SlideShare a Scribd company logo
1 of 14
MID-TERM REVIEW
TECHNICAL SUPPORT SERVCRES PROGRAM
14 January 2022
Overview
ABSTRACT
• Research Activities:
• Development Activities
• Total
STATUS as of 31 Dec 2021
• Completed:
• On-going:
• At risk:
1. Study on cropping intensity in
Sarpang
Target: Within April 2022
Status = Ongoing
Survey and data compilation
completed. Currently Report Writing
2. Compilation and publication of
annual report for FY 2021-22
Status: Completed
Compilation and Review. Submitted
to management. Office copy will be
printed along with other materials.
1. Rice Yield Gap Analysis in Sarpang
Target: Within May 2022
Status: On-going
Questionnaire and literature review completed.
On station and demonstration yield data
collected. Survey will be carried out in
February after completion of threshing.
2. Performance assessment of scientific demo
orchard established by ARDC Samtenling
Target: June 2022
Status: On-going
Data template developed. Field assessment
will be carried out in January 3rd week in
collaboration with HP.
1. Study on fallow land status in
Sarpang, Samtse and Samdrup
Jongkhar; challenges and
prospectus
Due to intensive data collection and
movement restriction, the activity
can’t be carried out in this FY.
2. Preparation, Review and
Assessment of APA for FY 2021-22
Within 7th July 2022
Status: On going
Mid Term Review Completed on 28th
December 2022.
RC Budget:
Approved: Nu.0.1m
Expenditure: Nu.0.04
% Budget Utilization = 40%
Plant Protection
Approved Budget
1. RGoB: 0.080M
• Expenditure: 0.025M (Adv- 6000)~31%
2. FSAPP: 0.100M
• Expenditure:
3. NoFP Deposit: 0.124+0.230=0.354
4. NPPC (AFACI) Deposit: 0.085+0.075=0.160
Total Budget: 0.694
1. Evaluation of organic pesticides
and botanicals in management of
mites in chilli
Target: Activity completed and report
submitted by last week of May,
2022
Status: Ongoing
2. Evaluation of biopesticides and
plant extracts against rice earhead
bug (Leptocorisa spp. Fabricius)
under rainfed ecosystem of
Samtenling.
Target: Activity completed and report
submitted by third week of
February, 2022
Status: Activities completed and
report writing
APA Activities
3. Demonstration on Integrated Pest
management in Chilli (Common pests and
disease management in chilli-
phythopthora, mites and aphids)
Target: Within 2nd week of June 2022
Status: Ongoing
4. Study on pest and disease resistance of 36
lines of irrigated rice introduced from
IRRI (INGER 2019)
Target: Within 2nd week of Feb 2022
Status: Completed
APA Activities
5. Evaluation of eco- friendly control
methods using locally available
plants and materials for red ant
(Dorylus orientalis Westwood) of
potato in naturally infested field at
ARDC Samtenling
Target: Within 1st week of June 2022
Status: Ongoing
APA Activities
1. Monitoring of plant and leaf hoppers
in paddy using light traps
Target: within 4th week of February 2022
Status: Completed
2. Evaluation of biopesticides and
botanical extracts against major
pests of cole crops (NCT)
Target: within 2nd week of June 2022
Status: Ongoing
Non APA Activities
3. Monitoring of Fall armyworm
using pheromone traps
Status: On going
4. Evaluation of different synthetic
and botanical pesticides against fall
army worm (Spodoptera
frugiperda)
Status: Ongoing
Non APA Activities
5. Construction of biopesticide utility
shed
Status: ongoing
Non APA Activities
MID-TERM REVIEW TSS.pptx

More Related Content

Similar to MID-TERM REVIEW TSS.pptx

Similar to MID-TERM REVIEW TSS.pptx (19)

2022-DMEA-2nd-QUARTER_PSDSs.pptx
2022-DMEA-2nd-QUARTER_PSDSs.pptx2022-DMEA-2nd-QUARTER_PSDSs.pptx
2022-DMEA-2nd-QUARTER_PSDSs.pptx
 
PPRD Accomplishments and TargetRegional Research Agenda and Frameworks.pptx
PPRD Accomplishments and TargetRegional Research Agenda and Frameworks.pptxPPRD Accomplishments and TargetRegional Research Agenda and Frameworks.pptx
PPRD Accomplishments and TargetRegional Research Agenda and Frameworks.pptx
 
The ESA-WB partnership powered by in partnership with Pushing the sustainab...
The ESA-WB partnership  powered by in partnership with  Pushing the sustainab...The ESA-WB partnership  powered by in partnership with  Pushing the sustainab...
The ESA-WB partnership powered by in partnership with Pushing the sustainab...
 
