SlideShare a Scribd company logo
1 of 6
Download to read offline
1
To the Chairperson and Members of the
North Central Area Committee
Review of Clontarf Seafront Footpath and Cycle Track Alignment from Alfie Byrne Road to
Conquer Hill Road.
The Environment and Transportation Dept., Roads and Traffic Planning Section has been
requested by the North Central Area Office to carry out a review of existing footpath and cycle
track alignment along the Clontarf seafront from Alfie Byrne Road to Conquer Hill Road. The
purpose of the review is to examine a number of conflict points between pedestrians and cyclists
identified along the route with regard to safety concerns for all users.
An inspection of the route from Alfie Byrne Road to Conquer Hill Road (Dublin Bus Depot) was
carried out in March 2015. Conflict points were noted in several areas along the route. Issues are
briefly discussed with accompanying recommendations/solutions. Enclosed aerial views 1, 2 and
3 illustrate proposed alignments.
Alfie Byrne Road /Clontarf Road (Aerial View 1, Area 1)
Issue:
The segregated two-way cycle track and footpath on the south-east side of this junction merges
into an undefined shared area. The footpath continues northwards on the opposite side of the
cycle track. The cycle track continues eastwards along the seafront. There is no footpath in the
immediate area for pedestrians wishing to continue eastwards along the seafront. Pedestrians
are therefore obliged to cross the cycle track if they wish to continue northwards to the junction or
walk along the cycle track if they wish to continue along the seafront, resulting in conflict with
cyclists.
Recommendation:
A raised defined crossing point is recommended for pedestrians wishing to continue northwards
to the junction (orange shaded area in aerial view). This crossing point should be clearly marked.
Signage should be provided to warn cyclists to yield to pedestrians.
A new footpath is also recommended (purple line) parallel to the existing two-way cycle track for
pedestrians wishing to continue walking along the seafront. This footpath should be clearly
defined and raised to deter cyclists encroaching onto it and should extend eastwards past the
Alfie Byrne Memorial to the existing shared two-way cycle track/footpath (south of Strandville
Avenue.) This footpath will also provide access to the Alfie Byrne Memorial.
Alfie Byrne Road / Clontarf Road (Aerial View 1, Area 2)
Issue:
Immediately west of the Alfie Byrne Memorial (Area 2), there is a two-way cycle track in this area
but no footpath. The cycle track also veers to the north to the existing pedestrian crossing on
Clontarf Road. Pedestrians are using the cycle track as a footpath and are in obvious conflict with
cyclists.
Recommendation:
As indicated above, a new footpath is recommended in this area (purple line), parallel to the
existing two-way cycle track and also northwards to the junction. Clearly defined crossing points
for pedestrians should be provided (orange shaded area) as well as warning signage to cyclists
to yield to pedestrians at the raised crossing point. A toucan crossing should be provided at the
existing pedestrian crossing on the east side of Alfie Byrne Road /Clontarf Road.
Alfie Byrne Road / Clontarf Road (Aerial View 1, Area 3)
Issue:
At Area 3, the existing combined two-way cycle track/footpath diverges, where the footpath veers
to the south, continuing along the seafront, and the two-way cycle track continues westwards.
Pedestrians wishing to continue west, walk along the two-way cycle track, causing conflict with
cyclists.
Additional conflict is caused by both cyclists and pedestrians leaving the path at this point to
travel north, over a wide concrete paved area, where a section of boundary wall has been broken
out to access Clontarf Road at Strandville Avenue East.
Recommendation:
2
The proposed footpath indicated for Areas 1 and 2 should end at Area 3, providing a facility for
pedestrians to continue west. It is proposed to close off access to the wide concrete paved area,
and repair the boundary wall, as access would be available from the footpath and cycle track to
Clontarf Road at Alfie Byrne Road.
Clontarf Road / Hollybrook Road Car Park (Aerial View 2)
Issue:
The proximity of the existing cycle track (green line) to the car park is a hazard to motorists as
they leave their vehicles and cross the cycle track to access the park area. Motorists who are
unfamiliar with the seafront may be unaware that they are stepping onto a cycle track as they
leave their vehicles, resulting in a hazard to both pedestrians and cyclists alike.
Recommendation:
A realignment of the existing two-way cycle track (red line) is recommended as shown on Aerial
View 2 where the existing combined cycle track/footpath diverges. The existing alignment (green
line) should be removed. This will remove the conflict at the car park and provide an opportunity
for pedestrians to take care as they cross the cycle track to access the footpath along the
seafront.
Clontarf Road /Belgrove Road /Vernon Avenue Car Park (Aerial View 3)
Issue:
This issue is similar to Hollybrook Road car park, where the cycle track is aligned along the rear
of the car park. Motorists leaving their vehicles are immediately confronted with cyclists on this
cycle track.
Recommendation:
A realignment of the cycle track is recommended as shown (red line). The new alignment would
run parallel to the existing cycle track. The existing cycle track would become a new footpath for
car park users (purple line). The footpath and cycle track would be separated with low hedge
planting, with designated crossing points across the cycle track for pedestrians (yellow areas).
Signage would be provided for cyclists at designated crossing points to yield to pedestrians.
Pedestrian facilities would be maintained to connect the existing seafront footpath with Vernon
Avenue junction by realigning the footpath as shown (purple line). The existing footpath behind
the ESB sub-station would become a new two-way cycle track as this footpath is not popular with
pedestrians (red line).
Clontarf Road / Vernon Avenue (Aerial View 3)
Issue:
The volume and speed of cyclists using this shared area is a hazard to pedestrians.
Recommendation:
As mentioned above, the existing footpath running behind the ESB sub-station would become a
new cycle track (red line), diverting commuter cyclists away from the current shared
pedestrian/cyclist area at Vernon Avenue. The existing cycle track /footpath shared area at
Vernon Avenue would remain to provide cycling facilities for Vernon Avenue cyclists access the
cycle track (as the new cycle track behind the ESB sub-station would join the existing track
further east of Vernon Avenue).The choice of cycle tracks in this area would enable commuter
(high speed) cyclists use the more direct track behind the ESB sub-station, thus reducing cycling
volume and speed at the shared area at Vernon Avenue.
Clontarf Yacht Club
Issue:
Removal of a barrier has opened the area for free parking for a small number of vehicles at the
Yacht Club slipway. Vehicles entering and exiting this area constitute a hazard for cyclists as
they cross the entrance to the slipway.
Recommendation:
The area is unsuitable for parking and the entrance/exit is substandard in terms of sight lines.
Replacement of the barrier is recommended to close off the area for parking. Management of the
barrier can be undertaken by Clontarf Yacht Club in agreement with DCC NCA Office.
DCC Car Park at Conquer Hill Road
Issue:
3
Motorists exiting the car park are unable to see cyclists due to poor visibility caused by dense
shrubs growing in the area. This issue is exacerbated by the high speed of some cyclists along
the route.
Recommendation:
Visibility for motorists can be improved by the removal of dense shrub planting in the immediate
area of the exit. Warning signage for cyclists to yield to traffic reviewed further and improved.
Dublin Bus Car Park at Conquer Hill Road
Issue:
A similar situation to the DCC car park exists here where motorists exiting the car park are
unable to see cyclists due to poor visibility caused by dense shrubs growing in the area.
Recommendation:
Visibility for motorists can be improved by the removal of dense shrub planting in the immediate
area of the exit. Warning signage for cyclists to yield to traffic reviewed further and improved.
Line marking of the two-way cycle track / footpath - Alfie Byrne Road to Conquer Hill
Road.
Issue:
Line marking along the combined two-way cycle track / footpath has become faded and is no
longer legible, causing confusion for cyclists and pedestrians regarding which side of the paved
area they should use. In some areas, it is not clear if the path is a footpath or cycle track.
Recommendation:
Re-lining of the entire route from Alfie Byrne Road to Conquer Hill Road is recommended in
accordance with the National Cycle Manual including pedestrian and cycle logos at 20.0m
intervals.
Implementation
Proposals for Aerial View 1 at Alfie Byrne Road / Clontarf Road will be included in the Clontarf to
Amiens Street Cycle Route Scheme, due for construction in 2016. Funding is approved by the
NTA for this scheme.
An application for funding for the completion of proposals in Aerial Views 2 and 3 will be
submitted to the NTA under their Sustainable Transport Measures Grant Programme, one of
which is the Cycling/Walking programme, supporting measures to improve the walking and
cycling environment. The application will also include a re-lining of the entire route from Alfie
Byrne Road to Conquer Hill Road.
It is recommended that the North Central Area Office replace the barrier at the Clontarf Yacht
Club, to prevent free parking in the area. This will remove the hazard for cyclists. Arrangements
should be made with the Yacht Club to manage the operation of the barrier.
DCC Parks Dept. will be requested to cut back dense growing shrubs at the entrance to both
DCC and Dublin Bus car parks at Conquer Hill Road to improve visibility.
DCC Traffic will review signage in this area on the cycle track to warn cyclists of vehicles
entering/exiting the car park.
Tony McGee
Executive Engineer
4
5
6

