PM World Today – September 2010 (Vol XII, Issue IX)


             PM WORLD TODAY – PM ADVISORY – SEPTEMBER 2010

  Phases of an Event of Scale from a Relief, Response and
                 Reconstruct Perspective

                                                  By Bob Prieto
                                         Senior Vice President, Fluor


Events of scale whether they are manmade or natural are becoming increasingly common
events in an increasingly complex and networked world. The impact of natural events is
further amplified by growing populations in vulnerable areas, prone to earthquake, wind or
water driven disasters. Preparing for and addressing these events requires increased levels
of engineering and logistical support, often requiring the mobilization and reconfiguration of
global supply chains. Anticipating and understanding the nature of this engineering and
logistical support and the prerequisites and lead times associated with effectively deploying it
are essential to today’s disaster response and reconstruction efforts.


To assist in better planning for the deployment of engineering and logistical elements post-
disaster, a phased event of scale framework is laid out in the following figure. The intent is
not to suggest that each of these activities is sequential but rather to define major phases for
purposes of delineating precursor activities and required capabilities. Only then can the often
missing event master schedule be created at an early stage.




© Bob Prieto 2010

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 1
PM World Today – September 2010 (Vol XII, Issue IX)




Pre-Event

Not all events of scale occur without warning and all do benefit from some degree of pre-
planning and preparation. This paper will not look at preparedness as a precursor condition
for an event of scale but rather only look at it in its aftermath. Having said that, certain events
of scale do offer a narrow pre-event period. These may be measured in minutes to hours for
tsunami and certain flooding events to days in the instance of major tropical storms, cyclones
and hurricanes. Pre-event activities during this period should include:

    1. Emergency notification, including a real time assessment of the emergency
         notification system for potential use during the event and the first response phase.
    2. Evacuation or sheltering, including an engineering and logistical assessment of
         evacuation routes or major shelters for the extent of the operation anticipated.
            a. For example, attempting to evacuate populations in excess of logistical
                 capability may result in a more exposed population than under a partial shelter
                 in place scenario

© Bob Prieto 2010

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 2
PM World Today – September 2010 (Vol XII, Issue IX)


            b. Similarly, sheltering decisions should consider ability to withstand the
                 anticipated event and begin consideration of first response challenges posed by
                 the selected sheltering strategy deployed
    3. Pre-positioning of engineering first response and logistical teams
            a. Engineering first response teams should be focused on assisting first response
                 efforts associated with life saving and rescue opportunities. Such activities may
                 include structural advice associated with ruble entrapped individuals or
                 continued habitability of damaged buildings. Risks to first responder operations
                 would also be assessed.
            b. Damage assessment teams or dispatch and management functions related to
                 such teams may be pre-positioned
            c. Logistical and communication teams may be pre-positioned during this period to
                 quickly bring vital logistical communications up immediately after the event and
                 to quickly identify available logistical routes and staging areas.


Event

Engineering and logistical activities during the event and continuing into its immediate
aftermath should be focused on predictive forecasting of the nature, type, extent and pattern
of damage. Areas at risk from secondary effects (such as flooding) should be identified and
prioritized. Geospatial models may need to be updated to reflect any significant modifications
caused by the event itself (new or blocked flow channels or basins as an example).Additional
event phase activities should include:

    1. Selection and refinement of disaster assessment checklists to be initially used
    2. Pre-mobilization (alert) of first response and initial relief capabilities that were not or
         could not be pre-positioned as described above
    3. Updated inventory of engineering, logistical and supply chain capabilities based on
         initial and evolving predictive modeling of event requirements.
    4. Identification of legal, regulatory, insurance, contractual or other enabling frameworks
         that must be activated or modified.
    5. Activation of disaster response teams associated with supplemental engineering
         assessment or logistical support to first responders

© Bob Prieto 2010

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 3
PM World Today – September 2010 (Vol XII, Issue IX)


            a. These may come in part from established disaster response organizations but,
                 based on the likely extent of the event, require supplement from other NGO or
                 commercial organizations. Management plans must be in place for a
                 coordinated engineering and logistical response


First Response

Engineering and logistical activities during the first response phase must, out of necessity,
rely largely on resources already on the ground in the disaster area. When it has been
possible to pre-position resources during the pre-event phase, these can provide a valuable
complement and organizing framework for local resources. Engineering and logistical
activities during the first response phase include:

    1. Prime focus on life saving activities such as providing assistance on assessing
         structural stability of collapsed or partially collapsed structures and ruble.
    2. Focus on minimization of additional loss of life, including loss of first responder lives,
         by identifying, categorizing and assessing potential life threatening hazards
         associated with subsequent engineering failures.
    3. Updating disaster assessment checklists to reflect the realities of the specific event
    4. Identifying evolving engineering and logistical needs during the First Response and
         Initial Relief phases and providing valuable input into mobilization plans for the Initial
         Relief phase
            a. These may include assessments of transitional shelter needs; availability and
                 time to repair potable water, power and sanitary waste systems
            b. Changing logistical patterns including staging areas and locations for the Initial
                 Relief phase and inputs into option analysis for the Transition Phase.
    5. Establishing logistical centers to meet the needs of the First Response phase and
         identifying engineering or other logistical limitations that must be addressed to meet
         First Response or Initial Relief phase activities




© Bob Prieto 2010

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 4
PM World Today – September 2010 (Vol XII, Issue IX)


Mobilization of Initial Relief

The mobilization of initial relief activities are typically the domain of the principle national or
international disaster relief organizations. The focus during this phase is very much about the
saving and preservation of life either in support of the first responder organizations already
on the scene or as added first responder capability where such capability proved to be
inadequate for the scale of event involved. Initial relief activities will consist of continued
rescue efforts such as those described above and in this regard additional engineering
resources may be deployed for what are effectively extended rescue operations. These must
be fully mobilized early in this mobilization phase.


During this phase emergency sheltering will be defined and part of the mobilization activity
must include assessment of existing structures for continued use. In addition plans for review
of selected transitional shelter sites for safety will also be developed during the Mobilization
of Initial Relief such that during the Initial Relief phase these assessments can be completed
in a timely manner before desirable sites become committed to less than optimum usage.
These site assessments are important even in the Initial Relief phase for example to ensure
shelters are not in potential flood plain as a result of event.


