SlideShare a Scribd company logo
1 of 1
DoD TRIPWIRE METRICS   Favorable is > 1.0, Unfavorable is < 1.0 Cost Efficiency  CPI  =  BCWP  /  ACWP Schedule Efficiency  SPI  =  BCWP  /  BCWS VARIANCES   Favorable is Positive, Unfavorable is Negative Cost Variance     CV =  BCWP  –  ACWP CV % = (CV /  BCWP )  * 100  Schedule Variance   SV =  BCWP  –  BCWS SV % = (SV /  BCWS )  *  100 Variance at Completion VAC =  BAC  –  EAC OVERALL STATUS % Schedule  =  ( BCWS CUM   /  BAC)  *  100 % Complete =  ( BCWP CUM   /  BAC)  *  100 % Spent =  ( ACWP CUM   /  BAC)  *  100 CPLI  =  (Critical Path Duration + Float Duration  (to baseline finish) ) / Critical Path Duration CRITICAL PATH LENGTH INDEX (CPLI) (Schedule Metric)   TO COMPLETE PERFORMANCE INDEX (TCPI)  # § TCPI EAC  =  Work Remaining / Cost Remaining = (BAC –  BCWP CUM )   / (EAC –  ACWP CUM ) ESTIMATE AT COMPLETION   # EAC =  Actuals to Date +  [(Remaining Work) / (Efficiency Factor)] EAC CPI =  ACWP CUM   +  [(BAC –  BCWP CUM ) / CPI CUM  ]   =   BAC / CPI CUM   EAC Composite =  ACWP CUM   +  [(BAC –  BCWP CUM ) / (CPI CUM   *  SPI CUM )] #   To Determine a Contract Level TCPI or EAC; You May Replace BAC with TAB §  To Determine the TCPI  BAC or LRE  Replace EAC with either BAC or LRE Earned Value Management ‘ Gold Card’ EVM Home Page =  https://acc.dau.mil/evm   eMail Address:  [email_address] DAU POC: (703) 805-5259 (DSN 655) Revised April 2008 TERMINOLOGY NCC Negotiated Contract Cost Contract price less profit / fee(s) AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitized CBB Contract Budget Base Sum of NCC and AUW OTB Over Target Baseline Sum of CBB and recognized overrun   TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB   BAC Budget At Completion Total budget for total contract thru any given level PMB Performance Measurement Baseline Contract time-phased budget plan MR Management Reserve Budget withheld by Ktr PM for unknowns / risk management UB Undistributed Budget Broadly defined activities not yet distributed to CAs  CA Control Account Lowest CWBS element assigned to a single focal   point to plan & control scope / schedule / budget WP Work Package Near-term, detail-planned activities within a CA   PP Planning Package Far-term CA activities not yet defined into WPs BCWS Budgeted Cost for Work Scheduled Value of work planned to be accomplished = PLANNED VALUE BCWP Budgeted Cost for Work Performed Value of work accomplished  = EARNED VALUE ACWP Actual Cost of Work Performed Cost of work accomplished  = ACTUAL COST EAC Estimate At Completion Estimate of total cost for total contract thru any given level; may be generated by Ktr, PMO, DCMA, etc. =  EAC Ktr / PMO / DCMA LRE Latest Revised Estimate Ktr’s EAC or EAC Ktr SLPP Summary Level Planning Package Far-term activities not yet defined into CAs   TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve an EAC EVM POLICY: DoDI 5000.2, Table E3.T2 .   EVMS in accordance with ANSI/EIA-748 is required for cost or incentive contracts, subcontracts, intra-government work agreements, & other agreements valued  >   $20M  ( T hen- Yr   $ ). EVMS contracts  >   $50M  ( TY $ ) require that the EVM system be formally validated by the cognizant contracting officer. Additional Guidance in  Defense Acquisition Guidebook and the Earned Value Management Implementation Guide (EVMIG).  EVMS is discouraged on  F irm- F ixed  P rice,  L evel  o f  E ffort, &  T ime  &   M aterial efforts regardless of cost.  EVM CONTRACTING REQUIREMENTS: Non-DoD   FAR Clauses – Solicitation – 52.234-2 (Pre-Award IBR) or 52.234-3 (Post Award IBR)    –   Solicitation & Contract – 52.234-4 DoD(  ≥ $20M) DFAR Clauses - 252.234-7001 for solicitations and 252.234-7002 for solicitations & contracts Contract Performance Report – DI-MGMT-81466A *  5 Formats (WBS, Organization, Baseline, Staffing & Explanation)  Integrated Master Schedule  – DI-MGMT-81650 *  (Mandatory for DoD EVMS contracts) Integrated Baseline Review (IBR)  -  Mandatory for all  EVMS contracts  * See the EVMIG for CPR and IMS tailoring guidance. Management Reserve Work Packages  Planning Packages  OVERRUN  AUW  Control  Accounts  NCC  Undistributed Budget OTB  CBB  TAB Profit / Fees  PMB  Summary Level  Planning Packages  Contract Price   BASELINE EXECUTION INDEX (BEI) (Schedule Metric) BEI  =  # of  Baseline Tasks Actually Completed /  # of Baseline Tasks Scheduled for Completion Management Reserve Cost Variance Schedule Variance ACWP BCWP BCWS $ EAC Time Now Completion  Date PMB TAB BAC time