More Related Content

What's hot

Draft bbp&pom bondi_beach_precinct_may_2013_final
Draft bbp&pom bondi_beach_precinct_may_2013_finalDraft bbp&pom bondi_beach_precinct_may_2013_final
Draft bbp&pom bondi_beach_precinct_may_2013_finallenore_kulakauskas
 
Ala Moana Park combined online and workshop report
Ala Moana Park combined online and workshop reportAla Moana Park combined online and workshop report
Ala Moana Park combined online and workshop reportomedina91
 
9.24 1 wikibanquinafuncióncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...
9.24  1 wikibanquinafuncióncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...9.24  1 wikibanquinafuncióncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...
9.24 1 wikibanquinafuncióncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...Sierra Francisco Justo
 
9.24 1 wikibanquinafuncioncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...
9.24  1 wikibanquinafuncioncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...9.24  1 wikibanquinafuncioncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...
9.24 1 wikibanquinafuncioncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...Sierra Francisco Justo
 
Aspen Hill MMPA Transportation Section & Appendix May '15
Aspen Hill MMPA Transportation Section & Appendix May '15Aspen Hill MMPA Transportation Section & Appendix May '15
Aspen Hill MMPA Transportation Section & Appendix May '15Aaron Zimmerman, PTP
 
Road Design Session
Road Design SessionRoad Design Session
Road Design SessionPraja
 
Chicago - Bicycle Facilities Guide
Chicago - Bicycle Facilities GuideChicago - Bicycle Facilities Guide
Chicago - Bicycle Facilities GuideDivvyBikes
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to roadKHUSHBU SHAH
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPTKavin Raval
 
Complete Streets Report
Complete Streets ReportComplete Streets Report
Complete Streets Reportjadamsm
 