Disaster assessment teams should be coming into full swing at this stage and logistical
centers for initial relief activities fully stood up. Planning for transitional phase activities
including identification and action on enabling activities should be begun and completed early
in the Initial Relief phase. Long lead transitional requirements should be initially established
and supply chains organized to meet these needs. This last item will evolve as the post event
period plays out.


At each stage, engineering and logistical efforts must be focused not only on meeting current
phase needs but also on establishing the framework for “vertical launch” of the subsequent
phase.


Recapping, during the Mobilization of Initial Relief, engineering and logistics activities
include:


© Bob Prieto 2010

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 5
PM World Today – September 2010 (Vol XII, Issue IX)


    1. Continued engineering support for rescue operations including:
            a. Ruble field assessment
            b. Structural stability assessments
            c. Mobilization and deployment of heavy lift equipment
    2. Assessment of integrity and adequacy of existing sheltering options
    3. Definition of required emergency shelter requirements and review of selected sites
         from a safety and logistics standpoint
    4. Assessment of transitional shelter requirements
    5. Development of review plans for transitional shelter sites
    6. Complete deployment of disaster assessment teams
    7. Standup logistical centers for initial relief activities
    8. Planning of transitional phase activities including:
            a. Identification and initiation of enabling activities
            b. Establishment of long lead requirements
            c. Configuration of event specific supply chains
    9. Planning for subsequent phases of event response initiated


Initial Relief

The initial relief phase comes quickly on the heels of the First Response phase and in many
ways the two overlap and the transition from one phase to another will likely be uneven at
best. While the First Response phase is very much focused on rescue and life saving
operations, the Initial Relief phase is focused on preserving life and avoiding an even greater
human tragedy by ensuring that the most basic human needs of shelter, food, water and
basic medical care are met.


During this initial relief effort the engineering and logistics effort is focused on supporting
these primary human relief efforts in several different ways, including:

    1. Ongoing assessment of existing shelter stability
    2. Identification of safe drinking water sources including emergency restoration of
         drinking water treatment and distribution systems where possible



© Bob Prieto 2010

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 6
PM World Today – September 2010 (Vol XII, Issue IX)


    3. Identification and stabilization of infrastructure essential to relief operations including
         airport, port, landing zone, road and rail access. Activities may include:
            a. Removal of debris
            b. Structural assessment and as required structural reinforcement
            c. Re-rating of damaged structures for emergency use in the Initial Relief phase
            d. Emergency dredging
            e. Reconfigured logistical chains associated with landside cargo handling at airport
                 and seaports
            f.   Restoration of power or provision of temporary power in support of Initial Relief
                 phase logistical operations
    4. Ongoing assessment of physical safety of sites associated with Initial Relief activities
         (structural collapse; flooding; mud slides)
    5. Operation of Initial Relief phase logistical centers
    6. Deployment of man camps to support Initial Relief phase activities including:
            a. Supporting infrastructure such as temporary power, water and waste treatment,
                 and communications
    7. Assessment of physical infrastructure and potential sites for transitional shelters to:
            a. Identify current condition, constraints and requirements to restore utility for the
                 Transition phase
            b. Select and reserve primary locations for transitional housing
            c. Facilitate long lead procurements
            d. Mobilize initial design and site preparation activities
            e. Identify requirements and availability of specialized labor; employment and
                 training requirements to meet Transition phase needs
    8. Identification of logistical needs for transition phase activities and initiation of enabling
         activities


Mobilization of Transition Phase

As Initial Relief operations stabilize the post event situation, attention turns to providing the
affected population with transitional assistance until reconstruction and other restoration
activities can begin in interest and ultimate transition to a new permanent condition


© Bob Prieto 2010

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 7
PM World Today – September 2010 (Vol XII, Issue IX)


completed. Much like the shift from First Response to Initial Relief phases, there will be an
overlap and staggered shift from Initial Relief to Transition phase activities. This changeover
is marked by the undertaking of various mobilization activities in anticipation of the Transition
phase.


During this mobilization for the Transition phase, engineering, construction and logistical
activities grow in relative importance when compared to other relief activities. This shift in
relative importance of the engineering and construction role is characteristic of post event
periods. By contrast, logistical operations, while growing throughout the post event period,
shift increasingly to more normal conditions.


Essential engineering, construction and logistical activities during Mobilization of the
Transition Phase include:

    1. Identification of elements of permanent potable water system to support Transition
         phase and mobilization of engineering and construction resources required
    2. Identification of elements of permanent waste disposal system (liquid and solid
         wastes) to support Transition phase and mobilization of engineering and construction
         resources required
    3. Identification of additional infrastructure repairs to be undertaken to support Transition
         phase and support initial Reconstruction phase activities and mobilization of
         engineering and construction resources required.
    4. Identification of permanent power generation repairs and replacements required and
         mobilization of engineering and construction resources required.
    5. Identification of reconfigured power distribution networks required to support
         Transition phase and early Reconstruction efforts and mobilization of engineering and
         construction resources required.
    6. Mobilization of engineering and construction resources to deploy Transition
         infrastructure including and transition shelter site infrastructure.
    7. Mobilization of construction and logistical resources to deploy transition phase
         shelters.



© Bob Prieto 2010

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 8
PM World Today – September 2010 (Vol XII, Issue IX)


    8. Mobilize labor related training and employment activities including targeted local hire
         programs
    9. Award long lead contracts to support engineering, construction and logistical activities
         including:
            a. Package treatment plants
            b. Power generation and distribution equipment
            c. Bulk material supply contracts related to aggregate, concrete and steel
            d. Ruble and debris processing equipment
            e. Hazardous material cleanup contracts to the extent not addressed in the Initial
                 Relief phase
            f.   Logistical operations


Transition Phase

Transition phase activities recognize that in events of scale there may be an extended period
after the initial relief phase before permanent reconstruction begins in earnest, providing final
solutions to the problems created by the event. During the transition phase the focus is on
returning some semblance of normalcy in meeting population and local economy needs while
at the same time completing the planning, approvals, resourcing for permanent
reconstruction. During this period engineering and construction activities continue to ramp up
and logistical efforts shift to a more normalized footing.

