2. A project to construct an assembly line is nearly complete. The project manager closes
procurements, shares the final project report, updates the lessons learned repository, and obtains
feedback from the relevant stakeholders.
What should the project manager do next?
A. Provide final payment to the suppliers
B. Send a summary of how the final product achieved the business needs
C. Transfer the completed assembly line to operations
D. Send formal written notice to the vendors that the contracts have been completed
HINT: All but one of the answer choices have already been completed in the scenario.
Question
3. Among the available choices, only transferring the completed assembly line to operations
represents a closing activity which has yet to be completed, making it the best response to the
question asked.
The correct answer is C.
The question implies that the Close Project or Phase process is underway. Actions and activities
necessary to transfer the project's products, services, or results to the next phase or production
and/or operations is one aspect of project closure.
Correctly answering this question is an exercise in the process of elimination. The incorrect
answer choices represent activities that have already been completed by the project manager in
this scenario.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.