Roadway condition survey & Traffic Volume Study
Roadway condition survey & Traffic Volume StudyRoadway condition survey & Traffic Volume Study
Roadway condition survey & Traffic Volume StudyStone Rayhan
 
Roundabouts for Traffic Engineering ~ Athens GA
Roundabouts for Traffic Engineering ~ Athens GARoundabouts for Traffic Engineering ~ Athens GA
Roundabouts for Traffic Engineering ~ Athens GAWilliams and Associates
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometricsKHUSHBU SHAH
 
Highway Engineering topics
Highway Engineering topicsHighway Engineering topics
Highway Engineering topicsShubham Sadh
 
Wilma Dykeman Riverway Road Intersection Re-modernization
Wilma Dykeman Riverway  Road Intersection Re-modernizationWilma Dykeman Riverway  Road Intersection Re-modernization
Wilma Dykeman Riverway Road Intersection Re-modernizationMsplcdYkee69
 

What's hot (20)

Draft bbp&pom bondi_beach_precinct_may_2013_final
Draft bbp&pom bondi_beach_precinct_may_2013_finalDraft bbp&pom bondi_beach_precinct_may_2013_final
Draft bbp&pom bondi_beach_precinct_may_2013_final
 
Ala Moana Park combined online and workshop report
Ala Moana Park combined online and workshop reportAla Moana Park combined online and workshop report
Ala Moana Park combined online and workshop report
 
9.24 1 wikibanquinafuncióncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...
9.24  1 wikibanquinafuncióncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...9.24  1 wikibanquinafuncióncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...
9.24 1 wikibanquinafuncióncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...
 
9.24 1 wikibanquinafuncioncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...
9.24  1 wikibanquinafuncioncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...9.24  1 wikibanquinafuncioncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...
9.24 1 wikibanquinafuncioncarril-2jordanriesgoscdc-3gdanskgravedadchoques 26...
 
Task 3.b: EN TRIPS Priority Corridors - Preliminary Street Redesign Alternat...
Task 3.b:  EN TRIPS Priority Corridors - Preliminary Street Redesign Alternat...Task 3.b:  EN TRIPS Priority Corridors - Preliminary Street Redesign Alternat...
Task 3.b: EN TRIPS Priority Corridors - Preliminary Street Redesign Alternat...
 
Aspen Hill MMPA Transportation Section & Appendix May '15
Aspen Hill MMPA Transportation Section & Appendix May '15Aspen Hill MMPA Transportation Section & Appendix May '15
Aspen Hill MMPA Transportation Section & Appendix May '15
 
05.ENTRIPS
05.ENTRIPS05.ENTRIPS
05.ENTRIPS
 
Road Design Session
Road Design SessionRoad Design Session
Road Design Session
 
Chicago - Bicycle Facilities Guide
Chicago - Bicycle Facilities GuideChicago - Bicycle Facilities Guide
Chicago - Bicycle Facilities Guide
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume Study
 
Complete Streets Report
Complete Streets ReportComplete Streets Report
Complete Streets Report
 
Roadway condition survey & Traffic Volume Study
Roadway condition survey & Traffic Volume StudyRoadway condition survey & Traffic Volume Study
Roadway condition survey & Traffic Volume Study
 
Cross section of road
Cross section of roadCross section of road
Cross section of road
 
Roundabouts for Traffic Engineering ~ Athens GA
Roundabouts for Traffic Engineering ~ Athens GARoundabouts for Traffic Engineering ~ Athens GA
Roundabouts for Traffic Engineering ~ Athens GA
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
 
Highway Engineering topics
Highway Engineering topicsHighway Engineering topics
Highway Engineering topics
 
Wilma Dykeman Riverway Road Intersection Re-modernization
Wilma Dykeman Riverway  Road Intersection Re-modernizationWilma Dykeman Riverway  Road Intersection Re-modernization
Wilma Dykeman Riverway Road Intersection Re-modernization
 
Thesis (2)
Thesis (2)Thesis (2)
Thesis (2)
 

Viewers also liked

TCIOceania15 The Australian Cluster Observatory
TCIOceania15 The Australian Cluster ObservatoryTCIOceania15 The Australian Cluster Observatory
TCIOceania15 The Australian Cluster ObservatoryTCI Network
 
Kas yra GETSHOPIN?
Kas yra GETSHOPIN?Kas yra GETSHOPIN?
Kas yra GETSHOPIN?GETSHOPIN
 
Rey Ferdin's Resume
Rey Ferdin's ResumeRey Ferdin's Resume
Rey Ferdin's ResumeRey Ferdin
 
Bonnes pratiques SEO pour les sites multilingues et internationaux
Bonnes pratiques SEO pour les sites multilingues et internationauxBonnes pratiques SEO pour les sites multilingues et internationaux
Bonnes pratiques SEO pour les sites multilingues et internationauxPeak Ace
 
Strefa inwestycyjna przy lotnisku w Krośnie – kompleks 2
Strefa inwestycyjna przy lotnisku w Krośnie – kompleks 2Strefa inwestycyjna przy lotnisku w Krośnie – kompleks 2
Strefa inwestycyjna przy lotnisku w Krośnie – kompleks 2coirzeszow
 
De energization and lockout safety reminder training
De energization  and lockout safety reminder trainingDe energization  and lockout safety reminder training
De energization and lockout safety reminder trainingTerry Penney
 
Fallstudie Intranet-ReLaunch eResult
Fallstudie Intranet-ReLaunch eResultFallstudie Intranet-ReLaunch eResult
Fallstudie Intranet-ReLaunch eResulteResult_GmbH
 

Viewers also liked (9)

TCIOceania15 The Australian Cluster Observatory
TCIOceania15 The Australian Cluster ObservatoryTCIOceania15 The Australian Cluster Observatory
TCIOceania15 The Australian Cluster Observatory
 
Kas yra GETSHOPIN?
Kas yra GETSHOPIN?Kas yra GETSHOPIN?
Kas yra GETSHOPIN?
 