Engineering, construction and logistics activities during this phase include:

    1. Engineering and construction of elements of permanent potable water system to
         support Transition phase
    2. Engineering and construction of elements of permanent waste disposal system (liquid
         and solid wastes) to support Transition phase
    3. Engineering and construction of additional infrastructure repairs to support Transition
         and initial Reconstruction phase activities
    4. Engineering and construction of permanent power generation repairs and
         replacements



© Bob Prieto 2010

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 9
PM World Today – September 2010 (Vol XII, Issue IX)


    5. Engineering and construction of reconfigured power distribution networks to support
         Transition and early Reconstruction efforts
    6. Engineering and construction of Transition infrastructure including transition shelter
         site infrastructure.
    7. Construction and logistical support of transition phase shelters.
    8. Implementation of labor related training and employment activities including targeted
         local hire programs
    9. Construction, installation and operation of:
            a. Package treatment plants
            b. Power generation and distribution equipment
            c. Bulk material supply contracts related to aggregate, concrete and steel
            d. Ruble and debris processing equipment
    10. Hazardous material cleanup
    11. Transition phase logistical operations
    12. Initial lessons learned assessments from an engineering, construction and logistics
         standpoint


Mobilization of Reconstruction

The mobilization activities for the Reconstruction phase are likely not to occur at singular
period of time; will likely have different development rates for different regions and different
elements of the built environment; and will occur throughout much of the Transition phase,
Specific engineering, construction and logistics activities will include:

    1. Reconstruction planning
            a. Public buildings including government buildings, hospitals, schools, memorials
            b. Infrastructure
            c. Privately owned utilities and infrastructure
            d. Housing
            e. Industrial and commercial developments
    2. Surveying to re-establish property lines and rights
    3. Code modification to build on lessons learned at the earliest stages of reconstruction
    4. Permitting and approvals

© Bob Prieto 2010

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 10
PM World Today – September 2010 (Vol XII, Issue IX)


    5. Estimates and budget development
    6. Funding and program management, engineering and construction contracting
         activities
            a. These will vary by sector and funding source
            b. Coordination to ensure broad priorities are met and logistical chain is adequate
                 is required
    7. Construction labor agreements
    8. Definition of requisite safety, quality and inspection programs


Reconstruction

Reconstruction activities, while representing the largest engineering and construction efforts
post-event, also mark a return to relative normalcy. Normal contracting strategies will tend to
take hold except for the most critical elements of infrastructure which may be undertaken on
an accelerated basis. Logistical chains during this period will have normalized to reflect the
now stabilized post event conditions.


Preparedness Assessment

Key to long term learning and preparation for the inevitable “next event” is the performance
of a Preparedness Assessment. This process acts to ensure that we have truly learned and
provided for the vital lessons we have learned through each stage of the post-event period.
As we have moved through the post-event period not only will our insights have become
deeper but so too will our perspective on some of the actions we undertook at the earliest
stages of the post-event response.


Did decisions on ruble disposal create delays or unneeded costs during the transition phase
or reconstruction phase? Did temporary infrastructure decisions result in wasted efforts when
permanent fixes could have been accomplished for marginally more time or money? Did
management frameworks established at the earliest stages of the post-disaster period
represent barriers for efficient reconstruction?




© Bob Prieto 2010

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 11
PM World Today – September 2010 (Vol XII, Issue IX)


The list of post-event lesson learned questions goes on. But more important may be whether
what we have rebuilt will provide a better pre-event condition that what existed before the last
event, or have we merely reconstructed a built environment the sows the seeds for shortfalls
in responding to the next event of scale.




© Bob Prieto 2010

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 12
PM World Today – September 2010 (Vol XII, Issue IX)




    About the Author:



                                         Bob Prieto
                                         Author




                               Bob Prieto is a Senior Vice President of Fluor
                               Corporation, one of America’s largest engineering,
                               construction and project management firms where he is
                               responsible for strategy in support of the firm’s Industrial
     & Infrastructure Group and its key clients. He focuses on the development,
     delivery and oversight of large, complex projects worldwide. Prior to joining Fluor,
     Bob served as chairman of Parsons Brinckerhoff Inc. He served as a member of
     the executive committee of the National Center for Asia-Pacific Economic
     Cooperation, a member of the Industry Leaders’ Council of the American Society
     of Civil Engineers (ASCE), and co-founder of the Disaster Resource Network. He
     currently serves on a number of committees looking at issues related to
     infrastructure delivery and resiliency and disaster response and rebuilding. Until
     2006 he served as one of three U.S. presidential appointees to the Asia Pacific
     Economic Cooperation (APEC) Business Advisory Council (ABAC) and
     previously served as chairman of the Engineering and Construction Governors of
     The World Economic Forum and co-chair of the infrastructure task force formed
     after September 11th by the New York City Chamber of Commerce. He recently
     completed a ten year tenure as a member of the board of trustees of Polytechnic
     University of New York culminating in its merger with New York University. Bob is
     the author of “Strategic Program Management” published by the Construction
     Management Association of America (CMAA) and more recently a companion
     work entitled “Topics in Strategic Program management”.




© Bob Prieto 2010

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 13

More Related Content

What's hot

Disaster management notes_and_questions
Disaster management notes_and_questionsDisaster management notes_and_questions
Disaster management notes_and_questionsSktabrej Hossain
 
Seismic mitigation final
Seismic mitigation finalSeismic mitigation final
Seismic mitigation finalSiDdu GowTham
 
Smp2 part b policy statements glos-sharpness only_final
Smp2 part b policy statements glos-sharpness only_finalSmp2 part b policy statements glos-sharpness only_final
Smp2 part b policy statements glos-sharpness only_finalSevern Estuary
 
C pccm operation protocol 20140331
C pccm operation protocol 20140331C pccm operation protocol 20140331
C pccm operation protocol 20140331Tudlo
 
D logistics operations protocol 20140331
D logistics operations protocol 20140331D logistics operations protocol 20140331
D logistics operations protocol 20140331Tudlo
 
Chapter4 emergency preparedness
Chapter4 emergency preparednessChapter4 emergency preparedness
Chapter4 emergency preparednessazak80
 
disaster management by tirth sodagar xc
 disaster management by tirth sodagar xc disaster management by tirth sodagar xc
disaster management by tirth sodagar xcTirth Sodagar
 
