SlideShare a Scribd company logo
1 of 13
BHOPAL DISASTER
Accident can happen in closed plant
Mr.Eduardo Munoz:-Convinced India government SEVIN Importance Jun1966
Mr.Satosh dayal : Broker who do deal of Factory land Jun1967
Mr.kamal parikh :-First Indian Transferred MIC from Haziali to BHOPAL 1973
Mr.Warren Anderson :- CEO of UCL flew to India for MIC production success 4May1980
Mr.Warren Woomer :-First Managing director UCIL May1980– 6Dec1982
Mr.Mohammed Ashraf Khan :-First death of UCIL by phosgene 23Dec1981
Mr.Jagannath Mukund: First Indian Managing Director After Woomar Dec1982
Mr.Rahaman Khan :-Started Cleaning Work 2Dec1983
Mr.A.V. Venugopalan Assign Cleaning Work 2Dec1983
Mr Suman day Superwiser in night shift 3Dec1983
Mr.Shakil Khuresi Superwisers in night 3Dec1983
Mr.V.N singh Workman in night shift Shift 3Dec1983
Mr.Mohanlal Varma workman in night Shift 3Dec1983
Bhopal plant lay out
Background
DDT was banned and all are wanting
replacement
INDIA also want
solution for DDT
replacement
Union Carbide a BIG name with
success and hence a TRUST on them
they know better
Mr. Munoz
convinced INIDIAN
GOV Advantage of
Sevin over DDT
DEAL:- UCL will give 1200T of SEVIN to INDIA and Indian Gov will give permission to build plant of SEVIN in INDIA
How it started ………
• Bhopal a heart of INDIA was selected as Mr . Santosh Dindayal a broker able to convince UCL and PM Indira
Gandhi also able to convince king for lifetime pension .
• It took 10 years to build same .MIC and phosgene, were main RM and both are very dangerous and hence
handled with safety precautions
• MIC initially Imported from USA and first consignment was bring in INDIA 16 drum of 150 lit each on 1976 by Mr.
KAMAL PARIKH .
• He ensured insulation of drums to be done and maintain temp.by continuous 38 hr journey from Haziali to
Bhopal.
• 4 May 1980 MIC was first time produced in INDIA Factory by UCIL.
• Mr. Warren Woomer was appointed as factory head by UCL for INDIA operations and Mr. Kamal Parikh was
another trained person .
• MIC storage tank 3 nos of 50 T each Burried underground and maintained at zero degree .(This is first Reason)
• First fatality occur on 23rd May 1981 due to phosgene, inhale by Mr. Mohammed Ashraf Khan
• Second on 10th FEB 1982 25 people exposed to phosgene, HCL and MIC because of pump seal fail but all were
saved .
Continue……
• Bad weather reduced SEVIN demand , sale drops down and in turn production reduced .Pressure
on cost reduction started (1st Reason)
• Date 6 Dec 1982 Mr. Warren Woomer was asked to come to USA (2nd Reason)
• Mr.Jagannath Mukund was appointed who has little knowledge about SEVIN process (3rd reason )
• Due to cost reduction pressure Mr.Jagannath Mukund stops refrigeration plant which was used to
keep temp of MIC at zero degree (4th Reason)
• Mr.Kamal Parik on 13 dec 1983 left organization by protesting against the shortcut taken against
safety (5th Reason )
• All in plant start believe that “BAND PLANT DO NOT HAVE ACCIDENTS” and hence MIC plant do
not required safety systems .(6th reason)
Safety Communication
TheNitrogenblanket
pressureofMICneed
tobemaintained
Do not
allow
water to
enter in
MIC tank
Theflareflamehasto
beonalltime
The stock
of MIC
should be
as low as
possible
Alwaysusehand
glovesandMask
whileoperatingin
plant
Ensure
scrubber
condition
healthy all
time
Bothphosgene,and
MICareheavythan
airsobecareful
Always
keep MIC
temp zero
degree .
Condition on 2nd DEC 1984
Refrigeration system (keep MIC at temperatures of 0-5 degrees C (32 to 42
degrees F) where it is less reactive
Refrigeration
shut down June
1984 and
coolant (Freon)
drained for use
elsewhere in
plant
The nitrogen
blanket to TANK E
610 not present as
the pressure
shown by gauge
zero
vent gas scrubber (uses caustic soda to neutralize toxic gas exhaust
from MIC plant and storage tanks before release thru vent
stack or flare)
on standby since MIC not
in active production but