More Related Content

What's hot

10 Safe Essential Elements to Achieve the Benefits of SAFe
10 Safe Essential Elements to Achieve the Benefits of SAFe10 Safe Essential Elements to Achieve the Benefits of SAFe
10 Safe Essential Elements to Achieve the Benefits of SAFeCprime
 
Managing Your Startup Board
Managing Your Startup BoardManaging Your Startup Board
Managing Your Startup BoardMark Suster
 
Lean planning with Oracle Primavera Cloud
Lean planning  with Oracle Primavera CloudLean planning  with Oracle Primavera Cloud
Lean planning with Oracle Primavera CloudPRMYAZILIM
 
PDCA - Learning Along the Way
PDCA - Learning Along the WayPDCA - Learning Along the Way
PDCA - Learning Along the WayMike Rother
 
Agile Program Management Best Practices
Agile Program Management Best PracticesAgile Program Management Best Practices
Agile Program Management Best PracticesPete Behrens
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisp6academy
 
Project Prioritizing Model Powerpoint Presentation Slides
Project Prioritizing Model Powerpoint Presentation SlidesProject Prioritizing Model Powerpoint Presentation Slides
Project Prioritizing Model Powerpoint Presentation SlidesSlideTeam
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14p6academy
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 

What's hot (20)

10 Safe Essential Elements to Achieve the Benefits of SAFe
10 Safe Essential Elements to Achieve the Benefits of SAFe10 Safe Essential Elements to Achieve the Benefits of SAFe
10 Safe Essential Elements to Achieve the Benefits of SAFe
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
S curves
S curvesS curves
S curves
 
Delay - EOT claims
Delay - EOT claimsDelay - EOT claims
Delay - EOT claims
 
Managing Your Startup Board
Managing Your Startup BoardManaging Your Startup Board
Managing Your Startup Board
 
Understand SAFe in 8 Pictures
Understand SAFe in 8 PicturesUnderstand SAFe in 8 Pictures
Understand SAFe in 8 Pictures
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
Lean planning with Oracle Primavera Cloud
Lean planning  with Oracle Primavera CloudLean planning  with Oracle Primavera Cloud
Lean planning with Oracle Primavera Cloud
 
PDCA - Learning Along the Way
PDCA - Learning Along the WayPDCA - Learning Along the Way
PDCA - Learning Along the Way
 
Agile Program Management Best Practices
Agile Program Management Best PracticesAgile Program Management Best Practices
Agile Program Management Best Practices
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysis
 
CCP Course - Introduction.pdf
CCP Course - Introduction.pdfCCP Course - Introduction.pdf
CCP Course - Introduction.pdf
 