Criteria 2 Ppt New.pptx
Criteria 2 Ppt New.pptxCriteria 2 Ppt New.pptx
Criteria 2 Ppt New.pptx
 
PROJECT MASK.docx
PROJECT MASK.docxPROJECT MASK.docx
PROJECT MASK.docx
 
PROJECT MASK.docx
PROJECT MASK.docxPROJECT MASK.docx
PROJECT MASK.docx
 
Item 2. ASP work from December 2016 to May 2018: Philippines
Item 2. ASP work from December 2016 to May 2018: PhilippinesItem 2. ASP work from December 2016 to May 2018: Philippines
Item 2. ASP work from December 2016 to May 2018: Philippines
 
TES-SECOND-SMEA-2022.pptx
TES-SECOND-SMEA-2022.pptxTES-SECOND-SMEA-2022.pptx
TES-SECOND-SMEA-2022.pptx
 
Item 4: Presentation of the TCP/RAB/3802 project
Item 4: Presentation of the TCP/RAB/3802 projectItem 4: Presentation of the TCP/RAB/3802 project
Item 4: Presentation of the TCP/RAB/3802 project
 
GDNet M&E Report 2012–Year 1
GDNet M&E Report 2012–Year 1GDNet M&E Report 2012–Year 1
GDNet M&E Report 2012–Year 1
 
Ar overview 2021
Ar overview 2021Ar overview 2021
Ar overview 2021
 
GDNet Year 2 M&E Report 2013
GDNet Year 2 M&E Report 2013GDNet Year 2 M&E Report 2013
GDNet Year 2 M&E Report 2013
 
Sarah Green wp5 Nov 2018
Sarah Green wp5 Nov 2018Sarah Green wp5 Nov 2018
Sarah Green wp5 Nov 2018
 
NL Agency - Sustainability Assessment Rice Husk gasifier Indonesia
NL Agency - Sustainability Assessment Rice Husk gasifier IndonesiaNL Agency - Sustainability Assessment Rice Husk gasifier Indonesia
NL Agency - Sustainability Assessment Rice Husk gasifier Indonesia
 
EU4Environment Water and Data - Implementing Partners' presentation atSecond ...
EU4Environment Water and Data - Implementing Partners' presentation atSecond ...EU4Environment Water and Data - Implementing Partners' presentation atSecond ...
EU4Environment Water and Data - Implementing Partners' presentation atSecond ...
 
Fourth IDMP CEE workshop: Increasing soil water holding capacity by Pavol Bi...
Fourth IDMP CEE workshop: Increasing soil water holding capacity by  Pavol Bi...Fourth IDMP CEE workshop: Increasing soil water holding capacity by  Pavol Bi...
Fourth IDMP CEE workshop: Increasing soil water holding capacity by Pavol Bi...
 
12 increasing soil water holding capacity act. 5.1_bielek
12 increasing soil water holding capacity act. 5.1_bielek12 increasing soil water holding capacity act. 5.1_bielek
12 increasing soil water holding capacity act. 5.1_bielek
 
SMEA Presentation1.pptx
SMEA Presentation1.pptxSMEA Presentation1.pptx
SMEA Presentation1.pptx
 
Improved Agricultural Monitoring Systems through satellite imagery for IRAN: ...
Improved Agricultural Monitoring Systems through satellite imagery for IRAN: ...Improved Agricultural Monitoring Systems through satellite imagery for IRAN: ...
Improved Agricultural Monitoring Systems through satellite imagery for IRAN: ...
 