How we managed disaster A Lecture by Mr Allah Dad Khan Visiting professor the...
How we managed disaster A Lecture by Mr Allah Dad Khan Visiting professor the...How we managed disaster A Lecture by Mr Allah Dad Khan Visiting professor the...
How we managed disaster A Lecture by Mr Allah Dad Khan Visiting professor the...Mr.Allah Dad Khan
 
Concept Note N D C C L L W Dec 17 To 18, 2009
Concept  Note  N D C C  L L W  Dec 17 To 18, 2009Concept  Note  N D C C  L L W  Dec 17 To 18, 2009
Concept Note N D C C L L W Dec 17 To 18, 2009Psdmn Phil
 
03 executive summary 20140331
03 executive summary 2014033103 executive summary 20140331
03 executive summary 20140331Tudlo
 
04 draft final_chapter one_20140331
04 draft final_chapter one_2014033104 draft final_chapter one_20140331
04 draft final_chapter one_20140331Tudlo
 
G ssr operations protocol 20140331
G ssr operations protocol 20140331G ssr operations protocol 20140331
G ssr operations protocol 20140331Tudlo
 
Smp2 part b policy statements newport-usk only_final
Smp2 part b policy statements newport-usk only_finalSmp2 part b policy statements newport-usk only_final
Smp2 part b policy statements newport-usk only_finalSevern Estuary
 
New microsoft office word document (6)
New microsoft office word document (6)New microsoft office word document (6)
New microsoft office word document (6)Rajesh Nair
 

What's hot (18)

Disaster management notes_and_questions
Disaster management notes_and_questionsDisaster management notes_and_questions
Disaster management notes_and_questions
 
Seismic mitigation final
Seismic mitigation finalSeismic mitigation final
Seismic mitigation final
 
Philippines - subnational development processes
Philippines - subnational development processesPhilippines - subnational development processes
Philippines - subnational development processes
 
Smp2 part b policy statements glos-sharpness only_final
Smp2 part b policy statements glos-sharpness only_finalSmp2 part b policy statements glos-sharpness only_final
Smp2 part b policy statements glos-sharpness only_final
 
C pccm operation protocol 20140331
C pccm operation protocol 20140331C pccm operation protocol 20140331
C pccm operation protocol 20140331
 
D logistics operations protocol 20140331
D logistics operations protocol 20140331D logistics operations protocol 20140331
D logistics operations protocol 20140331
 
Adaptive Disaster Risk Reduction
Adaptive Disaster Risk ReductionAdaptive Disaster Risk Reduction
Adaptive Disaster Risk Reduction
 
Adaptive Disaster Risk Reduction
Adaptive Disaster Risk ReductionAdaptive Disaster Risk Reduction
Adaptive Disaster Risk Reduction
 
Chapter4 emergency preparedness
Chapter4 emergency preparednessChapter4 emergency preparedness
Chapter4 emergency preparedness
 
disaster management by tirth sodagar xc
 disaster management by tirth sodagar xc disaster management by tirth sodagar xc
disaster management by tirth sodagar xc
 
How we managed disaster A Lecture by Mr Allah Dad Khan Visiting professor the...
How we managed disaster A Lecture by Mr Allah Dad Khan Visiting professor the...How we managed disaster A Lecture by Mr Allah Dad Khan Visiting professor the...
How we managed disaster A Lecture by Mr Allah Dad Khan Visiting professor the...
 
Concept Note N D C C L L W Dec 17 To 18, 2009
Concept  Note  N D C C  L L W  Dec 17 To 18, 2009Concept  Note  N D C C  L L W  Dec 17 To 18, 2009
Concept Note N D C C L L W Dec 17 To 18, 2009
 
03 executive summary 20140331
03 executive summary 2014033103 executive summary 20140331
03 executive summary 20140331
 
04 draft final_chapter one_20140331
04 draft final_chapter one_2014033104 draft final_chapter one_20140331
04 draft final_chapter one_20140331
 
G ssr operations protocol 20140331
G ssr operations protocol 20140331G ssr operations protocol 20140331
G ssr operations protocol 20140331
 
NOI - Champlain Hudson Power
NOI - Champlain Hudson PowerNOI - Champlain Hudson Power
NOI - Champlain Hudson Power
 
Smp2 part b policy statements newport-usk only_final
Smp2 part b policy statements newport-usk only_finalSmp2 part b policy statements newport-usk only_final
Smp2 part b policy statements newport-usk only_final
 
New microsoft office word document (6)
New microsoft office word document (6)New microsoft office word document (6)
New microsoft office word document (6)
 

Viewers also liked

Sustainability On Large Rev 1 01 31 11
Sustainability On Large Rev 1 01 31 11Sustainability On Large Rev 1 01 31 11
Sustainability On Large Rev 1 01 31 11Bob Prieto
 
Prieto post disaster reconstruction model 03 27 13
Prieto post disaster reconstruction model 03 27 13Prieto post disaster reconstruction model 03 27 13
Prieto post disaster reconstruction model 03 27 13Bob Prieto
 
Impediments for implementing a sound asset management system rev 2
Impediments for implementing a sound asset management system rev 2Impediments for implementing a sound asset management system rev 2
Impediments for implementing a sound asset management system rev 2Bob Prieto
 
Candidate Strategies to Reduce Risks in Large Engineering & Construction Prog...
Candidate Strategies to Reduce Risks in Large Engineering & Construction Prog...Candidate Strategies to Reduce Risks in Large Engineering & Construction Prog...
Candidate Strategies to Reduce Risks in Large Engineering & Construction Prog...Bob Prieto
 
A look at joint ventures
A look at joint venturesA look at joint ventures
A look at joint venturesBob Prieto
 
Assumption infatuation
Assumption infatuationAssumption infatuation
Assumption infatuationBob Prieto
 
Annoying habits of a poor listener
Annoying habits of a poor listenerAnnoying habits of a poor listener
Annoying habits of a poor listenerBob Prieto
 

Viewers also liked (7)

Sustainability On Large Rev 1 01 31 11
Sustainability On Large Rev 1 01 31 11Sustainability On Large Rev 1 01 31 11
Sustainability On Large Rev 1 01 31 11
 
Prieto post disaster reconstruction model 03 27 13
Prieto post disaster reconstruction model 03 27 13Prieto post disaster reconstruction model 03 27 13
Prieto post disaster reconstruction model 03 27 13
 
Impediments for implementing a sound asset management system rev 2
Impediments for implementing a sound asset management system rev 2Impediments for implementing a sound asset management system rev 2
Impediments for implementing a sound asset management system rev 2
 
Candidate Strategies to Reduce Risks in Large Engineering & Construction Prog...
Candidate Strategies to Reduce Risks in Large Engineering & Construction Prog...Candidate Strategies to Reduce Risks in Large Engineering & Construction Prog...
Candidate Strategies to Reduce Risks in Large Engineering & Construction Prog...
 