could be activated by
plant operators in event
of need
firewater spray pipes (to
control escaping gasses,
cool over-heated
Equipment or CAUSE
fires)
flare (burns toxic gasses to neutralize
them)
Insufficient capacity to burn large volumes of escaping gas; shut
down in November for replacement of a corroded pipe; MIC
process vents rerouted to the vent gas scrubber while repairs
proceed
LOCALTION OF MIC STORAGE TANKS
How tragedy happen
• A 19 year old Raheman Khan was assigned work of cleaning pipe line of SEVIN reactor.
• This is very critical job and he is not fully aware about process so Mr. A.V Venugopalan given him
SOP in written format. He miss very important isolation principle of pipe line i.e use of
“slipblinding “process
• The water started at around 9 :15 PM and kept On for cleaning
• But due to sedimentation in pipe lines one pipe got chocked at outlet and hence water was not
coming out from same this was communicated to Venugopalan by phone and he was advised to
keep water continue
• The water flown in all system pipe line and ran to the MIC tanks through improperly closed valves.
• The three tanks E610,E611,E612 all had MIC in them of 42T,20T and 1 T respectively.
• As E610 tank the Nitrogen blanket was not fully effective the water was allowed to flow in tank
and exothermic Run way Reaction of contaminant water and MIC started .
• The night shift operator observed gas leakage in pipes but overlooked as they all believe “Non
Production Plant do not have Accident “
Continue….
• The gas leakage increased and First time Workman feel that some thing is going wrong
• Mr Suman day,Mr.Shakil Khuresi were superwisers and Mr.V.N singh,Mr.Mohanlal Varma were
inside factory
• At 12:30 Dial gauge of reactor suddenly exceed its reading from 3 PSIG to 55 PSIG which was last
possible reading on dial gauge .
• When Mr.Suman approach to tank he found heavy sound of liquid from tank and Vibration to the
tank concrete causing cracks to concretes
• Such high pressure lead to opening of safety valve of E610 MIC tank and entire gas went to
scrubber tank which also not working
• The operator tried to switch it on but since it was under maintenance it fail to start.
• Then gas went to flare chamber 100 ft above ground and vented to atmosphere to kill innocent
people in town .The flame is also not working so no chance of Toxic gas burned inflame
• As per UCC this PIPE WASHING THEORY is not TRUE. But water was inserted through a pressure
gauge which was situated on tank no E 610 and is act of sabotage .
Learning of Bhopal disaster ……..
• Accident do happen in closed plant
• Leakages is first sign of abnormality and need immediate attention
• Safety system should not be kept under maintenance .IN this case, Refrigeration system ,Scrubber
system, Flare flame system ,The nitrogen blanket system, was under maintenance
• The untrained workforce should not be given critical work and should be identified by
management.
• The SOP must be displayed as communication may miss vital information i.e use of SLIP BLID to
isolate pipe line
• The temp and pressure are vital in case of chemical plant and should be maintained as per
requirement and we should not deviate .
• The community must be aware about the HAZARDS and how to cope with situation .In this case
no one knows what is MIC as all know SEVIN is UCIL product and doctor unable to help.
• No by pass for communication system for out side community.In Bhopal case they by passed out
side communication system and use for internal plant communication.
• The safety system should be tested and designed for worst possible situation. In Bhopal fire
hydrant water unable to reach 100 ft height to flame tower and hence last defense was failed
• In plant Safety system must be provided with stand by arrangement so when maintenance was
taken plant operations is still covered with defined safety and risk is low .
Thank you ……..