Rey Ferdin's Resume
Rey Ferdin's ResumeRey Ferdin's Resume
Rey Ferdin's Resume
 
9797 lme user_guide
9797 lme user_guide 9797 lme user_guide
9797 lme user_guide
 
Bonnes pratiques SEO pour les sites multilingues et internationaux
Bonnes pratiques SEO pour les sites multilingues et internationauxBonnes pratiques SEO pour les sites multilingues et internationaux
Bonnes pratiques SEO pour les sites multilingues et internationaux
 
Strefa inwestycyjna przy lotnisku w Krośnie – kompleks 2
Strefa inwestycyjna przy lotnisku w Krośnie – kompleks 2Strefa inwestycyjna przy lotnisku w Krośnie – kompleks 2
Strefa inwestycyjna przy lotnisku w Krośnie – kompleks 2
 
De energization and lockout safety reminder training
De energization  and lockout safety reminder trainingDe energization  and lockout safety reminder training
De energization and lockout safety reminder training
 
Fallstudie Intranet-ReLaunch eResult
Fallstudie Intranet-ReLaunch eResultFallstudie Intranet-ReLaunch eResult
Fallstudie Intranet-ReLaunch eResult
 
Sage temoignage client GRM
Sage temoignage client GRMSage temoignage client GRM
Sage temoignage client GRM
 

Similar to Cycleway realignment

2017.08.28 db ncac&cac clontarf to city centre cycle route part 8 expla...
2017.08.28 db   ncac&cac clontarf to city centre cycle route part 8 expla...2017.08.28 db   ncac&cac clontarf to city centre cycle route part 8 expla...
2017.08.28 db ncac&cac clontarf to city centre cycle route part 8 expla...Naoise
 
2017.09.07 dcc120033 cyclist safety slides
2017.09.07 dcc120033 cyclist safety slides2017.09.07 dcc120033 cyclist safety slides
2017.09.07 dcc120033 cyclist safety slidesNaoise
 
North East Bicycle Corridor linking Chandle Hiqhway and Alexandra Parade
North East Bicycle Corridor linking Chandle Hiqhway and Alexandra ParadeNorth East Bicycle Corridor linking Chandle Hiqhway and Alexandra Parade
North East Bicycle Corridor linking Chandle Hiqhway and Alexandra ParadeGreenlivingpedia
 
Balboa Station Plan Alternatives
Balboa Station Plan AlternativesBalboa Station Plan Alternatives
Balboa Station Plan AlternativesCirculateSD
 
Crosswalk to Horn Pond
Crosswalk to Horn PondCrosswalk to Horn Pond
Crosswalk to Horn Pondthopcroft
 
The Safer Bloomsbury Campaign
The Safer Bloomsbury CampaignThe Safer Bloomsbury Campaign
The Safer Bloomsbury Campaigngeorgio8
 
Complete Street PVAL PUP430
Complete Street PVAL PUP430Complete Street PVAL PUP430
Complete Street PVAL PUP430Peter Valenzuela
 
James Assinder | Transport Accessibility Review
James Assinder | Transport Accessibility ReviewJames Assinder | Transport Accessibility Review
James Assinder | Transport Accessibility ReviewJames Assinder
 
Nethermayne Site Planning Application
Nethermayne Site Planning ApplicationNethermayne Site Planning Application
Nethermayne Site Planning Applicationheppellf
 
Jay Street Pedestrian Plaza
Jay Street Pedestrian PlazaJay Street Pedestrian Plaza
Jay Street Pedestrian Plazasubtle116
 
Roadway condition survey
Roadway condition surveyRoadway condition survey
Roadway condition surveyapu roy
 
Hk harbourfront cycleway route by hkcall (rev 3)
Hk harbourfront cycleway route by hkcall (rev 3)Hk harbourfront cycleway route by hkcall (rev 3)
Hk harbourfront cycleway route by hkcall (rev 3)Nick Andrew
 
Letter from Askern Ward Parish Council
Letter from Askern Ward Parish CouncilLetter from Askern Ward Parish Council
Letter from Askern Ward Parish Councildoncasterrail
 
Designing for Cycling RTPI 15.6.16 Tim Pheby
Designing for Cycling RTPI 15.6.16 Tim PhebyDesigning for Cycling RTPI 15.6.16 Tim Pheby
Designing for Cycling RTPI 15.6.16 Tim PhebyTim Pheby
 
Mcm demo glasgow - august 11
Mcm demo   glasgow - august 11Mcm demo   glasgow - august 11
Mcm demo glasgow - august 11Cycling Scotland
 
CPR Yards Crossing Study - open house panels
CPR Yards Crossing Study - open house panelsCPR Yards Crossing Study - open house panels
CPR Yards Crossing Study - open house panelsCrowdbrite
 
The 3068 Group - Presentation to East West Link Assessment Panel
The 3068 Group - Presentation to East West Link Assessment PanelThe 3068 Group - Presentation to East West Link Assessment Panel
The 3068 Group - Presentation to East West Link Assessment PanelChris Goodman
 
ATS-16: Protected Bike Lanes: Lessons Learned in Planning and Implementation,...
ATS-16: Protected Bike Lanes: Lessons Learned in Planning and Implementation,...ATS-16: Protected Bike Lanes: Lessons Learned in Planning and Implementation,...
ATS-16: Protected Bike Lanes: Lessons Learned in Planning and Implementation,...BTAOregon
 

Similar to Cycleway realignment (20)

2017.08.28 db ncac&cac clontarf to city centre cycle route part 8 expla...
2017.08.28 db   ncac&cac clontarf to city centre cycle route part 8 expla...2017.08.28 db   ncac&cac clontarf to city centre cycle route part 8 expla...
2017.08.28 db ncac&cac clontarf to city centre cycle route part 8 expla...
 