A look at joint ventures
A look at joint venturesA look at joint ventures
A look at joint ventures
 
Assumption infatuation
Assumption infatuationAssumption infatuation
Assumption infatuation
 
Annoying habits of a poor listener
Annoying habits of a poor listenerAnnoying habits of a poor listener
Annoying habits of a poor listener
 

Similar to Phases Of An Event Of Scale

HADIDIAN MOGHADAM-Aviation industry and its actions on crisis management proc...
HADIDIAN MOGHADAM-Aviation industry and its actions on crisis management proc...HADIDIAN MOGHADAM-Aviation industry and its actions on crisis management proc...
HADIDIAN MOGHADAM-Aviation industry and its actions on crisis management proc...Global Risk Forum GRFDavos
 
Disaster management cycle, mitigation and preparedness
Disaster management cycle, mitigation and preparednessDisaster management cycle, mitigation and preparedness
Disaster management cycle, mitigation and preparednessShivani Khandelwal
 
Rehabilitation, reconstruction and recovery
Rehabilitation, reconstruction and recoveryRehabilitation, reconstruction and recovery
Rehabilitation, reconstruction and recoveryShahin MB
 
Running head the recovery phase of the disaster recovery cycle .docx
Running head the recovery phase of the disaster recovery cycle   .docxRunning head the recovery phase of the disaster recovery cycle   .docx
Running head the recovery phase of the disaster recovery cycle .docxtoltonkendal
 
Disaster Risk Reduction training .pptx
Disaster Risk Reduction training   .pptxDisaster Risk Reduction training   .pptx
Disaster Risk Reduction training .pptxKabul University
 
DRR Training FOR Agriculture and food Security
DRR Training  FOR Agriculture and food SecurityDRR Training  FOR Agriculture and food Security
DRR Training FOR Agriculture and food SecurityKabul University
 
Smarter CitiesThought Leadership White Paper21st centu.docx
Smarter CitiesThought Leadership White Paper21st centu.docxSmarter CitiesThought Leadership White Paper21st centu.docx
Smarter CitiesThought Leadership White Paper21st centu.docxwhitneyleman54422
 
BBB presentation.pptx
BBB presentation.pptxBBB presentation.pptx
BBB presentation.pptxcrizziepalejo
 
Introduction to emergency management.pdf
Introduction to emergency management.pdfIntroduction to emergency management.pdf
Introduction to emergency management.pdfroszansapon
 
Part6 disaster-management-risk-mitigation
Part6 disaster-management-risk-mitigationPart6 disaster-management-risk-mitigation
Part6 disaster-management-risk-mitigationzaffar abbasi
 
Empowering Resilience Through Effective Crisis Management
Empowering Resilience Through Effective Crisis ManagementEmpowering Resilience Through Effective Crisis Management
Empowering Resilience Through Effective Crisis ManagementI-Pix Technologies
 
Chapter 8 disaster management
Chapter 8 disaster managementChapter 8 disaster management
Chapter 8 disaster managementssusera952fa
 
Format Guide forWriting Hazard Specific Plan
Format Guide forWriting Hazard Specific PlanFormat Guide forWriting Hazard Specific Plan
Format Guide forWriting Hazard Specific PlanJeanmarieColbert3
 
Disaster Prepared Management
Disaster Prepared ManagementDisaster Prepared Management
Disaster Prepared ManagementAna Maramadaumasu
 
DRRR LP PDRRM law (upload).pptx
DRRR LP PDRRM law (upload).pptxDRRR LP PDRRM law (upload).pptx
DRRR LP PDRRM law (upload).pptxMariaRowenaFlores
 
Humanitarian task and its importance
Humanitarian task and its importanceHumanitarian task and its importance
Humanitarian task and its importanceRokonuzzaman Rony
 

Similar to Phases Of An Event Of Scale (20)

HADIDIAN MOGHADAM-Aviation industry and its actions on crisis management proc...
HADIDIAN MOGHADAM-Aviation industry and its actions on crisis management proc...HADIDIAN MOGHADAM-Aviation industry and its actions on crisis management proc...
HADIDIAN MOGHADAM-Aviation industry and its actions on crisis management proc...
 
Disaster management cycle, mitigation and preparedness
Disaster management cycle, mitigation and preparednessDisaster management cycle, mitigation and preparedness
Disaster management cycle, mitigation and preparedness
 
Emergency and Humanitarian Response
Emergency and Humanitarian ResponseEmergency and Humanitarian Response
Emergency and Humanitarian Response
 
Rehabilitation, reconstruction and recovery
Rehabilitation, reconstruction and recoveryRehabilitation, reconstruction and recovery
Rehabilitation, reconstruction and recovery
 
Running head the recovery phase of the disaster recovery cycle .docx
Running head the recovery phase of the disaster recovery cycle   .docxRunning head the recovery phase of the disaster recovery cycle   .docx
Running head the recovery phase of the disaster recovery cycle .docx
 
Disaster Risk Reduction training .pptx
Disaster Risk Reduction training   .pptxDisaster Risk Reduction training   .pptx
Disaster Risk Reduction training .pptx
 
DRR Training FOR Agriculture and food Security
DRR Training  FOR Agriculture and food SecurityDRR Training  FOR Agriculture and food Security
DRR Training FOR Agriculture and food Security
 
Smarter CitiesThought Leadership White Paper21st centu.docx
Smarter CitiesThought Leadership White Paper21st centu.docxSmarter CitiesThought Leadership White Paper21st centu.docx
Smarter CitiesThought Leadership White Paper21st centu.docx
 
BBB presentation.pptx
BBB presentation.pptxBBB presentation.pptx
BBB presentation.pptx
 
