SlideShare a Scribd company logo
1 of 65
Download to read offline
Knowledge Sharing
for ACMV Design & Installation in New
and Existing Building.
AUNG ZAW MYINT
M&E Manager
Lendlease Singapore Pte Ltd.
B.E (MECHANICAL)
GMM
SCEM (IES, Singapore)
1
CONTENTS
New Building
Secondary Chilled water distribution system in SOLARIS
Building.
Existing Building
Replacement of Kitchen Exhaust system in Raffle City
shopping mall.
2
3
4
SOLARIS POJECT
• The SOLARIS development project consist of 2 office tower, 16 storey (Tower-A), 10
storey (Tower-B) and 3 Basement car park.
• Original preliminary design was developed by CPG consultant.
• Our company was engaged to carry out the ACMV system to supply and install
accordingly but not limited to CPG original design for following system.
ACMV system with VAV Variable Air Volume terminals
Secondary Chilled water distribution system
BMS system.
Car park ventilation & smoke purging system.
Toilet exhaust & plant room Mechanical Ventilation system.
Staircase & lift lobby pressurization system.
Fresh air purging system @ offices.
• I was assigned as ACMV project manager to complete the project & achieved
Green Mark Platinum award from BCA
5
SOLARIS AHU Schematic Dwg
6
SOLARIS AHU Schematic Dwg
7
SOLARIS AHU Schematic Dwg
8
Chilled Water Distribution
• ACMV system of SOLARIS building is using the DCS (District Cooling System) heat
exchangers instead of using chillers in the building.
• Primary circuit of DCS system up to the heat exchanger plant room is by DCS
contractor. Our scope is from Heat Exchanger room to the whole building.
3nos heat exchangers @ 1,100 RT. (2 duty 1 stand-by)
3nos of Chilled water pump set with 152 l/s @ 30m,H. (Duty circle in sequence)
2nos of Chilled water pump set with 15 l/s @ 30m,H. (night mode)
4nos of Pre-cooled AHUs @ Roof level
43nos of AHUs @ each office floor
546 nos of VAV terminal units in offices area
30 nos of FCUs for common area and retail shops @ level-1.
196 nos of MV fans
95 nos of jet fan @ basement car park
9
SOLARIS Pipe Schematic Dwg-1
10
PIPE HEADER & RISER
• 450mm diameter suction header pipe from heat exchanger before each suction line
of 3 pumps.
• And another 450mm diameter discharge header pipe connecting with the each
discharge line of the pumps and distributed to office tower A and B by using 4nos
of separate riser pipes, each two risers at each block.
• riser-1 and 2 for the Tower-A and riser 3 and 4 for Tower-B. Each riser pipes are
300mm in diameter.
• One By-pass pipe c/w motorized control valve and isolation valves, inside the main
plant room, between suction and discharge headers.
11
CONTROL VALVES & BTU METERS
• 2 way motorized valves are installed at AHUs and FCUs to control and modulate in
accordance with the occupancy and / or cooling load demand.
• On each riser, pressure transducers are installed at the location, approximately two
third the distance of entire length.
• Btu meters and flow meter are installed at pipe headers and main plant room.
12
PROBLEM TO SOLVE
• Problem come to notice in the way that our chilled water system pumps are
consuming a lot of energy although there was not many demand, cooling load in
the building.
• There was one By-pass pipe c/w motorized control valve and isolation valves, inside
the main plant room, between suction and discharge headers.
• In accordance with the start-up procedure, system started running with all FCUs
and AHUs level by level.
• Then follow by the pumps running in the main plant room and request to turn on
DCS heat exchanger one by one according to the load demand from the FCUs and
AHUs inside the building.
13
PROBLEM TO SOLVE
• After system started, each and every FCU and AHU 2 way motorized valves are
open almost fully to achieve the designed room temperature in the office to cool
down the heat absorbed by the building.
• After running continuously for 30 to 45 minutes, 2 way motorized valves are start
to modulate and tends to close back due to very little occupancy in the office area.
• Once the differential pressure at one of the riser exceed the pre-set point for more
