SlideShare a Scribd company logo
1 of 7
UNIVERSITY OF BOTSWANA
Kagiso T. Lobeko
201000126
Assignment 1
9/8/2014
CBB 512 Construction Management I
Question 1 (a)
The tender price sets out the way in which the design team and client wish to review the breakdown
of the overall tender price provided by tendering contractors. It is generally prepared by cost
consultants (often quantity surveyors). (Buildings, 2014)
• Enable like for like comparison between tenders and the cost plan.
• Enable the cost consultant to assess where value lies within the different tenders (such as
roofing or water reticulation) allowing assessment of value for money.
• Identify any significant differences in pricing between tenderers to ensure the design has
been correctly interpreted.
• Identify areas of savings that might be negotiated with tenderers while still in competition.
• Form the financial basis of the tender report.
Question 1 (b)
Prime Cost Sum reflects the material allowance being made in the rate for a specific item. A quoted
rate normally consists of Material, Labour, Plant and mark-up (profit + overheads). By using the PC
sum reference the builder identifies what material sum he has allowed for in his rate. This is
normally done when the specification of the item has not yet been clarified (for example finishes,
tiles, taps, light fittings, etc.). The builder would allow a reasonably accepted average cost for that
item which is generally based on the builders past experience.
Provisional Sums on the other hand are estimated allowances for work that involves both supply of
material, labour and associated work. This normally involves a specialist subcontractor for example;
an allowance for the installation of new Kitchen cupboards. The builder may base his allowance on
an average market rate per metre of identified cupboard space. However, the final price will be
based on an agreed design and finishes as prepared by a specialist. Once agreed the Builder will be
entitled to add his agreed mark-up percentage to the subcontractor quotation.
Reasons for inclusion:
• More changes in scope of works and variations can be accommodated
• It reduces conflicts as in the occasion of undefined provisional sums client is taking
the risk for the works and the contractor may be entitled to an extension of time and
additional payments
• It protects the client from over pricing by the contractor as they are required to provide
receipts and invoices from the sub-contractor engaged
• The quality of work is not compromised as the contractor concentrates on their area of
expertise and works outside their area of expertize are implemented by specialists
2
Question 1 (c)
The method related charges is defined as a charge entered by the contractor to cover items of work
related to the intended method of executing the work, the costs of which are not proportional to the
quantities.
When the method related charges method is correctly used the following come as a result:
• There are fewer disputes regarding changes
• Payment is more realistic
• The use of method related charges increase the change in scope of works that can be
accommodated
• it provides the contractor with room to be innovative in terms methods of construction as
they have the budget to explore various construction techniques
• it reduces chances of delayed construction as the contractor can get access to equipment
that will fast track and simplify the construction process
Question 1 (d)
Method specification also known as recipe specification describes to the contractor the equipment,
material and procedure that they should use. When using this form of specification a supervising
agency commonly referred to as a consultant is obligated to monitor every aspect of the contractors
field operations and as such takes the responsibility for the outcome. It reduces job delays, contract
claims and escalation of future bid prices by ensuring the job is done right the first time.
Disadvantages are this method tends to stifle contractor innovation. Since a contractor’s only
motivation is instructional compliance, there is virtually no incentive to develop better, more
efficient construction methods. Second, since they are not statistically based and 100 percent
compliance is usually not possible, method specifications usually required “substantial compliance,”
a purposely vague and undefined term that can lead to disputes. (Interactive, 2009)
An end-result specification is one in which the final characteristics of the product are stipulated, and
the contractor is given considerable freedom in achieving those characteristics. In their roughest
form, the client will specify minimum, maximum or a range of values for any given characteristic and
base acceptance on conformance to these specifications; they do not rely on the nebulous
“substantial compliance” because they clearly define acceptable quality. The weakness of the end
result specification include the inability to identify or measure essential performance related
characteristics, the inability to quantify substantial compliance and to determine price adjustment
factors that relate to reduced or enhanced value and the uncertainty as to value to be gained from
the cost implementing statistically based end result specifications. (Smith, 1998)
Question 1 (e)
3
The Engineer shall be responsible for the enforcement and proper administration of the contract and
shall, with due care and diligence, carry out:
(i) The supervision of construction
(ii) The testing and commission of the works
(iii) The periodic and final account of the works
(iv) The resolution of disputes (first instance). The Engineer shall also be responsible for all
communications to the Contractor except where the contract expressly provides for
instructions to be given by the Employer.
Question 1 (f)
An estimate for construction work can be defined as the process of calculating the quantities and
costs of the various items needed in connection with the work; it is produced by the Estimator in
conjunction with the pre-contract Tendering team. They come up with it from information provided
by the Client to the Architect and Quantity Surveyor and investigations and planning carried out by
the team. The estimate is a net estimated cost of carrying out the work. (Gateway)
A tender is a written bid submitted by a Contractor to a Client in pursuance of the notification given,
to execute certain work at calculated rates with the terms and conditions laid down in the tender
documents.
Question 2 (a)