2017.09.07 dcc120033 cyclist safety slides
2017.09.07 dcc120033 cyclist safety slides2017.09.07 dcc120033 cyclist safety slides
2017.09.07 dcc120033 cyclist safety slides
 
North East Bicycle Corridor linking Chandle Hiqhway and Alexandra Parade
North East Bicycle Corridor linking Chandle Hiqhway and Alexandra ParadeNorth East Bicycle Corridor linking Chandle Hiqhway and Alexandra Parade
North East Bicycle Corridor linking Chandle Hiqhway and Alexandra Parade
 
Balboa Station Plan Alternatives
Balboa Station Plan AlternativesBalboa Station Plan Alternatives
Balboa Station Plan Alternatives
 
Crosswalk to Horn Pond
Crosswalk to Horn PondCrosswalk to Horn Pond
Crosswalk to Horn Pond
 
The Safer Bloomsbury Campaign
The Safer Bloomsbury CampaignThe Safer Bloomsbury Campaign
The Safer Bloomsbury Campaign
 
Complete Street PVAL PUP430
Complete Street PVAL PUP430Complete Street PVAL PUP430
Complete Street PVAL PUP430
 
James Assinder | Transport Accessibility Review
James Assinder | Transport Accessibility ReviewJames Assinder | Transport Accessibility Review
James Assinder | Transport Accessibility Review
 
A Fitts
A FittsA Fitts
A Fitts
 
Nethermayne Site Planning Application
Nethermayne Site Planning ApplicationNethermayne Site Planning Application
Nethermayne Site Planning Application
 
Jay Street Pedestrian Plaza
Jay Street Pedestrian PlazaJay Street Pedestrian Plaza
Jay Street Pedestrian Plaza
 
Roadway condition survey
Roadway condition surveyRoadway condition survey
Roadway condition survey
 
Hk harbourfront cycleway route by hkcall (rev 3)
Hk harbourfront cycleway route by hkcall (rev 3)Hk harbourfront cycleway route by hkcall (rev 3)
Hk harbourfront cycleway route by hkcall (rev 3)
 
Route 20 Shared Use Path - Albemarle/Charlottesville
Route 20 Shared Use Path - Albemarle/CharlottesvilleRoute 20 Shared Use Path - Albemarle/Charlottesville
Route 20 Shared Use Path - Albemarle/Charlottesville
 
Letter from Askern Ward Parish Council
Letter from Askern Ward Parish CouncilLetter from Askern Ward Parish Council
Letter from Askern Ward Parish Council
 
Designing for Cycling RTPI 15.6.16 Tim Pheby
Designing for Cycling RTPI 15.6.16 Tim PhebyDesigning for Cycling RTPI 15.6.16 Tim Pheby
Designing for Cycling RTPI 15.6.16 Tim Pheby
 
Mcm demo glasgow - august 11
Mcm demo   glasgow - august 11Mcm demo   glasgow - august 11
Mcm demo glasgow - august 11
 
CPR Yards Crossing Study - open house panels
CPR Yards Crossing Study - open house panelsCPR Yards Crossing Study - open house panels
CPR Yards Crossing Study - open house panels
 
The 3068 Group - Presentation to East West Link Assessment Panel
The 3068 Group - Presentation to East West Link Assessment PanelThe 3068 Group - Presentation to East West Link Assessment Panel
The 3068 Group - Presentation to East West Link Assessment Panel
 
ATS-16: Protected Bike Lanes: Lessons Learned in Planning and Implementation,...
ATS-16: Protected Bike Lanes: Lessons Learned in Planning and Implementation,...ATS-16: Protected Bike Lanes: Lessons Learned in Planning and Implementation,...
ATS-16: Protected Bike Lanes: Lessons Learned in Planning and Implementation,...
 

More from Naoise

Sk 069 - ga working drawings
Sk 069 - ga working drawingsSk 069 - ga working drawings
Sk 069 - ga working drawingsNaoise
 
Clontarf to city centre cycle scheme
Clontarf to city centre cycle schemeClontarf to city centre cycle scheme
Clontarf to city centre cycle schemeNaoise
 
17203 consultative forum no 3 30112018 issue compressed
17203 consultative forum no 3 30112018 issue compressed17203 consultative forum no 3 30112018 issue compressed
17203 consultative forum no 3 30112018 issue compressedNaoise
 
Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019Naoise
 
Report no. 082019 of the environment strategic policy committee changes to ...
Report no. 082019 of the environment strategic policy committee   changes to ...Report no. 082019 of the environment strategic policy committee   changes to ...
Report no. 082019 of the environment strategic policy committee changes to ...Naoise
 