than 10 minutes, BMS system start giving the commend signal to open the by-pass
motorized valve at plant room header to relief the pressure in the system.
• Then system is keep running without reducing frequency of any pumps although
the demand on the building is not that much. Pumps are keep circulating thru the
by-pass line just to maintain the constant running and wasting energy
unnecessarily.
14
SOLARIS Pipe Schematic Dwg-1
15
SOLUTION
• Finally, we realized that pumps are running without optimizing with the cooling
load requirement.
• In fact, pumps can be modulate to reduce the speed instead of opening the by-pass
valve. By-pass valve opening shall be the last resolve.
• The only thing we need to be carefully considered is to maintain the minimum
chilled water flow rate required by Heat Exchanger manufacturer. That means, we
cannot reduce the pump frequency and flow rate lower than minimum
requirement.
• More importantly, we also need to consider the furthest / longest AHU is achieving
the required chilled water when the pumps are ramping down. Because, once we
reduce the pump motor frequency, it was not only reducing the water flow rate,
but also the system pressure.
16
SOLARIS Pipe Schematic Dwg-2
17
SOLARIS Pipe Heat Exchanger Room
18
SOLARIS BMS Schematic Dwg
19
SOLARIS Main Header & Mtorized Valves
20
SOLARIS POJECT
Plant Room Header
21
SOLARIS Main Plant Room
22
SOLARIS Btu meter & VFD
23
SOLARIS Main Switch Board
24
SOLARIS Fcu & Duct work
25
SOLARIS AHU Testing
26
BMS Monitor
27
Actual Measurement
28
29
RAFFLES CITY PROJECT
30
• Design & Build ANA Job for Kitchen Exhaust System
• Add new centrifugal Kitchen Exhaust Fans c/w new starter panel.
• Implement new vibration monitoring system.
• Study existing system for improvement.
• Change and replace duct work & accessories wherever possible.
• Survey and recalculate design static pressure and air flow to meet optimum design
condition.
RAFFLES CITY PROJECT
31
Existing Design Concept
32
Existing Layout Plan
33
Proposed New Design Concept
34
Proposed New Layout Plan
35
RAFFLES CITY Static survey record
36
RAFFLES CITY CP requirement
37
RAFFLES CITY CP requirement
38
RAFFLES CITY CP requirement
39
RAFFLES CITY CP requirement
40
RAFFLES CITY CP requirement
41
RAFFLES CITY Static Site Measure-1
42
RAFFLES CITY Static Site Measure-2
43
RAFFLES CITY Static calculation
44
RAFFLES CITY Static calculation
45
RAFFLES CITY Static calculation
46
RAFFLES CITY Static calculation
47
RAFFLES CITY Fan Curve System-A
48
RAFFLES CITY Fan Curve System-B
49
RAFFLES CITY Equipment List
Equipment List
Raffles City Shopping Center @ 252 North Bridge Road
NEW KEAF INSTALLATION ANA WORK
S/N Description Tag Name Brand / Model Capacity Location Serving Area Remark
1 Kitchen Exhaust Fan KEAF-B1-5 Rosenberg / 542SWSI 85000CMH @ 2100Pa
B-1 Fan Room Tenant System B
2 Kitchen Exhaust Fan KEAF-B1-1 Rosenberg / 490SWSI 70000CMH @ 2500Pa
B-2 Fan Room Tenant System A
3 Kitchen Exhaust Fan KEAF-B1-2 Rosenberg / 490SWSI 70000CMH @ 2500Pa
B-2 Fan Room Tenant System A
4 Room Exhaust Fan EAF-B1-T11 Rosenberg / RS200 400CMH @ 250Pa
B-1 Fan Room Handicap / Nursing
5 Room Exhaust Fan EAF-B1-MV1
Rosenberg / UNO-67-450-
4EW 3000CMH @ 200Pa
B-1 Fan Room B-1 Fan Room
6 FCU FCU-B1-T11 Carrier / 40LM40 25936 Btu/hr
B-1 Fan Room Handicap / Nursing
7 VSD VSD-KEAF-B1-5 Mitsubishi / F740P-110K 110kW / 3phase
B-1 Fan Room LCP-KEAF-B1-5
8 VSD VSD-KEAF-B1-1 Mitsubishi / F740P-90K 90kW / 3phase
B-2 Fan Room LCP-KEAF-B1-1
9 VSD VSD-KEAF-B1-1 Mitsubishi / F740P-90K 90kW / 3phase
B-2 Fan Room LCP-KEAF-B1-1
50
RAFFLES CITY Equipment Proposal
51
RAFFLES CITY Fan Room section
52
RAFFLES CITY Fan weight & dimension
53
RAFFLES CITY Fan Room
54
RAFFLES CITY Static survey record
55
RAFFLES CITY Site Photos
56
RAFFLES CITY Site Photos
57
RAFFLES CITY Fan Install
58
RAFFLES CITY Fan Install
59
Vibration monitoring System
60
Vibration monitoring System
61
Vibration monitoring System
62
RAFFLES CITY Vibration Monitor
Vibration Test.MOV
63
64
THE END
65