Writing an accurate job description involves breaking the job down in to its component parts and
defining the key objectives.
The purpose of the job description is to:
• Detail the purpose, tasks and responsibilities of the post
• Enable jobseekers to read about the position before applying for it
• Use as a reference when short listing and interviewing applicants
• Assist with organising and designing the new staff member’s induction and training program
• Use in appraisals as an ongoing tool throughout the employment
The person specification details the necessary skills, qualifications, experience or other attributes
needed to carry out the job.
The purpose of the person specification is to:
• Detail what the person needs to fulfil the requirements of the position by providing a profile
of the skills and knowledge considered essential and desirable.
• It forms the basis for the advertisement i.e. where and how to advertise
4
• Provide information that enables job seekers to match themselves to the job role before
applying
• Provide a basis for shortlisting applicants
• Provide the interview panel with the selection of criteria by which to assess the best
candidate for the role
• Assist with organising and designing the new staff member’s induction and training program
Question 2 (b)
Negative Motivation
Negative motivation techniques focus on the consequences of underperforming and failing
to meet goals, as opposed to positive motivation, where the focus is on the benefits of
superior performance.
The danger of using negative motivation is the lack of morale that will ensue. Employees will
detest going to work because their day is filled with constant threats of punishment.
Ultimately, they will reach the limit of their ability to handle the constant negative barrage
and either rebel or seek work elsewhere. Using negative reinforcement undoubtedly
shortens the retention rate of your workforce, leaving you constantly searching for
replacements. Employee loyalty will not exist in an environment where superior
performance goes unrewarded and unrecognized while sub-par performance is instead
highlighted as negative reinforcement. (Gambone, 2014)
Frustration Reduction
• Managers can ensure that regular feedback is obtained between themselves and
employees regarding performance. They should let staff members know where they
stand in terms of accomplishing goals. If they have made some wrong turns, explain
when and where they went off track.
• Managers should set up an environment of openness, in which management will
listen to and act upon employees’ ideas and suggestions.
• Managers should ensure that employees have the information, tools, equipment,
supplies, and assistance they need to perform their jobs.
• Managers should give consistent organizational support for training
and development opportunities and encourage employees to use those
opportunities.
• Employee should be given a high level of freedom for how results are achieved
Question 2 (c)
5
The linear model views communication as a one-way or linear process in which the speaker
speaks and the listener listens. This model does not allow for feedback or comments from
the listener. It is commonly used in the army where are higher ranking officer gives
instructions or orders to a lower ranking officer for him to implement no questions asked.
Interactive model where the receiver or listener provides feedback to the sender or speaker.
The speaker or sender of the message also listens to the feedback given by the receiver or
listener. Both the speaker and the listener take turns to speak and listen to each other.
Feedback is given either verbally or non-verbally, or in both ways.
Question 2 (d)
• Employee Trust
Clear, open communication can create a sense of transparency in your organization, which
builds trust between levels of employees. Where keeping employees in the dark can result
in resentments, tension, and a feeling of low job security, strong communication can help
them feel valued and trusted. Open communication can reduce feelings of uncertainty and
cluelessness about the state of the company, which makes for a more-positive work
environment and staff who feel secure and safe.
• Relationships
Communication is essential to building relationships between staff members and between
levels of employees, both on a professional and social level. An atmosphere of open
communication makes it safe for employees to express their ideas; as a result, you will have
the benefit of your staff's combined experience in coming up with innovative solutions.
Communication prevents employees from feeling isolated, builds teamwork, and creates a
more collegial atmosphere in the office. When relationships are strong, employees are
better able to trust one another and work together more effectively.
• Clarity
In an organization, confusion and ambiguity can create negative feelings and a tense
atmosphere. By making roles and responsibilities clear to everyone on staff, you can give
your employees the information they need to get their jobs done; this is particularly
important when your employees are dispersed or come from different backgrounds.
Communication reduces misunderstandings and cuts the costs associated with mistakes.
• Collaboration
6
Communication can help your employees collaborate effectively, which will make for a
more-productive team overall. When you have multiple departments who are working on
different facets of the same project, communication can streamline the process and
improve the end result. When your staff talks openly to each other, they can communicate
potential issues, requirements and feedback that can make the result stronger.
Communication can ensure that everyone is on the same page and prevent problems down
the road.
Bibliography
1. Buildings, D. (2014, May 17). Designing Buildings Ltd. Retrieved September 7, 2014, from
Designing Buildings : http://www.designingbuildings.co.uk/wiki/Tender_pricing_document
2. Gambone, G. (2014). Demand Media. Retrieved September 7, 2014, from Small Bussiness:
http://smallbusiness.chron.com/use-negative-motivation-workplace-16692.html
3. Gateway, C. L. (n.d.). Construction Learning Gateway. Retrieved from Estimating &
Measuring Work.
4. Interactive, P. (2009, June 5). Pavement Interactive. Retrieved September 7, 2014, from
Pavement Interactive: http://www.pavementinteractive.org/article/end-result-
specifications/
5. Smith, G. R. (1998). State DOT Management Techniques for Materials and Construction
Acceptance. Arizona: Transportation Research Board.
7

