1. Back ground
Occidental (Oxy) isdevelopingOnshore Block3inthe southernpart of AbuDhabi emirate.Initial
productionfromthisblockshall be transportedtoADNODASABfacilitiesforfurtherprocessingand
export.OxyisindiscussionwithADNOCin finalizingthese options.
Scope of work
Scope of workfor thisservice orderistoconduct a fieldsurveyof proposedflow lineroute for
developmentof constructiondrawings,constructabilitymethodandenvironmental impactassessment.
Biddershall follow latestADNOCspecifications,proceduresandmethodologieswhile conductingthe
survey.
Attachment1 isa proposedroute of the Flowline fromBlock3 wellstoASABRDS2.
Basedon fieldconditions,bidderisencouragedtopropose alternate routesif they are more
constructionfriendlyand/orlessenvironmental impact.
Actual manifoldslotfortie-inshallbe confirmedatlaterstage.Forthissurvey,flow line shallterminate
at 15 metersbefore the batterylimitof ASABRDS2 stationfrom flow line approachangle.
Biddershall be responsibletoobtainall requiredpermit(fromADNOCoranyothergovernmental
agencies) forthe surveywhichincludesCICPA areaandenvironmentallyprotectedarea.
Biddershall provide all requiredmanpower,vehicles,toolsand anyotherresourcesforthiswork.
Deliverables
1. Approvedforconstruction (AFC) workpackwithall drawingsincluding butnotlimitedto
a. P&IDs(shall be issuedfordesign (IFD) revision)
b. Flow line alignmentsheets
c. On-plot(wellpad) pipingisometrics
d. Road crossing,pipeline/flow linecrossingsdrawings
e. Bill of material
f. Rightof waydrawings
2. Data sheetforlongleaditemslike wellheadcontrol panel, SSVs,chemical injectionskidsandall
otherequipmentrequiredtocomplete the well hook-upandFlowlineuptoaRDS station
3. Pipeline route andalignmentdrawingsshall be referencedtoUTM WGS 84 datum.
a. GPS coordinatesshall be extractedtoanMicrosoftExcel file
Schedule
Work shall commence on or around 19th
Jan 2020
Priorityshall be given inthe followingorder
a. Flowline route andalignmentsheets(includingGPScoordinates) โby31st
Jan 2020
b. Rightof waydrawings โ by 31st
Jan 2020
c. P&IDs(shall be issuedfordesign(IFD) revision) โby10th
Feb2020
2. d. Bill of material &Data sheetsforlongleaditems โby 10th
Feb2020
e. On-plot(wellpad) isometrics โby10th
Feb2020
f. Road crossing,pipeline/flow linecrossingsdrawings โby10th
Feb2020
Final close outshall be by18th
Feb2020