Letter to An Taoiseach
Letter to An TaoiseachLetter to An Taoiseach
Letter to An TaoiseachNaoise
 
DCC CEO Report to ABP
DCC CEO Report to ABPDCC CEO Report to ABP
DCC CEO Report to ABPNaoise
 
Doc09102017 00001
Doc09102017 00001Doc09102017 00001
Doc09102017 00001Naoise
 
Abp150416
Abp150416Abp150416
Abp150416Naoise
 
DCC Dollymount Flood Defence Report
DCC Dollymount Flood Defence ReportDCC Dollymount Flood Defence Report
DCC Dollymount Flood Defence ReportNaoise
 
Dollymount Flood Defence schematic
Dollymount Flood Defence schematicDollymount Flood Defence schematic
Dollymount Flood Defence schematicNaoise
 
Dollymount flood wall review feb 2016 rev2
Dollymount flood wall review feb 2016 rev2Dollymount flood wall review feb 2016 rev2
Dollymount flood wall review feb 2016 rev2Naoise
 
Draft Litter Management Plan
Draft Litter Management PlanDraft Litter Management Plan
Draft Litter Management PlanNaoise
 
Dollymount externalexpert ommgoc
Dollymount externalexpert ommgocDollymount externalexpert ommgoc
Dollymount externalexpert ommgocNaoise
 
Dollymount External Expert
Dollymount External ExpertDollymount External Expert
Dollymount External ExpertNaoise
 
Proposed additional car parking facility - south of Timber Bridge
Proposed additional car parking facility  - south of Timber BridgeProposed additional car parking facility  - south of Timber Bridge
Proposed additional car parking facility - south of Timber BridgeNaoise
 
Fairview Christmas Lights Switchon
Fairview Christmas Lights SwitchonFairview Christmas Lights Switchon
Fairview Christmas Lights SwitchonNaoise
 
S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015Naoise
 
S2S driver eye level below Sea Wall
S2S driver eye level below Sea WallS2S driver eye level below Sea Wall
S2S driver eye level below Sea WallNaoise
 
Item06a part8
Item06a part8Item06a part8
Item06a part8Naoise
 

More from Naoise (20)

Sk 069 - ga working drawings
Sk 069 - ga working drawingsSk 069 - ga working drawings
Sk 069 - ga working drawings
 
Clontarf to city centre cycle scheme
Clontarf to city centre cycle schemeClontarf to city centre cycle scheme
Clontarf to city centre cycle scheme
 
17203 consultative forum no 3 30112018 issue compressed
17203 consultative forum no 3 30112018 issue compressed17203 consultative forum no 3 30112018 issue compressed
17203 consultative forum no 3 30112018 issue compressed
 
Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019
 
Report no. 082019 of the environment strategic policy committee changes to ...
Report no. 082019 of the environment strategic policy committee   changes to ...Report no. 082019 of the environment strategic policy committee   changes to ...
Report no. 082019 of the environment strategic policy committee changes to ...
 
Letter to An Taoiseach
Letter to An TaoiseachLetter to An Taoiseach
Letter to An Taoiseach
 
DCC CEO Report to ABP
DCC CEO Report to ABPDCC CEO Report to ABP
DCC CEO Report to ABP
 
Doc09102017 00001
Doc09102017 00001Doc09102017 00001
Doc09102017 00001
 
Abp150416
Abp150416Abp150416
Abp150416
 
DCC Dollymount Flood Defence Report
DCC Dollymount Flood Defence ReportDCC Dollymount Flood Defence Report
DCC Dollymount Flood Defence Report
 
Dollymount Flood Defence schematic
Dollymount Flood Defence schematicDollymount Flood Defence schematic
Dollymount Flood Defence schematic
 
Dollymount flood wall review feb 2016 rev2
Dollymount flood wall review feb 2016 rev2Dollymount flood wall review feb 2016 rev2
Dollymount flood wall review feb 2016 rev2
 
Draft Litter Management Plan
Draft Litter Management PlanDraft Litter Management Plan
Draft Litter Management Plan
 
Dollymount externalexpert ommgoc
Dollymount externalexpert ommgocDollymount externalexpert ommgoc
Dollymount externalexpert ommgoc
 
Dollymount External Expert
Dollymount External ExpertDollymount External Expert
Dollymount External Expert
 
Proposed additional car parking facility - south of Timber Bridge
Proposed additional car parking facility  - south of Timber BridgeProposed additional car parking facility  - south of Timber Bridge
Proposed additional car parking facility - south of Timber Bridge
 
Fairview Christmas Lights Switchon
Fairview Christmas Lights SwitchonFairview Christmas Lights Switchon
Fairview Christmas Lights Switchon
 
S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015
 
S2S driver eye level below Sea Wall
S2S driver eye level below Sea WallS2S driver eye level below Sea Wall
S2S driver eye level below Sea Wall
 
Item06a part8
Item06a part8Item06a part8
Item06a part8
 

Recently uploaded

Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Christina Parmionova
 
(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证mbetknu
 
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...Suhani Kapoor
 
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...narwatsonia7
 
(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书mbetknu
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalorenarwatsonia7
 
WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.Christina Parmionova
 
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Christina Parmionova
 
(官方原版办理)BU毕业证国外大学毕业证样本
(官方原版办理)BU毕业证国外大学毕业证样本(官方原版办理)BU毕业证国外大学毕业证样本
(官方原版办理)BU毕业证国外大学毕业证样本mbetknu
 
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...narwatsonia7
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...ankitnayak356677
 
Building the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized StorageBuilding the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized StorageTechSoup
 
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfyalehistoricalreview
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…nishakur201
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...ResolutionFoundation
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Christina Parmionova
 

Recently uploaded (20)

Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Palam Vihar🔝 9953056974 🔝 escort Service
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.
 