Recently uploaded

如何办理(Wintec毕业证书)怀卡托理工学院毕业证成绩单原件一模一样
如何办理(Wintec毕业证书)怀卡托理工学院毕业证成绩单原件一模一样如何办理(Wintec毕业证书)怀卡托理工学院毕业证成绩单原件一模一样
如何办理(Wintec毕业证书)怀卡托理工学院毕业证成绩单原件一模一样
qyguxu
 
如何办理(UW毕业证书)滑铁卢大学毕业证成绩单原件一模一样
如何办理(UW毕业证书)滑铁卢大学毕业证成绩单原件一模一样如何办理(UW毕业证书)滑铁卢大学毕业证成绩单原件一模一样
如何办理(UW毕业证书)滑铁卢大学毕业证成绩单原件一模一样
qyguxu
 
Abortion pills in Jeddah Saudi Arabia (+966572737505) buy cytotec
Abortion pills in Jeddah Saudi Arabia (+966572737505) buy cytotecAbortion pills in Jeddah Saudi Arabia (+966572737505) buy cytotec
Abortion pills in Jeddah Saudi Arabia (+966572737505) buy cytotec
Abortion pills in Riyadh +966572737505 get cytotec
 
B. A. (Prog.) Political Science 6th Semester 2019.pdf
B. A. (Prog.) Political Science 6th Semester 2019.pdfB. A. (Prog.) Political Science 6th Semester 2019.pdf
B. A. (Prog.) Political Science 6th Semester 2019.pdf
paraspiyush3
 
如何办理(Indiana State毕业证书)印第安纳州立大学毕业证成绩单原件一模一样
如何办理(Indiana State毕业证书)印第安纳州立大学毕业证成绩单原件一模一样如何办理(Indiana State毕业证书)印第安纳州立大学毕业证成绩单原件一模一样
如何办理(Indiana State毕业证书)印第安纳州立大学毕业证成绩单原件一模一样
qyguxu
 
如何办理(PITT毕业证书)匹兹堡大学毕业证成绩单原件一模一样
如何办理(PITT毕业证书)匹兹堡大学毕业证成绩单原件一模一样如何办理(PITT毕业证书)匹兹堡大学毕业证成绩单原件一模一样
如何办理(PITT毕业证书)匹兹堡大学毕业证成绩单原件一模一样
qyguxu
 
Common breast clinical based cases in Tanzania.pptx
Common breast clinical based cases in Tanzania.pptxCommon breast clinical based cases in Tanzania.pptx
Common breast clinical based cases in Tanzania.pptx
JustineNDeodatus
 
如何办理(Galway毕业证书)爱尔兰高威大学毕业证成绩单原件一模一样
如何办理(Galway毕业证书)爱尔兰高威大学毕业证成绩单原件一模一样如何办理(Galway毕业证书)爱尔兰高威大学毕业证成绩单原件一模一样
如何办理(Galway毕业证书)爱尔兰高威大学毕业证成绩单原件一模一样
qyguxu
 
unit-5-final-cn-unit-5-notes-important-questions.pdf
unit-5-final-cn-unit-5-notes-important-questions.pdfunit-5-final-cn-unit-5-notes-important-questions.pdf
unit-5-final-cn-unit-5-notes-important-questions.pdf
radheeshyam1176
 
如何办理(UST毕业证书)圣托马斯大学毕业证成绩单原件一模一样
如何办理(UST毕业证书)圣托马斯大学毕业证成绩单原件一模一样如何办理(UST毕业证书)圣托马斯大学毕业证成绩单原件一模一样
如何办理(UST毕业证书)圣托马斯大学毕业证成绩单原件一模一样
muwyto
 
如何办理(CSU毕业证书)圣马科斯分校毕业证成绩单原件一模一样
如何办理(CSU毕业证书)圣马科斯分校毕业证成绩单原件一模一样如何办理(CSU毕业证书)圣马科斯分校毕业证成绩单原件一模一样
如何办理(CSU毕业证书)圣马科斯分校毕业证成绩单原件一模一样
qyguxu
 

Recently uploaded (20)

如何办理(Wintec毕业证书)怀卡托理工学院毕业证成绩单原件一模一样
如何办理(Wintec毕业证书)怀卡托理工学院毕业证成绩单原件一模一样如何办理(Wintec毕业证书)怀卡托理工学院毕业证成绩单原件一模一样
如何办理(Wintec毕业证书)怀卡托理工学院毕业证成绩单原件一模一样
 
Master SEO in 2024 - The Complete Beginner's Guide
Master SEO in 2024 - The Complete Beginner's GuideMaster SEO in 2024 - The Complete Beginner's Guide
Master SEO in 2024 - The Complete Beginner's Guide
 