More Related Content

What's hot

LEED 301 - ASE,WSE,Kyoto,Munters
LEED 301 - ASE,WSE,Kyoto,MuntersLEED 301 - ASE,WSE,Kyoto,Munters
LEED 301 - ASE,WSE,Kyoto,MuntersNorival Corrêa
 
Energy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and EngineersEnergy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and Engineersenergytrustor
 
Application of adiabactic gas coolers for refrigerated warehouse applications
Application of adiabactic gas coolers for refrigerated warehouse applicationsApplication of adiabactic gas coolers for refrigerated warehouse applications
Application of adiabactic gas coolers for refrigerated warehouse applicationsATMOsphere Conferences & Events
 
Data Center Free Cooling in the Middle East
Data Center Free Cooling in the Middle EastData Center Free Cooling in the Middle East
Data Center Free Cooling in the Middle EastSyskaHennessy
 
Telehouse North Two Presentation 2015 - Adiabatic and Evaporative cooling
Telehouse North Two Presentation 2015 - Adiabatic and Evaporative coolingTelehouse North Two Presentation 2015 - Adiabatic and Evaporative cooling
Telehouse North Two Presentation 2015 - Adiabatic and Evaporative coolingTelehouse Europe
 
Eric Smith, International Institute of Ammonia Refrigeration (IIAR)
Eric Smith, International Institute of Ammonia Refrigeration (IIAR)Eric Smith, International Institute of Ammonia Refrigeration (IIAR)
Eric Smith, International Institute of Ammonia Refrigeration (IIAR)ATMOsphere Conferences & Events
 
M2G May 2015 GTI Presentation
M2G May 2015 GTI PresentationM2G May 2015 GTI Presentation
M2G May 2015 GTI PresentationCharles Rice
 
IHEA Robina Hospital Chiller Plant Optimisation
IHEA Robina Hospital Chiller Plant OptimisationIHEA Robina Hospital Chiller Plant Optimisation
IHEA Robina Hospital Chiller Plant OptimisationHydroChem
 
Enhancing performance of transcritical CO2 heat pumps with heat recovery
Enhancing performance of transcritical CO2 heat pumps with heat recoveryEnhancing performance of transcritical CO2 heat pumps with heat recovery
Enhancing performance of transcritical CO2 heat pumps with heat recoveryATMOsphere Conferences & Events
 
resume mechanical
resume mechanicalresume mechanical
resume mechanicalravi a
 
cooling tower annual audit process by John A. Herbert
cooling tower annual audit process by John A. Herbertcooling tower annual audit process by John A. Herbert
cooling tower annual audit process by John A. HerbertJohn A Herbert
 
X472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leedX472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leedmichaeljmack
 
Jet Propulsion Library - Overview
Jet Propulsion Library - OverviewJet Propulsion Library - Overview
Jet Propulsion Library - OverviewModelon
 

What's hot (20)

LEED 301 - ASE,WSE,Kyoto,Munters
LEED 301 - ASE,WSE,Kyoto,MuntersLEED 301 - ASE,WSE,Kyoto,Munters
LEED 301 - ASE,WSE,Kyoto,Munters
 
Maximize subcritical hours with adiabatic technology
Maximize subcritical hours with adiabatic technologyMaximize subcritical hours with adiabatic technology
Maximize subcritical hours with adiabatic technology
 
Energy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and EngineersEnergy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and Engineers
 
Application of adiabactic gas coolers for refrigerated warehouse applications
Application of adiabactic gas coolers for refrigerated warehouse applicationsApplication of adiabactic gas coolers for refrigerated warehouse applications
Application of adiabactic gas coolers for refrigerated warehouse applications
 