Introduction to emergency management.pdf
Introduction to emergency management.pdfIntroduction to emergency management.pdf
Introduction to emergency management.pdf
 
Chapter viii sw 18
Chapter viii sw 18Chapter viii sw 18
Chapter viii sw 18
 
Part6 disaster-management-risk-mitigation
Part6 disaster-management-risk-mitigationPart6 disaster-management-risk-mitigation
Part6 disaster-management-risk-mitigation
 
Ch 17
Ch 17Ch 17
Ch 17
 
Empowering Resilience Through Effective Crisis Management
Empowering Resilience Through Effective Crisis ManagementEmpowering Resilience Through Effective Crisis Management
Empowering Resilience Through Effective Crisis Management
 
Chapter 8 disaster management
Chapter 8 disaster managementChapter 8 disaster management
Chapter 8 disaster management
 
Format Guide forWriting Hazard Specific Plan
Format Guide forWriting Hazard Specific PlanFormat Guide forWriting Hazard Specific Plan
Format Guide forWriting Hazard Specific Plan
 
Emergency response and disaster recovery
Emergency response and disaster recoveryEmergency response and disaster recovery
Emergency response and disaster recovery
 
Disaster Prepared Management
Disaster Prepared ManagementDisaster Prepared Management
Disaster Prepared Management
 
DRRR LP PDRRM law (upload).pptx
DRRR LP PDRRM law (upload).pptxDRRR LP PDRRM law (upload).pptx
DRRR LP PDRRM law (upload).pptx
 
Humanitarian task and its importance
Humanitarian task and its importanceHumanitarian task and its importance
Humanitarian task and its importance
 

More from Bob Prieto

Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Bob Prieto
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startupBob Prieto
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projectsBob Prieto
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projectsBob Prieto
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programsBob Prieto
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryBob Prieto
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface ManagementBob Prieto
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsBob Prieto
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global WarmingBob Prieto
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project successBob Prieto
 
Large complex project success
Large complex project successLarge complex project success
Large complex project successBob Prieto
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Bob Prieto
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under UncertaintyBob Prieto
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasBob Prieto
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentBob Prieto
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Bob Prieto
 

More from Bob Prieto (20)

Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startup
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projects
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projects
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programs
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project delivery
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface Management
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction Projects
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global Warming
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project success
 
Large complex project success
Large complex project successLarge complex project success
Large complex project success
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under Uncertainty
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the Bahamas
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environment
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
 
Chapter 9
Chapter 9Chapter 9
Chapter 9
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7
 