More Related Content

What's hot

Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Sow Wei Henn
 
Unit 9 - Measurung & Estimating & Tendering Process.pdf
Unit 9 - Measurung & Estimating & Tendering Process.pdfUnit 9 - Measurung & Estimating & Tendering Process.pdf
Unit 9 - Measurung & Estimating & Tendering Process.pdfmuhammadadli28
 
Guide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on ProcurementGuide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on ProcurementSarah Fox
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriaNewman Jonathan
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
The Art of Planning and Writing Specifications and Requirements
The Art of Planning and Writing Specifications and Requirements The Art of Planning and Writing Specifications and Requirements
The Art of Planning and Writing Specifications and Requirements Thomas Tanel
 
Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and schedulingsmumbahelp
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Project Procurment Management
Project Procurment ManagementProject Procurment Management
Project Procurment ManagementSaad Al Jabri
 
Planning can we do with out it?
Planning can we do with out it?Planning can we do with out it?
Planning can we do with out it?Catherine Bendell
 
Procurment Management
Procurment ManagementProcurment Management
Procurment Managementwellanet
 

What's hot (20)

Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Unit 9 - Measurung & Estimating & Tendering Process.pdf
Unit 9 - Measurung & Estimating & Tendering Process.pdfUnit 9 - Measurung & Estimating & Tendering Process.pdf
Unit 9 - Measurung & Estimating & Tendering Process.pdf
 
A lecture on CCP Certificate
A lecture on CCP CertificateA lecture on CCP Certificate
A lecture on CCP Certificate
 
Guide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on ProcurementGuide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on Procurement
 
9. project procurement management
9. project procurement management9. project procurement management
9. project procurement management
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Common contract types
Common contract typesCommon contract types
Common contract types
 
The Art of Planning and Writing Specifications and Requirements
The Art of Planning and Writing Specifications and Requirements The Art of Planning and Writing Specifications and Requirements
The Art of Planning and Writing Specifications and Requirements
 
Contract closing ppt
Contract closing pptContract closing ppt
Contract closing ppt
 
Contract management
Contract managementContract management
Contract management
 
Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and scheduling
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
 
PMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost ManagementPMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost Management
 
TQM QFD
TQM QFDTQM QFD
TQM QFD
 
Project Procurment Management
Project Procurment ManagementProject Procurment Management
Project Procurment Management
 
Planning can we do with out it?
Planning can we do with out it?Planning can we do with out it?
Planning can we do with out it?
 
