KOTA SUPER THERMAL POWER STATION
(Kota) Delivered by:-
Krishn Kumar
Assistant Professor
Electical Engg Dept.
R N MODI ENGINEERING COLLEGE
RAJASTHAN TECHNICAL UNIVERSITY, KOTA
Mechanical Energy Electrical Energy
1.Thermal Station: - The turbine is rotated by steam which is
produced by the heat generated by burning fuel in boiler e
THERMAL POWER PLANT
 The coal is brought and crushed to powder. This is feed to Boiler for producing heat
 In Boiler the water is converted to steam.
 In Super heater the moisture content is removed from the steam and that steam is called
super heated steam
 The superheated steam rotates the shaft of the High pressure turbine
 The Exhausted steam is sent to preheater and the steam then rotates the Intermediate
pressure(IP) Turbine
 The steam from the IP turbine is then feed to low pressure turbine.
 The turbine shaft is connected to the Generator, which produces Electric Power.
 The power generated is then Transmitted.
KOTA SUPER THERMAL POWER PLANT
Ideally on the left
Bank of Chambal at up
stream of kota barrage
LAND
Land measuring
approx 250
hectare was
required for the
project
in 1976.
COAL
Coal India ltd supply
coal from its coal
producing
Subsidiaries
BCCL,SECL.ECL
Through railways
wagons.
WATER
The source of water
for power station
is reservoir formed
by Kota Barrage
On the Chambal
river.
Stage -1
2*110 MW
Stage-2
2*210 MW
Stage-3
1*210 MW
Stage-4
1*195 MW
Stage-5
1*195 MW
Net power generation= 1240 MW
Coal handling plant
D-M Water plant
Boiler
Turbine
Generator
Ash Handling plant
Switch Yard
Raw Coal Wagon- Coal is brought to the site through a
Wagon as per requirement.
Wagon tippler-The coal is unloaded from the Wagon
and is transported to crushers and for
storage place through conveyor.
Junction tower- JT’s are used where the conveyor has
any angular deviation.
Primary Crusher-The Raw coal is crushed into fine
pieces to 45mm grit). Primary crusher is also
called Rotary Breaker since the coal is
crushed by a rotating plate.
Secondary Crusher-The fine pieces of coal is crushed to
powder (to 25mm grit)
Rejected- The
stones and
unwanted coal
is rejected
Coal Handling Plant
Two way conveyor
Junction Tower
Mill Bunker-The 25mm grit coal is crushed into very fine
powder for feeding the boiler. We will have a spare
Bunker for each Boiler.
BOILER
Water in a Power Plant is used for
1. Production of Steam- for rotating turbine.
2. Cooling Purpose- For cooling of various equipment .
Water is recycled and used for various purpose:-Principal problem in HP Boiler is corrosion are
steam impurities these impurities form deposit over
turbine blades.
Raw
Water
Purified
DM
water
For
cooling
purpose
Steam
Conden
ser
Reservoir
Water Clarification
DM Plant
(Demineralized Plant)
Chlorification
&
Filtration
Various Equipment
Cooling Water
Cooling Tower
CT
Auxiliary cooling
Water (ACW)
DMCWP
DMCW Demineralized
cooling Water
CWP
CT CWP CWP
Condenser
Boiler
Steam
water
Cool water
Hot water
Hot Well
Dearator
25D  35D
25D  20D
PHE
Various Equipment
D-Degrees
CWP-cooling water Pump
PHE-Pre heat Exchange
Water Cycle
Flue gases
Boiler water tubes
& various stages
Boiler
furnace
Pulverized
coal
Air from
environment
via draft fans
Ash
handling
plant
DM water
Super
heated
steam
stack
BOILER:-
 The Boiler are capacity steam
generators used purely for
the steam power generation.
 In boiler heat energy is
Released from the combustion
of fossil fuel and heat is
Transferred to different fluids
In the system .
Technical specification-
 Type
 Make
 Capacity
 Steam pressure
 Efficiency
 Steam temperature
tangentially fired natural
circulation
Balanced draft water tube boiler
BHEL
375 tons per hour
139 kg/sq. cm
86.6%
540 deg.
The various heat transfer section in boiler –
 furnace
 Super heater & Reheater
 Economiser
In a Thermal Power Plant generally 3 turbines are used to increase the efficiency.
 High Pressure Turbine(HPT): The superheated steam is directly fed to this turbine to rotate it.
 Intermediate Pressure Turbine(IPT): The out put from the HPT is reheated in a reheater(RH) and used to
rotate IPT .
 Low Pressure Turbine(LPT): The Exhausted steam from the IPT is directly fed to rotate the shaft of LPT.
Condenser
HPT IPT LPT
RH
Steam
Super
Heater
Generator
Steam
Shaft
*All the turbines are connected to a single shaft which is connected to the Generator.
Turbine is a m/c which shaft is rotated steadily by impact of steam upon blades of turbine.
It converts heat energy into mechanical energy.
Two pole
Synchronous
generator
Rotation
speed
Of 3000 rpm
Of 50 Hz.
H2 gas
For
cooling
Star- delta
connection
The Synchronous Generator is used to Generate power by connecting the shaft of the Turbine to the shaft of the
generator which cuts the magnetic flux producing Emf.
 The Generated Voltage will generally 11KV to 20 KV max.
 The Generated Voltage is stepped up by connecting Step up transformer and is transmitted and is also used
for Auxiliary purposes.
Bus Duct
Generator
Transformer
20KV to 400KV
SYNCHRONOUS
GENERATOR
UAT
20Kv to 6.KV
Unit Auxiliary Transformer: This transformer is used to step down the produced voltage and use
for Auxiliary purpose.
Syncronization- Bring speed of 3000rpm ,voltage is slowly built up.
1)Voltage 2)frequency 3)phase displacement
4)Waveform 5) phase sequence
The Ash from the boiler is collected in two forms:
1. Bottom Ash(Slurry):It’s a waste which is dumped into a Ash Pond
2. Fly ash: Fly ash is separated from Flue Gases in ESP(Electro static
Precipitator).
Fly Ash
& Flue
Gases
Economizer ESP
Bottom
ash(wet ash)
Ash Pond
Boiler
Cylo
Cement
Factory
Economizer : Reduces the temperature
Chimney
Fly ash
Flue Gases
Flue Gases
 Air pollution preventing equipment.
 It is used to extract suspended particles from flue gases.
 TWO 220 kv bus bar have been provided in switchyard and are inter connected through
A bus coupler
It consist of several part-
o Bus bar
o Circuit breaker
o Current Transformer
(C.T.)
o Lightning Arresters
o Potential Transformer
(P.T.)
o Isolator
Whenever maintanace or repaire work is to be
carried out on equipment in swichyard it is
disconnected from suppy isolation
ISOLATOR IN CLOSED CONDITION
 LA also called the surge diverter.
 Connected between line & earth i.e. in
parallel with equipment.
It provides the low resistance path to the
lightning and switching over current.
LA is the first and last equipment in any
switchyard.
INSULATOR:-
Used to provide the proper
Insulation.
The current transformer is used to
measure the current in power line.
 Dampers are used to prevent
the vibration in power line.
 It converts the vibrational
energy into relative motion of
dampers.
STOCKBRIDGE DAMPER
Fan control-
 Primary Air fan
 Furnace pressure
 Force draft fan
 Induced draft fan
Turbine control-
 Pressure control
 Load control
 Speed control
Fuel control-
 Coal ,oil flow,
 oil pressure
 Flow of air control
Generator control-
 Stator ,rotor temperature
 For stator cooling
a) H2 pressure b) H2o pressure
Steam and water control-
 Drum level control
 Flow of steam & water
 Pressure of steam and water
 Temperature of steam and
water
presentation_thermal_power_plant_1447503788_165600.pptx