Phases Of An Event Of Scale

  • 1. PM World Today – September 2010 (Vol XII, Issue IX) PM WORLD TODAY – PM ADVISORY – SEPTEMBER 2010 Phases of an Event of Scale from a Relief, Response and Reconstruct Perspective By Bob Prieto Senior Vice President, Fluor Events of scale whether they are manmade or natural are becoming increasingly common events in an increasingly complex and networked world. The impact of natural events is further amplified by growing populations in vulnerable areas, prone to earthquake, wind or water driven disasters. Preparing for and addressing these events requires increased levels of engineering and logistical support, often requiring the mobilization and reconfiguration of global supply chains. Anticipating and understanding the nature of this engineering and logistical support and the prerequisites and lead times associated with effectively deploying it are essential to today’s disaster response and reconstruction efforts. To assist in better planning for the deployment of engineering and logistical elements post- disaster, a phased event of scale framework is laid out in the following figure. The intent is not to suggest that each of these activities is sequential but rather to define major phases for purposes of delineating precursor activities and required capabilities. Only then can the often missing event master schedule be created at an early stage. © Bob Prieto 2010 PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 1
  • 2. PM World Today – September 2010 (Vol XII, Issue IX) Pre-Event Not all events of scale occur without warning and all do benefit from some degree of pre- planning and preparation. This paper will not look at preparedness as a precursor condition for an event of scale but rather only look at it in its aftermath. Having said that, certain events of scale do offer a narrow pre-event period. These may be measured in minutes to hours for tsunami and certain flooding events to days in the instance of major tropical storms, cyclones and hurricanes. Pre-event activities during this period should include: 1. Emergency notification, including a real time assessment of the emergency notification system for potential use during the event and the first response phase. 2. Evacuation or sheltering, including an engineering and logistical assessment of evacuation routes or major shelters for the extent of the operation anticipated. a. For example, attempting to evacuate populations in excess of logistical capability may result in a more exposed population than under a partial shelter in place scenario © Bob Prieto 2010 PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 2
  • 3. PM World Today – September 2010 (Vol XII, Issue IX) b. Similarly, sheltering decisions should consider ability to withstand the anticipated event and begin consideration of first response challenges posed by the selected sheltering strategy deployed 3. Pre-positioning of engineering first response and logistical teams a. Engineering first response teams should be focused on assisting first response efforts associated with life saving and rescue opportunities. Such activities may include structural advice associated with ruble entrapped individuals or continued habitability of damaged buildings. Risks to first responder operations would also be assessed. b. Damage assessment teams or dispatch and management functions related to such teams may be pre-positioned c. Logistical and communication teams may be pre-positioned during this period to quickly bring vital logistical communications up immediately after the event and to quickly identify available logistical routes and staging areas. Event Engineering and logistical activities during the event and continuing into its immediate aftermath should be focused on predictive forecasting of the nature, type, extent and pattern of damage. Areas at risk from secondary effects (such as flooding) should be identified and prioritized. Geospatial models may need to be updated to reflect any significant modifications caused by the event itself (new or blocked flow channels or basins as an example).Additional event phase activities should include: 1. Selection and refinement of disaster assessment checklists to be initially used 2. Pre-mobilization (alert) of first response and initial relief capabilities that were not or could not be pre-positioned as described above 3. Updated inventory of engineering, logistical and supply chain capabilities based on initial and evolving predictive modeling of event requirements. 4. Identification of legal, regulatory, insurance, contractual or other enabling frameworks that must be activated or modified. 5. Activation of disaster response teams associated with supplemental engineering assessment or logistical support to first responders © Bob Prieto 2010 PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 3
  • 4. PM World Today – September 2010 (Vol XII, Issue IX) a. These may come in part from established disaster response organizations but, based on the likely extent of the event, require supplement from other NGO or commercial organizations. Management plans must be in place for a coordinated engineering and logistical response First Response Engineering and logistical activities during the first response phase must, out of necessity, rely largely on resources already on the ground in the disaster area. When it has been possible to pre-position resources during the pre-event phase, these can provide a valuable complement and organizing framework for local resources. Engineering and logistical activities during the first response phase include: 1. Prime focus on life saving activities such as providing assistance on assessing structural stability of collapsed or partially collapsed structures and ruble. 2. Focus on minimization of additional loss of life, including loss of first responder lives, by identifying, categorizing and assessing potential life threatening hazards associated with subsequent engineering failures. 3. Updating disaster assessment checklists to reflect the realities of the specific event 4. Identifying evolving engineering and logistical needs during the First Response and Initial Relief phases and providing valuable input into mobilization plans for the Initial Relief phase a. These may include assessments of transitional shelter needs; availability and time to repair potable water, power and sanitary waste systems b. Changing logistical patterns including staging areas and locations for the Initial Relief phase and inputs into option analysis for the Transition Phase. 5. Establishing logistical centers to meet the needs of the First Response phase and identifying engineering or other logistical limitations that must be addressed to meet First Response or Initial Relief phase activities © Bob Prieto 2010 PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 4
  • 5. PM World Today – September 2010 (Vol XII, Issue IX) Mobilization of Initial Relief The mobilization of initial relief activities are typically the domain of the principle national or international disaster relief organizations. The focus during this phase is very much about the saving and preservation of life either in support of the first responder organizations already on the scene or as added first responder capability where such capability proved to be inadequate for the scale of event involved. Initial relief activities will consist of continued rescue efforts such as those described above and in this regard additional engineering resources may be deployed for what are effectively extended rescue operations. These must be fully mobilized early in this mobilization phase. During this phase emergency sheltering will be defined and part of the mobilization activity must include assessment of existing structures for continued use. In addition plans for review of selected transitional shelter sites for safety will also be developed during the Mobilization of Initial Relief such that during the Initial Relief phase these assessments can be completed in a timely manner before desirable sites become committed to less than optimum usage. These site assessments are important even in the Initial Relief phase for example to ensure shelters are not in potential flood plain as a result of event. Disaster assessment teams should be coming into full swing at this stage and logistical centers for initial relief activities fully stood up. Planning for transitional phase activities including identification and action on enabling activities should be begun and completed early in the Initial Relief phase. Long lead transitional requirements should be initially established and supply chains organized to meet these needs. This last item will evolve as the post event period plays out. At each stage, engineering and logistical efforts must be focused not only on meeting current phase needs but also on establishing the framework for “vertical launch” of the subsequent phase. Recapping, during the Mobilization of Initial Relief, engineering and logistics activities include: © Bob Prieto 2010 PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 5
  • 6. PM World Today – September 2010 (Vol XII, Issue IX) 1. Continued engineering support for rescue operations including: a. Ruble field assessment b. Structural stability assessments c. Mobilization and deployment of heavy lift equipment 2. Assessment of integrity and adequacy of existing sheltering options 3. Definition of required emergency shelter requirements and review of selected sites from a safety and logistics standpoint 4. Assessment of transitional shelter requirements 5. Development of review plans for transitional shelter sites 6. Complete deployment of disaster assessment teams 7. Standup logistical centers for initial relief activities 8. Planning of transitional phase activities including: a. Identification and initiation of enabling activities b. Establishment of long lead requirements c. Configuration of event specific supply chains 9. Planning for subsequent phases of event response initiated Initial Relief The initial relief phase comes quickly on the heels of the First Response phase and in many ways the two overlap and the transition from one phase to another will likely be uneven at best. While the First Response phase is very much focused on rescue and life saving operations, the Initial Relief phase is focused on preserving life and avoiding an even greater human tragedy by ensuring that the most basic human needs of shelter, food, water and basic medical care are met. During this initial relief effort the engineering and logistics effort is focused on supporting these primary human relief efforts in several different ways, including: 1. Ongoing assessment of existing shelter stability 2. Identification of safe drinking water sources including emergency restoration of drinking water treatment and distribution systems where possible © Bob Prieto 2010 PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 6