Type of Contracts.
Type of Contracts.Type of Contracts.
Type of Contracts.
 
Procurment Management
Procurment ManagementProcurment Management
Procurment Management
 

Viewers also liked

USB Video Production Studios
USB Video Production StudiosUSB Video Production Studios
USB Video Production StudiosPaul Richards
 
Radio Waves beyond Broadcasting
Radio Waves beyond BroadcastingRadio Waves beyond Broadcasting
Radio Waves beyond Broadcastingchde
 
Who Were the Beatles?
Who Were the Beatles?Who Were the Beatles?
Who Were the Beatles?chde
 
Radio Waves Presentation
Radio Waves PresentationRadio Waves Presentation
Radio Waves PresentationGoonerMiles
 
Uses Of Radio Waves
Uses Of Radio WavesUses Of Radio Waves
Uses Of Radio Waveskinghez
 
Radio waves/ Gelombang Radio SMAKBO 57 2013
Radio waves/ Gelombang Radio SMAKBO 57 2013Radio waves/ Gelombang Radio SMAKBO 57 2013
Radio waves/ Gelombang Radio SMAKBO 57 2013Nur Ziah
 
Radio Waves Presentation
Radio Waves PresentationRadio Waves Presentation
Radio Waves Presentationbina16
 
Radio waves presentation
Radio waves presentationRadio waves presentation
Radio waves presentation04burkem
 
Characteristics of radio waves
Characteristics of radio wavesCharacteristics of radio waves
Characteristics of radio wavesKundan Kumar
 
Radio Waves
Radio WavesRadio Waves
Radio WavesSashwaah
 
Radio waves presentation
Radio waves presentationRadio waves presentation
Radio waves presentationR_elsbeth
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedSlideShare
 

Viewers also liked (19)

USB Video Production Studios
USB Video Production StudiosUSB Video Production Studios
USB Video Production Studios
 
Radio waves
Radio wavesRadio waves
Radio waves
 
Radio Waves beyond Broadcasting
Radio Waves beyond BroadcastingRadio Waves beyond Broadcasting
Radio Waves beyond Broadcasting
 
Who Were the Beatles?
Who Were the Beatles?Who Were the Beatles?
Who Were the Beatles?
 
Radio Waves Presentation
Radio Waves PresentationRadio Waves Presentation
Radio Waves Presentation
 
Uses Of Radio Waves
Uses Of Radio WavesUses Of Radio Waves
Uses Of Radio Waves
 
Radio waves/ Gelombang Radio SMAKBO 57 2013
Radio waves/ Gelombang Radio SMAKBO 57 2013Radio waves/ Gelombang Radio SMAKBO 57 2013
Radio waves/ Gelombang Radio SMAKBO 57 2013
 
Radio Waves SMAKBO
Radio Waves SMAKBORadio Waves SMAKBO
Radio Waves SMAKBO
 
Radio waves
Radio waves Radio waves
Radio waves
 
Radio waves
Radio wavesRadio waves
Radio waves
 
Radio Waves Presentation
Radio Waves PresentationRadio Waves Presentation
Radio Waves Presentation
 
Radio waves presentation
Radio waves presentationRadio waves presentation
Radio waves presentation
 
Radio Waves
Radio WavesRadio Waves
Radio Waves
 
Radio waves ppt
Radio waves pptRadio waves ppt
Radio waves ppt
 
Characteristics of radio waves
Characteristics of radio wavesCharacteristics of radio waves
Characteristics of radio waves
 