(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证(多少钱)Dal毕业证国外本科学位证
(多少钱)Dal毕业证国外本科学位证
 
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
 
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
 
(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
 
WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.WORLD CREATIVITY AND INNOVATION DAY 2024.
WORLD CREATIVITY AND INNOVATION DAY 2024.
 
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.Earth Day 2024 - AMC "COMMON GROUND'' movie night.
Earth Day 2024 - AMC "COMMON GROUND'' movie night.
 
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
9953330565 Low Rate Call Girls In Adarsh Nagar Delhi NCR
 
(官方原版办理)BU毕业证国外大学毕业证样本
(官方原版办理)BU毕业证国外大学毕业证样本(官方原版办理)BU毕业证国外大学毕业证样本
(官方原版办理)BU毕业证国外大学毕业证样本
 
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
Russian Call Girl Hebbagodi ! 7001305949 ₹2999 Only and Free Hotel Delivery 2...
 
Model Town (Delhi) 9953330565 Escorts, Call Girls Services
Model Town (Delhi)  9953330565 Escorts, Call Girls ServicesModel Town (Delhi)  9953330565 Escorts, Call Girls Services
Model Town (Delhi) 9953330565 Escorts, Call Girls Services
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
 
The Federal Budget and Health Care Policy
The Federal Budget and Health Care PolicyThe Federal Budget and Health Care Policy
The Federal Budget and Health Care Policy
 
Building the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized StorageBuilding the Commons: Community Archiving & Decentralized Storage
Building the Commons: Community Archiving & Decentralized Storage
 
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
 
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
Goa Escorts WhatsApp Number South Goa Call Girl … 8588052666…
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...
 
Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...Enhancing Indigenous Peoples' right to self-determination in the context of t...
Enhancing Indigenous Peoples' right to self-determination in the context of t...
 