More Related Content

Similar to presentation_thermal_power_plant_1447503788_165600.pptx

Similar to presentation_thermal_power_plant_1447503788_165600.pptx (20)

Ntpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyardNtpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyard
 
Harsh ntpc
Harsh ntpcHarsh ntpc
Harsh ntpc
 
kstps training report
kstps training reportkstps training report
kstps training report
 
Coal Base Thermal Power Plant
Coal Base Thermal Power PlantCoal Base Thermal Power Plant
Coal Base Thermal Power Plant
 
Ntpc ppt complete
Ntpc ppt completeNtpc ppt complete
Ntpc ppt complete
 
Kota super thermal power station, kota
Kota super thermal power station, kotaKota super thermal power station, kota
Kota super thermal power station, kota
 
Attachment.doc
Attachment.docAttachment.doc
Attachment.doc
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
KTPS
KTPSKTPS
KTPS
 
rajwest thermal power plant
rajwest thermal power plantrajwest thermal power plant
rajwest thermal power plant
 
Pm ppt
Pm pptPm ppt
Pm ppt
 
panki power plant training.ppt
panki power plant training.pptpanki power plant training.ppt
panki power plant training.ppt
 
Dev
DevDev
Dev
 
MTPS Bappa main
MTPS Bappa mainMTPS Bappa main
MTPS Bappa main
 
Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01
 
Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01
 
Thermal power point
Thermal power pointThermal power point
Thermal power point
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT
 
compalete file 2023 (AutoRecovered).docx
compalete file 2023 (AutoRecovered).docxcompalete file 2023 (AutoRecovered).docx
compalete file 2023 (AutoRecovered).docx
 
suratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavsuratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadav
 