More Related Content

What's hot

Piper alpha disaster 1988
Piper alpha disaster 1988Piper alpha disaster 1988
Piper alpha disaster 1988Shahbaz Sardar
 
British petroleum & gulf oil spill of 2010
British petroleum & gulf oil spill of 2010British petroleum & gulf oil spill of 2010
British petroleum & gulf oil spill of 2010Aditi Podder
 
Bhopal Gas Tragedy- The Night of Death
Bhopal Gas Tragedy- The Night of DeathBhopal Gas Tragedy- The Night of Death
Bhopal Gas Tragedy- The Night of DeathParidhi Khandelwal
 
Bhopal gas tragedy and Seveso Disaster
Bhopal gas tragedy and Seveso DisasterBhopal gas tragedy and Seveso Disaster
Bhopal gas tragedy and Seveso DisasterAnkush Kularkar
 
Bhopal gas tragedy, 1984
Bhopal gas tragedy, 1984Bhopal gas tragedy, 1984
Bhopal gas tragedy, 1984sameersailesh
 
Bhopal Gas Tragedy
Bhopal Gas TragedyBhopal Gas Tragedy
Bhopal Gas TragedyANJALI DUBEY
 
Bhopal gas tragedy ! :)
Bhopal gas tragedy ! :) Bhopal gas tragedy ! :)
Bhopal gas tragedy ! :) ASHMITA NAHAR
 
Deepwater Horizon oil spill case
Deepwater Horizon oil spill caseDeepwater Horizon oil spill case
Deepwater Horizon oil spill caseCaterpillar Inc.
 
Bhopal gas tragedy
Bhopal gas tragedyBhopal gas tragedy
Bhopal gas tragedyRohit Shinde
 
Assignment piper alpha
Assignment piper alphaAssignment piper alpha
Assignment piper alphaJohnin Taimin
 
Flixborough disaster
Flixborough disasterFlixborough disaster
Flixborough disasterSameer Phadke
 
Pm bhopal gas disaster
Pm bhopal gas disasterPm bhopal gas disaster
Pm bhopal gas disastervision2d16
 
Bhopal gas tragedy presentation
Bhopal gas tragedy presentationBhopal gas tragedy presentation
Bhopal gas tragedy presentationbhavin dhandhukiya
 

What's hot (20)

Bhopal gas tragedy
Bhopal gas tragedyBhopal gas tragedy
Bhopal gas tragedy
 
Piper alpha disaster 1988
Piper alpha disaster 1988Piper alpha disaster 1988
Piper alpha disaster 1988
 
British petroleum & gulf oil spill of 2010
British petroleum & gulf oil spill of 2010British petroleum & gulf oil spill of 2010
British petroleum & gulf oil spill of 2010
 
Bhopal Gas Tragedy- The Night of Death
Bhopal Gas Tragedy- The Night of DeathBhopal Gas Tragedy- The Night of Death
Bhopal Gas Tragedy- The Night of Death
 
Bhopal gas tragedy and Seveso Disaster
Bhopal gas tragedy and Seveso DisasterBhopal gas tragedy and Seveso Disaster
Bhopal gas tragedy and Seveso Disaster
 
Bhopal gas tragedy, 1984
Bhopal gas tragedy, 1984Bhopal gas tragedy, 1984
Bhopal gas tragedy, 1984
 
Bhopal Gas Tragedy
Bhopal Gas TragedyBhopal Gas Tragedy
Bhopal Gas Tragedy
 
case study Bhopal gas tragedy
case study Bhopal gas tragedycase study Bhopal gas tragedy
case study Bhopal gas tragedy
 
Bhopal gas tragedy ! :)
Bhopal gas tragedy ! :) Bhopal gas tragedy ! :)
Bhopal gas tragedy ! :)
 