Cycleway realignment

  • 1. 1 To the Chairperson and Members of the North Central Area Committee Review of Clontarf Seafront Footpath and Cycle Track Alignment from Alfie Byrne Road to Conquer Hill Road. The Environment and Transportation Dept., Roads and Traffic Planning Section has been requested by the North Central Area Office to carry out a review of existing footpath and cycle track alignment along the Clontarf seafront from Alfie Byrne Road to Conquer Hill Road. The purpose of the review is to examine a number of conflict points between pedestrians and cyclists identified along the route with regard to safety concerns for all users. An inspection of the route from Alfie Byrne Road to Conquer Hill Road (Dublin Bus Depot) was carried out in March 2015. Conflict points were noted in several areas along the route. Issues are briefly discussed with accompanying recommendations/solutions. Enclosed aerial views 1, 2 and 3 illustrate proposed alignments. Alfie Byrne Road /Clontarf Road (Aerial View 1, Area 1) Issue: The segregated two-way cycle track and footpath on the south-east side of this junction merges into an undefined shared area. The footpath continues northwards on the opposite side of the cycle track. The cycle track continues eastwards along the seafront. There is no footpath in the immediate area for pedestrians wishing to continue eastwards along the seafront. Pedestrians are therefore obliged to cross the cycle track if they wish to continue northwards to the junction or walk along the cycle track if they wish to continue along the seafront, resulting in conflict with cyclists. Recommendation: A raised defined crossing point is recommended for pedestrians wishing to continue northwards to the junction (orange shaded area in aerial view). This crossing point should be clearly marked. Signage should be provided to warn cyclists to yield to pedestrians. A new footpath is also recommended (purple line) parallel to the existing two-way cycle track for pedestrians wishing to continue walking along the seafront. This footpath should be clearly defined and raised to deter cyclists encroaching onto it and should extend eastwards past the Alfie Byrne Memorial to the existing shared two-way cycle track/footpath (south of Strandville Avenue.) This footpath will also provide access to the Alfie Byrne Memorial. Alfie Byrne Road / Clontarf Road (Aerial View 1, Area 2) Issue: Immediately west of the Alfie Byrne Memorial (Area 2), there is a two-way cycle track in this area but no footpath. The cycle track also veers to the north to the existing pedestrian crossing on Clontarf Road. Pedestrians are using the cycle track as a footpath and are in obvious conflict with cyclists. Recommendation: As indicated above, a new footpath is recommended in this area (purple line), parallel to the existing two-way cycle track and also northwards to the junction. Clearly defined crossing points for pedestrians should be provided (orange shaded area) as well as warning signage to cyclists to yield to pedestrians at the raised crossing point. A toucan crossing should be provided at the existing pedestrian crossing on the east side of Alfie Byrne Road /Clontarf Road. Alfie Byrne Road / Clontarf Road (Aerial View 1, Area 3) Issue: At Area 3, the existing combined two-way cycle track/footpath diverges, where the footpath veers to the south, continuing along the seafront, and the two-way cycle track continues westwards. Pedestrians wishing to continue west, walk along the two-way cycle track, causing conflict with cyclists. Additional conflict is caused by both cyclists and pedestrians leaving the path at this point to travel north, over a wide concrete paved area, where a section of boundary wall has been broken out to access Clontarf Road at Strandville Avenue East. Recommendation:
  • 2. 2 The proposed footpath indicated for Areas 1 and 2 should end at Area 3, providing a facility for pedestrians to continue west. It is proposed to close off access to the wide concrete paved area, and repair the boundary wall, as access would be available from the footpath and cycle track to Clontarf Road at Alfie Byrne Road. Clontarf Road / Hollybrook Road Car Park (Aerial View 2) Issue: The proximity of the existing cycle track (green line) to the car park is a hazard to motorists as they leave their vehicles and cross the cycle track to access the park area. Motorists who are unfamiliar with the seafront may be unaware that they are stepping onto a cycle track as they leave their vehicles, resulting in a hazard to both pedestrians and cyclists alike. Recommendation: A realignment of the existing two-way cycle track (red line) is recommended as shown on Aerial View 2 where the existing combined cycle track/footpath diverges. The existing alignment (green line) should be removed. This will remove the conflict at the car park and provide an opportunity for pedestrians to take care as they cross the cycle track to access the footpath along the seafront. Clontarf Road /Belgrove Road /Vernon Avenue Car Park (Aerial View 3) Issue: This issue is similar to Hollybrook Road car park, where the cycle track is aligned along the rear of the car park. Motorists leaving their vehicles are immediately confronted with cyclists on this cycle track. Recommendation: A realignment of the cycle track is recommended as shown (red line). The new alignment would run parallel to the existing cycle track. The existing cycle track would become a new footpath for car park users (purple line). The footpath and cycle track would be separated with low hedge planting, with designated crossing points across the cycle track for pedestrians (yellow areas). Signage would be provided for cyclists at designated crossing points to yield to pedestrians. Pedestrian facilities would be maintained to connect the existing seafront footpath with Vernon Avenue junction by realigning the footpath as shown (purple line). The existing footpath behind the ESB sub-station would become a new two-way cycle track as this footpath is not popular with pedestrians (red line). Clontarf Road / Vernon Avenue (Aerial View 3) Issue: The volume and speed of cyclists using this shared area is a hazard to pedestrians. Recommendation: As mentioned above, the existing footpath running behind the ESB sub-station would become a new cycle track (red line), diverting commuter cyclists away from the current shared pedestrian/cyclist area at Vernon Avenue. The existing cycle track /footpath shared area at Vernon Avenue would remain to provide cycling facilities for Vernon Avenue cyclists access the cycle track (as the new cycle track behind the ESB sub-station would join the existing track further east of Vernon Avenue).The choice of cycle tracks in this area would enable commuter (high speed) cyclists use the more direct track behind the ESB sub-station, thus reducing cycling volume and speed at the shared area at Vernon Avenue. Clontarf Yacht Club Issue: Removal of a barrier has opened the area for free parking for a small number of vehicles at the Yacht Club slipway. Vehicles entering and exiting this area constitute a hazard for cyclists as they cross the entrance to the slipway. Recommendation: The area is unsuitable for parking and the entrance/exit is substandard in terms of sight lines. Replacement of the barrier is recommended to close off the area for parking. Management of the barrier can be undertaken by Clontarf Yacht Club in agreement with DCC NCA Office. DCC Car Park at Conquer Hill Road Issue:
  • 3. 3 Motorists exiting the car park are unable to see cyclists due to poor visibility caused by dense shrubs growing in the area. This issue is exacerbated by the high speed of some cyclists along the route. Recommendation: Visibility for motorists can be improved by the removal of dense shrub planting in the immediate area of the exit. Warning signage for cyclists to yield to traffic reviewed further and improved. Dublin Bus Car Park at Conquer Hill Road Issue: A similar situation to the DCC car park exists here where motorists exiting the car park are unable to see cyclists due to poor visibility caused by dense shrubs growing in the area. Recommendation: Visibility for motorists can be improved by the removal of dense shrub planting in the immediate area of the exit. Warning signage for cyclists to yield to traffic reviewed further and improved. Line marking of the two-way cycle track / footpath - Alfie Byrne Road to Conquer Hill Road. Issue: Line marking along the combined two-way cycle track / footpath has become faded and is no longer legible, causing confusion for cyclists and pedestrians regarding which side of the paved area they should use. In some areas, it is not clear if the path is a footpath or cycle track. Recommendation: Re-lining of the entire route from Alfie Byrne Road to Conquer Hill Road is recommended in accordance with the National Cycle Manual including pedestrian and cycle logos at 20.0m intervals. Implementation Proposals for Aerial View 1 at Alfie Byrne Road / Clontarf Road will be included in the Clontarf to Amiens Street Cycle Route Scheme, due for construction in 2016. Funding is approved by the NTA for this scheme. An application for funding for the completion of proposals in Aerial Views 2 and 3 will be submitted to the NTA under their Sustainable Transport Measures Grant Programme, one of which is the Cycling/Walking programme, supporting measures to improve the walking and cycling environment. The application will also include a re-lining of the entire route from Alfie Byrne Road to Conquer Hill Road. It is recommended that the North Central Area Office replace the barrier at the Clontarf Yacht Club, to prevent free parking in the area. This will remove the hazard for cyclists. Arrangements should be made with the Yacht Club to manage the operation of the barrier. DCC Parks Dept. will be requested to cut back dense growing shrubs at the entrance to both DCC and Dublin Bus car parks at Conquer Hill Road to improve visibility. DCC Traffic will review signage in this area on the cycle track to warn cyclists of vehicles entering/exiting the car park. Tony McGee Executive Engineer
  • 4. 4
  • 5. 5
  • 6. 6