More from rajam575648

corona on transmission lines
corona on transmission linescorona on transmission lines
corona on transmission linesrajam575648
 
Transmission_Lines.pptx
Transmission_Lines.pptxTransmission_Lines.pptx
Transmission_Lines.pptxrajam575648
 
ENGINEERING.pptx
ENGINEERING.pptxENGINEERING.pptx
ENGINEERING.pptxrajam575648
 
PAPER ID 107.pptx
PAPER ID 107.pptxPAPER ID 107.pptx
PAPER ID 107.pptxrajam575648
 
Alumni_Success_Story_EN.pptx
Alumni_Success_Story_EN.pptxAlumni_Success_Story_EN.pptx
Alumni_Success_Story_EN.pptxrajam575648
 
Power Generation-10n.ppt
Power Generation-10n.pptPower Generation-10n.ppt
Power Generation-10n.pptrajam575648
 

More from rajam575648 (6)

corona on transmission lines
corona on transmission linescorona on transmission lines
corona on transmission lines
 
Transmission_Lines.pptx
Transmission_Lines.pptxTransmission_Lines.pptx
Transmission_Lines.pptx
 
ENGINEERING.pptx
ENGINEERING.pptxENGINEERING.pptx
ENGINEERING.pptx
 
PAPER ID 107.pptx
PAPER ID 107.pptxPAPER ID 107.pptx
PAPER ID 107.pptx
 
Alumni_Success_Story_EN.pptx
Alumni_Success_Story_EN.pptxAlumni_Success_Story_EN.pptx
Alumni_Success_Story_EN.pptx
 
Power Generation-10n.ppt
Power Generation-10n.pptPower Generation-10n.ppt
Power Generation-10n.ppt
 

Recently uploaded

GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 

Recently uploaded (20)

GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 

presentation_thermal_power_plant_1447503788_165600.pptx

  • 1. KOTA SUPER THERMAL POWER STATION (Kota) Delivered by:- Krishn Kumar Assistant Professor Electical Engg Dept. R N MODI ENGINEERING COLLEGE RAJASTHAN TECHNICAL UNIVERSITY, KOTA
  • 2. Mechanical Energy Electrical Energy 1.Thermal Station: - The turbine is rotated by steam which is produced by the heat generated by burning fuel in boiler e THERMAL POWER PLANT
  • 3.  The coal is brought and crushed to powder. This is feed to Boiler for producing heat  In Boiler the water is converted to steam.  In Super heater the moisture content is removed from the steam and that steam is called super heated steam  The superheated steam rotates the shaft of the High pressure turbine  The Exhausted steam is sent to preheater and the steam then rotates the Intermediate pressure(IP) Turbine  The steam from the IP turbine is then feed to low pressure turbine.  The turbine shaft is connected to the Generator, which produces Electric Power.  The power generated is then Transmitted.
  • 4. KOTA SUPER THERMAL POWER PLANT Ideally on the left Bank of Chambal at up stream of kota barrage LAND Land measuring approx 250 hectare was required for the project in 1976. COAL Coal India ltd supply coal from its coal producing Subsidiaries BCCL,SECL.ECL Through railways wagons. WATER The source of water for power station is reservoir formed by Kota Barrage On the Chambal river.
  • 5. Stage -1 2*110 MW Stage-2 2*210 MW Stage-3 1*210 MW Stage-4 1*195 MW Stage-5 1*195 MW Net power generation= 1240 MW
  • 6. Coal handling plant D-M Water plant Boiler Turbine Generator Ash Handling plant Switch Yard
  • 7. Raw Coal Wagon- Coal is brought to the site through a Wagon as per requirement. Wagon tippler-The coal is unloaded from the Wagon and is transported to crushers and for storage place through conveyor. Junction tower- JT’s are used where the conveyor has any angular deviation. Primary Crusher-The Raw coal is crushed into fine pieces to 45mm grit). Primary crusher is also called Rotary Breaker since the coal is crushed by a rotating plate. Secondary Crusher-The fine pieces of coal is crushed to powder (to 25mm grit) Rejected- The stones and unwanted coal is rejected Coal Handling Plant
  • 8. Two way conveyor Junction Tower Mill Bunker-The 25mm grit coal is crushed into very fine powder for feeding the boiler. We will have a spare Bunker for each Boiler. BOILER
  • 9. Water in a Power Plant is used for 1. Production of Steam- for rotating turbine. 2. Cooling Purpose- For cooling of various equipment . Water is recycled and used for various purpose:-Principal problem in HP Boiler is corrosion are steam impurities these impurities form deposit over turbine blades. Raw Water Purified DM water For cooling purpose Steam Conden ser
  • 10. Reservoir Water Clarification DM Plant (Demineralized Plant) Chlorification & Filtration Various Equipment Cooling Water Cooling Tower CT Auxiliary cooling Water (ACW) DMCWP DMCW Demineralized cooling Water CWP CT CWP CWP Condenser Boiler Steam water Cool water Hot water Hot Well Dearator 25D  35D 25D  20D PHE Various Equipment D-Degrees CWP-cooling water Pump PHE-Pre heat Exchange Water Cycle
  • 11. Flue gases Boiler water tubes & various stages Boiler furnace Pulverized coal Air from environment via draft fans Ash handling plant DM water Super heated steam stack
  • 12. BOILER:-  The Boiler are capacity steam generators used purely for the steam power generation.  In boiler heat energy is Released from the combustion of fossil fuel and heat is Transferred to different fluids In the system . Technical specification-  Type  Make  Capacity  Steam pressure  Efficiency  Steam temperature tangentially fired natural circulation Balanced draft water tube boiler BHEL 375 tons per hour 139 kg/sq. cm 86.6% 540 deg. The various heat transfer section in boiler –  furnace  Super heater & Reheater  Economiser
  • 13. In a Thermal Power Plant generally 3 turbines are used to increase the efficiency.  High Pressure Turbine(HPT): The superheated steam is directly fed to this turbine to rotate it.  Intermediate Pressure Turbine(IPT): The out put from the HPT is reheated in a reheater(RH) and used to rotate IPT .  Low Pressure Turbine(LPT): The Exhausted steam from the IPT is directly fed to rotate the shaft of LPT. Condenser HPT IPT LPT RH Steam Super Heater Generator Steam Shaft *All the turbines are connected to a single shaft which is connected to the Generator. Turbine is a m/c which shaft is rotated steadily by impact of steam upon blades of turbine. It converts heat energy into mechanical energy.
  • 14. Two pole Synchronous generator Rotation speed Of 3000 rpm Of 50 Hz. H2 gas For cooling Star- delta connection
  • 15. The Synchronous Generator is used to Generate power by connecting the shaft of the Turbine to the shaft of the generator which cuts the magnetic flux producing Emf.  The Generated Voltage will generally 11KV to 20 KV max.  The Generated Voltage is stepped up by connecting Step up transformer and is transmitted and is also used for Auxiliary purposes. Bus Duct Generator Transformer 20KV to 400KV SYNCHRONOUS GENERATOR UAT 20Kv to 6.KV Unit Auxiliary Transformer: This transformer is used to step down the produced voltage and use for Auxiliary purpose. Syncronization- Bring speed of 3000rpm ,voltage is slowly built up. 1)Voltage 2)frequency 3)phase displacement 4)Waveform 5) phase sequence
  • 16. The Ash from the boiler is collected in two forms: 1. Bottom Ash(Slurry):It’s a waste which is dumped into a Ash Pond 2. Fly ash: Fly ash is separated from Flue Gases in ESP(Electro static Precipitator). Fly Ash & Flue Gases Economizer ESP Bottom ash(wet ash) Ash Pond Boiler Cylo Cement Factory Economizer : Reduces the temperature Chimney Fly ash Flue Gases Flue Gases
  • 17.  Air pollution preventing equipment.  It is used to extract suspended particles from flue gases.
  • 18.  TWO 220 kv bus bar have been provided in switchyard and are inter connected through A bus coupler It consist of several part- o Bus bar o Circuit breaker o Current Transformer (C.T.) o Lightning Arresters o Potential Transformer (P.T.) o Isolator
  • 19. Whenever maintanace or repaire work is to be carried out on equipment in swichyard it is disconnected from suppy isolation ISOLATOR IN CLOSED CONDITION
  • 20.  LA also called the surge diverter.  Connected between line & earth i.e. in parallel with equipment. It provides the low resistance path to the lightning and switching over current. LA is the first and last equipment in any switchyard. INSULATOR:- Used to provide the proper Insulation.
  • 21. The current transformer is used to measure the current in power line.  Dampers are used to prevent the vibration in power line.  It converts the vibrational energy into relative motion of dampers. STOCKBRIDGE DAMPER
  • 22. Fan control-  Primary Air fan  Furnace pressure  Force draft fan  Induced draft fan Turbine control-  Pressure control  Load control  Speed control Fuel control-  Coal ,oil flow,  oil pressure  Flow of air control Generator control-  Stator ,rotor temperature  For stator cooling a) H2 pressure b) H2o pressure Steam and water control-  Drum level control  Flow of steam & water  Pressure of steam and water  Temperature of steam and water