Deepwater Horizon oil spill case
Deepwater Horizon oil spill caseDeepwater Horizon oil spill case
Deepwater Horizon oil spill case
 
Bhopal gas tragedy
Bhopal gas tragedyBhopal gas tragedy
Bhopal gas tragedy
 
Case study on
Case study onCase study on
Case study on
 
Assignment piper alpha
Assignment piper alphaAssignment piper alpha
Assignment piper alpha
 
Flixborough disaster
Flixborough disasterFlixborough disaster
Flixborough disaster
 
Pm bhopal gas disaster
Pm bhopal gas disasterPm bhopal gas disaster
Pm bhopal gas disaster
 
Flixborough Disaster slide
Flixborough Disaster slideFlixborough Disaster slide
Flixborough Disaster slide
 
Bhopal disaster
Bhopal disasterBhopal disaster
Bhopal disaster
 
Piper alpha disaster 1988
Piper alpha disaster 1988Piper alpha disaster 1988
Piper alpha disaster 1988
 
Bhopal gas tragedy presentation
Bhopal gas tragedy presentationBhopal gas tragedy presentation
Bhopal gas tragedy presentation
 
Bhopal gas tragedy
Bhopal gas tragedyBhopal gas tragedy
Bhopal gas tragedy
 

Similar to The lessons of bhopal tragedy

Bhopal gas Tragedy.pptx
Bhopal gas Tragedy.pptxBhopal gas Tragedy.pptx
Bhopal gas Tragedy.pptxARTINADEKA
 
Assignment 3 Title Bhopal Disaster PRESENTED BY
Assignment 3 Title   Bhopal Disaster PRESENTED BYAssignment 3 Title   Bhopal Disaster PRESENTED BY
Assignment 3 Title Bhopal Disaster PRESENTED BYAngie Miller
 
Bhopal gas tragedy
Bhopal gas tragedyBhopal gas tragedy
Bhopal gas tragedySONAL GARG
 
Bhopal gas tragedy - best presentation ever
Bhopal gas tragedy - best presentation everBhopal gas tragedy - best presentation ever
Bhopal gas tragedy - best presentation everYousuf S A
 
PROCESS INSTRUMENTATION NOTES ARE THERE IN
PROCESS INSTRUMENTATION NOTES ARE THERE INPROCESS INSTRUMENTATION NOTES ARE THERE IN
PROCESS INSTRUMENTATION NOTES ARE THERE INvijetakumari201ch059
 
Bhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDES
Bhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDES
Bhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDESARUNPRAKASHS7
 
Bhopal slides
Bhopal slidesBhopal slides
Bhopal slidesRahulAren
 
Industrial disasters
Industrial disasters Industrial disasters
Industrial disasters ravali52
 
Case study: Fire in IOC terminal Jaipur & IOC terminal Hazira
Case study: Fire in IOC terminal Jaipur & IOC terminal HaziraCase study: Fire in IOC terminal Jaipur & IOC terminal Hazira
Case study: Fire in IOC terminal Jaipur & IOC terminal HaziraAbhishant Baishya
 
Flixborough disaster
Flixborough disasterFlixborough disaster
Flixborough disasterSameer Phadke
 
Engineers responsibility for safety
Engineers responsibility for safetyEngineers responsibility for safety
Engineers responsibility for safetyBhupender Sharma
 
ALTA2016_MondoMineralsNickelSulfideBioleachProject_JohnNealeArtoLaukka_V2 (2)
ALTA2016_MondoMineralsNickelSulfideBioleachProject_JohnNealeArtoLaukka_V2 (2)ALTA2016_MondoMineralsNickelSulfideBioleachProject_JohnNealeArtoLaukka_V2 (2)
ALTA2016_MondoMineralsNickelSulfideBioleachProject_JohnNealeArtoLaukka_V2 (2)Stephen CC Barnett
 
internship report final.DOC
internship report final.DOCinternship report final.DOC
internship report final.DOCqazi faisal
 