如何办理(UW毕业证书)滑铁卢大学毕业证成绩单原件一模一样
如何办理(UW毕业证书)滑铁卢大学毕业证成绩单原件一模一样如何办理(UW毕业证书)滑铁卢大学毕业证成绩单原件一模一样
如何办理(UW毕业证书)滑铁卢大学毕业证成绩单原件一模一样
 
Abortion pills in Jeddah Saudi Arabia (+966572737505) buy cytotec
Abortion pills in Jeddah Saudi Arabia (+966572737505) buy cytotecAbortion pills in Jeddah Saudi Arabia (+966572737505) buy cytotec
Abortion pills in Jeddah Saudi Arabia (+966572737505) buy cytotec
 
Rahul Chauhan - Data Scientist Resume.pdf
Rahul Chauhan - Data Scientist Resume.pdfRahul Chauhan - Data Scientist Resume.pdf
Rahul Chauhan - Data Scientist Resume.pdf
 
B. A. (Prog.) Political Science 6th Semester 2019.pdf
B. A. (Prog.) Political Science 6th Semester 2019.pdfB. A. (Prog.) Political Science 6th Semester 2019.pdf
B. A. (Prog.) Political Science 6th Semester 2019.pdf
 
Crafting an effective CV for AYUSH Doctors.pdf
Crafting an effective CV for AYUSH Doctors.pdfCrafting an effective CV for AYUSH Doctors.pdf
Crafting an effective CV for AYUSH Doctors.pdf
 
Ochsen Screenplay Coverage - JACOB - 10.16.23.pdf
Ochsen Screenplay Coverage - JACOB - 10.16.23.pdfOchsen Screenplay Coverage - JACOB - 10.16.23.pdf
Ochsen Screenplay Coverage - JACOB - 10.16.23.pdf
 
如何办理(Indiana State毕业证书)印第安纳州立大学毕业证成绩单原件一模一样
如何办理(Indiana State毕业证书)印第安纳州立大学毕业证成绩单原件一模一样如何办理(Indiana State毕业证书)印第安纳州立大学毕业证成绩单原件一模一样
如何办理(Indiana State毕业证书)印第安纳州立大学毕业证成绩单原件一模一样
 
如何办理(PITT毕业证书)匹兹堡大学毕业证成绩单原件一模一样
如何办理(PITT毕业证书)匹兹堡大学毕业证成绩单原件一模一样如何办理(PITT毕业证书)匹兹堡大学毕业证成绩单原件一模一样
如何办理(PITT毕业证书)匹兹堡大学毕业证成绩单原件一模一样
 
Common breast clinical based cases in Tanzania.pptx
Common breast clinical based cases in Tanzania.pptxCommon breast clinical based cases in Tanzania.pptx
Common breast clinical based cases in Tanzania.pptx
 
如何办理(Galway毕业证书)爱尔兰高威大学毕业证成绩单原件一模一样
如何办理(Galway毕业证书)爱尔兰高威大学毕业证成绩单原件一模一样如何办理(Galway毕业证书)爱尔兰高威大学毕业证成绩单原件一模一样
如何办理(Galway毕业证书)爱尔兰高威大学毕业证成绩单原件一模一样
 
unit-5-final-cn-unit-5-notes-important-questions.pdf
unit-5-final-cn-unit-5-notes-important-questions.pdfunit-5-final-cn-unit-5-notes-important-questions.pdf
unit-5-final-cn-unit-5-notes-important-questions.pdf
 
Rachel_Ochsenschlager_Resume_May_2024.docx
Rachel_Ochsenschlager_Resume_May_2024.docxRachel_Ochsenschlager_Resume_May_2024.docx
Rachel_Ochsenschlager_Resume_May_2024.docx
 
如何办理(UST毕业证书)圣托马斯大学毕业证成绩单原件一模一样
如何办理(UST毕业证书)圣托马斯大学毕业证成绩单原件一模一样如何办理(UST毕业证书)圣托马斯大学毕业证成绩单原件一模一样
如何办理(UST毕业证书)圣托马斯大学毕业证成绩单原件一模一样
 
We’re looking for a Technology consultant to join our Team!
We’re looking for a Technology consultant to join our Team!We’re looking for a Technology consultant to join our Team!
We’re looking for a Technology consultant to join our Team!
 
