: +/- 7,5% • Best ground measurement at site: +/- 3,0% • Important note: Besides uncertainty of irradiation data, there is also uncertainty within the simulation model and nameplate capacity. However, the latter are comparably small so that we will, to keep the example simple, only look at resource uncertainty. In real-life, when it comes to detailed project development, one should always ask the project developer to provide information about his uncertainty assumptions. 22
  • 23. Worked example – Grid-tied PV in Egypt • Project type: Grid-tied • Location at latitude: 20° North • Reference irradiation: 2500 kWh/m²/a • Reference specific yield (P50): 1880 MWh/MWp • System size: 10 MWp • Specific project CAPEX: 2.000.000 USD/MWp • Project annual OPEX: 1.5% of project CAPEX • Discount rate (WACC): 8% • Project duration: 30 years • Inverter replacements: 2 • Solar panel degradation: 0,7% p.a. (linear) 23
  • 24. Exceedance probability (alternative view) 24 P50: 1880 MWh/MWp P90
  • 25. LCOE depends on quality of meteo data 25
  • 26. LCOE is key factor for PPA tariff calculation • Assuming a 10% premium on the LCOE as margin for IPP  Best case: 128 USD/MWh +10% = 141 USD/MWh  Worst case: 149 USD/MWh +10% = 164 USD/MWh  Delta: 23 USD/MWh (incl. 10% premium) 26
  • 27. Country sets a 5% PV goal by 2020 • Sample: Egypt • Total electricity demand 2012: 109 TWh (Source: indexmundi.com) • 5% of total: 5.45 TWh • PPA tariff difference: 23 USD/MWh • „Unnecessary“ payments in 2020: 5,450,000 MWh * 23 USD/MWh =125.4 Mio USD • PV power needed: 3,014 MWp (with best P90 value) 27
  • 28. „Unnecessary“ payments due to inaccurate data • PV power needed by 2020: 3,014 MWp (with best P90 value) • Aviodable payments: 376 Mio USD 28
  • 29. 29 © RENAC 2014 Irradiation on tilted plane (Wh/m²/a) Energy generation costs at specific site (€/Wh) Conversion horizontal solar radiation to optimally tilted plane Optimal tilt angle Energy output calculation Pre-conversion losses Conversion losses System losses (%) CAPEX OPEX WACC Life time Economic parameters (PV plant and grid connection) Annual energy prod. (Wh/km2/a) PV capacity per area (W/km2) CAPEX = Capital expenditure, OPEX = Operation expenditure, WACC = Weighted average cost of capital (debt, equity) Areas potentially suitable for PV systems (km2) Site assessment (solar atlas data, solar radiation (kWh/m²/a); open-land and settlements (roofs) Exclusion of non-suitable areas Nature conservation areas Exclusion of non-suitable built-up areas (i.e. non-suitable roofs) Transport, supply and communication infrastructure; very remote areas Areas technically not suitable (high slope and above certain altitude, etc.) Landscape, historic area, other non- usable land (glaciers, rivers, roads etc.) Areas potentially suitable for PV systems (km2) Priority areas for PV (km2), potentially installed capacity (W), potentially generated energy (Wh/a) and costs Energy policy analysis Economic assessment Performance Ratio done done done
  • 30. Thank you very much for your attention! Volker Jaensch Renewables Academy (RENAC) Phone +49 30 52 689 58-85 jaensch@renac.de www.renac.de