Safety aspects on construction site in noida area Anshul
Safety aspects on construction site in noida area AnshulSafety aspects on construction site in noida area Anshul
Safety aspects on construction site in noida area AnshulAnshul Shakya
 

Similar to The lessons of bhopal tragedy (20)

Bhopal gas Tragedy.pptx
Bhopal gas Tragedy.pptxBhopal gas Tragedy.pptx
Bhopal gas Tragedy.pptx
 
Assignment 3 Title Bhopal Disaster PRESENTED BY
Assignment 3 Title   Bhopal Disaster PRESENTED BYAssignment 3 Title   Bhopal Disaster PRESENTED BY
Assignment 3 Title Bhopal Disaster PRESENTED BY
 
Bhopal gas tragedy
Bhopal gas tragedyBhopal gas tragedy
Bhopal gas tragedy
 
Bhopal gas tragedy - best presentation ever
Bhopal gas tragedy - best presentation everBhopal gas tragedy - best presentation ever
Bhopal gas tragedy - best presentation ever
 
PROCESS INSTRUMENTATION NOTES ARE THERE IN
PROCESS INSTRUMENTATION NOTES ARE THERE INPROCESS INSTRUMENTATION NOTES ARE THERE IN
PROCESS INSTRUMENTATION NOTES ARE THERE IN
 
Bhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDES
Bhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDES
Bhopal_SLIDESBhopal_SLIDESBhopal_SLIDESBhopal_SLIDES
 
Bhopal slides
Bhopal slidesBhopal slides
Bhopal slides
 
Industrial disasters
Industrial disasters Industrial disasters
Industrial disasters
 
Case study: Fire in IOC terminal Jaipur & IOC terminal Hazira
Case study: Fire in IOC terminal Jaipur & IOC terminal HaziraCase study: Fire in IOC terminal Jaipur & IOC terminal Hazira
Case study: Fire in IOC terminal Jaipur & IOC terminal Hazira
 
Flixborough disaster
Flixborough disasterFlixborough disaster
Flixborough disaster
 
JK LAKSHMI CEMENT (SIROHI)
JK LAKSHMI CEMENT (SIROHI)JK LAKSHMI CEMENT (SIROHI)
JK LAKSHMI CEMENT (SIROHI)
 
Jaipur Fire
Jaipur FireJaipur Fire
Jaipur Fire
 
ppt for ucp.pptx
ppt for ucp.pptxppt for ucp.pptx
ppt for ucp.pptx
 
Explosion carling 2009 synthese english
Explosion carling 2009 synthese englishExplosion carling 2009 synthese english
Explosion carling 2009 synthese english
 
Engineers responsibility for safety
Engineers responsibility for safetyEngineers responsibility for safety
Engineers responsibility for safety
 
ALTA2016_MondoMineralsNickelSulfideBioleachProject_JohnNealeArtoLaukka_V2 (2)
ALTA2016_MondoMineralsNickelSulfideBioleachProject_JohnNealeArtoLaukka_V2 (2)ALTA2016_MondoMineralsNickelSulfideBioleachProject_JohnNealeArtoLaukka_V2 (2)
ALTA2016_MondoMineralsNickelSulfideBioleachProject_JohnNealeArtoLaukka_V2 (2)
 
internship report final.DOC
internship report final.DOCinternship report final.DOC
internship report final.DOC
 
Mine enargia
Mine enargiaMine enargia
Mine enargia
 
Safety aspects on construction site in noida area Anshul
Safety aspects on construction site in noida area AnshulSafety aspects on construction site in noida area Anshul
Safety aspects on construction site in noida area Anshul
 
Boiler explosion at exxon mobil singapore
Boiler explosion at exxon mobil singaporeBoiler explosion at exxon mobil singapore
Boiler explosion at exxon mobil singapore
 