  • 7. PM World Today – September 2010 (Vol XII, Issue IX) 3. Identification and stabilization of infrastructure essential to relief operations including airport, port, landing zone, road and rail access. Activities may include: a. Removal of debris b. Structural assessment and as required structural reinforcement c. Re-rating of damaged structures for emergency use in the Initial Relief phase d. Emergency dredging e. Reconfigured logistical chains associated with landside cargo handling at airport and seaports f. Restoration of power or provision of temporary power in support of Initial Relief phase logistical operations 4. Ongoing assessment of physical safety of sites associated with Initial Relief activities (structural collapse; flooding; mud slides) 5. Operation of Initial Relief phase logistical centers 6. Deployment of man camps to support Initial Relief phase activities including: a. Supporting infrastructure such as temporary power, water and waste treatment, and communications 7. Assessment of physical infrastructure and potential sites for transitional shelters to: a. Identify current condition, constraints and requirements to restore utility for the Transition phase b. Select and reserve primary locations for transitional housing c. Facilitate long lead procurements d. Mobilize initial design and site preparation activities e. Identify requirements and availability of specialized labor; employment and training requirements to meet Transition phase needs 8. Identification of logistical needs for transition phase activities and initiation of enabling activities Mobilization of Transition Phase As Initial Relief operations stabilize the post event situation, attention turns to providing the affected population with transitional assistance until reconstruction and other restoration activities can begin in interest and ultimate transition to a new permanent condition © Bob Prieto 2010 PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 7
  • 8. PM World Today – September 2010 (Vol XII, Issue IX) completed. Much like the shift from First Response to Initial Relief phases, there will be an overlap and staggered shift from Initial Relief to Transition phase activities. This changeover is marked by the undertaking of various mobilization activities in anticipation of the Transition phase. During this mobilization for the Transition phase, engineering, construction and logistical activities grow in relative importance when compared to other relief activities. This shift in relative importance of the engineering and construction role is characteristic of post event periods. By contrast, logistical operations, while growing throughout the post event period, shift increasingly to more normal conditions. Essential engineering, construction and logistical activities during Mobilization of the Transition Phase include: 1. Identification of elements of permanent potable water system to support Transition phase and mobilization of engineering and construction resources required 2. Identification of elements of permanent waste disposal system (liquid and solid wastes) to support Transition phase and mobilization of engineering and construction resources required 3. Identification of additional infrastructure repairs to be undertaken to support Transition phase and support initial Reconstruction phase activities and mobilization of engineering and construction resources required. 4. Identification of permanent power generation repairs and replacements required and mobilization of engineering and construction resources required. 5. Identification of reconfigured power distribution networks required to support Transition phase and early Reconstruction efforts and mobilization of engineering and construction resources required. 6. Mobilization of engineering and construction resources to deploy Transition infrastructure including and transition shelter site infrastructure. 7. Mobilization of construction and logistical resources to deploy transition phase shelters. © Bob Prieto 2010 PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 8
  • 9. PM World Today – September 2010 (Vol XII, Issue IX) 8. Mobilize labor related training and employment activities including targeted local hire programs 9. Award long lead contracts to support engineering, construction and logistical activities including: a. Package treatment plants b. Power generation and distribution equipment c. Bulk material supply contracts related to aggregate, concrete and steel d. Ruble and debris processing equipment e. Hazardous material cleanup contracts to the extent not addressed in the Initial Relief phase f. Logistical operations Transition Phase Transition phase activities recognize that in events of scale there may be an extended period after the initial relief phase before permanent reconstruction begins in earnest, providing final solutions to the problems created by the event. During the transition phase the focus is on returning some semblance of normalcy in meeting population and local economy needs while at the same time completing the planning, approvals, resourcing for permanent reconstruction. During this period engineering and construction activities continue to ramp up and logistical efforts shift to a more normalized footing. Engineering, construction and logistics activities during this phase include: 1. Engineering and construction of elements of permanent potable water system to support Transition phase 2. Engineering and construction of elements of permanent waste disposal system (liquid and solid wastes) to support Transition phase 3. Engineering and construction of additional infrastructure repairs to support Transition and initial Reconstruction phase activities 4. Engineering and construction of permanent power generation repairs and replacements © Bob Prieto 2010 PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 9
  • 10. PM World Today – September 2010 (Vol XII, Issue IX) 5. Engineering and construction of reconfigured power distribution networks to support Transition and early Reconstruction efforts 6. Engineering and construction of Transition infrastructure including transition shelter site infrastructure. 7. Construction and logistical support of transition phase shelters. 8. Implementation of labor related training and employment activities including targeted local hire programs 9. Construction, installation and operation of: a. Package treatment plants b. Power generation and distribution equipment c. Bulk material supply contracts related to aggregate, concrete and steel d. Ruble and debris processing equipment 10. Hazardous material cleanup 11. Transition phase logistical operations 12. Initial lessons learned assessments from an engineering, construction and logistics standpoint Mobilization of Reconstruction The mobilization activities for the Reconstruction phase are likely not to occur at singular period of time; will likely have different development rates for different regions and different elements of the built environment; and will occur throughout much of the Transition phase, Specific engineering, construction and logistics activities will include: 1. Reconstruction planning a. Public buildings including government buildings, hospitals, schools, memorials b. Infrastructure c. Privately owned utilities and infrastructure d. Housing e. Industrial and commercial developments 2. Surveying to re-establish property lines and rights 3. Code modification to build on lessons learned at the earliest stages of reconstruction 4. Permitting and approvals © Bob Prieto 2010 PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 10
  • 11. PM World Today – September 2010 (Vol XII, Issue IX) 5. Estimates and budget development 6. Funding and program management, engineering and construction contracting activities a. These will vary by sector and funding source b. Coordination to ensure broad priorities are met and logistical chain is adequate is required 7. Construction labor agreements 8. Definition of requisite safety, quality and inspection programs Reconstruction Reconstruction activities, while representing the largest engineering and construction efforts post-event, also mark a return to relative normalcy. Normal contracting strategies will tend to take hold except for the most critical elements of infrastructure which may be undertaken on an accelerated basis. Logistical chains during this period will have normalized to reflect the now stabilized post event conditions. Preparedness Assessment Key to long term learning and preparation for the inevitable “next event” is the performance of a Preparedness Assessment. This process acts to ensure that we have truly learned and provided for the vital lessons we have learned through each stage of the post-event period. As we have moved through the post-event period not only will our insights have become deeper but so too will our perspective on some of the actions we undertook at the earliest stages of the post-event response. Did decisions on ruble disposal create delays or unneeded costs during the transition phase or reconstruction phase? Did temporary infrastructure decisions result in wasted efforts when permanent fixes could have been accomplished for marginally more time or money? Did management frameworks established at the earliest stages of the post-disaster period represent barriers for efficient reconstruction? © Bob Prieto 2010 PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 11
  • 12. PM World Today – September 2010 (Vol XII, Issue IX) The list of post-event lesson learned questions goes on. But more important may be whether what we have rebuilt will provide a better pre-event condition that what existed before the last event, or have we merely reconstructed a built environment the sows the seeds for shortfalls in responding to the next event of scale. © Bob Prieto 2010 PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 12
  • 13. PM World Today – September 2010 (Vol XII, Issue IX) About the Author: Bob Prieto Author Bob Prieto is a Senior Vice President of Fluor Corporation, one of America’s largest engineering, construction and project management firms where he is responsible for strategy in support of the firm’s Industrial & Infrastructure Group and its key clients. He focuses on the development, delivery and oversight of large, complex projects worldwide. Prior to joining Fluor, Bob served as chairman of Parsons Brinckerhoff Inc. He served as a member of the executive committee of the National Center for Asia-Pacific Economic Cooperation, a member of the Industry Leaders’ Council of the American Society of Civil Engineers (ASCE), and co-founder of the Disaster Resource Network. He currently serves on a number of committees looking at issues related to infrastructure delivery and resiliency and disaster response and rebuilding. Until 2006 he served as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC) and previously served as chairman of the Engineering and Construction Governors of The World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. He recently completed a ten year tenure as a member of the board of trustees of Polytechnic University of New York culminating in its merger with New York University. Bob is the author of “Strategic Program Management” published by the Construction Management Association of America (CMAA) and more recently a companion work entitled “Topics in Strategic Program management”. © Bob Prieto 2010 PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 13