Optimizing Existing Rooftop Unit Energy Efficiency
Optimizing Existing Rooftop Unit Energy EfficiencyOptimizing Existing Rooftop Unit Energy Efficiency
Optimizing Existing Rooftop Unit Energy Efficiency
 
RLS Logistics futureproofs with CO2
RLS Logistics futureproofs with CO2 RLS Logistics futureproofs with CO2
RLS Logistics futureproofs with CO2
 
Data Center Free Cooling in the Middle East
Data Center Free Cooling in the Middle EastData Center Free Cooling in the Middle East
Data Center Free Cooling in the Middle East
 
Condensing Boiler Optimization
Condensing Boiler OptimizationCondensing Boiler Optimization
Condensing Boiler Optimization
 
Using HTRI technology within Petro-SIM
Using HTRI technology within Petro-SIM Using HTRI technology within Petro-SIM
Using HTRI technology within Petro-SIM
 
Telehouse North Two Presentation 2015 - Adiabatic and Evaporative cooling
Telehouse North Two Presentation 2015 - Adiabatic and Evaporative coolingTelehouse North Two Presentation 2015 - Adiabatic and Evaporative cooling
Telehouse North Two Presentation 2015 - Adiabatic and Evaporative cooling
 
Eric Smith, International Institute of Ammonia Refrigeration (IIAR)
Eric Smith, International Institute of Ammonia Refrigeration (IIAR)Eric Smith, International Institute of Ammonia Refrigeration (IIAR)
Eric Smith, International Institute of Ammonia Refrigeration (IIAR)
 
Mexico's first transcritical system at Casa Ley
Mexico's first transcritical system at Casa LeyMexico's first transcritical system at Casa Ley
Mexico's first transcritical system at Casa Ley
 
M2G May 2015 GTI Presentation
M2G May 2015 GTI PresentationM2G May 2015 GTI Presentation
M2G May 2015 GTI Presentation
 
IHEA Robina Hospital Chiller Plant Optimisation
IHEA Robina Hospital Chiller Plant OptimisationIHEA Robina Hospital Chiller Plant Optimisation
IHEA Robina Hospital Chiller Plant Optimisation
 
Air cooled condensers
Air cooled condensersAir cooled condensers
Air cooled condensers
 
Enhancing performance of transcritical CO2 heat pumps with heat recovery
Enhancing performance of transcritical CO2 heat pumps with heat recoveryEnhancing performance of transcritical CO2 heat pumps with heat recovery
Enhancing performance of transcritical CO2 heat pumps with heat recovery
 
resume mechanical
resume mechanicalresume mechanical
resume mechanical
 
cooling tower annual audit process by John A. Herbert
cooling tower annual audit process by John A. Herbertcooling tower annual audit process by John A. Herbert
cooling tower annual audit process by John A. Herbert
 
X472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leedX472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leed
 
Jet Propulsion Library - Overview
Jet Propulsion Library - OverviewJet Propulsion Library - Overview
Jet Propulsion Library - Overview
 

Similar to Mechanical Engineering Seminar 2017_3

Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.pptssuser8006c7
 
Sabardairy Training Report
Sabardairy Training ReportSabardairy Training Report
Sabardairy Training ReportNiravDesai66
 
Comparison between Systems
Comparison between SystemsComparison between Systems
Comparison between SystemsVictor Ashkenazy
 
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...Radha Krishna Sahoo
 
API Pumps design, application and selection
API Pumps design, application and selectionAPI Pumps design, application and selection
API Pumps design, application and selectionAlireza Bagherian
 
Wcfx r134a - hermatic screw chiller
Wcfx r134a - hermatic screw chillerWcfx r134a - hermatic screw chiller
Wcfx r134a - hermatic screw chillerAruna Amarasekara
 
Textile Companies(EID Intern, GE Power & Water (RGM) Industrial System )
Textile Companies(EID Intern, GE Power & Water (RGM) Industrial System )Textile Companies(EID Intern, GE Power & Water (RGM) Industrial System )
Textile Companies(EID Intern, GE Power & Water (RGM) Industrial System )Mostafa Elmeshad
 
Concept NoteR1.ppt
Concept NoteR1.pptConcept NoteR1.ppt
Concept NoteR1.pptMILIND569137
 
