This document contains the resume of Chennappan Bhoopalan, who has over 9 years of experience as a Quantity Surveyor in Singapore. He is currently working as a Quantity Surveyor at NCL Building Construction Pte Ltd and has worked on projects like Changi East to Effect 3 Runway Operations At Singapore Changi Airport and General Industrial Factory MK13. He lists his responsibilities as preparing progress claims, certifying subcontractor payments, coordinating with contractors and more. Prior to his current role, he has worked as a Quantity Surveyor and Electrical & Mechanical Senior Supervisor in Singapore and Dubai.
1. Chennappan Bhoopalan
MBA & Quantity Surveying
(Singapore)
Blk195B, Punggol
Singapore763861
Mobile:+65-91647514
Email: bhoopalan2ncl@gmail.com
PROFESSIONALEXPERIENCE
Aug 2016 Quantity Surveyor (NCL Building Construction Pte, Ltd)
– Present Project: Changi East to Effect 3 Runway Operations At Singapore Changi Airport-Package 1
Main Contractor: Koh Brothers Building & Civil Engineering Contractor Pte Ltd.
Contract Sum: $ 7,592,119.11
Singapore
Aug 2015 Quantity Surveyor (NCL Building Construction Pte, Ltd)
– Aug 2016 General Industrial Factory MK13 at 12 Woodlands Link (Sembawang Planning Area.
Main Contractor: He Zhan Construction Pte, Ltd
Contract Sum: $ 1,071,557.95
Singapore
July 2013 Quantity Surveyor (NCL Building Construction Pte, Ltd)
-July 2016 Project: Water Town, Punggol.
Main Contractor: MA Builders Pte, Ltd
Contract Sum: $11,996,713.00
Singapore
Quantity Surveyor Achievement
Preparing Monthly progress claim and discuss withConsultant Project Manager.
Certify Sub-contractors’ payment certificates for Archi and M&E works
Liaise with consultant quantity surveyor and submitting cost break down of VO’s.
Assist to contract manager to prepare letter of award /Letter of intent.
Coordinate with site team and purchase order
Preparing final accounts
Quantity take off, Material enquiries and call quotations for tender
Preparing tender documents for submission
Attend monthly site progress meeting & VO meeting
PROFILE
A hard- working, self-motivated, and adaptable Electricals & mechanical & Maintenance & Quantity
Surveyor, with excellent organizational and team working skills and with 9 years’ experience. Capable of
working without supervision and willing to assume additional responsibility, is looking for a position in an
innovative, learning and challenging working environment that recognizes and fully utilizes my capabilities
and competencies
Availableto starts immediately
Current Salary:$ 3500
Expected Salary: Negotiable
2. August 2012 – Jun
2013
Quantity Surveyor (NCL Construction)
Project: Fusinopolis 2a. Tower A & B.
Main Contractor: GS Engineering & Constriction Pte, Ltd
Contract Sum: $6,000,000.
Quantity Surveyor Achievements:
Handling subcontractor Bills and payments
Costing and processing variations
Prepare final accounts and contract charges
Prepared cost reports
Measuring and recording site information
Review all the drawings and specifications supplied by client
for quotation
• Prepare Weekly Accomplishment Report and Monthly Progress Report.
• Progress Claim
o Preparation of GENCON monthly progress claim for Civil Structural and
Architectural Works.
o Reconcile Accomplishment (Progress Claim) with Construction
Managers and Quantity Surveying Consultants.
o Assesment and Evaluation of Subcontractors’ progress claim.
• Material Procurement/ Subcontactor’s Account
o Post Tender Quantity Take Off (Rehash) and compare with the Bill of
Quantities.
o Source and compilequotation and prepare cost analysis
o Review and submit technical brochures with respect to the
specifications.
o Evaluate and compare suppliers’ cost proposals versus site budget.
o Endorse suppliers with approved technical brochures and lowest cost
proposal to the Head Office for negotiation and awarding.
o Monitoring of down payment and material delivery.
o Reconcile subcontractors’ Variation Order and endorse for revision of
Purchase Order.
o Monitor supplier/subcon progress until completion of works.
o Processing Variation Orders/ Change Orders Claims
o Preapare Quantity Take Off for revised and/or additional works.
o Reconcile quantities and cost of VO with the Owner’s Representative.
o Prepare documents for the approved/reconciled variation order.
• Prepare charges/deductions to subcontractors.
• Monitor Productivity Rate (Concreting, Rebar Works, Formworks,
Architectural Works, etc.)
July 2008-Dec 2009 Electrical & Mechanical Senior Supervisor (Hitachi Plant Technology Ltd)
Project: Palm Jumeirah Monorail
Main Contractor: Marubeni Corporation
Dubai(UAE)
He Responsibilities Involved:
Experience in installation of power equipment’s like panelboards, Switchgear, Transformers and cable laying etc.
