1. A0
Completion of Gabon 2 million ton
per year Crude Oil Refinery
Time
Money
Crude Oil
NODE: NO.: LH001A-0 TITLE: Completion Gabon 2 million ton per year Crude Oil Refinery
Other Resources
HSE
Standards
Regulations Schedule
Petrochemical
Products
Standards
Customer
Requirements
Products ready to be sold
Refining Process
3. 5
Conduct
Procurement List
Proposal
Evaluation
Techniques
6
Open Bid to
Suppliers
Final
Design
9
Review and accept
items procured
Procurement
Engieers
Advertising
7
Qualify Suppliers
List
Bidder
Conference
8
Complete Purchase
Orders & Issue to
Suppliers
Owner
&
Supervisors
Junior
Procurement
Engineers
Superviors
Senior
Construction
Engineers
Technical
Managers
Procurement
List
Unqualied Suppilers
PO
Equipment
& Materials
Spec.
Funds
Contract
Contract
Manager
Refining
Process
Mothodologies
Equipment
&
Material
Cost
Control
Financial
Regulations
Deliver
To
Site
Prequalification Bidding
Requirements
Bidding Regulations
NODE: NO.: LH003A2 TITLE: Project Procurement Phase
4. 10
Survey & Analysis
of Existing
Conditions
Topographical
Survey
Team
FEED
& Design
Documents
Geotechnical
Engineers
11
Site Development
(Level Ground &
Excavation)
Access
To
Site
Equipment
Deliver To Site
13
Foundation
&
Civil Works
Mechanicals
Construction
Project Engineers
14
Instrumentation
& Equipment
Erection
12
Utilities Set Up
Water, Gas,
Electrical,
Sewer,
Waste Processing
Geotechnical
Survey
Report
Project
Design
15
Test
Construction
Code
Inspections
Technical
& Quality
Manager
Ready
To
Operate
Owner
&
Supervisor
H.S.E
Refinery
Operation
Instructions
16
Construction
Rework
Defects
Environmental
Regulations
Materials
Deliver To Site
Technical
Engineers
Technical
Engineers
Geographic
Information
Geographic
Survey
Permission
NODE: NO.: LH004A-3 TITLE: Project Construction Phase