Project Prioritizing Model Powerpoint Presentation Slides
Project Prioritizing Model Powerpoint Presentation SlidesProject Prioritizing Model Powerpoint Presentation Slides
Project Prioritizing Model Powerpoint Presentation Slides
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Patreon Success Diaries
Patreon Success DiariesPatreon Success Diaries
Patreon Success Diaries
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 

Viewers also liked

Evms Presentation (July2006)Repro
Evms Presentation (July2006)ReproEvms Presentation (July2006)Repro
Evms Presentation (July2006)ReproJim Kendrick
 
Great deals on life insurance for seniors over 65
Great deals on life insurance for seniors over 65Great deals on life insurance for seniors over 65
Great deals on life insurance for seniors over 65LifeNet Insurance Solutions
 
Resilency
 Resilency  Resilency
Resilency price56
 
Teradata Demand Chain Management (DCM): Version 4
Teradata Demand Chain Management (DCM): Version 4Teradata Demand Chain Management (DCM): Version 4
Teradata Demand Chain Management (DCM): Version 4Teradata
 

Viewers also liked (6)

Evms Presentation (July2006)Repro
Evms Presentation (July2006)ReproEvms Presentation (July2006)Repro
Evms Presentation (July2006)Repro
 
Great deals on life insurance for seniors over 65
Great deals on life insurance for seniors over 65Great deals on life insurance for seniors over 65
Great deals on life insurance for seniors over 65
 
TDGI New presentation 2016 English Version
TDGI New presentation 2016 English VersionTDGI New presentation 2016 English Version
TDGI New presentation 2016 English Version
 
Lapsed policy
Lapsed policyLapsed policy
Lapsed policy
 
Resilency
 Resilency  Resilency
Resilency
 
Teradata Demand Chain Management (DCM): Version 4
Teradata Demand Chain Management (DCM): Version 4Teradata Demand Chain Management (DCM): Version 4
Teradata Demand Chain Management (DCM): Version 4
 

Similar to EVMS Gold Card

Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Dr Ezzat Mansour
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfNabeel Ahmad
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...Tipsographic . com
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptRedhaElhuni
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfNajm Naqvi
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)Glen Alleman
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance ProgressGlen Alleman
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 

Similar to EVMS Gold Card (20)

dfgd
dfgddfgd
dfgd
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Platinum card for agile ev mr4
Platinum card for agile ev mr4Platinum card for agile ev mr4
Platinum card for agile ev mr4
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance Progress
 
CCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost ControlCCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost Control
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 

Recently uploaded

Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfOverkill Security
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesrafiqahmad00786416
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Orbitshub
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyKhushali Kathiriya
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...Zilliz
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistandanishmna97
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdfSandro Moreira
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...DianaGray10
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...apidays
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingEdi Saputra
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAndrey Devyatkin
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...apidays
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsNanddeep Nachan
 

Recently uploaded (20)

Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdf
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 