Recently uploaded

LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 

Recently uploaded (13)

Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 

The lessons of bhopal tragedy

  • 1. BHOPAL DISASTER Accident can happen in closed plant Mr.Eduardo Munoz:-Convinced India government SEVIN Importance Jun1966 Mr.Satosh dayal : Broker who do deal of Factory land Jun1967 Mr.kamal parikh :-First Indian Transferred MIC from Haziali to BHOPAL 1973 Mr.Warren Anderson :- CEO of UCL flew to India for MIC production success 4May1980 Mr.Warren Woomer :-First Managing director UCIL May1980– 6Dec1982 Mr.Mohammed Ashraf Khan :-First death of UCIL by phosgene 23Dec1981 Mr.Jagannath Mukund: First Indian Managing Director After Woomar Dec1982 Mr.Rahaman Khan :-Started Cleaning Work 2Dec1983 Mr.A.V. Venugopalan Assign Cleaning Work 2Dec1983 Mr Suman day Superwiser in night shift 3Dec1983 Mr.Shakil Khuresi Superwisers in night 3Dec1983 Mr.V.N singh Workman in night shift Shift 3Dec1983 Mr.Mohanlal Varma workman in night Shift 3Dec1983
  • 3. Background DDT was banned and all are wanting replacement INDIA also want solution for DDT replacement Union Carbide a BIG name with success and hence a TRUST on them they know better Mr. Munoz convinced INIDIAN GOV Advantage of Sevin over DDT DEAL:- UCL will give 1200T of SEVIN to INDIA and Indian Gov will give permission to build plant of SEVIN in INDIA
  • 4. How it started ……… • Bhopal a heart of INDIA was selected as Mr . Santosh Dindayal a broker able to convince UCL and PM Indira Gandhi also able to convince king for lifetime pension . • It took 10 years to build same .MIC and phosgene, were main RM and both are very dangerous and hence handled with safety precautions • MIC initially Imported from USA and first consignment was bring in INDIA 16 drum of 150 lit each on 1976 by Mr. KAMAL PARIKH . • He ensured insulation of drums to be done and maintain temp.by continuous 38 hr journey from Haziali to Bhopal. • 4 May 1980 MIC was first time produced in INDIA Factory by UCIL. • Mr. Warren Woomer was appointed as factory head by UCL for INDIA operations and Mr. Kamal Parikh was another trained person . • MIC storage tank 3 nos of 50 T each Burried underground and maintained at zero degree .(This is first Reason) • First fatality occur on 23rd May 1981 due to phosgene, inhale by Mr. Mohammed Ashraf Khan • Second on 10th FEB 1982 25 people exposed to phosgene, HCL and MIC because of pump seal fail but all were saved .
  • 5. Continue…… • Bad weather reduced SEVIN demand , sale drops down and in turn production reduced .Pressure on cost reduction started (1st Reason) • Date 6 Dec 1982 Mr. Warren Woomer was asked to come to USA (2nd Reason) • Mr.Jagannath Mukund was appointed who has little knowledge about SEVIN process (3rd reason ) • Due to cost reduction pressure Mr.Jagannath Mukund stops refrigeration plant which was used to keep temp of MIC at zero degree (4th Reason) • Mr.Kamal Parik on 13 dec 1983 left organization by protesting against the shortcut taken against safety (5th Reason ) • All in plant start believe that “BAND PLANT DO NOT HAVE ACCIDENTS” and hence MIC plant do not required safety systems .(6th reason)
  • 6. Safety Communication TheNitrogenblanket pressureofMICneed tobemaintained Do not allow water to enter in MIC tank Theflareflamehasto beonalltime The stock of MIC should be as low as possible Alwaysusehand glovesandMask whileoperatingin plant Ensure scrubber condition healthy all time Bothphosgene,and MICareheavythan airsobecareful Always keep MIC temp zero degree .