Dry Back Scotch Marine Boiler
Dry Back Scotch Marine BoilerDry Back Scotch Marine Boiler
Dry Back Scotch Marine BoilerCTi Controltech
 
The design of_fire_pump_rooms_-_v2
The design of_fire_pump_rooms_-_v2The design of_fire_pump_rooms_-_v2
The design of_fire_pump_rooms_-_v2خالد محمود
 
Control Valves for the Power Generation Industry" A Product and Applications ...
Control Valves for the Power Generation Industry" A Product and Applications ...Control Valves for the Power Generation Industry" A Product and Applications ...
Control Valves for the Power Generation Industry" A Product and Applications ...Belilove Company-Engineers
 
ADR PRV Presentation.pptx
ADR PRV Presentation.pptxADR PRV Presentation.pptx
ADR PRV Presentation.pptxRaja Sv
 
280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...
280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...
280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...Callaghan Pump and Controls, Inc.
 
MEP JUGAADS.pptx
MEP JUGAADS.pptxMEP JUGAADS.pptx
MEP JUGAADS.pptxSHANDEEP1
 
CASE STUDY OF KLPAC.pptx
CASE STUDY OF KLPAC.pptxCASE STUDY OF KLPAC.pptx
CASE STUDY OF KLPAC.pptxA04AnkitSharma
 
Cw design guidelines
Cw design guidelinesCw design guidelines
Cw design guidelinessiva_observer
 

Similar to Mechanical Engineering Seminar 2017_3 (20)

Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.ppt
 
Sabardairy Training Report
Sabardairy Training ReportSabardairy Training Report
Sabardairy Training Report
 
Comparison between Systems
Comparison between SystemsComparison between Systems
Comparison between Systems
 
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
 
API Pumps design, application and selection
API Pumps design, application and selectionAPI Pumps design, application and selection
API Pumps design, application and selection
 
DEAP Heat Pump Webinar 2
DEAP Heat Pump Webinar 2DEAP Heat Pump Webinar 2
DEAP Heat Pump Webinar 2
 
Wcfx r134a - hermatic screw chiller
Wcfx r134a - hermatic screw chillerWcfx r134a - hermatic screw chiller
Wcfx r134a - hermatic screw chiller
 
Textile Companies(EID Intern, GE Power & Water (RGM) Industrial System )
Textile Companies(EID Intern, GE Power & Water (RGM) Industrial System )Textile Companies(EID Intern, GE Power & Water (RGM) Industrial System )
Textile Companies(EID Intern, GE Power & Water (RGM) Industrial System )
 
Concept NoteR1.ppt
Concept NoteR1.pptConcept NoteR1.ppt
Concept NoteR1.ppt
 
Dry Back Scotch Marine Boiler
Dry Back Scotch Marine BoilerDry Back Scotch Marine Boiler
Dry Back Scotch Marine Boiler
 
The design of_fire_pump_rooms_-_v2
The design of_fire_pump_rooms_-_v2The design of_fire_pump_rooms_-_v2
The design of_fire_pump_rooms_-_v2
 
Control Valves for the Power Generation Industry" A Product and Applications ...
Control Valves for the Power Generation Industry" A Product and Applications ...Control Valves for the Power Generation Industry" A Product and Applications ...
Control Valves for the Power Generation Industry" A Product and Applications ...
 
ADR PRV Presentation.pptx
ADR PRV Presentation.pptxADR PRV Presentation.pptx
ADR PRV Presentation.pptx
 
280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...
280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...
280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...
 
Piping system
Piping systemPiping system
Piping system
 
Appsolu
AppsoluAppsolu
Appsolu
 
MEP JUGAADS.pptx
MEP JUGAADS.pptxMEP JUGAADS.pptx
MEP JUGAADS.pptx
 
CASE STUDY OF KLPAC.pptx
CASE STUDY OF KLPAC.pptxCASE STUDY OF KLPAC.pptx
CASE STUDY OF KLPAC.pptx
 
Cw design guidelines
Cw design guidelinesCw design guidelines
Cw design guidelines
 
INTRODUCING AQUAFAN
INTRODUCING AQUAFANINTRODUCING AQUAFAN
INTRODUCING AQUAFAN
 

Recently uploaded

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 

Recently uploaded (20)