Experience in Extra High Voltage A.C /D. C Transmission
Panelboard reading observation and corrective actions.
To perform the original drawings, prepare and submit the as-built drawings for the above project.
ATP Signal:
a) Installation of ATP Box
b) Signal Cable Laying & Termination
c) Track switches Signal Cabling & Termination.
d) Fiber optical cable laying to OCMK Panel
e) F.O. PATCH CORD Cable for OCMK Panel
Power Contact Lines:
a) Installation of insulator-shaped copper conductor, expansion joint, wire mesh.
b) FRP Plate, Jumper Cable, DC Cable pulling, Termination & Megger Test
c) Installation & Cable Termination of Bogie drop, Transverse & Shunting unit.
d) Installation of Scissor Lift, Fork Lift, Gantry Crane & Monorail Hoist.
Analog Telephone:
a) Installation of Telephone, cable laying &Termination.
b) Installation of G.I conduit, Trucking, Cable Ladder, Cable Tray.
11 KV Substations
Installation & Maintenance of 11kV Substation, 1MVA Standby Generator, Uninterruptible Power Supply (UPS), Emergency
Change over Switch (ECS).
Cable Pulling (10 Sq.mm up to 300 Sq.mm)
Experience in Extra High Voltage A.C /D. C Transmission
3. CCTV.
a) Installation and cable laying for CCTV.
b) Installation and Cable laying for camera
c) F.O PATCH CORD Cable Laying
d) PATCHCORD CAT 6 UTP SNAG PROOP Cable Laying for CCTV Panel
Antennae
Installation and cable pulling for Antennae.
Equipment grounding termination, grounding copper plate cable termination and grounding concrete pit installation.
Conduct Megger Test for high and low power cables
Testing for Earth Resistance, continuity test and Earth equipment test for all electrical
Equipment’s.
Dec 2004-July2008: Maintenance Technician(E & M) (Innox Power Engineering (S) Pte, Ltd.)
Project: Sentosa Express Monorail Development Corporation, Singapore.
Main Contractor: Hitachi PlantTechnologyLtd
Singapore
Maintenance, Job Description SentosaExpress Monorail.
Carry out maintenance of Sentosa Express (Monorail) Equipment and facilities being maintained are: 22KVSubstation,
1MVA Standby Generator.
Uninterruptible Power Supply (UPS),Emergency Change over Switch (ECS) Track, Disconnecting Switch Panel(DSP),
Power Contact Lines, Communication equipment (Transponder),Wayside Electronic Marker, RTU-S, ATP &RB).
Communication System (CentralRadio Equipment,PA system, SOS Telephone / Clock, Train Stop Button (ESB),Emergency
Train Stop (ETS), OCC Supervisory Control System (SCS).
Depot equipment:
Maintenance Vehicle, Lifting Jack, Gantry Crane,Monorail Hoist, Scissor Lift, Tire Changer,Train Battery Charger and
Rescue Vehicle.
Depot control:
Operator of Traverser, Maintenance Vehicle, Lifting Jack, Gantry Crane,Monorail Hoist, Scissor Lift, Tire Changer,
Maintenance:
a) Track switch
b) Traverser
c) Car wash
d) Depot
e) Maintenance Vehicle
4. EDUCATION QUALAIFICATIONS
2015-2016 Specialist Diploma in Quantity surveyor (SDQS)
Global School of Technology’s & Management , Singapore
2010-2012 Master of Business Administration-Financial Management (MBA)
Annamalai University, Tamil Nadu, India.
1999-2002 Bachelor of Business Administration (BBA)
University of Madras, Tamil Nadu, India.
ADDITIONAL QUALIFICATIONS
Sep2013-Dec 2013 Auto CAD 2D & 3D modeling
G.Tec Computer Education Centre, Singapore.
Mar 2008-July 2008 Building Construction Supervisors Safety course
NTUC Learning Hub, Singapore.
COMPUTERSKILLS
Applications Auto CAD, QS pro constructor
Project Management MS Project
MS Office Word, Excel, Power Point, Access
Graphics Packages Photoshop, CorelDraw
PERSONALDETAILS
Age 35 Status Marriage
Nationality Indian Language English(fluent) and Tamil(native)
Availability Immediately Interests Sports, ReadingBook, &
News
REFEREERANCE
Mr. Mariano Glorionito Castillano(Greg)
Maintenance Engineer
SMRT Services
Tel: +6591731463
Email: marianoGC@smrt.com.sg
Mr. Somanath
Quantity Surveyor
NCL Building Construction Pte Ltd
Tel: +6591678075
Email: somanath2009@live.com