Navigating the Tech Industry Journey GDSC UNIDEB
Navigating the Tech Industry Journey GDSC UNIDEBNavigating the Tech Industry Journey GDSC UNIDEB
Navigating the Tech Industry Journey GDSC UNIDEB
 
LinkedIn For Job Search Presentation May 2024
LinkedIn For Job Search Presentation May 2024LinkedIn For Job Search Presentation May 2024
LinkedIn For Job Search Presentation May 2024
 
We’re looking for a junior patent engineer to join our Team!
We’re looking for a junior patent engineer to join our Team!We’re looking for a junior patent engineer to join our Team!
We’re looking for a junior patent engineer to join our Team!
 
如何办理(CSU毕业证书)圣马科斯分校毕业证成绩单原件一模一样
如何办理(CSU毕业证书)圣马科斯分校毕业证成绩单原件一模一样如何办理(CSU毕业证书)圣马科斯分校毕业证成绩单原件一模一样
如何办理(CSU毕业证书)圣马科斯分校毕业证成绩单原件一模一样
 

MID-TERM REVIEW TSS.pptx

  • 1. MID-TERM REVIEW TECHNICAL SUPPORT SERVCRES PROGRAM 14 January 2022
  • 2. Overview ABSTRACT • Research Activities: • Development Activities • Total STATUS as of 31 Dec 2021 • Completed: • On-going: • At risk:
  • 3. 1. Study on cropping intensity in Sarpang Target: Within April 2022 Status = Ongoing Survey and data compilation completed. Currently Report Writing 2. Compilation and publication of annual report for FY 2021-22 Status: Completed Compilation and Review. Submitted to management. Office copy will be printed along with other materials.
  • 4. 1. Rice Yield Gap Analysis in Sarpang Target: Within May 2022 Status: On-going Questionnaire and literature review completed. On station and demonstration yield data collected. Survey will be carried out in February after completion of threshing. 2. Performance assessment of scientific demo orchard established by ARDC Samtenling Target: June 2022 Status: On-going Data template developed. Field assessment will be carried out in January 3rd week in collaboration with HP.
  • 5. 1. Study on fallow land status in Sarpang, Samtse and Samdrup Jongkhar; challenges and prospectus Due to intensive data collection and movement restriction, the activity can’t be carried out in this FY. 2. Preparation, Review and Assessment of APA for FY 2021-22 Within 7th July 2022 Status: On going Mid Term Review Completed on 28th December 2022.
  • 6. RC Budget: Approved: Nu.0.1m Expenditure: Nu.0.04 % Budget Utilization = 40%
  • 7. Plant Protection Approved Budget 1. RGoB: 0.080M • Expenditure: 0.025M (Adv- 6000)~31% 2. FSAPP: 0.100M • Expenditure: 3. NoFP Deposit: 0.124+0.230=0.354 4. NPPC (AFACI) Deposit: 0.085+0.075=0.160 Total Budget: 0.694
  • 8. 1. Evaluation of organic pesticides and botanicals in management of mites in chilli Target: Activity completed and report submitted by last week of May, 2022 Status: Ongoing 2. Evaluation of biopesticides and plant extracts against rice earhead bug (Leptocorisa spp. Fabricius) under rainfed ecosystem of Samtenling. Target: Activity completed and report submitted by third week of February, 2022 Status: Activities completed and report writing APA Activities
  • 9. 3. Demonstration on Integrated Pest management in Chilli (Common pests and disease management in chilli- phythopthora, mites and aphids) Target: Within 2nd week of June 2022 Status: Ongoing 4. Study on pest and disease resistance of 36 lines of irrigated rice introduced from IRRI (INGER 2019) Target: Within 2nd week of Feb 2022 Status: Completed APA Activities
  • 10. 5. Evaluation of eco- friendly control methods using locally available plants and materials for red ant (Dorylus orientalis Westwood) of potato in naturally infested field at ARDC Samtenling Target: Within 1st week of June 2022 Status: Ongoing APA Activities
  • 11. 1. Monitoring of plant and leaf hoppers in paddy using light traps Target: within 4th week of February 2022 Status: Completed 2. Evaluation of biopesticides and botanical extracts against major pests of cole crops (NCT) Target: within 2nd week of June 2022 Status: Ongoing Non APA Activities
  • 12. 3. Monitoring of Fall armyworm using pheromone traps Status: On going 4. Evaluation of different synthetic and botanical pesticides against fall army worm (Spodoptera frugiperda) Status: Ongoing Non APA Activities
  • 13. 5. Construction of biopesticide utility shed Status: ongoing Non APA Activities