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 

Mechanical Engineering Seminar 2017_3

  • 1. Knowledge Sharing for ACMV Design & Installation in New and Existing Building. AUNG ZAW MYINT M&E Manager Lendlease Singapore Pte Ltd. B.E (MECHANICAL) GMM SCEM (IES, Singapore) 1
  • 2. CONTENTS New Building Secondary Chilled water distribution system in SOLARIS Building. Existing Building Replacement of Kitchen Exhaust system in Raffle City shopping mall. 2
  • 3. 3
  • 4. 4
  • 5. SOLARIS POJECT • The SOLARIS development project consist of 2 office tower, 16 storey (Tower-A), 10 storey (Tower-B) and 3 Basement car park. • Original preliminary design was developed by CPG consultant. • Our company was engaged to carry out the ACMV system to supply and install accordingly but not limited to CPG original design for following system. ACMV system with VAV Variable Air Volume terminals Secondary Chilled water distribution system BMS system. Car park ventilation & smoke purging system. Toilet exhaust & plant room Mechanical Ventilation system. Staircase & lift lobby pressurization system. Fresh air purging system @ offices. • I was assigned as ACMV project manager to complete the project & achieved Green Mark Platinum award from BCA 5
  • 9. Chilled Water Distribution • ACMV system of SOLARIS building is using the DCS (District Cooling System) heat exchangers instead of using chillers in the building. • Primary circuit of DCS system up to the heat exchanger plant room is by DCS contractor. Our scope is from Heat Exchanger room to the whole building. 3nos heat exchangers @ 1,100 RT. (2 duty 1 stand-by) 3nos of Chilled water pump set with 152 l/s @ 30m,H. (Duty circle in sequence) 2nos of Chilled water pump set with 15 l/s @ 30m,H. (night mode) 4nos of Pre-cooled AHUs @ Roof level 43nos of AHUs @ each office floor 546 nos of VAV terminal units in offices area 30 nos of FCUs for common area and retail shops @ level-1. 196 nos of MV fans 95 nos of jet fan @ basement car park 9
  • 11. PIPE HEADER & RISER • 450mm diameter suction header pipe from heat exchanger before each suction line of 3 pumps. • And another 450mm diameter discharge header pipe connecting with the each discharge line of the pumps and distributed to office tower A and B by using 4nos of separate riser pipes, each two risers at each block. • riser-1 and 2 for the Tower-A and riser 3 and 4 for Tower-B. Each riser pipes are 300mm in diameter. • One By-pass pipe c/w motorized control valve and isolation valves, inside the main plant room, between suction and discharge headers. 11
  • 12. CONTROL VALVES & BTU METERS • 2 way motorized valves are installed at AHUs and FCUs to control and modulate in accordance with the occupancy and / or cooling load demand. • On each riser, pressure transducers are installed at the location, approximately two third the distance of entire length. • Btu meters and flow meter are installed at pipe headers and main plant room. 12
  • 13. PROBLEM TO SOLVE • Problem come to notice in the way that our chilled water system pumps are consuming a lot of energy although there was not many demand, cooling load in the building. • There was one By-pass pipe c/w motorized control valve and isolation valves, inside the main plant room, between suction and discharge headers. • In accordance with the start-up procedure, system started running with all FCUs and AHUs level by level. • Then follow by the pumps running in the main plant room and request to turn on DCS heat exchanger one by one according to the load demand from the FCUs and AHUs inside the building. 13
