2. The purpose of this presentation is to
inform you about the Rinconada Reliability
Project
• Provide Project Background
• Describe the Phases of the Project
• Explain how you can stay informed
3. • Original Rinconada WTP finished in 1968
• Sole District Water supply to West Valley
Service Area
• Current Project
Planning completed June 2012
Design completed January 2015
Construction started July 2015
Construction completion July 2020?
4. • Replace facilities and components that are
near the “end of their useful life”
• Meet increasingly stringent water quality
standards
• Comply with current seismic codes
• Improve plant safety
5. • Increase Water Production Capacity from
• 80 MGD to 100 MGD
• Provide new facilities
• Raw Water Ozonation
• Flocculation and Plate Settler Clarification
• Dual Media Filtration
6.
7.
8.
9.
10.
11. Residuals
Ops Bldg Seismic
Quito Bridge
Rinconada Reliability Improvement Project Construction Phases
Phase
1 Phase 2 Phase 3 Phase 4 Phase 5
Coordinating Schedule
with Other Activities
12. Stay Informed:
• Visit the District’s website and blog at
www.RinconadaReliabilityProject.com
• Contact District’s Public Affairs Representative Tony
Mercado
Telephone number: 408-426-1039
E-mail address: Tmercado@valleywater.org