  • 7. Condition on 2nd DEC 1984 Refrigeration system (keep MIC at temperatures of 0-5 degrees C (32 to 42 degrees F) where it is less reactive Refrigeration shut down June 1984 and coolant (Freon) drained for use elsewhere in plant The nitrogen blanket to TANK E 610 not present as the pressure shown by gauge zero vent gas scrubber (uses caustic soda to neutralize toxic gas exhaust from MIC plant and storage tanks before release thru vent stack or flare) on standby since MIC not in active production but could be activated by plant operators in event of need firewater spray pipes (to control escaping gasses, cool over-heated Equipment or CAUSE fires) flare (burns toxic gasses to neutralize them) Insufficient capacity to burn large volumes of escaping gas; shut down in November for replacement of a corroded pipe; MIC process vents rerouted to the vent gas scrubber while repairs proceed
  • 8. LOCALTION OF MIC STORAGE TANKS
  • 9.
  • 10.
  • 11. How tragedy happen • A 19 year old Raheman Khan was assigned work of cleaning pipe line of SEVIN reactor. • This is very critical job and he is not fully aware about process so Mr. A.V Venugopalan given him SOP in written format. He miss very important isolation principle of pipe line i.e use of “slipblinding “process • The water started at around 9 :15 PM and kept On for cleaning • But due to sedimentation in pipe lines one pipe got chocked at outlet and hence water was not coming out from same this was communicated to Venugopalan by phone and he was advised to keep water continue • The water flown in all system pipe line and ran to the MIC tanks through improperly closed valves. • The three tanks E610,E611,E612 all had MIC in them of 42T,20T and 1 T respectively. • As E610 tank the Nitrogen blanket was not fully effective the water was allowed to flow in tank and exothermic Run way Reaction of contaminant water and MIC started . • The night shift operator observed gas leakage in pipes but overlooked as they all believe “Non Production Plant do not have Accident “
  • 12. Continue…. • The gas leakage increased and First time Workman feel that some thing is going wrong • Mr Suman day,Mr.Shakil Khuresi were superwisers and Mr.V.N singh,Mr.Mohanlal Varma were inside factory • At 12:30 Dial gauge of reactor suddenly exceed its reading from 3 PSIG to 55 PSIG which was last possible reading on dial gauge . • When Mr.Suman approach to tank he found heavy sound of liquid from tank and Vibration to the tank concrete causing cracks to concretes • Such high pressure lead to opening of safety valve of E610 MIC tank and entire gas went to scrubber tank which also not working • The operator tried to switch it on but since it was under maintenance it fail to start. • Then gas went to flare chamber 100 ft above ground and vented to atmosphere to kill innocent people in town .The flame is also not working so no chance of Toxic gas burned inflame • As per UCC this PIPE WASHING THEORY is not TRUE. But water was inserted through a pressure gauge which was situated on tank no E 610 and is act of sabotage .
  • 13. Learning of Bhopal disaster …….. • Accident do happen in closed plant • Leakages is first sign of abnormality and need immediate attention • Safety system should not be kept under maintenance .IN this case, Refrigeration system ,Scrubber system, Flare flame system ,The nitrogen blanket system, was under maintenance • The untrained workforce should not be given critical work and should be identified by management. • The SOP must be displayed as communication may miss vital information i.e use of SLIP BLID to isolate pipe line • The temp and pressure are vital in case of chemical plant and should be maintained as per requirement and we should not deviate . • The community must be aware about the HAZARDS and how to cope with situation .In this case no one knows what is MIC as all know SEVIN is UCIL product and doctor unable to help. • No by pass for communication system for out side community.In Bhopal case they by passed out side communication system and use for internal plant communication. • The safety system should be tested and designed for worst possible situation. In Bhopal fire hydrant water unable to reach 100 ft height to flame tower and hence last defense was failed • In plant Safety system must be provided with stand by arrangement so when maintenance was taken plant operations is still covered with defined safety and risk is low . Thank you ……..