EVMS Gold Card

  • 1. DoD TRIPWIRE METRICS Favorable is > 1.0, Unfavorable is < 1.0 Cost Efficiency CPI = BCWP / ACWP Schedule Efficiency SPI = BCWP / BCWS VARIANCES Favorable is Positive, Unfavorable is Negative Cost Variance CV = BCWP – ACWP CV % = (CV / BCWP ) * 100 Schedule Variance SV = BCWP – BCWS SV % = (SV / BCWS ) * 100 Variance at Completion VAC = BAC – EAC OVERALL STATUS % Schedule = ( BCWS CUM / BAC) * 100 % Complete = ( BCWP CUM / BAC) * 100 % Spent = ( ACWP CUM / BAC) * 100 CPLI = (Critical Path Duration + Float Duration (to baseline finish) ) / Critical Path Duration CRITICAL PATH LENGTH INDEX (CPLI) (Schedule Metric) TO COMPLETE PERFORMANCE INDEX (TCPI) # § TCPI EAC = Work Remaining / Cost Remaining = (BAC – BCWP CUM ) / (EAC – ACWP CUM ) ESTIMATE AT COMPLETION # EAC = Actuals to Date + [(Remaining Work) / (Efficiency Factor)] EAC CPI = ACWP CUM + [(BAC – BCWP CUM ) / CPI CUM ] = BAC / CPI CUM EAC Composite = ACWP CUM + [(BAC – BCWP CUM ) / (CPI CUM * SPI CUM )] # To Determine a Contract Level TCPI or EAC; You May Replace BAC with TAB § To Determine the TCPI BAC or LRE Replace EAC with either BAC or LRE Earned Value Management ‘ Gold Card’ EVM Home Page = https://acc.dau.mil/evm eMail Address: [email_address] DAU POC: (703) 805-5259 (DSN 655) Revised April 2008 TERMINOLOGY NCC Negotiated Contract Cost Contract price less profit / fee(s) AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitized CBB Contract Budget Base Sum of NCC and AUW OTB Over Target Baseline Sum of CBB and recognized overrun TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB BAC Budget At Completion Total budget for total contract thru any given level PMB Performance Measurement Baseline Contract time-phased budget plan MR Management Reserve Budget withheld by Ktr PM for unknowns / risk management UB Undistributed Budget Broadly defined activities not yet distributed to CAs CA Control Account Lowest CWBS element assigned to a single focal point to plan & control scope / schedule / budget WP Work Package Near-term, detail-planned activities within a CA PP Planning Package Far-term CA activities not yet defined into WPs BCWS Budgeted Cost for Work Scheduled Value of work planned to be accomplished = PLANNED VALUE BCWP Budgeted Cost for Work Performed Value of work accomplished = EARNED VALUE ACWP Actual Cost of Work Performed Cost of work accomplished = ACTUAL COST EAC Estimate At Completion Estimate of total cost for total contract thru any given level; may be generated by Ktr, PMO, DCMA, etc. = EAC Ktr / PMO / DCMA LRE Latest Revised Estimate Ktr’s EAC or EAC Ktr SLPP Summary Level Planning Package Far-term activities not yet defined into CAs TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve an EAC EVM POLICY: DoDI 5000.2, Table E3.T2 . EVMS in accordance with ANSI/EIA-748 is required for cost or incentive contracts, subcontracts, intra-government work agreements, & other agreements valued > $20M ( T hen- Yr $ ). EVMS contracts > $50M ( TY $ ) require that the EVM system be formally validated by the cognizant contracting officer. Additional Guidance in Defense Acquisition Guidebook and the Earned Value Management Implementation Guide (EVMIG). EVMS is discouraged on F irm- F ixed P rice, L evel o f E ffort, & T ime & M aterial efforts regardless of cost. EVM CONTRACTING REQUIREMENTS: Non-DoD FAR Clauses – Solicitation – 52.234-2 (Pre-Award IBR) or 52.234-3 (Post Award IBR) – Solicitation & Contract – 52.234-4 DoD( ≥ $20M) DFAR Clauses - 252.234-7001 for solicitations and 252.234-7002 for solicitations & contracts Contract Performance Report – DI-MGMT-81466A * 5 Formats (WBS, Organization, Baseline, Staffing & Explanation) Integrated Master Schedule – DI-MGMT-81650 * (Mandatory for DoD EVMS contracts) Integrated Baseline Review (IBR) - Mandatory for all EVMS contracts * See the EVMIG for CPR and IMS tailoring guidance. Management Reserve Work Packages Planning Packages OVERRUN AUW Control Accounts NCC Undistributed Budget OTB CBB TAB Profit / Fees PMB Summary Level Planning Packages Contract Price BASELINE EXECUTION INDEX (BEI) (Schedule Metric) BEI = # of Baseline Tasks Actually Completed / # of Baseline Tasks Scheduled for Completion Management Reserve Cost Variance Schedule Variance ACWP BCWP BCWS $ EAC Time Now Completion Date PMB TAB BAC time