The document provides a cost analysis comparing a concrete truss structural system to the original steel braced frame design for a building project in Greensboro, NC. The concrete truss system was estimated to cost over $5 million for the structure alone, accounting for 33.6% of the original estimated $14 million total cost. In comparison, the estimated cost of the original steel frame structure was just over $1.5 million, accounting for around 11% of the total cost. The concrete system would increase construction time due to the need for extensive formwork and reinforcement before pouring. The steel frame can be erected more quickly using prefabricated members connected by bolting.