  • 14. PROBLEM TO SOLVE • After system started, each and every FCU and AHU 2 way motorized valves are open almost fully to achieve the designed room temperature in the office to cool down the heat absorbed by the building. • After running continuously for 30 to 45 minutes, 2 way motorized valves are start to modulate and tends to close back due to very little occupancy in the office area. • Once the differential pressure at one of the riser exceed the pre-set point for more than 10 minutes, BMS system start giving the commend signal to open the by-pass motorized valve at plant room header to relief the pressure in the system. • Then system is keep running without reducing frequency of any pumps although the demand on the building is not that much. Pumps are keep circulating thru the by-pass line just to maintain the constant running and wasting energy unnecessarily. 14
  • 16. SOLUTION • Finally, we realized that pumps are running without optimizing with the cooling load requirement. • In fact, pumps can be modulate to reduce the speed instead of opening the by-pass valve. By-pass valve opening shall be the last resolve. • The only thing we need to be carefully considered is to maintain the minimum chilled water flow rate required by Heat Exchanger manufacturer. That means, we cannot reduce the pump frequency and flow rate lower than minimum requirement. • More importantly, we also need to consider the furthest / longest AHU is achieving the required chilled water when the pumps are ramping down. Because, once we reduce the pump motor frequency, it was not only reducing the water flow rate, but also the system pressure. 16
  • 18. SOLARIS Pipe Heat Exchanger Room 18
  • 20. SOLARIS Main Header & Mtorized Valves 20
  • 23. SOLARIS Btu meter & VFD 23
  • 25. SOLARIS Fcu & Duct work 25
  • 29. 29
  • 31. • Design & Build ANA Job for Kitchen Exhaust System • Add new centrifugal Kitchen Exhaust Fans c/w new starter panel. • Implement new vibration monitoring system. • Study existing system for improvement. • Change and replace duct work & accessories wherever possible. • Survey and recalculate design static pressure and air flow to meet optimum design condition. RAFFLES CITY PROJECT 31
  • 34. Proposed New Design Concept 34
  • 36. RAFFLES CITY Static survey record 36
  • 37. RAFFLES CITY CP requirement 37
  • 38. RAFFLES CITY CP requirement 38
  • 39. RAFFLES CITY CP requirement 39
  • 40. RAFFLES CITY CP requirement 40
  • 41. RAFFLES CITY CP requirement 41
  • 42. RAFFLES CITY Static Site Measure-1 42
  • 43. RAFFLES CITY Static Site Measure-2 43
  • 44. RAFFLES CITY Static calculation 44
  • 45. RAFFLES CITY Static calculation 45
  • 46. RAFFLES CITY Static calculation 46
  • 47. RAFFLES CITY Static calculation 47
  • 48. RAFFLES CITY Fan Curve System-A 48
  • 49. RAFFLES CITY Fan Curve System-B 49
  • 50. RAFFLES CITY Equipment List Equipment List Raffles City Shopping Center @ 252 North Bridge Road NEW KEAF INSTALLATION ANA WORK S/N Description Tag Name Brand / Model Capacity Location Serving Area Remark 1 Kitchen Exhaust Fan KEAF-B1-5 Rosenberg / 542SWSI 85000CMH @ 2100Pa B-1 Fan Room Tenant System B 2 Kitchen Exhaust Fan KEAF-B1-1 Rosenberg / 490SWSI 70000CMH @ 2500Pa B-2 Fan Room Tenant System A 3 Kitchen Exhaust Fan KEAF-B1-2 Rosenberg / 490SWSI 70000CMH @ 2500Pa B-2 Fan Room Tenant System A 4 Room Exhaust Fan EAF-B1-T11 Rosenberg / RS200 400CMH @ 250Pa B-1 Fan Room Handicap / Nursing 5 Room Exhaust Fan EAF-B1-MV1 Rosenberg / UNO-67-450- 4EW 3000CMH @ 200Pa B-1 Fan Room B-1 Fan Room 6 FCU FCU-B1-T11 Carrier / 40LM40 25936 Btu/hr B-1 Fan Room Handicap / Nursing 7 VSD VSD-KEAF-B1-5 Mitsubishi / F740P-110K 110kW / 3phase B-1 Fan Room LCP-KEAF-B1-5 8 VSD VSD-KEAF-B1-1 Mitsubishi / F740P-90K 90kW / 3phase B-2 Fan Room LCP-KEAF-B1-1 9 VSD VSD-KEAF-B1-1 Mitsubishi / F740P-90K 90kW / 3phase B-2 Fan Room LCP-KEAF-B1-1 50
  • 51. RAFFLES CITY Equipment Proposal 51
  • 52. RAFFLES CITY Fan Room section 52
  • 53. RAFFLES CITY Fan weight & dimension 53
  • 54. RAFFLES CITY Fan Room 54
  • 55. RAFFLES CITY Static survey record 55
  • 56. RAFFLES CITY Site Photos 56
  • 57. RAFFLES CITY Site Photos 57
  • 58. RAFFLES CITY Fan Install 58
  • 59. RAFFLES CITY Fan Install 59
  • 63. RAFFLES CITY Vibration Monitor Vibration Test.MOV 63
  • 64. 64