Radio waves
Radio wavesRadio waves
Radio waves
 
Radio Waves
Radio WavesRadio Waves
Radio Waves
 
Radio waves presentation
Radio waves presentationRadio waves presentation
Radio waves presentation
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
 

Similar to Cbb 512 assignment_1

Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportArissa Loh
 
Study on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryStudy on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryIRJET Journal
 
Section 2 of Philippine Institute of Civil Engineers Manual
Section 2 of Philippine Institute of Civil Engineers ManualSection 2 of Philippine Institute of Civil Engineers Manual
Section 2 of Philippine Institute of Civil Engineers Manualchristinetorio6
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)tfkc1212
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services Ashok Tundare
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to EstimationMuthanna Abbu
 
Estimating Seminar (QS)
Estimating Seminar (QS)Estimating Seminar (QS)
Estimating Seminar (QS)Hasif Alias
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practiceseenyeeyong
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
Pp1 report
Pp1 reportPp1 report
Pp1 reportahmong4
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
3 developing project proposals
3 developing project proposals3 developing project proposals
3 developing project proposalsDaw Juguilon
 
10 me667 chap6 performance measures
10 me667 chap6 performance measures10 me667 chap6 performance measures
10 me667 chap6 performance measuresPavan Kumar
 

Similar to Cbb 512 assignment_1 (20)

Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Study on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryStudy on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction Industry
 
Pp report
Pp reportPp report
Pp report
 
Section 2 of Philippine Institute of Civil Engineers Manual
Section 2 of Philippine Institute of Civil Engineers ManualSection 2 of Philippine Institute of Civil Engineers Manual
Section 2 of Philippine Institute of Civil Engineers Manual
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
Estimating Seminar (QS)
Estimating Seminar (QS)Estimating Seminar (QS)
Estimating Seminar (QS)
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practice
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
PP1 report
PP1 reportPP1 report
PP1 report
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
3 developing project proposals
3 developing project proposals3 developing project proposals
3 developing project proposals
 
10 me667 chap6 performance measures
10 me667 chap6 performance measures10 me667 chap6 performance measures
10 me667 chap6 performance measures
 

Recently uploaded

VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 

Recently uploaded (20)

VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 

Cbb 512 assignment_1

  • 1. UNIVERSITY OF BOTSWANA Kagiso T. Lobeko 201000126 Assignment 1 9/8/2014 CBB 512 Construction Management I
  • 2. Question 1 (a) The tender price sets out the way in which the design team and client wish to review the breakdown of the overall tender price provided by tendering contractors. It is generally prepared by cost consultants (often quantity surveyors). (Buildings, 2014) • Enable like for like comparison between tenders and the cost plan. • Enable the cost consultant to assess where value lies within the different tenders (such as roofing or water reticulation) allowing assessment of value for money. • Identify any significant differences in pricing between tenderers to ensure the design has been correctly interpreted. • Identify areas of savings that might be negotiated with tenderers while still in competition. • Form the financial basis of the tender report. Question 1 (b) Prime Cost Sum reflects the material allowance being made in the rate for a specific item. A quoted rate normally consists of Material, Labour, Plant and mark-up (profit + overheads). By using the PC sum reference the builder identifies what material sum he has allowed for in his rate. This is normally done when the specification of the item has not yet been clarified (for example finishes, tiles, taps, light fittings, etc.). The builder would allow a reasonably accepted average cost for that item which is generally based on the builders past experience. Provisional Sums on the other hand are estimated allowances for work that involves both supply of material, labour and associated work. This normally involves a specialist subcontractor for example; an allowance for the installation of new Kitchen cupboards. The builder may base his allowance on an average market rate per metre of identified cupboard space. However, the final price will be based on an agreed design and finishes as prepared by a specialist. Once agreed the Builder will be entitled to add his agreed mark-up percentage to the subcontractor quotation. Reasons for inclusion: • More changes in scope of works and variations can be accommodated • It reduces conflicts as in the occasion of undefined provisional sums client is taking the risk for the works and the contractor may be entitled to an extension of time and additional payments • It protects the client from over pricing by the contractor as they are required to provide receipts and invoices from the sub-contractor engaged • The quality of work is not compromised as the contractor concentrates on their area of expertise and works outside their area of expertize are implemented by specialists 2
  • 3. Question 1 (c) The method related charges is defined as a charge entered by the contractor to cover items of work related to the intended method of executing the work, the costs of which are not proportional to the quantities. When the method related charges method is correctly used the following come as a result: • There are fewer disputes regarding changes • Payment is more realistic • The use of method related charges increase the change in scope of works that can be accommodated • it provides the contractor with room to be innovative in terms methods of construction as they have the budget to explore various construction techniques • it reduces chances of delayed construction as the contractor can get access to equipment that will fast track and simplify the construction process Question 1 (d) Method specification also known as recipe specification describes to the contractor the equipment, material and procedure that they should use. When using this form of specification a supervising agency commonly referred to as a consultant is obligated to monitor every aspect of the contractors field operations and as such takes the responsibility for the outcome. It reduces job delays, contract claims and escalation of future bid prices by ensuring the job is done right the first time. Disadvantages are this method tends to stifle contractor innovation. Since a contractor’s only motivation is instructional compliance, there is virtually no incentive to develop better, more efficient construction methods. Second, since they are not statistically based and 100 percent compliance is usually not possible, method specifications usually required “substantial compliance,” a purposely vague and undefined term that can lead to disputes. (Interactive, 2009) An end-result specification is one in which the final characteristics of the product are stipulated, and the contractor is given considerable freedom in achieving those characteristics. In their roughest form, the client will specify minimum, maximum or a range of values for any given characteristic and base acceptance on conformance to these specifications; they do not rely on the nebulous “substantial compliance” because they clearly define acceptable quality. The weakness of the end result specification include the inability to identify or measure essential performance related characteristics, the inability to quantify substantial compliance and to determine price adjustment factors that relate to reduced or enhanced value and the uncertainty as to value to be gained from the cost implementing statistically based end result specifications. (Smith, 1998) Question 1 (e) 3
  • 4. The Engineer shall be responsible for the enforcement and proper administration of the contract and shall, with due care and diligence, carry out: (i) The supervision of construction (ii) The testing and commission of the works (iii) The periodic and final account of the works (iv) The resolution of disputes (first instance). The Engineer shall also be responsible for all communications to the Contractor except where the contract expressly provides for instructions to be given by the Employer. Question 1 (f) An estimate for construction work can be defined as the process of calculating the quantities and costs of the various items needed in connection with the work; it is produced by the Estimator in conjunction with the pre-contract Tendering team. They come up with it from information provided by the Client to the Architect and Quantity Surveyor and investigations and planning carried out by the team. The estimate is a net estimated cost of carrying out the work. (Gateway) A tender is a written bid submitted by a Contractor to a Client in pursuance of the notification given, to execute certain work at calculated rates with the terms and conditions laid down in the tender documents. Question 2 (a) Writing an accurate job description involves breaking the job down in to its component parts and defining the key objectives. The purpose of the job description is to: • Detail the purpose, tasks and responsibilities of the post • Enable jobseekers to read about the position before applying for it • Use as a reference when short listing and interviewing applicants • Assist with organising and designing the new staff member’s induction and training program • Use in appraisals as an ongoing tool throughout the employment The person specification details the necessary skills, qualifications, experience or other attributes needed to carry out the job. The purpose of the person specification is to: • Detail what the person needs to fulfil the requirements of the position by providing a profile of the skills and knowledge considered essential and desirable. • It forms the basis for the advertisement i.e. where and how to advertise 4
  • 5. • Provide information that enables job seekers to match themselves to the job role before applying • Provide a basis for shortlisting applicants • Provide the interview panel with the selection of criteria by which to assess the best candidate for the role • Assist with organising and designing the new staff member’s induction and training program Question 2 (b) Negative Motivation Negative motivation techniques focus on the consequences of underperforming and failing to meet goals, as opposed to positive motivation, where the focus is on the benefits of superior performance. The danger of using negative motivation is the lack of morale that will ensue. Employees will detest going to work because their day is filled with constant threats of punishment. Ultimately, they will reach the limit of their ability to handle the constant negative barrage and either rebel or seek work elsewhere. Using negative reinforcement undoubtedly shortens the retention rate of your workforce, leaving you constantly searching for replacements. Employee loyalty will not exist in an environment where superior performance goes unrewarded and unrecognized while sub-par performance is instead highlighted as negative reinforcement. (Gambone, 2014) Frustration Reduction • Managers can ensure that regular feedback is obtained between themselves and employees regarding performance. They should let staff members know where they stand in terms of accomplishing goals. If they have made some wrong turns, explain when and where they went off track. • Managers should set up an environment of openness, in which management will listen to and act upon employees’ ideas and suggestions. • Managers should ensure that employees have the information, tools, equipment, supplies, and assistance they need to perform their jobs. • Managers should give consistent organizational support for training and development opportunities and encourage employees to use those opportunities. • Employee should be given a high level of freedom for how results are achieved Question 2 (c) 5
  • 6. The linear model views communication as a one-way or linear process in which the speaker speaks and the listener listens. This model does not allow for feedback or comments from the listener. It is commonly used in the army where are higher ranking officer gives instructions or orders to a lower ranking officer for him to implement no questions asked. Interactive model where the receiver or listener provides feedback to the sender or speaker. The speaker or sender of the message also listens to the feedback given by the receiver or listener. Both the speaker and the listener take turns to speak and listen to each other. Feedback is given either verbally or non-verbally, or in both ways. Question 2 (d) • Employee Trust Clear, open communication can create a sense of transparency in your organization, which builds trust between levels of employees. Where keeping employees in the dark can result in resentments, tension, and a feeling of low job security, strong communication can help them feel valued and trusted. Open communication can reduce feelings of uncertainty and cluelessness about the state of the company, which makes for a more-positive work environment and staff who feel secure and safe. • Relationships Communication is essential to building relationships between staff members and between levels of employees, both on a professional and social level. An atmosphere of open communication makes it safe for employees to express their ideas; as a result, you will have the benefit of your staff's combined experience in coming up with innovative solutions. Communication prevents employees from feeling isolated, builds teamwork, and creates a more collegial atmosphere in the office. When relationships are strong, employees are better able to trust one another and work together more effectively. • Clarity In an organization, confusion and ambiguity can create negative feelings and a tense atmosphere. By making roles and responsibilities clear to everyone on staff, you can give your employees the information they need to get their jobs done; this is particularly important when your employees are dispersed or come from different backgrounds. Communication reduces misunderstandings and cuts the costs associated with mistakes. • Collaboration 6
  • 7. Communication can help your employees collaborate effectively, which will make for a more-productive team overall. When you have multiple departments who are working on different facets of the same project, communication can streamline the process and improve the end result. When your staff talks openly to each other, they can communicate potential issues, requirements and feedback that can make the result stronger. Communication can ensure that everyone is on the same page and prevent problems down the road. Bibliography 1. Buildings, D. (2014, May 17). Designing Buildings Ltd. Retrieved September 7, 2014, from Designing Buildings : http://www.designingbuildings.co.uk/wiki/Tender_pricing_document 2. Gambone, G. (2014). Demand Media. Retrieved September 7, 2014, from Small Bussiness: http://smallbusiness.chron.com/use-negative-motivation-workplace-16692.html 3. Gateway, C. L. (n.d.). Construction Learning Gateway. Retrieved from Estimating & Measuring Work. 4. Interactive, P. (2009, June 5). Pavement Interactive. Retrieved September 7, 2014, from Pavement Interactive: http://www.pavementinteractive.org/article/end-result- specifications/ 5. Smith, G. R. (1998). State DOT Management Techniques for Materials and Construction Acceptance. Arizona: Transportation Research Board. 7